PERFORMANCE INDICATORS - 2011/2012



Performance Indicator
Actual
Target for 2012/2013




1
The percentage of applications receipted and acknowledged within 3 working days
100%
100%




2
The percentage of plans vetted and applicants advised of defects / amendments in 3 weeks
75.3%
92%




3
The percentage of decisions issued within statutory deadlines
97.4%
100%




4
Number of fee-paying applications1
1006
N/A




5
Fees received, both deposit and inspection
£384,200 (approx)
N/A




6
Approximate value of works inspected2
£10,611,409
N/A




7
Number of inspections carried out
9326
N/A



Notes
1
Fee paying applications means Full Plans, Building Notices, Regularisation applications and the number of Partner Authority Scheme applications checked as the plan checking Authority. This figure excludes resubmissions.
2
Excludes value of resubmissions.



Page last updated on: 13/06/2012