| Performance Indicator | Actual | Target for 2005/2006 |
| | | |
1 | The percentage of applications receipted and acknowledged within 3 working days | 99% | 100% |
| | | |
2 | The percentage of plans vetted and applicants advised of defects/amendments in 3 weeks | 56% | 65% |
| | | |
3 | The percentage of decisions issued within statutory deadlines | 96% | 98% |
| | | |
4 | Number of fee-paying applications1 | 1342 | N/A |
| | | |
5 | Fee’s received, both deposit and inspection | TBC | N/A |
| | | |
6 | Approximate value of works inspected2 | £55,631,244.15 | N/A |
| | | |
7 | Number of inspections carried out | 10,523 | N/A |
| Notes |
1 | Fee paying applications means Full Plans, Building Notices, Regularisation applications and the number of Partner Authority Scheme applications checked as the plan checking Authority. |
2 | Excludes value of resubmissions. |
Page last updated on: 20/04/2009