TRANSITIONAL PROVISIONS

Previous Regulations continue to apply provided;
1

Building Regulation application submitted before 6 April 2006 and work commences before 6 April 2006;


Or
2

Where contract entered into for the building work before 6 April 2006 and that work does not require a full plans application and the works commence before 1 October 2006;


Or
3

Full Plans application Approved without conditions (or conditions discharged) prior to 6 April 2006 and work commences before 1 April 2007;


Or
4

The building would previously have been exempt but must now meet the energy efficiency requirements of the regulations and either;
  1. The work commences before 6 April 2006 or
  2. The contract for the provision of the work is entered into before 6 April 2006 and work commences before 1 April 2007.