PAPER B
Purpose
: for Decision
REPORT
TO THE EXECUTIVE
Date : 30th JUNE 2004
Proforma : PAN MASTERPLAN – SUPPLEMENTARY PLANNING
GUIDANCE
REPORT OF THE PORTFOLIO HOLDER FOR
SUSTAINABLE DEVELOPMENT, ENVIRONMENT AND PLANNING POLICY
IMPLEMENTATION DATE : 12TH
JULY 2004
1.
To consider the Pan Masterplan, as produced by the
Council’s consultants. The draft SPG
addresses the key issues raised through the various stakeholder workshops and
public consultation. The draft SPG is
attached to this report as Appendix A.
2.
None
BACKGROUND
3.
The Unitary Development Plan includes an allocation
adjoining Pan for some 20 hectares of housing and employment development. The Council resolved that the best way of
bringing forward what is largely a Council owned site was to undertake a
Masterplan exercise and to this end appointed Tibbalds as the consultants for
the project. Since their appointment,
Tibbalds, in conjunction with Council officers, have been progressing the Plan
through a series of stakeholder workshops, discussion with individual agencies,
survey work and information gathering to inform preparation of the Masterplan.
4.
Options were prepared and discussed and following a
broad consensus from the stakeholder workshops, a local public consultation
exercise was carried out over 2 weeks at Downside Middle School. Views and comments from this process have
enabled the Plan to be further refined.
5.
The Masterplan is not intended to be a rigid blueprint
but will set the context for the consideration of more detailed design and the
planning applications that will come
forward. In order to give it
appropriate weight, the intention is that the Plan will become Supplementary
Planning Guidance (SPG) to the UDP.
6.
In order for the Masterplan to achieve SPG status, the
Council had to undertake a further
round of public consultation and report all the comments received (together
with how those responses were dealt with) back to the Executive prior to
adoption.
7.
Members will also be aware of the new Planning
legislation that will come into effect on 13th July 2004. The impact of the new legislation will mean
that local authorities will no longer have the powers to progress SPG that, under the new system, will be replaced
by Supplementary Planning Documents (SPD).
If decisions about this draft SPG is delayed beyond 13th July
2004, the Council will be left with no alternative but to start the process
again on SPD, which could result in a further 12-18 month timescale. The impact would not only be to duplicate
work already done, but will leave the Council without adopted supplementary
guidance which could delay the Council bringing forward this site for development.
8.
The site is allocated in the UDP for mixed housing and
employment use and needs to come forward for development to ensure the Council
can meet both its general and affordable housing needs.
9.
As the site is in Council ownership, the Masterplan
will ensure that the housing provided will go some way to addressing
homelessness on the Island and to keep families out of bed and breakfast
accommodation, both of which are key achievements of the Corporate Plan and
Community Strategy, and will help with the Housing PSA target.
10.
The Masterplan will also provide strong linkages with
the existing Pan community and the ongoing Neighbourhood Renewal Project. One of the main reasons for the success of
the renewal bid was the ongoing Masterplan exercise and the opportunity to
build one cohesive community at Pan.
CONSULTATION
11.
The Masterplan has been developed to this draft stage
through a continuing dialogue with a wide range of stakeholders. The exercise has included three stakeholder
workshops with representation from the following:
·
Isle of Wight Council (Members and officers)
·
Housing Associations
·
Community Groups (Pan Can Forum)
·
Environment Agency
·
Police
·
Southern Water
·
Business Groups
·
IW Economic Partnership
·
Education (local school governors and head teacher)
·
SEEDA
12.
In order to adopt SPG, national guidance in PPG12
makes it clear that proper consultation should be carried out, with relevant
stakeholders and that any comments are considered and reflected upon before any
decision is taken. In the case of the
SPG on Pan the Council has notified interested parties, placed the draft SPG on
the website and advertised its availability through the County Press for a
period which will end on 28th June 2004.
13.
As this report is being compiled prior to the end of
the consultation exercise, the comments and objections received will be report
to the Executive verbally.
FINANCIAL/BUDGET
IMPLICATIONS
14.
The costs of commissioning the consultants to carry
out the Masterplan have been previously agreed and have been funded from
capital receipts. The value of the site
to the Council is in the order of £15m.
15.
In order to meet its housing requirements set out in
the Regional Planning Guidance and Part 1 of the UDP, it has been demonstrated
through the Urban Capacity Study that the land allocated is necessary to meet
both general and affordable needs.
16.
Once adopted as SPG there will be a need to print the
final document. The cost of this
printing has already been identified within the planning services budget.
17.
Under paragraph 3.15 of PPG12 Supplementary Planning
guidance can be used as a means of setting out more detailed guidance on the
way in which the policies in the UDP will be applied in particular
circumstances or areas. It will not form part of the plan but must be
consistent with the plan and with national and regional guidance. The local planning authority must take
into account the Human Rights Act and be sure that it has considered any
relevant articles and that its decisions are proportionate and in accordance
with the legitimate aims of the council.
LEGAL
IMPLICATIONS
18.
The power to adopt SPG to an existing development plan
is set out in PPG12 (and revised PPS12).
This is on the basis of proper consultation and that the SPG is
supplementary to existing policy and not creating new policy. The Council has taken legal advice in
respect of previous SPG at Project Cowes and the process for adoption of this
document is considered to be in line with advice contained within PPG12. The issues of the Human Rights Act and the
balancing of the rights of any affected residents as against the rights of any
developers and the duties of the Council have been carefully considered and the
recommendation is held to be proportionate and in line with the legitimate line
of the Council.
OPTIONS
19.
Although the recommendation is that this SPG should be
adopted, the Council have three other courses of action it could pursue.
(1) To
adopt as SPG
(2) Not to
adopt as SPG
(3) To
delay adoption and pursue SPD as part of the new planning legislation
(4) To
adopt as interim guidance.
20.
OPTION 1
To
adopt as SPG.
21. OPTION 2
Not to
adopt as SPG would leave the Council without guidance on an important
site. During the pre Best Value
Inspection meeting the lack of up-to-date SPG was identified as a major
weakness of the Service.
22.
OPTION 3
Delaying
adoption would leave a policy gap for a period of approximately 12-18 months,
duplicate work and consultation already undertaken. Other major greenfield sites coming forward may prevent Pan from
being released.
23.
OPTION 4
The Council could adopt the guidance on a more informal basis, which does comply with current advice. This however, would give it little weight in the development control process and could render the document ineffective or powerless.
24. Option 1 is the preferred option as it is the only one, which allows for the adoption of SPG prior to the enactment of the new legislation. The SPG is required to ensure that the site can be brought forward for development.
25.
Adoption of SPG could result in High Court challenge
if objections to the document are not properly considered or the document is
not considered to supplement existing policy.
If however, this were the case, the Council would choose not to
implement the SPG through the DC process as it is only through its
implementation with regard to a specific application that individuals could
become aggrieved.
26.
In order to ascertain the effectiveness and use of SPG
it will be necessary to monitor its application and any resulting appeals. Through this process, the SPG can be kept
under review and reconsidered (if necessary) as SPD in the new Planning
process.
27.
There is always the possibility of costs being awarded
against the Council through the appeal process, however, adopted SPG is seen as
a way of reducing uncertainty.
RECOMMENDATIONS 28.
That the Executive endorse the adoption of SPG on
the Pan Masterplan, attached as Appendix 1,
subject to any further changes agreed by the Portfolio Holder in consultation
with the Head of Planning Services (resulting from comments and objections
received from the consultation period). |
BACKGROUND
PAPERS
UDP
2001
Urban
Capacity Study 2002
Pan
Project Brief – Expression of Interest
PPG12
Contact
Point : Ashley Curzon, ext 4557,
[email protected]
Head
of Service Andrew
Ashcroft Head
of Planning Services |
Portfolio
Holder Cllr
Terry Butcher Portfolio
Holder for Sustainable Development, Environment and Planning Policy |