PAPER B
Committee: ENVIRONMENT AND
TRANSPORT SELECT COMMITTEE
Date: 27 NOVEMBER
2002
Title BUDGET
MONITORING REPORT AS AT END OF OCTOBER 2002
Service |
Expenditure |
Income |
Net |
|
|||
|
Budget |
To date |
Budget |
To date |
Budget |
To date |
Comment |
|
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
|
1,278.9 |
1,097.7 |
-148.8 |
-192.8 |
1,130.1 |
904.9 |
||
874.7 |
696.2 |
-212.7 |
-135.5 |
662.0 |
560.7 |
||
Waste management and recycling |
6,139.1 |
1,897.6 |
-7.1 |
-19.3 |
6,132.0 |
1,878.3 |
Budget includes all aspects of the Integrated Waste
Management contract, and also includes the landfill tax budget. IWM contract
invoices tend to be some weeks in arrears, hence the apparent budget surplus |
Public conveniences and first time sewerage |
438.5 |
178.5 |
-6.2 |
-0.4 |
432.3 |
178.1 |
Main budgets are for the contractual cleaning of
the public conveniences and operational costs such as rates, water and
electricity |
Building control |
428.3 |
229.1 |
-394.8 |
-272.1 |
33.5 |
-43.0 |
Income presently ahead of target due in part to amounts
received last year relating to works not yet started, hence accrued into the
current year |
Street and beach cleaning |
1,350.0 |
637.0 |
-0.3 |
-1.1 |
1,349.7 |
635.9 |
As is the case for the waste management and
recycling budgets, street cleansing invoices in particular tend to be some
weeks in arrears, hence the apparent budget surplus |
Highway maintenance |
1,874.7 |
1,407.1 |
-33.5 |
-32.6 |
1,841.2 |
1,374.5 |
Budget on target at this stage of the financial
year – however possible budget pressure areas are highway drainage and
highway clearance/safety sweeping |
Service |
Expenditure |
Income |
Net |
|
|||
|
Budget |
To date |
Budget |
To date |
Budget |
To date |
Comment |
|
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
|
Traffic management and
road safety |
663.6 |
551.4 |
-14.0 |
-13.7 |
649.6 |
537.7 |
Budget on target to date,
including cliff stabilisation works linked to highway safety |
Street Lighting |
627.7 |
482.0 |
-10.0 |
-14.9 |
617.7 |
467.1 |
Budget covers all aspects
of the street lighting service, including power, planned maintenance and
routine maintenance. On target |
County Transport |
435.0 |
1,429.9 |
-300.2 |
-164.6 |
134.8 |
1,265.3 |
Budget includes
operational costs of Wightbus, Home to School Transport and the Council’s
vehicles and plant prior to their reallocation to service areas. The budgets
shown are net of recharges to service user budgets, however no recharges have
taken place to date, hence the current overspend shown |
Public Transport including
Cowes Floating Bridge |
1,586.9 |
1,061.5 |
-597.7 |
-334.8 |
989.2 |
726.7 |
This budget contains the
costs of subsidised local bus services, Rural Bus Grant Services and
concessionary fares schemes, as well as the operation of the Cowes Floating
Bridge. Income is mainly from the Floating Bridge and the Rural Bus Grant |
Car Parking |
610.6 |
463.0 |
-2,118.3 |
-1,841.6 |
-1,507.7 |
-1,378.6 |
The main focus of this
budget tends to be on income generation because of its relative significance
and the impact it can have on the delivery of other service areas e.g.
traffic management and public transport. Income is accruing well to date,
although a significant proportion is seasonal |
Environmental Initiatives
including Agenda 21 |
161.0 |
91.2 |
-95.7 |
-16.1 |
65.3 |
75.1 |
This budget includes the
Coastal Visitors Centre and associated projects as well as the Agenda 21
budget. Much of the income relates to project budgets for which recharges
have yet to take place |
Totals |
16,469.0 |
10,222.2 |
-3,939.3 |
-3,039.5 |
12,529.7 |
7,182.7 |
Percentage of year elapsed
to date – 58.3% Percentage net budget
spent to date – 57.3% Percentage excluding
County Transport – 47.7% |