PAPER D
Committee : AUDIT COMMITTEE
Date : 12 JANUARY
2006
Title : CAPITAL
BUDGET MANAGEMENT - ADVANCE OUTLAY
REPORT OF THE ACCOUNTANCY
SERVICES MANAGER
1.
At the meeting on 22
November 2005 the Cabinet received a Financial Exception Report for the period
to 31 October 2005. One of the decisions taken at the meeting was to refer to
this Committee a report assessing the risks associated with capital programmes
spending significant sums in advance of funding being secured. This report provides
the background to the issue and makes recommendations to how such expenditure
should be managed effectively in future.
BACKGROUND
2.
The Code of Practice on
Local Authority Accounting in the UK (SORP) sets out a definition of capital
expenditure with which all local authorities are obliged to comply. Basically,
expenditure on the acquisition of a tangible fixed asset, or expenditure which
adds to the value of an existing asset, should be treated as capital
expenditure and classified as a tangible fixed asset provided that it yields a
benefit to the authority for more than one year. A definition of capital
expenditure is set out in Appendix A.
Preparatory Costs of Major Schemes
3.
In local authority terms,
for specific large capital projects, particularly infrastructure projects,
there may be a requirement for a considerable amount of investment in a project
prior to its submission to a Government department for formal approval. This
can involve option appraisals, feasibility studies, consultation exercises,
public enquiries and advance scheme design. The SORP specifically states that
such costs are ineligible to the extent that they relate to activity that takes
place before the intention to acquire or construct a particular fixed asset has
been confirmed, unless they contribute to the scoping of the asset ultimately
acquired.
Major Highway Schemes
4.
The most significant
projects in the highways capital programme are those for Ryde Interchange
(£5.56m) and Undercliff Drive (£12.88m). The projects were approved in
principle as part of the LTP settlements for 2003/04 and 2004/05 respectively.
However, in both cases the point was made by the Department for Transport that
acceptance was provisional only and subject to completion of all relevant
statutory processes. Furthermore, funding allocations need to be confirmed each
year, and Ministers reserved the right to reconsider their decision if the
outcome of the statutory processes leads to any significant changes in the
scheme. There is no guarantee on meeting any increase in costs over and above
the Government’s agreed total contribution.
5.
Details of the Council’s
annual LTP allocations from the DfT are shown in Table 1 on Appendix B. Tables 2 and 3 on the Appendix show the
approved budgets for the two major projects and details of expenditure and
commitments to date. It can be seen from the information included in the Table
that in terms of budget impact each of the two major schemes requires a significant
investment when compared with the annual capital programme for the remainder of
the highways and public transport network. Given that context, at the time the
DfT had issued guidance with regard to preparatory costs for major schemes. It
is a generally accepted principle that local authorities must take the
additional risk of developing major schemes in order to demonstrate a genuine
local commitment to it. In order to restrict such works to realistic schemes
the DfT will consider the provision of funding for preparatory costs only after
a scheme has been fully accepted. Fully accepted means the scheme has passed
all the Government’s appraisal tests as well as all necessary statutory and
planning procedures, and any other conditions. Eligible preparatory costs
considered for approval would include detailed design of the scheme and work on
preparing the scheme appraisal for submission to the DfT.
6.
Since the projects were
provisionally accepted, the Dft have issued further guidance for major schemes,
which is specifically for schemes submitted after July 2005, but which GOSE
believe the DfT plan to apply to all provisionally accepted schemes still not
fully approved. In our case that would include both Ryde Interchange and
Undercliff Drive. The major change is with regard to the approval process which
now has three stages. Provisional approval of a project is now called Programme
Entry, although the definition is much the same. A new intermediate approval
stage is introduced at the point where full approval would previously have
taken place. This is known as Conditional Approval and is a commitment to
funding, subject to the cost estimates and risks remaining unchanged and the
scheme being ready to commence within a certain period. Full Approval will not
now be given until procurement has taken place and prices and risk allocation
are known. Any application for Conditional or Full Approval must contain a full
explanation of any cost increases, including the extent to which this was due
to circumstances within, or not within, the authority’s control. The DfT will
expect the authority to make some contribution to major scheme cost increases
from their own resources, but also to provide the likely impact this will have
on the wider capital programme. The final point in the revised guidance is that
if a scheme is presented for Full Approval with a significant cost increase or
a substantial design change, Full Approval may be denied or delayed, especially
where the scheme no longer appears to represent sufficient value for
money.
Coast Protection Schemes
7.
Major coast protection
schemes are one type of infrastructure asset where preparatory costs tend to be
incurred. Currently, advance design costs are incurred prior to the schemes’
approval by DEFRA. Coast protection projects tend to be approved on a project
by project basis and, up to now, DEFRA approval of such schemes has recognised
the full costs of the scheme, thereby allowing grant and borrowing approvals to
be applied to the advance design fees retrospectively.
Property Assets
8.
The Council has a
considerable property portfolio, including schools, leisure sites, fire
stations and office accommodation. In terms of annual capital investment the
most significant part of the capital programme tends to be for expenditure on
schools development and major maintenance. There has been increasing slippage
of capital projects in recent years, particularly in aspects of the schools
programme including devolved capital budgets, the Middle Schools programme and
to a lesser extent the Primary Schools programme. In a report on the Financial
Health of the Council, the Audit Commission have noted that point, and
suggested that the capital programme has become too ambitious and is driven by
available resources from the Government rather than Council priorities, which
has tended to lead to further underspends. As one of their recommendations for
improvement, they have suggested that a solution to this problem is to create
an inventory of projects which have been designed in advance in order that they
can be substituted for delayed projects, thereby allowing the best possible use
of available resources.
OUTCOME OF CONSULTATIONS
9.
Consultation on this
report has been undertaken with representatives of Engineering Services, Property
Services and Children’s Services. The views of the Audit Commission have also
been sought on the broader issue of reporting on the Council’s capital
programme, and recent comments on the Council’s Use of Resources
self-assessment make it plain that the Audit Commission view the provision of
relevant, up to date financial management information to an appropriate forum
of elected members as a key element of effective performance management.
FINANCIAL IMPLICATIONS
10.
There are a number of
financial implications arising from the information contained within this
report. Clearly there is a risk to the Council’s financial well-being
associated with having to invest sums of money in projects well in advance of
formal Government approval of the project, particularly when the project is one
of the magnitude of Undercliff Drive and the amounts in question are well in
excess of £1.5 million. Such an investment requires positive budget management
but, even so, it will inevitably have a detrimental impact on the ability to
deliver other projects in the period until all necessary procedures have been
completed and the Government release the approved funding for the project.
11.
By contrast, continued
slippage in aspects of the capital programme also has financial implications in
terms of the use of resources available to fund the projects, but also that
continued slippage of approved projects to a significant degree represents a
threat to the effective delivery of the Council’s objectives.
12.
Previous Government
capital settlement methodology may have had an impact on the planning of
schemes in advance to the extent that the settlements were for one year only,
with no guarantees of future funding. It is anticipated that relaxation of
Government controls in terms of the Prudential Code for borrowing, together
with the implementation of three year settlements from 2006/07, will allow
better asset management by affording the ability to plan capital programmes for
an extended period with prior knowledge of available resources.
LEGAL IMPLICATIONS
13.
There are no legal
implications arising from this report. The report is the outcome of a quarterly
performance management report to the Cabinet and, as such, is internally
generated. The Council has the ability to choose how to improve the financial
management of expenditure in advance of external funding being secured in order
to ensure best use is made of available resources.
OPTIONS
1.
To take no further
action.
2.
To recommend to the
Cabinet that all capital projects should be evaluated in accordance with the
Council’s risk assessment process; that all capital projects which are judged
as medium or high risk having undergone the process should be recorded in the
Council’s risk register to acknowledge the impact they can have on both the Council’s
financial well-being and delivery of the Council’s strategic objectives; that
all such projects recorded in the risk register should be the subject of
regular progress reports (via the quarterly financial exception reports) in
order that members are kept up to date with all aspects of project delivery;
that all major capital projects should be subject to a Gateway review process
in order to provide assurances as to progress through the various project
stages up to and including procurement processes, and to include value for
money considerations to ensure that the project continues to offer good value
for money for the Council.
3.
To recommend to the
Cabinet that where appropriate, resources should be made available for advance
design works in order that an inventory of projects is available to replace
those delayed for any reason.
RECOMMENDATIONS
14.
Option 2 and 3 |
BACKGROUND PAPERS
15.
Code of Practice on Local
Authority Accounting in the United Kingdom – A Statement of Recommended
Practice
Audit Commission Report – Financial Health, Isle of Wight Council, Audit 2004/05
ADDITIONAL INFORMATION
16.
None
APPENDICES ATTACHED
17.
Appendix
A – Definition of Capital Expenditure.
18.
Appendix
B – Tables of LTP Settlements and Major Schemes Budget and Expenditure
Contact Point: Stuart Fraser, Accountancy Services
Manager ( 823657, email: [email protected]
STUART FRASER
Accountancy Services Manager