INTEGRATED RISK MANAGEMENT – PLANNING PROCESS OVERVIEW
In order that this project remains focused and fulfils the criteria laid down by the ODPM, the following process chart may be beneficial. This information will be cross-mapped to the Integrated Risk Management Plan Timetable and will refer to phases within the plan.
PHASE |
PROCESS |
OUTPUTS |
CONSULTATION/ LIAISON |
INFORM |
1. |
Identify existing risks (actual
& potential). |
Risk Maps showing level of risk
based on analysis of all available data. |
Statistician FCO
Function Managers Police Social
Services Housing
Association
Planning Communication & PR Manager CFS Officer |
IRM
Management Board |
2. |
Evaluate effectiveness of
current arrangements. |
Assessment of our: 3
Policies 3
Resources/Activities 3
Performance |
IRM
Management Board Rep
Bodies
Function Managers |
Select
Committee HMFSI |
3. |
Identify improvement
opportunities. Determine policies and
standards. |
3
Improved balance between prevention and intervention. 3
Policies that deliver fewer incidents, deaths and injuries. 3
Standards for Prevention and Response. |
Relevant Stakeholders Police Social
Services NHS
Trust
Ambulance Trust Rep
Bodies IRM
Management Board |
Select
Committee Joint
Liaison Group |
PHASE |
PROCESS |
OUTPUTS |
CONSULTATION/ LIAISON |
INFORM |
3. Cont: |
|
|
HMFSI
Function Managers Chief
Fire Officers’ Group Brigade
Management Team CFS
Officer |
|
4. |
Determine resource requirements |
Appropriate resources to meet
identified local needs. |
Chief
Fire Officers’ Group Brigade
Management Team IRM
Management Board Finance |
Select
Committee Rep
Bodies |
5. |
Produce draft IRMP and Action Plan. |
|
Executive Committee IRM
Management Board HMFSI |
Chief
Fire Officers’ Group Brigade
Management Team |
6. |
Consultation on draft IRMP and
Action Plan. |
|
Communications and PR Manager All
Stakeholders |
|
7. |
Reporting, Monitoring and
Auditing Development. |
Systems to assist in the
monitoring and quality control of all of the outputs recorded above. |
IRM
Management Board Brigade
Management Team HMFSI |
Select
Committee
Executive Committee |
PHASE |
PROCESS |
OUTPUTS |
CONSULTATION/ LIAISON |
INFORM |
8. |
Analysis of consultation
replies. |
Realign IRMP and Action Plan to
produce final plan. |
IRM
Management Board Rep
Bodies
Function Managers Chief
Fire Officers’ Group Brigade
Management Team
Communications and PR Manager |
Select
Committee
Executive Committee |
9. |
Final decision on Fire Authority
IRM and Action Plan. |
Strategy of Isle of Wight Fire
Authority to comply with ODPM. |
Directors’
Executive Committee Full
Council |
Chief
Fire Officers’ Group Brigade
Management Team
Stakeholders |
10. |
Implementation of Action Plan /
IRMP |
Refer to Phase 7. |
|
|