PAPER E

 

                                                                                                              Purpose : For Decision

                        REPORT TO THE CABINET

 

Date :              7 JUNE 2005

 

Title :               HIGHWAY IMPROVEMENT, UNDERCLIFF DRIVE, ST LAWRENCE – COMPULSORY PURCHASE ORDER

                       

REPORT OF THE CABINET MEMBER FOR RESOURCES, AUDIT,  AN EFFICIENT COUNCIL AND CUSTOMER CHAMPION AND THE CABINET MEMBER FOR ENVIRONMENT, TRANSPORT AND PLANNING POLICY

 

IMPLEMENTATION DATE : 20 June 2005

 


 


SUMMARY/PURPOSE

 

1.                     That the Council resolves to make a Compulsory Purchase Order under Section 240 of the Highway Act 1980. To acquire the land described in this report, and to continue negotiations with landowners.

 

BACKGROUND

 

2.                     The A3055 Undercliff Drive is an important section of the Island’s highway infrastructure that links the West Wight to the coastal towns of Ventnor, Shanklin and Sandown.  It is also a vital part of the tourist route around the Island.

 

3.                     Periodic damage had occurred to the road over a long period of time necessitating its realignment in the 1920s. In 2001 a major landslide caused substantial damage to the highway.  Four sections of the highway have been identified as requiring remedial engineering works to reinstate the highway, including moving the route inland at one location. The severe damage means that this is the only technical solution and a ‘make do and mend’ approach is no longer possible.

 

4.                     The Council’s geotechnical consulting engineers, High-Point Rendel, have undertaken detailed investigative works and their proposals have subsequently secured planning consent.  The land involved can be seen in the plan annexed to this report.  The Department for Transport will fund the £12.88 million for this scheme, which is included in its capital programme. However, this funding cannot be accessed until the Council has secured landowner agreements for all lands to implement the scheme.

 

5.                     In total there are eleven landowners involved, one of which is the Isle of Wight Council.  Your Officers have been negotiating with the landowners to secure land required to implement this scheme.  Written or verbal agreement has been reached with five landowners and none have completed a binding agreement.  Some landowners are wholly against the scheme and believe it to be a waste of Council resources.  Other frontagers have differing views as to land value.

 

6.                     Given the current position of some landowners it is increasingly likely that the Council will be unable to reach agreement by negotiation.  If this proves to be the case then the Council is at risk of losing the funding allocated to it by the Department for Transport. The loss of the opportunity to extend the life of the A3055 would have very serious implications for the economy of Ventnor, the Islands tourist industry and the highway network, quite apart from the environmental impact to properties on the alternative route.  It is therefore proposed to initiate formal procedures in parallel with negotiations.

 

7.                     As this is an important highway scheme and because the Council could potentially lose the funding to finance this work the Council is being recommended to use statutory powers to purchase the land needed for the scheme. Subject to approval by the Secretary of State the right to acquire property by compulsion is vested in the Council as Highway Authority through a confirmed Compulsory Purchase Order (CPO).

 

8.                     Given that Council officers have been in discussions with landowners affected by this proposed Order and whilst some are not content with the Council’s proposals, it is considered that the local and Island wide benefits of reinstating the Undercliff Drive on balance outweigh their concerns.

 

DESCRIPTION, LOCATION AND PRESENT USE OF THE LAND

 

The proposed Order is made up of 13 different plots in four areas along the Undercliff Drive.  Plans showing the land required under this Order can be seen in Appendix 1.  Map 1 referred to in the table below will be displayed at the Cabinet Meeting.

                                                                                                                       

Land to be Acquired 

Extent, description and situation of the land

Owners or reputed owners

Number of Map

Number on Map

1

 

 

(Area 1)

1

Land at The Orchard Estate, Undercliff Drive.

·         5,794m² or thereabouts

·         Copse and meadow

·         Severely affected by landslip.

Mr R Etherington

1

 

(Area 1)

2

Land at Orchard Dene, Undercliff Drive.

·         2,515m² or thereabouts

·         Garden of Orchard Dene

·         Severely affected by landslip

Mrs S Goodman

1

 

(Area 1)

3

Land at Orchard Close, Undercliff Drive.

·         32m² or thereabouts

·         Small area of garden of Orchard Close

 

 

Mr M Goodman

1

(Area 2)

4

Land at Mirables, Undercliff Drive.

·         6,366m² or thereabouts

·         Copse land

Mr and Mrs A Fish

1

 

(Area 3)

5

Land at Mirables, Undercliff Drive.

·         2,125 square metres or thereabouts

·         Copse land

Mr and Mrs A Fish

1

 

(Area 3)

6

Land to the west of Undercliff Drive Nature Reserve

·         1,896 square metres or thereabouts

·         Copse land

Owner unknown

1

 

(Area 3)

7

Land at Undercliff Drive Nature Reserve.

·         4,206 square metres or thereabouts

·         Copse land

·         Extremely close to edge of landslip

Hants and IW Wildlife Trust

1

 

(Area 3)

8

Land opposite Undercliff Drive Nature Reserve.

·         8,928 square metres or thereabouts

·         Devastated by landslip

·         Former copse land

Mr and Mrs S Twining

1

 

(Area 3)

9

Undercliff Glen Caravan Park.

·         2,243 square metres or thereabouts

·         Directly adjacent and affected by landslip

Mr and Mrs C Mimms

1

 

(Area 3)

10

‘Woodington’, Undercliff Drive.

·         4,496 square metres or thereabouts

·         Entire property

Mr and Mrs C Morris

1

 

(Area 3)

11

‘Timber’, Undercliff Drive.

·         1,098 square metres or thereabouts

·         Part of lower garden

Mrs T Hall

1

 

(Area 3)

12

Old Park Hotel.

·         843 square metres or thereabouts

·         Old track devastated by landslip

Mr and Mrs J Sharp

1

 

(Area 4)

13

Old Park Hotel.

·         4,086 square metres or thereabouts

·         Dense copse

·         Affected by southern ends of works

Mr and Mrs J Sharp

 

 

PLANNING IMPLICATIONS

 

9.                     Planning consent for this scheme was granted on 15th February 2005 and involved consultation with bodies including The Environment Agency, English Nature, the AONB Unit and Town and Parish Councils.  In seeking a CPO the Council must be able, as part of demonstrating that there is a reasonable prospect of the scheme going ahead, to show that it is unlikely to be blocked by any impediment to implementation.

 

10.                 The Undercliff Defence Committee comprising of it is believed 6 local landowners has been formed and has stated in writing its intention to seek a Judicial Review of the Planning Permission on various grounds.  The Council will seek to resist this review.  However, if the Judicial Review is brought and results in the permission being quashed, the Council will undertake the planning process once again. 

 

11.                 It is a fundamental policy contained within the UDP (Policy TR12 – The Strategic Road Network) to “approve proposals which maintain the effectiveness of the strategic road network which is presently defined as follows: a)  all existing A class roads”.  The Council is of the view that if a fresh planning application has to be submitted, this is likely to be successful, therefore it is unlikely that the scheme will be blocked by any impediment to implementation.

 

12.                 The Undercliff is a sensitive area in terms of planning use and includes areas designated as Areas of Outstanding Natural Beauty (AONB) and Sites of Special Scientific Interest (SSSI).

 

STRATEGIC CONTEXT

 

13.                 Transport is one of seven key themes that have been identified in the development and implementation of the measures set out in the Council’s Community Plan.  The transport theme is being led by the Quality Transport Partnership (QTP) who look to see how transport on the Island can be improved, including integration and accessibility and reduce accidents and congestion.

 

14.                 The Council use this information in conjunction with the Local Transport Plan (LTP). The LTP takes into account a range of existing national, regional and European policy, including Planning Policy Guidance 13 for Transport and Regional Planning Guidance 9, and considers the A3055 to be a route of strategic significance to the Island.  The LTP funding recognises this is a scheme of national importance because it had to bid in competition with other authorities.

 

15.                 By approving this request to initiate compulsory purchase proceedings the Council will, should the order be confirmed, be able to implement this scheme and help achieve the goals and objectives set out in both the regional and national policies as set out above.

 

CONSULTATION

 

16.                 Consultation has taken place with the local Town and Parish Council, local Members and Officers.  The Council’s consultants have also held public meetings and an exhibition, most recently in January 2005 at the Ventnor Winter Gardens, where local residents were invited to raise their concerns and issues regarding the proposal and The Environment Agency and English Nature have also been consulted throughout the planning process as were the AONB Unit.

 

FINANCIAL/BUDGET IMPLICATIONS

 

17.                 Compulsory Purchase Orders can be a costly process and it is almost impossible to predict the time it will take to reach conclusion.  The CPO process is detailed below.

 

18.                 The Council has already approved the spending of over £1 million on the design, advice and planning for the scheme. Should the Council not proceed with this proposal then this money will be abortive and will need to be funded from our own resources as access to the £12.88 million allocated by the Department for Transport, which was intended to cover such costs, will be lost.

 

19.                 A confirmed Compulsory Purchase Order will enable the Council to proceed with the scheme.  This will incur both construction and acquisition costs.  Construction costs are anticipated to be in the region of £12.5 million with acquisition costs estimated at £550,000. In addition, there will be legal fees incurred estimated to be in the region of £4,000 with the possibility of additional legal fees being awarded to the landowners by a Lands Tribunal. The majority of these costs will be paid for out of the funding granted by the Department for Transport.  However, this funding was determined without the consideration that a CPO would be required, and a supplementary bid may need to be submitted once greater detail is known. 

 

THE COMPULSORY PURCHASE ORDER PROCESS

 

20.                 Planning consent for the scheme that forms the CPO must be in place before the Council can make an application for the Order.  The application must be made on Form 1 in accordance with the Compulsory Purchase of Land Regulations 1994.  The form is then submitted to the confirming authority and must include a Statement of Reasons.

 

21.                 A Statement of Reasons details the reasons behind the requirement of a CPO.  The process that your officers and Highpoint Rendel have gone through to achieve planning consent has proved an excellent case for the reinstatement of Undercliff Drive.  This will be of considerable help in getting a Compulsory Purchase Order confirmed.

 

22.                 Notices must be placed in local newspapers for at least two weeks and allow at least 21 days for objections to be submitted.  Similarly, landowners affected by the scheme must be served notices and allowed at least 21 days to object.

 

23.                 If no objections are made or are withdrawn the Order can be confirmed.  However, given the difficulties encountered in the negotiation process it is unlikely that this application will not receive any objections.

 

24.                 If objections are received it is usual practice for the application to go to a public local enquiry unless a Compensation Tribunal can resolve the objections.

 

LEGAL IMPLICATIONS

 

25.                 A Compulsory Purchase Order application can be made whilst negotiating with landowners in parallel.

 

26.                 The confirming Act that provides the Council with the power to make a Compulsory Purchase Order is the Highway Act 1980. Procedural advice can be found under the Acquisition of Land Act 1981.

 

27.                 Should the proposed Judicial Review result in the planning consent being quashed then the Council will need to go through the planning process once more.  However provided it can be demonstrated that there is a reasonable prospect of the scheme going ahead, within a reasonable timescale, the fact that a planning consent may not be in place at the time confirmation of the CPO is sought from the Secretary of State will not prevent the order being so confirmed.

 

HUMAN RIGHTS IMPLICATION

 

28.                 Consideration has been given to the rights set out in Article 8 (Right to Privacy) and Article 1 of the First Protocol (Right to Peaceful Enjoyment of Possessions) of the European Convention on Human Rights.  The impact this proposal may have on the owners/occupiers of the land in question and other third parties have been carefully considered.

 

29.                 There will be interference with the rights of the various landowners to varying degrees.  However, having regard to the public interest in the Highway Reinstatement Scheme and the economic and environmental improvements that will result, together with the assistance and compensation that will be given to those displaced or affected, it is considered that the degree of interference is proportional to the legitimate aim of the Council and is in the public interest.

 

CRIME AND DISORDER IMPLICATIONS

 

30.                 There are no Crime and Disorder issues apparent in respect of this scheme and purpose of this report.

 

OPTIONS

 

(a)               That the Council resolves to make a Compulsory Purchase Order under Section 240 Highway Act 1980. To acquire the land described in this report, and to continue negotiations with landowners.

 

(b)               To continue with negotiations and hope for a successful conclusion by agreement.

 

(c)                To look at an alternative route.

 

(d)               Do nothing.

 

EVALUATION/RISK MANAGEMENT

 

31.                 The initiation of CPO proceedings will have costly implications for the Council and approval of the application is not guaranteed.  Receiving a notice that a CPO has been served may encourage the landowners to negotiate terms for the land by agreement.

 

32.                 Although negotiations for the remainder of land required are on going there is a risk not initiating a CPO now.  Should Officers be unable to agree terms in say, 6 months time, then a CPO would still be required and we would be in exactly the same position as we are now delaying the matter further.

 

33.                 Negotiations will continue regardless of the outcome of this report.  However, negotiations have already been protracted and may continue to be so.  The initiation of CPO proceedings will emphasise the Council’s intent to undertake this scheme.

 

34.                 To do nothing will jeopardise this scheme and its funding and no doubt lose the potential to reinstate Undercliff Drive, St Lawrence for many years if ever at all.

 

35.                 In addition to this, to do nothing will lose the Island an important tourist route used by both tourists and businesses alike. The impact on the smaller, local businesses could potentially force them to close down. This scheme is also vital to provide management of the water flows at the Undercliff, without which, the winter peaks that have previously caused so much damage could become more frequent.

 

36.                 Consideration has been given to look at alternative routes, including one that provides a bypass north of Niton. This was assessed and costed during the bidding process to Government Office of the South East (GOSE) and the cost of the alternative route was far in excess of the current scheme. In addition to this, works would still be required in areas 1, 2 and 4 to maintain access for local residents.

 

RECOMMENDATIONS

 

37.                 That the Council resolves to make a Compulsory Purchase Order under Section 240 of the Highway Act 1980. To acquire the land described in this report, and to continue negotiations with landowners.

 

BACKGROUND PAPERS

 

A3055 Undercliff Drive Remediation Proposals – September 2003

A3055 Undercliff Drive Environmental Statement – July 2004

Acquisition of Woodington – Executive, 15th December 2004

 

 

Contact Point :           Kevin Gillett, Valuation Surveyor, Property Services F 823467

                                    [email protected]

 

MR T FLOWER

Head of Property Services

 

CLLR J WOOD

Portfolio Holder for Resources, Audit, an Efficient Council and Customer Champion

 

CLLR WARD

Cabinet Member for Environment Transport and Planning Policy

 


 

 

 

 

 


REPORT AUTHOR’S CHECKLIST

Title of Report :

Place Y for yes and N for no in the box below

·          Can the decision be taken under delegated powers by :

 

·           The relevant portfolio holder?

 

·           An Officer?

 

·          Has the decision appeared on the forward plan?

 

·          Has the relevant Select Committee had the opportunity to consider the issue?

 

·          Does the Director’s Group need the opportunity to discuss the report?

 

·          If so, insert the date of the meeting where the report was considered?

 

·          Has the portfolio holder approved the report?

 

·          Has sufficient consultation taken place?

 

·          Is the consultation set out and evaluated in the report?

 

·          If the recommendation is not consistent with the outcome of consultation, are reasons given?

 

·          Can an elected Member (or member of the public) with no previous knowledge of the report see sufficient background information (which can include reference to previous reports) to allow them to understand the issue?

 

·          Does the report identify what strategic or policy aim is achieved or contributed to by the decision?

 

·          Are all reasonable options identified and appraised?

 

·          Is there additional risk management information that needs to be set out?

 

·          Has specialist advice been taken for the following:

 

·           Financial?

 

·           Legal?

 

·           Personnel?

 

·           Other?

 

·          Is the cost associated with the decision fully set out and the source of any funding identified?

 

·          Have the following been considered and explained (where necessary) in the report:

 

·           Human Rights issues?

 

·           Crime and Disorder issues?

 

·          Is risk management properly addressed?

 

·          Are all background papers listed and available?

 

·          Is the implementation date clearly identified?

 

·          If the report is confidential or exempt is the reason for the confidentiality or exemption clearly identified?

 

·          Are there clear recommendations with reasons?

 

·          Are the report author and contact officer clearly identified?