PAPER B

 

Purpose: for Decision

 

REPORT TO CABINET

 

Date :            5 SEPTEMBER 2006

 

Subject:          HIGHWAYS MAINTENANCE PRIVATE FINANCE INITIATIVE                       EXPRESSION OF INTEREST

 

Report of:       THE STRATEGIC DIRECTOR OF ECONOMIC DEVELOPMENT AND

                      REGENERATION

 

IMPLEMENTATION DATE: 18 SEPTEMBER 2006

 

PURPOSE

 

1.                   To approve the submission of an Expression of Interest for a Highway Maintenance Private Finance Initiative to the department of transport by 10th September 2006.

 

BACKGROUND

 

2.                   Notwithstanding recent increases in highway maintenance budgets, the condition of the Island’s road network remains below standard.  Routine inspections and various structural condition surveys indicate that urgent and substantial investment is needed to improve and maintain the highway network asset.

 

3.                   The decline in road condition is accompanied by a decline in asset value and increased highway maintenance costs are generated in restoring roads to a good condition.  There is a high national demand for conventional capital funding for highway maintenance as all responsible local authorities endeavour to address their maintenance backlog. 

 

4.                   The Government has set local authorities the target of arresting decay in the highway asset by 2005 and removing the backlog of repairs by 2011.

 

5.                   The needs of the highway network on the Island are therefore considered to be beyond the current financial resources of the Council, particularly when viewed against the traditional funding competition from other service areas.  To enable an acceptable transport asset management plan (TAMP) to be delivered, it is essential that alternative funding sources were identified and utilised.

 

6.                   The benefits of improved funding will ensure that maintenance backlogs are properly addressed and life cycle asset management techniques and strategies implemented to ensure that the restored highway network is maintained in a good condition.   Failure to secure the necessary levels of investment will result in continued and accelerated deterioration of the highway network.  Restrictions on the use of road space will increase through safety considerations with attendant reductions in accessibility.  There will follow inevitable adverse consequences for the economic, social and


environmental wellbeing of the Island.  Even at present rates of maintenance funding, it is estimated that the highway network will be life expired, i.e. having nil residual life within the next 10 to 12 years.

 

7.                   The term of the PFI Project is likely to be 25 years with major capital investment being undertaken in the first 7 years to rehabilitate the network to a sustainable level.  Whole life cycle maintenance strategies would then be implemented for the remainder of the term.  The affordability gap, i.e. the difference between the cost of the PFI Project and the Council’s spend on highway asset management, is bridged by PFI Credit.  PFI Credit is a non-refundable Special Grant and not permission to borrow.

 

8.                   The commitment required from the Council is that its Highways FSS will need to be 100% ring fenced to the PFI Project.  Whilst this will mean some reduction in overall Council budget flexibility, it does ensure that highway network is guaranteed proper levels of funding.

 

9.                   In February this year the DfT announced a pathfinder round for Local Government Private Finance Initiative (PFI) in Highway Maintenance (HM).  A fund of £600m PFI credits was to be made available to local authorities applying through this round.

 

10.              Local authorities were invited to submit Expressions of Interest (EoI) by 10th September 2006.

 

11.              The Council has maintained an open dialogue with DfT and with a range of advisors concerning the development of a PFI in this area, and have closely observed the process through which Birmingham and Portsmouth City Councils have secured PFI projects for highway maintenance.

 

STRATEGIC CONTEXT

 

12.              The proposed PFI sits within the objectives of a range of local strategies and plans seeking to deliver a long-term vision for how the Island is developed. The Local Strategic Partnership, Island Futures, have set the overarching “2020 Vision” to “build an Island with a future” which is contained within the Island’s Community Strategy.

 

13.              This informs the Local Development Framework (LDF), the “Island Plan” that provides the broad planning policy for the Island.  Feeding into the LDF is the second Local Transport Plan (LTP 2006-2011) for the Isle of Wight; this was submitted in March 2006.  The PFI will seek to deliver the Council’s aspirations in LTP2 for effective highway asset management.

 

14.              Within the IW Council’s regeneration strategies and initiatives derived from the over arching Area Investment Framework (AIF), the PFI has a significant role to improve the local infrastructure and support economic regeneration of the Island.  While at the same time the Highways network is a key component of creating a quality public realm that will underpin work to deliver Council strategies such as the Tourism Development Plan and Crime & Disorder Strategy.  Issues of sustainability within the PFI project will be addressed in line with the Council’s commitments as part of Agenda 21.

15.              At a corporate level, the PFI seeks to deliver two of the Council’s five key objectives “to drive the sustainable regeneration and development of the Island” and “to create safer and stronger communities”.  Within the recently agreed Local Area Agreement it is a key priority for improving the Island’s infrastructure through the delivery of economic development objectives.

 

16.              In line with the Government’s agenda for public service reform, there is innovation in the means of procuring policy solutions with an increasing recognition that partnership with the private sector can yield benefits.  Such benefits are achieved through a better allocation of risk, which gives the incentive to develop creative solutions with regard for the long term, drawing on the experience of private sector partners in planning, project development and risk mitigation whilst maintaining public control on policy initiatives.  A partnership will enable the Council to draw on private sector approaches to business development, asset life-cycle management and supply chain management.  The Council has placed this approach at the heart of its recently adopted “Aim High Change Management” plan.

 

CONSULTATION

 

17.              The Quality Transport Partnership, Chamber of Commerce, Government Office for the South East (GOSE) and Partnerships UK have been consulted on the PFI proposals.

 

 

FINANCIAL/BUDGET IMPLICATIONS

 

18.              As stated in paragraph 8 above, it is anticipated that the financial commitment required from the Council will be no more than its existing revenue budget contribution to the highway maintenance service, and that this amount plus annual adjustments for inflation will have to be fully ring fenced to the PFI Project for the entire 25 year period. This is based on the premise that any affordability gap will be bridged by the award of PFI credits for the project.  The risk created by this premise is analysed below.

 

19.              The nature of PFI Projects is such that the Government will provide PFI credits for the capital elements of any scheme and not ongoing increases in revenue budget requirements. For a significant ‘fence to fence’ highway maintenance project the most significant aspects of capital expenditure will take place in the initial 7 year rehabilitation period. However, the whole life cycle maintenance strategies would require additional capital expenditure throughout the remainder of the project life to retain the highways network at the improved standard achieved in the first 7 years of the project.

 

20.              In order to calculate the likely amount of PFI credit required, each of the components must be built into a financial model of the project. These components will include backlog maintenance, whole life cycle maintenance, potential insurance premiums and claims costs and the likely costs a successful contractor would build into any tender to secure the requirements of an output specification.

 

21.              The Council has been working with its external advisors to identify each of these components and their potential impact on the financial model. By their nature, some of these components are essentially revenue expenditure. As a result of the requirement for PFI credits to be linked to capital expenditure only, this can have a significant impact on the affordability gap, and adjustments must then be made to the financial model to reduce any affordability gap identified.

 

 

LEGAL IMPLICATIONS

 

22.              The Council has a duty under the Highways Act (S41 HA 198) to maintain the highway network and therefore has the power to investigate alternative funding arrangements in order to discharge that duty.  Statutory Instrument 1999 No. 2106 The Local Authorities (Contracting Out of Highway Functions) Order 1999.

 

“Contracting out of functions of local highway authorities

2. Any function of a local highway authority which is conferred by or under any of the provisions described in Schedule 1, 2 or 3 to this Order may be exercised by, or by employees of, such person (if any) as may be authorised in that behalf by the local highway authority whose function it is.”

 

24.       The submission of an EoI creates no future obligations but, if the EoI is approved by the Department for Transport will enable development of the next stage of the bidding process through drafting an outline business case.

 

OPTIONS

 

25.              The needs of the highway network on the Island both in terms of backlog of repairs and life cycle costs are considered to be beyond the current financial resources of the Council.  The only affordable option currently available appears to be a PFI.  The options are therefore:-

 

                                    I.       To submit an EoI for a highway maintenance PFI.

                                  II.       Not to submit an EoI for a highway maintenance PFI and to identify alternative funding opportunities to restore and maintain the highway network.

 

EVALUATION/RISK MANAGEMENT

 

26.              One of the key aims and immediate priorities within the Council’s Corporate Plan is to ‘Have an accessible, effective and integrated transport system for the Island’. Delivering a Highway Maintenance PFI will achieve the aim. Submitting an EoI on 10 September 2006 is a key step to achieving the corporate priority.

 

27.              The risk held on the Council’s corporate risk register notes that the appointment of external advisors and the development of a Transport Asset Management Plan and Highways Infrastructure Asset Register have provided the necessary information to enable progress to be made towards an effective EoI submission. A recent meeting with the Department of Transport has also supported a submission being made.

 

28.              As the first step towards achieving approval for a Highway Maintenance PFI project, the risk to achievement of the corporate aim is reduced by submitting the EoI. By contrast, not submitting an EoI will mean that the corporate risk will remain at a high level, with little prospect of its being substantially reduced through conventional finance streams.

 

29.              A risk in this process is the possibility of there being an affordability gap requiring a greater contribution from Council revenue budgets, as set out in paragraphs 8 and 19 above.

 

30.              The next stage in the process is the development and submission of an Outline Business Case (OBC). The OBC part of the project plan will involve further discussions with the Department of Transport (DfT), and may require some of the financial components included within the EoI to be reassessed. Such a reassessment could result in the identification of an affordability gap which would need to be considered by the Council before submission of the OBC and Treasury Programme Review Group approval of the project.  

 

31.              The best possible EoI must be submitted, taking account of the latest guidance from the DfT and from the Council’s advisers.

 

32.              The draft EoI attached will require further work prior to the Cabinet meeting in the event that any significant changes are proposed a revised version of the draft will be circulated at the Cabinet.

 

33.              The period following the Cabinet but prior to submission of the EoI may require further revisions to this draft.  The recommendation made by this report enables further amendments to be made, provided they are within defined parameters, up to the submission deadlines.

 

34.              The potential PFI project is the largest public project ever contemplated on the Isle of Wight.  The development of the project will benefit from public scrutiny and the recommendations include a request to the Scrutiny Committee to add a line of enquiry to their work programme.

 

RECOMMENDATIONS

 

 

 

35.              That the Head of Engineering Services be authorised to:

 

(1)   submit an Expression of Interest to the Department of Transport seeking a highways maintenance PFI project.

 

(2)    agree, in consultation with the Cabinet Member for Environment, Planning and Transport, the final draft Expression of Interest ensuring that the submission draft does not depart from the draft available to the Cabinet, only in order to improve the quality of the Council submission.

 

36.              That the Cabinet invite the Scrutiny Committee to add one or more lines of enquiry to its work programme as the development of the proposed PFI continues.

 

 

 

BACKGROUND PAPERS

 

             Project group working papers

 

APPENDICES

 

Expression of Interest for Highway Maintenance PFI

 

 

Contact Point:            Stephen Matthews

                                        [email protected]

                                        Tel: (01983) 823777

 

 

 

DEREK ROWELL

CLLR IAN WARD

Strategic Director of Economic Development and Regeneration

Cabinet Member for Environment, Planning and Transport