PAPER B
Purpose : for Decision
Committee: CABINET
Date : 3 OCTOBER 2006
Title : VALUE FOR MONEY REVIEW OF
LEISURE (PHASE I) – BLUE PAPER OF THE POLICY COMMISSION FOR THE ECONOMY,
TOURISM, REGENERATION AND TRANSPORT
REPORT OF THE CABINET MEMBER FOR
THE ECONOMY, THE CUSTOMER, COMMUNICATIONS, LEISURE AND TOURISM
IMPLEMENTATION DATE : 13 October 2006
1.
To consider the recommendations of the Policy
Commission for Economy, Tourism, Regeneration and Transport arising from its
Value for Money Review of Leisure.
BACKGROUND
2.
The Policy Commission for Economy, Tourism,
Regeneration and Transport reached a critical point in the completion of its
Value For Money review of Leisure Services and decided to undertake a ‘gateway’
review of its findings to date. As a
consequence it has prepared the attached Blue Paper for the consideration of
the Cabinet. It considers that the
views of the Cabinet are necessary before (or if) it continues with any further
work on the study.
3.
In completing its work to date the Commission has been
provided with independent advice from specialist leisure consultants. In order to make the most effective use of
time available the review has also begun the early stages of the procurement of
private sector companies interested in running the Council’s leisure facilities. This involved the receipt of expressions of
interest and completion of pre-qualification questionnaires (PQQs) from such
companies. Fourteen companies expressed
an interest and of these seven returned PQQs.
4.
One of the key pieces of work undertaken by the
consultants was the development of a target operating budget (shadow bid) for
the leisure facilities if they were to be operated by the private sector. This budget was to serve as a benchmark to
judge any potential tenders against. It
showed an annual saving of £116,500 on the Council’s costs of running the
facilities (based on 2005/06 figures).
5.
In producing the shadow bid, the consultants made the
assumption that there would be minimal financial risk to the contractor from
the existing state of repair of the leisure facilities, especially in relation
to the fabric of the building and condition of plant and equipment.
6.
In order to make an assessment of the level of this
risk, condition surveys of the leisure facilities were commissioned. These surveys identified a significant
underinvestment in planned preventative maintenance over many years resulting
in a repairs backlog of £1.7m. These
repairs are those that would be necessary to put the buildings into the
conditions assumed in the shadow bid.
The average annual cost (over 10 years) of addressing this repairs
backlog through prudential borrowing would be £212,000.
7.
Therefore, on the basis of the assumptions made and
financial calculations, the operation of these facilities by the private sector
could potentially cost the Council an additional £95,500 per annum for the next
10 years and not realise an overall saving to the revenue budget for 18 years
(all other things being equal).
8.
In the light of this knowledge, the Commission has
taken a view that before the Council considers committing to expenditure to
overcome this repairs backlog, it needs to satisfy itself that it has the right
portfolio of leisure facilities to meet the current and future needs of the
Island’s community. Any such review
should take into account not only the Council’s direct leisure provision, but
also that of the private and voluntary sectors.
9.
During the review, it became apparent through the
number of consultation events held, that there is support for the creation of a
single centre of excellence for leisure/indoor sports. Such a development would require significant
levels of investment (public, private or a mixture) and would need to replace
some of the existing leisure provision.
The support for such a development was given further impetus by the
Island Games Association’s successful bid for the 2011 International Island
Games and the Council’s declared intention to bid for preparation camp status
for the 2012 London Olympics.
10.
The potential for such a centre of excellence would
need to be at the heart of any overall review of the Island’s portfolio leisure
facilities.
11.
The investment required in Council-run sports and
leisure facilities, if realised as a product of this review, would not just
provide better buildings and facilities for Islanders and visitors alike. Improved facilities would enable the Council
to offer a wider range of services, promoting physical fitness and well-being
to more people, of all ages. This could
be developed as a series of programmes engaging the public in the Island Games
and using this as inspiration for more general activity programmes. This in turn could build increased levels of
physical activity on-Island (supporting a LAA target) and could secure a
lasting legacy of improved public health on the Island as a result.
CONSULTATION
12.
The VFM Review carried out a series of focus groups
with key stakeholders, as detailed in the attached report.
13.
In addition, the review team liaised closely with the
ETRTC Lead Member and Chairman throughout the process.
FINANCIAL/BUDGET
IMPLICATIONS
14.
The production of a shadow bid has identified that the
operation of the facilities by the private sector could save the Council an
estimated £116,500 pa. In order to
achieve this level of saving, the Council may need to invest £1.7m to upgrade
the facilities at an annual cost of £212,000 for 10 years.
15.
The cost of completing the procurement of a private
sector contractor is estimated to be in the order of £150,000 and is mainly
associated with the completion of legal documentation. This may be recoverable from any savings
over the lifetime of the contract.
16.
A leisure needs analysis and completion of a leisure
facilities plan will cost approximately £50,000 to produce if procured from
external advisors. One-off resources are available to fund this amount.
LEGAL
IMPLICATIONS
17.
The Council has statutory powers to provide a wide
range of leisure provision however the level of provision of leisure services
is at the Council’s own discretion.
18.
The Local Government Act 2000 provides the Council
with the authority to do anything which it feels appropriate to improve the
economic, social or environmental well-being of its area. A review of leisure facilities provision
will enable the Council to plan for a portfolio of facilities that support the
aspirations of the Local Government Act 2000.
19.
Any subsequent decisions to amend the current
portfolio of facilities and methods of management will need to be taken in the
context of relevant HR legislation.
OPTIONS
20.
The Policy Commission discussed a number of options
for recommendation to the Council. Its final
recommendation and the details of each option are given in the attached Blue
Paper. In summary the options are:
(a)
Continue the procurement of a private sector operator
for the leisure facilities.
(b)
Suspend the procurement of a private sector operator
for the leisure facilities.
(c)
Stop the procurement of a private sector operator for
the leisure facilities.
(d)
Undertake a whole Island leisure needs analysis and
produce an Island leisure facilities plan that meets the needs of the Island
community.
(e)
Agree to deliver the management and implementation of
the leisure facilities plan by the most appropriate mechanism (private sector,
not for profit organisation, in-house).
(f)
Support the use of limited invest to save bids by the
Council’s leisure management team to improve the current financial operating
costs of the facilities.
21.
The attached Blue Paper contains a risk analysis for
the options discussed by Policy Commission.
22.
Continuation of the procurement of a private sector
contractor may, on the face of the information presented by the Commission, not
realise any savings to the Council in the operation of these facilities. Indeed it could add to the current operating
costs without bringing about the improvements to the service that the Council
would wish to see.
23.
A fundamental review of the leisure needs of the
Island’s community will enable the Council to target its resources where they
are most needed in either directly providing facilities or enabling their
provision. The review would be likely
to identify the need to rationalise and/or replace facilities, but with the
express intention of improving the quality of the services and facilities, the
range of available leisure opportunities and the value for money they offer to
the Council.
24.
The production of an Island wide leisure review could
be done in-house or with external consultancy advice. The independent role of an external advisor would greatly assist
with the speed of production of such a review.
RECOMMENDATIONS 25.
To approve options (c) to (f) of the report and to
receive a further report on the completion of the leisure needs analysis in
January 2007. |
Appendix 1 - ETRTC Blue
Paper 9 August 2006
Contact
Point : John Metcalfe, Assistant Chief
Executive ' 5661
[email protected]
JOHN METCALFE Assistant Chief Executive |
COUNCILLOR TIM HUNTER-HENDERSON Cabinet Member for the Economy, The Customer, Communications, Leisure and Tourism |