APPENDIX 1
ISLE OF WIGHT COUNCIL
QUARTERLY PERFORMANCE MANAGEMENT REPORT
SELECT COMMITTEE REPORT – SOCIAL SERVICES, HOUSING
& BENEFITS
FOURTH QUARTER – 1ST JANUARY TO 31ST
MARCH 2004
Quarterly Performance Management Report
select committee Social Services, Housing & Benefits
Quarter 4 January – March 2004
Contents
Section 1 : Summary Page 3 - 4
1.1
Performance Summary:
·
Performance Indicators – KPI’s & PSA Targets
1.2
Priority Improvement Areas Page 4
1.3
Best Value Reviews Page 5
Section 2 : Performance
Management & Assessment Page
6
·
Key Achievements for the Quarter Page 7
·
Areas to Watch and action to be taken Page 7
·
Updates on Areas to Watch reported in Q1 – Q2 – Q3 Page 8
·
Performance Management Indicators – KPI’s & PSA Targets Page 9 - 11
Section
3 : Corporate Actions Page 12
Summary
report of those key actions achieved and those that are on-going, as of the 31st March 2004.
Revenue
& Capital Report
SECTION 1 : Summary -
Quarterly Performance Management Report - Q4 (January to March 2004)
Performance
Summary :–
1.1 Performance Indicators
Summary provides information for all of the Performance Indicator
Targets by Portfolio for the past year 2003-04
The
first table presents those Performance Indicators that refer to the Select
Committee. There are 9 indicators:
|
No.
of Indicators |
Target Achieved
|
Target Not Achieved
|
Information Not Provided
|
DELETED
INDICATORS |
KPI Basket Targets Social
Services & Housing |
4 |
0 |
4 |
- |
- |
Public
Service Agreement Targets Social
Services & Housing |
4 |
2 |
2 |
- |
- |
Annual Action Statement
Targets
Social Services & Housing
|
0 |
0 |
0 |
- |
- |
TOTAL |
8 |
2 (25%) |
6 (75%) |
|
|
Table 2 provides a snapshot
of all of the 58 performance indicators and presents these against the relevant
corporate objective.
Corporate Objective
|
No.
of Indicators |
Target Achieved
|
Target Not Achieved
|
Information Not Provided
|
DELETED
INDICATORS |
Improving
health, housing and quality of life for all |
9 |
2 (22%) |
7 (78%) |
0 (0%) |
- |
Encouraging
job creation & prosperity |
5 |
4 (80%) |
1 (20%) |
0 (0%) |
- |
Raising
education standards and promoting lifelong learning |
8 |
6 (75%) |
2 (25%) |
0 (0%) |
- |
Creating
safe & crime-free communities |
8 |
6 (75%) |
2 (25%) |
0 (0%) |
- |
Improving
public transport and the highways infrastructure |
7 |
2 (28.6%) |
3 (42.8%) |
0 (0%) |
2 (28.6%) KPI
19-20 |
Protecting
the Island’s physical environment |
6 |
6 (100%) |
0 (0%) |
0 (0%) |
- |
IWC
Corporate Health |
15 |
7 (46.6%) |
7 (46.6%) |
1 (6.7%) |
- |
TOTAL |
58 |
33 (56.9%) |
22 (37.9%) |
1 (1.7%) |
2 (3.5%) |
Through the CPA process last year, there were a number of service areas that were highlighted as areas for improvement. To progress these areas for improvement and identify support needed from across the Council a framework has been devised beginning with initial briefing sessions to help scope the area for support and improvement. Action Plan summaries will then be produced, monitoring of which will be through this section in the Quarterly Performance Management Report.
·
Homelessness
Continuing
improvements have been made in the area of homelessness. The PSA target for removing families with children
from bed and breakfast has been achieved.
Peer review from Beacon homelessness authorities indicates that many of
the recent improvements have been effective and the service is on track for an
improved rating.
·
Housing Benefits
The
Benefits Fraud Inspectorate have expressed themselves satisfied with the
Councils action plan and response to the inspection report. A number of other
positive factors point to an improving service, including:
· ICT upgrade and a new computer system is now in place (19 January). Two of the three Key Performance Indicators
demonstrate improvement in performance, however all three KPI’s that relate to
the Service area did not achieve the Target for the year 2003-04 (Please refer
to Page 9 KPI’s, 2, 3 & 4)
· Significant improvement in treatment of overpayments has attracted BFI
praise
· BFI performance improvement team will start work shortly
· New management post filled from 1st June (focus on customer
services, training and development)
A combined
improvement plan, incorporating issues from the Best Value review and the work
of the Benefit Fraud Inspectors, is being finalised.
This section of the report shows the progress
and achievements that have been made in each of the Portfolio’s of the
Council. The report records and
demonstrates:
How
are targets judged?
Has the Target been achieved?:
-
will be ‘yes’ if the year end target has been met/achieved. (This applies to most targets, some may work
differently).
-
will be ‘no’ if the target has not been achieved
The comments box can be used by services to explain
data. Some targets compare themselves with the same quarter a year ago to
eliminate effects of seasonality.
Level of performance against previous
quarter:
·
will be ‘lower’ if the level of performance is 10% or more lower
than previous quarter î
Assessment
of Performance for the Year
Compares the actual performance to the Target for year
end:
J Indicates that the target is
achieved or exceeded
L Indicates that the target is
not achieved
Year
end Actual
This figure is expressed as either:
·
the cumulative Total for the
year - (Q1+Q2+Q3+Q4)
·
or, the Average for the year –
(Q1+Q2+Q3+Q4)
divided by 4
KEY
ACHIEVEMENTS QUARTER 4
Portfolio - Social Services & Housing Corporate Objective - Improving health, housing & quality of life |
|
|
|
|
|
|
|
|
|
QUARTER
4 - AREAS TO WATCH
Areas to Watch |
Action taken / to be
taken |
Pressure on and the business processes of
our “front door” services-Children’s Services |
Action plan in place which will form part
of the forthcoming Inspection Action Plan. |
Dealing with young people with challenging
behaviour including those with Attention Deficit Hyperactivity Disorder-Children’s Services |
Services planned to enhance provision in
this area will form part of the forthcoming Inspection Action Plan. |
Occupational therapy-Housing Services |
Need to sign a Section 31 Agreement (to set
up a pooled budget) to enable the integration of Hospital and Social Services
& Housing Occupational Therapists. |
AREAS
TO WATCH – UPDATES FROM THE PREVIOUS QUARTERS
|
AREA TO WATCH |
ACTION TAKEN |
PREVIOUS QUARTERLY UPDATE |
NEW QUARTERLY UPDATE |
Q1 Q2 Q3 Q4 |
The Directorate is
expected to reduce the number of placements made in residential and nursing
homes and support people at home with intensive home care. The difficulty is
the current lack of home care provision-Adult
Services |
The hourly rate we pay
for providers for home care has been increased to try and push up the wages
and attract more people to this area of work. |
Still an area of concern and plans for managing
this are moving forward. Revised commissioning strategy agreed with the
PCT. Tendering process for block locality contracts to start in May 2005. |
Block contracts have been developed with all
homecare providers. There is now an
Admissions Panel in place that meets on a weekly basis. Nursing Homes have agreed a set price for
the next two years, which is a great achievement. |
Q3 Q4 |
Educational Performance
of Looked After Children-Children’s
Services |
Work is in hand to
enhance performance in this regard through the Looked After Children
Education Service; introduction of School Liaison Officer; focus on ensuring
Personal Education Plans in place for all children and targeting support to
individual children, especially at a younger age. There will be an ongoing
review of performance in this area through the Development and Improvement
Statement and the LPSA agreement. |
Improved performance in
completion of PEPS. Reporting of performance to Members LACES working group
more robust. |
Staffing changes in LACES
group have led to some destabilisation and an opportunity to review current
structure |
Q1 Q2 Q3 Q4 |
Key benefits performance
indicators below Government targets-Benefits |
Close performance
monitoring, improved ICT capacity, review of structures, implementation of
Best Value Review and Benefit Fraud
Inspection recommendations (when received) |
Further slippage in ICT
upgrade – now expected up and running in January |
ICT upgrade now complete
and has resulted in improved performance |
Corporate
Priority (Corporate
Plan 2002 to 2005) |
KPI
Description |
Actual 2002 / 3 |
Q1 Apr-Jun 2003 |
Q2 July-Sept 2003 |
Q3 Oct-Dec 2003 |
Q4 Jan-Mar
2004 |
Target for 2003 / 04 |
Performance
assessment for the year Year end
Actual |
Comments |
Performance
against the previous Quarter |
Target
Achieved |
||||||||
Protecting
and providing for vulnerable adults &
children |
1. The number of looked
after children per 10,000 less than 18yrs at end of quarter |
56.7 |
57.6 |
60.9 |
58.4 |
60.9 |
55 |
L Average
= 58.8 |
Small numbers
disproportionately affect percentages. Our LAC figures are
relatively stable compared with national figures |
|
|
è |
è |
è |
No |
||||
Cutting
deprivation & social exclusion |
2. Benefits –
average calendar days this quarter to process a new housing benefits claim |
64.9 |
78.6 |
75.73 |
69.9 days |
59.5 days |
36 |
L Average
= 70.9 |
New computer system is now operational from the 19
January. Increased sickness levels
experienced during March. |
|
|
è |
è |
ì |
No |
||||
3. Benefits - %
of renewal housing benefit claims this quarter processed on time |
78.53% |
67.96% |
71.13% |
71.8% |
79.44% |
83% |
L Average
= 72.6% |
New
computer system is now operational from the 19 January. Increased sickness levels experienced
during March. |
|
|
|
è |
è |
ì |
No |
||||
4. Benefits - %
of new housing benefit claims this quarter determined within 14 days of
receipt of all necessary information |
N/a |
59.04% |
58.37% |
61.8% |
60.71% |
64% |
L Average
= 60% |
New
computer system is now operational
from the 19 January. Increased
sickness levels experienced during March. Year
end average = 60% |
|
|
|
è |
è |
è |
No |
PSA TARGETS
Corporate Objective |
CPSA Target |
PSA Target Summary |
Q1 Data |
Q2 Data |
Q3 Data |
Q4 Data |
Year Target |
Comments |
||||||
Target Achieved |
||||||||||||||
Improving
health, housing & quality of life for all
|
|
Reduce
the number of families with children & other households in B&B
accommodation |
56 |
58 |
38 |
21 |
26 |
Target
has been achieved and good progress
made in reducing the numbers of families in B&B accommodation |
||||||
Yes |
||||||||||||||
5. Social Services |
Rehabilitation
care for the older people & a reduction in delay of discharges from
hospital |
D41- 37.56 C28 – 5.8 C26 – 67.3 |
D41-12 C28-7.9 C26-144 |
D41 –12.69 C28 – 8.9 C26 - 113 |
D41 – 0 C28 – 9.1 C26 - 107 |
D41 – 7 C28 – 7.36 C26 - 96 |
Availability of home
care a problem but a Strategy is in place to improve. Although the situation remains a risk,
incremental progress has been made in reducing admissions and increasing
intensive homecare. Transformational
progress from year 2005-06 from the restructuring of home care and the
introduction of additional extra care & sheltered housing projects. D41 = Delayed transfers
of care from hospital this part of the target has been over-achieved. No delayed discharges were reported in
Q4, testimony to the hard and dedicated work of the service areas involved. C28 = Intensive Home
Care – improvements in the levels of this provision has reached a new
high. As a PAF figure, this is
captured in the September HH1 return sample week and so none of the
subsequent improvements will count in the final result C26 = Admission of
supported residents aged 65 yrs or over, to residential care/nursing
care. The estimated population over
65 years is increasing & the average age on admission is rising. |
|||||||
No Only the first part of
this PSA target has been achieved |
Corporate Objective |
CPSA Target |
PSA Target Summary |
Q1 Data |
Q2 Data |
Q3 Data |
Q4 Data |
Year Target |
Comments |
||||||||
Target Achieved |
||||||||||||||||
Raising
Education Standards & Promoting Lifelong Learning |
6.
Social Services |
A4-the
% of those young people who were looked after on 1 April in their 17th
year who were engaged in education, training or employment at the age of 19 QP8-the
proportion of looked after children obtaining 5 GCSEs at Grades A*-C- during
the most recent school year as a ratio of the proportion of all children in
the local authority achieving this standard |
A4– 64.7% QP8 - 18.8% |
A4 – 65% QP8 -14% |
A4–53% QP8– 0% |
A4–52% QP8–33% |
A4–57% QP8–46% |
QP8 – this years target equates with the non stretch
target which can be expected due to the short time that the teacher has been
in post. We expect to achieve the
target in Q2 2004-05. The risks
associated with the volatility of the cohort group and the sudden school
exclusions can significantly impact on the figure. |
||||||||
No |
||||||||||||||||
Improving health, housing
& quality of life for all |
7. Social Services |
Increase the number of young people who are getting
treatment for drug or alcohol dependency (Drug Action Team) |
Information not supplied |
440 persons = total Q1&Q2 |
201 persons |
48 persons |
852 by 31 March 2006 |
The project achieved – 689 young people receiving
treatment. The project has now
achieved 81% of its project life target (31st March 2006) |
||||||||
Yes |
||||||||||||||||
SECTION 3 : CORPORATE ACTIONS
Significant
progress has been made on the Corporate Actions, which includes the
Comprehensive Performance Assessment (CPA) Improvement Plan, Annual Action
Statement Actions and Actions in response to the District Audit Letter. This section of the Report records the highlights
of some of the key actions that have been achieved by the 31st March
2004 and those that are on-going through 2004-05. A full listing of all of the Corporate Actions that are on-going
and to be carried forward through 2004-05 will be available for viewing on the
Council’s Intranet at the following link: direction/performance/quarterly
performance management reports/
CPA Improvement Plan
Actions – None identified for Social Services, Housing & Benefits
Annual Action
Statement Actions by Directorate
Social Services & Housing
Achievements
Not achieved by the 31st
March and to be carried forward into 2004-05
Actions in response
to the District Audit Letter – None identified for Social Services, Housing
& Benefits
SECTION 4 : FINANCE REPORT
Social Services & Housing
|
|
Social Services |
Cost pressures include £148,000 from the loss of
Promoting Independence grant last year which is still an issue. The Independent Living Resources Centres
are important in reducing bed blocking and promoting independence. A savings requirement of £44,000 is yet to
be formally identified. However, due
to savings elsewhere in the service area, namely Children’s Services, at
present it is projected that there will be a net service under spend of
£5,000. The largest unknown item at present is the level of residential care
client contributions due to changes in the benefit system from October 03
relating to Pension Credit and Residential Allowance which has resulted in
financial assessments being undertaken for affected clients. It is anticipated that the full impact of
this on the budget for residential care will not be fully evident until the
final adjustments for the financial year have been made. |
Housing |
Current net projected overspend of £158,000. This
is mainly due to the Homelessness budget and spending on leasing which should
result in lower B&B spending. A
lower level of net spending as a result of this strategy should be evident in
the next financial year. |
Housing Benefits |
Housing Benefit expenditure is currently in line
with budget expectations for the year. Income in the form of a Government
subsidy is received monthly on account, and is based on previous year’s
figures until the external audit is complete. The final settlement is
received after the year end, but the appropriate adjustments are taken into
account in closing the accounts for the year |
4.2 : Capital Expenditure
A
list of capital spending against budget in 2003-04 on a summarised version for
the services provided by this Select Committee is available by clicking on the
following link:
Fuller
details, on a project by project basis, are also available on the Financial
Services intranet pages.