RESPONSIBLE BODY Policy
Commission for Business and Infrastructure |
|
PROJECT NAME Island Ports Sustainability Study |
REFERENCE NUMBER E1/06 |
1. PURPOSE OF ENQUIRY AND PROPOSED OUTCOMES 1.1
To recommend
to Cabinet how the Isle of Wight Council can work with stakeholders to
sustain and develop 1.2
To provide
Island residents with sustainable cross |
|
2. RECOMMENDATIONS The Council will: 2.1.
Encourage
investment in existing terminals which will optimise their potential,
efficiency and reduce the impact of peak flow congestion on the surrounding
highway network and community. Consideration will need to be given to the
visual impacts of any terminal development which are the gateways to the 2.2.
Seek the
co-operation of ferry service providers to ensure that where additional route
carrying capacity is proposed the full consideration of shoreside impacts and
provision of required new or upgraded infrastructure form part of the
proposals. 2.3.
Support the
continuation of choice of routes and methods of crossing the Solent to ensure
flexibility and reduce the risk of disruption to service and impact on 2.4.
In principle
support opportunities for additional or alternative port facilities where
these will secure the longer term sustainability of ferry services to the
Island subject to provision (and ongoing maintenance) of adequate supporting
infrastructure. 2.5.
Recognise the
environmental sensitivity of the 2.6.
Ensure that
any additional scheduled ferry services are provided on an all year round
basis as a service to the 2.7.
Encourage
initiatives to spread the demand for ferry crossings more evenly through the
seasons, week and day to make better use of existing and future capacity
within the ferry services. 2.8.
Prepare
contingency plans to deal with any major disruption to cross 2.9.
Work with the
ferry operators to improve access to up to date travel information including
web site alerts and advance variable message signing. 2.10.
Encourage
proposals to promote park and ride, bus services, taxis, cycling or walking
to passenger terminals to reduce the impact of car parking and car traffic in
the vicinity of terminals. 2.11.
Promote the
establishment of a Quality Freight Partnership and to examine in greater
detail the issues and options relating to dispersal of trailer parking and
storage and the transportation of construction and building materials. |
|
This body of work and the above recommendations were
agreed and accepted by Members of the Policy Commission for Economy, Tourism,
Regeneration and Transport on xxxx
2007. |
|
3. BACKGROUND TO ENQUIRY THE NATIONAL CONTEXT 3.1
The Isle of Wight is the only inhabited Island in THE LOCAL
CONTEXT 3.2
As an Island the Isle of Wight relies on cross Solent transport
connections for the movement of all imported and exported goods and personal
travel and are a major impact factor to the social- economic development and
economic prosperity of the 3.3
Concerns have been expressed that the growing demand for cross Solent
transport of goods and passengers are placing strains on the 3.4
The emerging Island Plan and the second Local Transport Plan recognise
that transport networks and infrastructure are of critical importance to the 3.5
A common issue for any uses and services located on the coast is that
of operating in a dynamic environment and in particular ensuring that port
and ferry facilities are capable of being upgraded to operationally take
account of increasing rates of sea level rise and flood risk to essential
elements of the |
|
4. CONSULTATION 4.1
Key stakeholders were invited to present
evidence to the Enquiry either in person directly to the Commission,
informally, or in writing. 4.2
A formal presentation was made to the
Commission by consultants MVA for Planning Services. This presentation was of
a report entitled ‘Cross Solent Movement Study’ dated June 2006, and was
published and available as the basis for wider consultation with other
Stakeholders. Subsequent presentations were made to the Commission by The
Isle of Wight Economic Partnership, Chamber of Commerce, The Federation of
Small Businesses, The Quality Transport Partnership and Steve Porter
Transport Group. 4.3
Informal presentations were given by and
discussions held with Wightlink, Red Funnel, Hovertravel, Natural England
(formerly English Nature), 4.4
Written representations were received from
Cowes Harbour Commissioners and W A Horne via Andrew Turner MP. 4.5
An
article and questionnaire were widely circulated in the |
|
|
|
6.2
However the Council could seek the reduction
of impacts of ferry traffic on areas surrounding existing terminals in the
short term by encouraging the ferry companies to upgrade and improve existing marshalling areas sooner rather
than later. Options are available at East Cowes to replace the current split
marshalling area with a single marshalling area as part of the 6.3 Each of the vehicle ferry terminals has a finite capacity based on the size and number of ferries capable of being serviced and the capacity to assemble and marshal vehicle loads. If demands on the services continue to grow then routes will need to relocate to provide all the infrastructure to create the greater capacity or stagnate. For the longer term therefore the Council should promote the relocation of existing terminals and services to new facilities with appropriate level of supporting infrastructure and/or the provision of additional terminals. The Council will be in a position to apply conditions to any planning consents granted for new or expanded terminals and to ensure that adequate off site infrastructure is provided. 6.4 It has been suggested that the creation of a new multi berth terminal which would be available for current ferry operators to relocate to is the way to resolve the problems at existing terminals and cater for future growth. The provision of new larger shared terminal facilities for the consolidation of ferry services into one focussed location is one potential option. 6.5
An alternative proposition is to promote and
encourage the provision of additional terminal location(s) together with
additional ferry services to spread the load of peak capacity and future
predicted growth and introduce additional competition and choice into cross In relation to the introduction of additional services these could take two forms :- 6.6 One is the provision of additional seasonal services just to address the peak capacity problem. The existing services have sufficient capacity, particularly if marshalling area improvements above are enacted, other than at peak times or during operational problems. The concern with the introduction of services during only busy periods (of the season or day) or for the easiest traffic to deal with (i.e. cars) is that the costs of providing the service of ferries in quiet times which alone would not be economic is in effect subsidised by the times when the ferries are full. Specialist peak services could lead to reduction in quiet time services and/or the need to recoup costs by higher fares. 6.7
The alternative which is probably preferable
is to seek to ensure that any new terminals and services are for all year
services not just for peaks which will ensure that new services truly add to
the ferry service to the 6.8
The
issue of trailer storage other than when assembled for immediate embarkation
takes capacity at existing terminals but remote storage requires additional
handling and costs. Options suggested include a centralised trailer handling
facility for the 7.RISK ASSESSMENT – IMPACT x
LIKELIHOOD For details of risk scoring and matrix, see Appendix 2. Recommendation in paragraph 2.2
- Failure to secure co-operation of service providers could result in the
need for additional expenditure from the Council to deal with highway and
infrastructure capacity. Risk Score 2 x 2 = 5 Recommendation in paragraph 2.9
- Risk of inaccurate information on variable message signing or web sites,
safety, highway compliance, capital and revenue costs and cost of operation
of system. Risk Score 2 x 3 = 8 The rest of the recommendations represent a low risk, and are not likely to represent a financial risk to the Council. |
|
Internal ·
IWC. Notes of evidence and presentation from MVA -
Policy Commission for Economy, Tourism, Regeneration & Transport. ·
IWC. Ports
sustainability study stakeholder meeting – Andrew Willson (Chief Executive,
Wightlink), and John Burrows (Operations General Manager, Wightlink). ·
IWC. Ports
sustainability study stakeholder meeting – Tom Docherty (Managing Director,
Red Funnel), Colin Hetherington (Commercial Director, Red Funnel) and Richard
Scott (Finance Director, Red Funnel). ·
IWC. Ports
sustainability study stakeholder meeting – Richard Box (Chief Executive,
Hovertravel). ·
IWC. Notes of evidence and presentation by the ·
IWC. Notes of evidence and presentation by Steve Porter
of the Steve Porter Transport Group - Policy Commission for Economy, Tourism,
Regeneration & Transport. ·
IWC. Ports
sustainability study stakeholder meeting – Chris Lisher ( ·
IWC. Ports sustainability
study stakeholder meeting – Tony Cosgrove (Government Team, Natural ·
IWC. Notes of evidence - Policy Commission for Economy,
Tourism, Regeneration & Transport.
·
IWC. Ports
sustainability study stakeholder meeting – Pete Brunskill (Transport Policy
Team Leader, Southampton City Council), Peter Murnaghan (Transport Policy,
Hampshire County Council), and Captain Rupert Taylor (Harbour Master, ·
IWC. Notes of evidence and presentation from Norman
Arnold, Chairman of the Isle of Wight Branch of the Federation of Small
Businesses - Policy Commission for Economy, Tourism, Regeneration &
Transport. ·
IWC. Notes of evidence of public consultation findings
and presentation by Cllr Hancock - Policy Commission for Economy, Tourism,
Regeneration & Transport. ·
IWC. |
|
Prepared by: Cllr
Charles Hancock, Lead Member; Mr Dave Moore, Planning Projects Team Leader;
Miss Date |
APPENDIX 1
CROSS
Updated Table 2.2 Annual Two-way Cross
Route |
Passengers (in millions) |
|||||||
|
By Foot |
Car |
Coach |
Total |
||||
(Hovertravel) |
0.79 |
19% |
- |
- |
- |
- |
0.79 |
9% |
(Fastcat) |
1.44 |
34% |
- |
- |
- |
- |
1.44 |
16% |
|
0.12 |
3% |
2.07 |
45% |
0.43 |
84% |
2.62 |
28% |
Southampton – |
0.23 |
6% |
1.62 |
35% |
- |
- |
1.85 |
20% |
Southampton – |
1.23 |
29 |
- |
- |
- |
- |
1.23 |
13% |
Lymington – |
0.38 |
9% |
0.89 |
19% |
0.08 |
16% |
1.35 |
14% |
TOTAL |
4.19 |
|
4.58 |
|
0.51 |
|
9.28 |
|
Updated Table
2.3 Annual Two-way Cross
|
Cars (millions) |
Coach (‘000) |
Commercial Vehicles (‘000) |
|||
Southampton
– |
0.55 |
32% |
5.7 |
(24%) |
96.4 |
(35%) |
(Wightlink) |
0.83 |
48% |
15.6 |
(65%) |
141.1 |
(51%) |
Lymington
– Wightlink |
0.36 |
21% |
2.7 |
(12%) |
39.8 |
(14%) |
Total Vehicles |
1.74 |
|
24.00 |
|
277.3 |
|
APPENDIX 2
Risk Prioritisation Matrix
Likelihood/Probability |
4 V. Likely |
7 |
11 |
14 |
16 |
3 Likely |
4 |
8 |
12 |
15 |
|
2 Unlikely |
2 |
5 |
9 |
13 |
|
1 Remote |
1 |
3 |
6 |
10 |
|
|
Scale |
1 Low |
2 Medium |
3 High |
4 Major |
Impact/Severity
15 - 16 |
Red |
V. high risk |
12 - 14 |
Red |
High risk |
7 - 11 |
Amber |
Medium risk |
1 - 6 |
Green |
Low risk |
Likelihood/Probability
Criteria
FACTOR |
SCALE |
THREATS - DESCRIPTION |
INDICATORS |
Very
likely |
4 |
More than 75% chance of
occurrence |
Regular occurrence
Circumstances frequently encountered -daily/weekly/monthly |
Likely |
3
|
40% - 75% chance of occurrence |
Likely to
happen at some point within the next 1-2 years Circumstances occasionally
encountered (few times a year) |
Unlikely |
2 |
10% - 40% chance of occurrence |
Only
likely to happen 3 or more years |
Remote |
1 |
Less than 10% chance of occurrence |
Has
happened rarely/never before |
Impact/Severity Criteria
Factor |
Scale |
Effect on Service |
Embarrassment/reputation |
Personal Safety |
Personal privacy
infringement |
Failure to provide
statutory duties/meet legal obligations |
Financial |
Effect on Project
Objectives/ Schedule Deadlines |
Major |
4 |
Major loss of service,
including several important areas of service and /or protracted period. Service Disruption 5+ Days |
Adverse and persistent
national media coverage Adverse central government
response, involving (threat of) removal of delegated powers Officer(s) and/or Members
forced to resign |
Death of an individual or
several people |
All personal details
compromised/ revealed |
Litigation/claims/fines from Departmental
£250k + Corporate £500k + |
Costing over £500,000 Up to 75% of Budget |
Complete failure of
project/ extreme delay – 3 months or more |
High
|
3 |
Complete loss of an
important service area for a short period Major effect to services in
one or more areas for a period of weeks Service Disruption 3-5 Days |
Adverse publicity in
professional/municipal press, affecting perception/standing in
professional/local government community Adverse local publicity of
a major and persistent nature |
Major injury to an
individual or several people |
Many individual personal
details compromised/ revealed |
Litigation/claims/fines from Departmental £50k to £125k Corporate £100k to £250k |
Costing between £50,000 and
£500,000 Up to 50% of Budget |
Significant impact on
project or most of expected benefits fail/ major delay – 2-3 months |
Medium
|
2 |
Major effect to an
important service area for a short period Adverse effect to services
in one or more areas for a period of weeks Service Disruption 2-3 Days |
Adverse local publicity
/local public opinion aware Statutory prosecution of a
non-serious nature |
Severe injury to an
individual or several people |
Some individual personal
details compromised/ revealed |
Litigation/claims/fines from Departmental
£25k to £50k Corporate £50k to £100k |
Costing between £5,000 and
£50,000 Up to 25% of Budget |
Adverse effect on project/
significant slippage – 3 weeks–2
months |
Low |
1 |
Brief disruption of
important service area Significant effect to non-crucial service area Service Disruption 1Day |
Contained within
section/Unit or Directorate Complaint from
individual/small group, of arguable merit |
Minor injury or discomfort to an individual or
several people |
Isolated individual personal detail compromised/
revealed |
Litigation/claims/fines from Departmental
£12k to £25k Corporate £25k to £50k |
Costing less than £5,000 Up to 10% of Budget |
Minimal impact to project/ slight delay less than
2 weeks |