CAPITAL EXPENDITURE SUMMARY as at end of January 2005
Description Revised Expenditure Commitment Total Budget  
  Budget     Spend/Committed Left  
Capitalised Salaries - Property Services 234,736 247,300 0 247,300 -12,564 Anticipated Capitalised Salaries 2004-05
Capital Strategy 29,156 20,064 12,751 32,815 -3,659 Expenditure relates to investment in ICT systems to further progress the Capital Strategy and Asset Management Plan.
Management of Asbestos 58,151 27,796 5,125 32,921 25,230 Scheme requires on-going survey of all Council owned property, now in progress
Disability Discrimination Act 172,082 71,110 26,489 97,599 74,483 Expenditure on schemes progressing in accordance to plan
Upgrade of Hot & Cold water supplies 40,521 13,483 16,970 30,453 10,068 Residential Homes - upgrades
Planned Maintenance 147,882 102,917 24,752 127,669 20,213 Expenditure on schemes progressing in accordance to plan
Upgrade of Electrical Supply to County Hall 213,165 236,491 900 237,391 -24,226 Work now substantially complete
Accommodation Review - Wight Leisure 0 6,423 16,115 22,538 -22,538 To be funded under the Accommodation Review
Accommodation Review - Training Centre/ Wightcare 0 958 0 958 -958 To be funded under the Accommodation Review
Accommodation Review - Library Headquarters 0 9,305 0 9,305 -9,305 To be funded under the Accommodation Review
Accommodation Review - Enterprise House 0 227,835 23,024 250,859 -250,859 relocation of engineering services
Accommodation Review - Jubilee Stores 0 8,417 60,524 68,941 -68,941 relocation of consumer protection
Accommodation Review - Rights of Way 0 7,277 0 7,277 -7,277 To be funded under the Accommodation Review
Accommodation Review - Vectis Building 0 3,894 0 3,894 -3,894 To be funded under the Accommodation Review
Accommodation Review - St Nicholas 0 5,416 0 5,416 -5,416 To be funded under the Accommodation Review
Newport Harbour Redevelopment 0 78,972 0 78,972 -78,972 Expenditure to be offset against future capital receipt
Refurbishment of Bungalow (Surestart) 9,104 3,253 0 3,253 5,851 Funded by grant based on expenditure
Acquisition of Land at Pan 200,000 200,000 0 200,000 0 First of four annual payments
Ventnor Tennis Club 245,860 0 685 685 245,175 expenditure to occur
Total for Report 1,350,657 1,270,911 187,335 1,458,246 -107,589