PAPER D

 

 

RESOURCES SELECT COMMITTEE – 23 JANUARY 2003

 

CONNECTING WITH THE PUBLIC BEST VALUE REVIEW

 

REPORT OF MR ANDY SUTTON -  LEAD MEMBER FOR THE REVIEW

 

 

REASON FOR SELECT COMMITTEE CONSIDERATION

 

This report has been submitted at the request of the Appraisal Group for the Review, prior to the paper “Great Access to Great Services” being presented to the Executive.

 

ACTION REQUIRED BY THE SELECT COMMITTEE

 

1.         That the Select Committee support the work being undertaken towards a future vision for public access.

 

2.         That the Select Committee recommend to the Executive the delay of phases 2 and 3 of the review

BACKGROUND

 

1. The work on the first phase of the review, how we deal with the public when they come to us, has now largely been completed. The attached paper “Organisational Development - Great Access to Great Services” contains a high-level summary of the work, with a vision of how the Council could handle public access in the future. This paper is to be presented to the Executive at the end of January and the to full Council in February.

 

The work involved in delivering that vision is closely linked with other on-going projects such as Customer Relationship Management, Implementing Electronic Government, and the accommodation review.

 

It is proposed to bring these pieces of work together under a single Programme Board of Senior Officers and Members, to drive the agenda forward.

 

2. Phase 2 of the review is to cover Information and Communication. It is proposed to delay that part of the review until 6 months after the forthcoming appointment of a Communications and PR manager. This will give the appointee time to implement some of the findings of the review so far, such as the need for an audit of the current provision of communications and the development of a communications strategy.

 

3. Phase 3 of the review is to cover Consultation. Similar to point 2 above, an audit of current consultation, to include how much use we make of it, how much it costs, and how we can share it across the authority, will help to develop a consultation strategy (which would also have strong links with the communications strategy). It is proposed to also delay this phase of the review to allow that work to be completed.

 

If the above proposals are adopted it would mean re-launching phases 2 and 3 in the early Autumn.

 

Any issues which have arisen from the review, which can be implemented immediately and do not require further development as under points 1 to 3 above, will be presented to the Committee at a later date in the form of a proposed action plan.

 


FINANCIAL, LEGAL, CRIME AND DISORDER IMPLICATIONS

 

There are no such implications in the above proposals.

 

APPENDICES ATTACHED

 

Organisational Development - Great Access to Great Services

 

BACKGROUND PAPERS USED IN THE PREPARATION OF THIS REPORT

 

Notes from the Best Value Appraisal Group for Connecting with the Public 19th December 2003

 

 

Contact Point : Don Roe BV Review Unit   823687   [email protected]

 

 

MR A SUTTON

Lead Member for the Review