PAPER C

 

Committee:     RESOURCES SELECT COMMITTEE

 

Date:               20 DECEMBER 2002

 

Title:                CORPORATE POLICY & COMMUNICATIONS –

REORGANISATION & DRAFT SERVICE IMPROVEMENT PLAN FOR 2003/4

 

REPORT OF THE STRATEGIC DIRECTOR OF CORPORATE AND ENVIRONMENT SERVICES

 

 

SUMMARY / PURPOSE :

This report outlines changes to the structure and organisation of the Corporate Policy & Communications Unit together with details of the draft Service Improvement Plan for 2003/4.

 

BACKGROUND

As part of the re-structuring of senior management within the Council, a new Corporate Policy & Communications Unit has been created. This has brought together the following services :

 

·         Corporate Policy

·         Press & PR

·         Graphic Design

·         Economic Development

·         LA21

·         Help Centres

 

In June 2002 a new Head of Service was appointed. This appointment coincided with development of a Corporate Plan for the Council and with commencement of the Government’s new Comprehensive Performance Assessment (CPA) inspection process. Both activities have highlighted the need to re-focus the organisation of the corporate support functions within the authority.

 

The Corporate Policy & Communications Unit has, accordingly, been re-organised into 5 teams to provide a better match with the Council’s new corporate agenda :

 

  1. Corporate Policy

Bringing members of the previous Policy Team together with economic development and LA21 staff, the new team provides a generic pool of policy specialists. Key functions of the team include responsibility for the Corporate Plan, performance management, economic development, LA21 and public health, research & information, complaints, etc.

 

The team manager is Tony Geeson.

 

  1. Communications & PR

Bringing together the Press & PR and Graphics services, the new team provides the basis for a stronger corporate focus on communications activities. Key functions of the team include responsibility for external and internal communications, Wight Insight, graphic design, corporate events, etc.

 

The team manager position is currently out to advert.

  1. Community Partnerships

This is a new team which aims to bring an improved focus to customer services and external partnership activities. It brings together responsibility for the Council Help Centres, liaison with external partnerships (including the Island Futures partnership) and social inclusion and equalities issues.

The team manager is Sue Chilton.

 

  1. Crime & Disorder

The team is responsible for management of the Crime & Disorder Partnership on the Island and is staffed by Council employees and secondees from other agencies.

 

The team manager is Niki Haytack.

 

  1. Office Support

In order to provide effective administrative support to the Unit, a new team has been created combining the administrative resources of the previous Policy and Economic Development teams.

 

These organisational changes have been discussed and agreed by the Vacancy Panel

 

DRAFT SERVICE IMPROVEMENT PLAN 2003/4

With the creation of the new Unit, appointment of the new Head of Service and subsequent internal reorganisation of the team, the focus of effort in the current year has been on the Corporate Plan and CPA inspection. These two activities have shaped the Service Plan priorities for 2003/4. 

 

Key achievements to date over the current year include :

 

 

Disappointments over the year to date include :

 

 

Attached to this report (Annex 1), is a summary of the Service Improvement Plan for 2003/4; this is designed in the new format agreed by members for Service Plans. Priorities for service improvement are set out for each of the new teams within the Unit. Member attention is particularly drawn to the following :

 

 

1.                  Corporate Policy Team

Particular priorities include :

 

·         development of a corporate performance management framework

·         co-ordination of delivery of Corporate Plan and Annual Action Statement (including support for key corporate initiatives)

·         development of an external funding service

·         on-going support for economic development and the Isle of Wight Economic Partnership

·         development of an action plan to deliver the Renewable Energy Strategy

·         development of a Green Awards scheme

·         delivery of the Public Service Agreement

 

2.                  Communications & PR Team

Particular priorities include :

 

·         development of a Communications Strategy to improve both internal and external communications

·         production of quarterly media monitoring reports

·         development of a corporate events programme

·         improvements to Wight Insight (including tendering for print production and securing a sponsorship deal)

 

3.         Community Partnerships Team

Particular priorities include :

 

·         development of a Community Partnerships & Consultation strategy

·         development of an Equalities scheme

·         development of an Action Plan for future roll-out of Help Centres and improved customer services

·         development of an Action Plan for delivery of the Social Inclusion Strategy

·         development of an Action Plan for the Island Futures partnership

·         development of a Voluntary Sector compact

 

3.                  Crime & Disorder Team

Particular priorities include :

 

·         implementation of improved ASBO service

·         implementation of improved system for reporting of racist attacks

·         improved mainstreaming of Section 17 duties throughout the Council

·         delivery of the Island Safe and Crimebeat programmes

·         improved architectural liaison service

 

It should be noted that Annex 1 outlines priorities for service improvement only ie. it is not an exhaustive list of all team activities.

 

Performance measures and targets will be established for all proposed activities.

 

Members are invited to comment upon the draft Service Improvement Plan. Areas for enquiry may include :

 

 

FINANCIAL IMPLICATIONS

Financial implications will be assessed during finalisation of the draft Plan.

 

RECOMMENDATIONS

That the Committee :

 

Consider and comment upon the draft Service Improvement Plan for 2003/4

 

BACKGROUND PAPERS

Corporate Plan, 2002/5

CPA Corporate Assessment, 2002

Best Value Performance Plan, 2001/02

 

Contact point : John Bentley, Head of Corporate Policy & Communications

                          Tel 823346

 

 

MIKE FISHER

Head of Paid Service

 

 

 

 

 


Task

 

 


A. Corporate Policy

 

Develop corporate performance management framework.

 

Co-ordinate delivery of CPA Improvement Plan

 

Co-ordinate development and delivery of Annual Action Statement

 

Establish External Funding service

 

 

 

Achieve Investors in People recognition for whole Unit

 

 

 

Target Date

 

 

 

April

03

 

 

 

Full year

 

 

 

Full year

 

 

 

 

April

03

 

 

 

Dec

03

Outcome

 

 

 

 

Council-wide framework in place

 

 

Satisfactory report from Audit Commission

 

Achievement of Corporate Plan aims

 

Maximising the attraction of external funding

 

Improved staff management

Responsible officer

 

 

 

TG

 

 

 

 

JB

 

 

 

 

JB

 

 

 

TG

 

 

 

 

TG

Dependencies

 

 

 

 

Members, Directors, and Heads of Service support

 

 

 

Members, Directors, and Heads of Service support

 

 

 

Members, Directors, and Heads of Service support

 

 

Directors, and Heads of Service support

 

 

 

Staff time

Key Objectives to be achieved

 

 

 

Excellence in service delivery

 

 

 

Excellence in service delivery

 

 

 

Excellence in service delivery

 

 

Excellence in service delivery

 

 

 

Excellence in service delivery

Task

Target Date

Outcome

Responsible Officer

Dependencies

Key Objectives to be achieved

 

 

Deliver Economic Development BV Improvement Plan

 

Deliver Partnership Review Improvement Plan

 

Deliver BVPP Review Improvement Plan

 

 

Develop Action Plan for Renewable Energy Strategy

 

Establish Green Awards scheme

 

 

 

 

 

 

March

04

 

 

March

04

 

 

March

04

 

 

April

04

 

 

June

04

Compliance with Action Plan

 

Compliance with Action Plan

 

Compliance with Action Plan

 

Achievement of Strategy

 

 

Support delivery of LA21 strategy

 

 

TG

 

 

 

TG

 

 

 

TG

 

 

 

TG

 

 

 

TG

IWEP support

 

 

 

IWEP support

 

 

 

Directors & Heads of Service support

 

 

Directors, Heads of Service & partner support

 

 

Partner support

 

 

 

 

Excellence in service delivery

 

 

Excellence in service delivery

 

 

Excellence in service delivery

 

 

Protecting the Island’s natural environment

 

 

Protecting the Island’s natural environment

 

 

Task

Target Date

Outcome

Responsible Officer

Dependencies

Key Objectives to be achieved

Co-ordinate delivery of PSA

 

Develop corporate research and information service

 

Co-ordinate work for Peer Group review

 

 

B. Communications and PR

 

Develop Communication and PR strategy

 

Develop internal communications plan

 

 

Wight Insight

·  Tender for printing

·  Secure                    sponsorship

On-going

 

July

03

 

 

Sept

03

 

 

 

 

 

July

03

 

 

April

03

 

 

April 03

 

Achievement of targets

 

Improved information service

 

Maintain improvement momentum

 

 

 

 

Improved communications

 

 

Improved internal communications

 

Improved value for money

 

TG

 

 

TG

 

 

 

TG

 

 

 

 

 

 

New Manager

 

 

BT

 

 

 

SW/DH

Director & Heads of Service support

 

Staff time

 

 

 

Director & Heads of Service support

 

 

 

 

 

Director & Heads of Service support

 

 

Director & Heads of Service support

 

 

Staff time

Excellence in service delivery

 

Excellence in service delivery

 

 

Excellence in service delivery

 

 

 

 

 

Improved community focus

 

 

Improved community focus

 

 

Improved community focus

 

Task

Target Date

Outcome

Responsible Officer

Dependencies

Key Objectives to be achieved

Produce quarterly media monitoring reports

 

 

 

Develop corporate events programme

 

Review press liaison arrangements

 

 

Review graphic design service

 

 

 

 

 

 

 

 

Quarterly

 

 

 

 

 

April 03

 

 

Sept 03

 

 

Sept 03

Improved awareness of impact of communications service

 

Improved service

 

 

Improved service

 

 

Improved service

CL

 

 

 

 

 

BT

 

 

New manager

 

 

New manager

 

Staff time

 

 

 

 

 

Director & Heads of Service support

 

Director & Heads of Service support

 

 

Director & Heads of Service support

Improved community focus

 

 

 

 

Improved community focus

 

Improved community focus

 

 

Excellence in service delivery

 

 

 

 

 

Task

Target Date

Outcome

Responsible Officer

Dependencies

Key Objectives to be achieved

C.Community Partnerships

 

Develop Community Partnerships and Consultation Strategy

 

Development of Equalities scheme

 

 

Action Plan for future development of Help Centres

 

Action Plan for delivery of Social Inclusion Strategy

 

 

 

 

 

 

 

May

03

 

 

 

April

03

 

 

April

03

 

June

03

 

 

 

Framework for future activities

 

 

 

Compliance with CRE requirements

 

Improved public service/dialogue

 

 

Improved service delivery

 

 

 

SC

 

 

 

 

SC

 

 

 

SC

 

 

 

SC

 

 

 

Director & Heads of Service support

 

 

 

Director & Heads of Service support

 

 

Director & Heads of Service support

 

 

Director & Heads of Service support

 

 

 

Improved community focus

 

 

 

 

Improved community focus

 

 

 

Improved community focus

 

 

 

Improved community focus

 

 

 

 

 

 

Task

Target Date

Outcome

Responsible Officer

Dependencies

Key Objectives to be achieved

Development Plan for Island Futures partnership

 

 

Establish approved Voluntary Sector Compact

 

April

03

 

 

 

May

03

Strengthened partnership working

 

 

Strengthened partnership working

 

 

SC

 

 

 

 

SC

Partner support

 

 

 

 

Partner support

 

Improved community focus

 

 

 

 

Improved community focus

 

 

 

 

 

Task

Target Date

Outcome

Responsible Officer

Dependencies

Key Objectives to be achieved

D. Crime and Disorder

 

Review Crime and Disorder Strategy

 

 

Implement improved ASBO Strategy

 

Implementation of improved system for racist incidents

 

 

Develop & deliver training programme for mainstreaming of S.17 duties

 

Develop & promote Crimebeat programme

 

 

 

 

 

 

 

 

May 03

 

 

 

April 03

 

 

 

May 03

 

 

 

 

March 04

 

 

 

March 04

 

 

 

 

Achievement of  C & D partnership aims

 

Appointment of ASBO co-ordinator

 

Launch of new reporting system

 

 

 

Compliance with statutory duty

 

 

Involvement of young people in tackling crime

 

 

 

 

NH

 

 

 

NH

 

 

 

NH

 

 

 

 

NH

 

 

 

NH

 

 

 

Partner support

 

 

 

Partnership funding

 

 

 

Partnership support (esp. links with Integration in our Island Group)

 

 

Director & Heads of Service support

 

 

Partner support

 

 

 

Creating safe & crime-free communities

 

 

Creating safe & crime-free communities

 

 

Creating safe & crime-free communities

 

 

 

Creating safe & crime-free communities

 

 

Creating safe & crime-free communities

Task

Target Date

Outcome

Responsible Officer

 

 

 

Dependencies

Key Objectives to be achieved

 

Review and update Crime and Disorder website

 

 

Develop improved architectural liaison service

 

Develop improved arrangements for monitoring and applying best practice

 

 

Quarterly

 

 

 

 

March 04

 

 

 

March 04

 

Provision of accurate and up-to-date information

 

Improved service

 

 

Improved service

 

NH

 

 

 

 

DG / NH

 

 

 

NH

 

Staff time

 

 

 

 

Partner support

 

 

 

Partner support

 

Creating safe & crime-free communities

 

 

 

Creating safe & crime-free communities

 

 

Creating safe & crime-free communities