DEVELOPMENT CONTROL PERFORMANCE ANALYSIS 2002/03
|
(1) DTLR Performance Target for
2001/02 |
(2) DTLR Performance
standard for 2001/02 |
(3) DTLR Performance
standard for failing Authorities for 2003/04 |
(4) DTLR new performance
targets for 2002/03 |
(5) IWC (Dev Con)
performance for 2001/02 |
(6a) IWC (Dev Con) Performance over
last quarter |
(6b) IWC (Dev Con) Performance for 2002/03 |
(7) IWC (Dev Con)
Performance for 2002/03 Set 5/02 |
(8) IWC (Dev Con) target
2003/04 Set 5/02 |
||||
|
|
10/02 |
12/02 |
01/03 |
3/03 |
|
|
||||||
a) Number of applications dealt with in 8 weeks |
80% |
- |
- |
- |
60.5% |
70.1% |
67.7% |
69.1% |
69.0% |
69.3% |
65% |
70% |
|
b) Major applications dealt with in 13 weeks |
- |
28% |
50% |
60% |
20.4% |
40.7% |
41.3% |
42.4% |
41.2% |
41.9% |
45% |
50% |
|
c) Minor applications dealt with in 8 weeks |
- |
37% |
55% |
65% |
52.4% |
66.1% |
60.0% |
61.3% |
61.1% |
62.5% |
55% |
65% |
|
d) Other application dealt with in 8 weeks |
- |
55% |
70% |
80% |
71.3% |
78.3% |
75.6% |
77.3% |
77.7% |
77.6% |
74% |
80% |
|
e) Delegated decisions |
80% |
- |
- |
90% |
80.1% |
90.6% |
88.2% |
88.6% |
89.01% |
89.2% |
84% |
85% |
|
I:\SECRETAR\Judith\CSH\DC Performance
Analysis.doc
(a)
Eight week figure deemed to be effectively obsolete by Government as of
31/3/02, but nevertheless continues to be an important measurement of overall
performance. IWC performance for
2001/02 [see (a)(5)] represents an 11% improvement on 2000/01 despite a 20%
increase in the overall number of applications received over the same period
and a similar improvement has been achieved in 2002/03 with a 9% further
improvement in performance, despite another substantial increase in the number
of applications. The figure for the
last financial year (ie. up to 31/3/03) was 69.3%, which was in excess of our
target for 2002/03 and extremely close to our target for 2003/04 of 70%. Nevertheless, this still remains short of
the 80% target set by the DTLR in 2001/02.
(b) New performance target introduced in November 2001. Performance standard "names and shames" 66 authorities who have failed to achieve a 28% return for 2001/02 [see (b)(2)]. Our performance in 2001/02 [see (b)(5)] means that this Council has been cited as a failing Authority in 2001/02 in this particular area. Consequently, it is imperative that the target for the current financial year [see (b)(7)] achieves the same standard as that expected for the failing Authorities in 2000/01 (ie 45%) and the target for next year (2003/04) is that prescribed by the ODPM [see (b)(8)]. When compared with 2001/02, we have shown a significant improvement, up by 20%, but still remain a few points short of our target for 2002/03. The target for next year 2003/04 of 50% to meet the ODPM performance standard for failing Authorities is extremely challenging if you give due regard to the complications which can beset a major submission and the lack of staff resources, which, as some stage, should be supplemented by a Major Submissions Officer as a new appointment but affected by restructuring and the identified retirement of a very experienced Senior Officer in the next few months.
(c) This is an area where we have achieved the new ODPM performance target [see (c)(4)]. We have exceeded our own target for 2002/03 [see (c)(7) by 7.5%.
(d)
Our performance in this area indicates a 7% improvement on 2001/02
beyond our own performance target for 2002/03 and approaching the ODPM
performance target of 80%. It is
anticipated that our target in 2003/04 of 80% will be achieved in this area.
(e)
Following the review of the delegation arrangements, we were below the
original ODPM performance target [see (e)(1)] of 80%. However the level of delegation is increasing and is now
approaching 90%, which is the new performance targets set by the DTLR [see
(e)(4)]. Quite clearly we have exceeded
our own targets for 2002/03 and 2003/04 and it is suggested that the target for
2003/04 should be set at 90% with the objective of maintaining that level of
delegation, which will help improve the effectiveness and the efficiency of
delivery and allow DCC to concentrate on major and/or contentious applications.
NB. The figures appearing in
column (6b) IWC (Dev. Con.) Performance for 2002/03 in the right hand column
3/03 are for the whole twelve month period confirming significant improvements
in all areas.
C S Hougham
Development
Control Manager 1.4.03 (Revised)