REPORT OF THE HEAD OF PLANNING SERVICES
UPDATE – OUTSTANDING ISLE OF WIGHT COUNCIL
ENFORCEMENT ACTIONS
POSITION AS OF 30 JUNE 2004
Officer:
Mr S Cornwell Tel: (01983)
823592
Background
One of the commitments within the adopted
Enforcement Policy which Members agreed at the 2 September 2003 Development
Control Committee meeting was to report back on a regular basis with some
information on performance levels.
Outlined below are a range of enforcement
statistics comparing the second quarter performance levels this year with
figures for 2002 and 2003.
Members will recall that when considering the
last report, at the 11 May 2004 Development Control Committee Meeting, it was
noted we had achieved a 79% performance target from taking applications from
their receipt to a point where a decision was made on how to remedy the breach
for the six month period 1 September 2003 to 29 February 2004. The policy
target is 80%.
I regret to advise Members that whilst I can
report the receipt of 96 complaints in the last quarter due to the ongoing
staffing difficulties within the Enforcement Team it has not been possible to
calculate the performance figure to include the months of April, May and June.
I do however anticipate that in the next Progress Report this matter will have
been addressed.
To give Members some further insight into
the work of the Enforcement Team I have also produced a breakdown of figures
relating to overall complaints and the service of Notices on a quarter by
quarter basis.
The total number of notices issued in the
last quarter was 4. I believe that this reduction in the number of notices is
also a reflection of the current staffing difficulties. Members should note
however that whilst the number of planning contravention notices issued is
recorded at 2, 1 of these was served to each of the 49 properties at Island
Harbour, Newport relating to the ongoing investigation at this site.
For Members information, the Enforcement
Team went through the last quarter with a complement of 3 members of staff out
of 5. A commencement officer has now been recruited and whilst the west area
enforcement officer has recently retired (21 July 2004) a replacement for that
post has been appointed and will start in September. This leaves one post, the
Junior Enforcement Assistant, to be filled.
Jan-March |
April-June |
July-Sept |
Oct-Dec |
TOTAL |
118 |
123 |
122 |
95 |
458 |
106 |
147 |
147 |
108 |
508 |
112 |
96 est. |
|
|
|
2002
2003
2004
Jan-March |
April-June |
July-Sept |
Oct-Dec |
TOTAL |
6 |
11 |
5 |
4 |
26 |
4 |
5 |
3 |
6 |
18 |
5 |
2 |
|
|
|
ENFORCEMENT NOTICES
2002
2003
2004
Jan-March |
April-June |
July-Sept |
Oct-Dec |
TOTAL |
6 |
4 |
8 |
5 |
23 |
9 |
23 |
19 |
2 |
53 |
5 |
0 |
|
|
|
2002
2003
2004
Jan-March |
April-June |
July-Sept |
Oct-Dec |
TOTAL |
3 |
2 |
4 |
5 |
14 |
3 |
1 |
3 |
8 |
15 |
3 |
2* |
|
|
|
2002
2003
2004
Also, at the back of this report is the further
update on progress regarding outstanding enforcement actions. At the end
of this report I have also referred to the Section 215 Notices that Members
have authorised over the past few months and also the court cases that have been progressed.
If any individual Member has a specific case
that they wish for further clarification on, I would request that they contact
me before the Committee Meeting on the above number or by e mail.
It is intended that the next report would
come in front of the Committee on 26 October 2004.
Finally, Members will note that the Planning
Enforcement Policy, which was adopted on 2 September 2003, will shortly be a
year old. It was always intended to be a “living document” to be reviewed and
revised to reflect changing circumstances. I would propose that we revisit the
document at the 7 December 2004 meeting which gives time for the new powers of
the Planning and Compulsory Purchase Act 2004 to be fully assessed.
That Members note
the attached report
Head of Planning Services
SG
Site
|
Details
|
Minute/Date
|
Notes/Present Position
|
1. Land adjacent to Long Lane
Plantation, Long Lane, Newport
|
Enforcement action authorised against residential use of coach,
storage of vehicles on land and construction of a building.
|
5.12.2000
|
Land divided into multiple plots resulted in delay of issuing
Enforcement Notice.
Enforcement Notice
issued 12 July 2001. Effective date 24 August 2001. Compliance date 24 October 2001. Appeal made against Enforcement Notice on
22 August 2001. Planning Committee agreed to extend
compliance period through to 1 May 2002 if applicant withdrew appeal 8
January 2002. Residential use had ceased at this time. Site checked after 1 May 2002, vehicles
and building still remain. Potential prosecution statement drafted
for Legal. Ownership of individual items
on site and land parcels changed making identification of responsible parties
more difficult. Following Legal Section contacting new
owners coach and number of vehicles moved from their original positions. Site visited by Officer, all the cars have
been removed but the coach and the shed remain. The coach (which is not owned by a plot holder) has been moved
into a new position. Plot holder
indicated he will take measures to get coach and shed removed. Quantity of spoil tipped across centre of
site limiting access to upper area. Travellers moved on to lower part of site,
one of which has indicated ownership of plot they occupy and this is
currently being checked by Legal. Travellers given copy of Enforcement
Notice on 11 July 2003 with request that they meet LPA in 10 days time. At meeting Travellers given deadline to
vacate site otherwise action to be taken. Travellers vacated site but left behind
large van. Coach has been removed but
shed remains. LPA currently trying to
get remaining structures removed and get site secured so Travellers cannot
return. Consideration being given to some form of direct action to resolve
matter. |
Site
|
Details
|
Minute/Date
|
Notes/Present Position
|
2.
Land east of Sandown Airport, Newport Road, Sandown |
Planning permission refused for part
retrospective development and enforcement action authorised requiring
cessation of use of site as a trailer and lorry park. 9 months to comply. |
3.8.2001 |
Enforcement Notice issued 30 January 2002. Effective date 12 March 2002. Original compliance date 12 March 2003. Enforcement Notice appeal submitted dated
28 February 2002. Appeal dismissed and Enforcement Notice
varied 22 October 2002. New compliance date set 22 October 2003 Site visited 10 November 2003, no
indications any requirements of Enforcement Notice been complied with. Evidence gathered statement produced to
form basis of a prosecution for failing to comply with the requirements of
the notice. First Magistrates’ Court Hearing date 20
February 2004, second Hearing date 12 March 2004. At third Hearing date 19
March 2004 operator pleaded guilty for not complying with the Notice and was
fined Ł1000 with Ł1000 costs. Site visited 21 April 2004. Further actions taken to comply with
Notice, these currently being evaluated by Officers. |
3. Brookfield Willows, Ventnor Road, Whitwell |
Enforcement action authorised against the
disposal of inert waste material on the land. Time period for compliance 3 months. |
15.8.2001 |
Enforcement Notice issued 24 April 2001. Effective date 11 June 2001. Original compliance date 11 September
2001. Appeal against Enforcement Notice
submitted 8 June 2001. Inspector’s decision letter received 6
September 2002, Notice upheld but time period extended to 9 months. New compliance date 6 June 2003. Site checked, material not removed. Case
conference with Legal Services. Decision to
initiate a prosecution for failing to comply with the Enforcement
Notice. Evidence
gathered, prosecution statements
produced. Matter now being progressed through Court
action (see specific section at end of report) |
Site
|
Details
|
Minute/Date
|
Notes/Present Position
|
4.
Land north east Rodgebrook Farm, Whitehouse Road, Newport |
Enforcement action authorised against
non-agricultural use of land, pond, timber storage |
7.12.2001 |
Enforcement Notices issued 4 May 2001. Effective date 8 June 2001. Compliance date 8 December 2001. Site condition improved, but notice not
fully complied with. Further application submitted, refused
December 2001. Appeal submitted 6
February 2003. Inspector’s decision
letter issued 30 June 2003 dismissing appeal. Planning revisited site to collect
evidence to form basis of prosecution statement for failing to comply with
the requirements of the original Enforcement Notice. As a result of threat of impending action
the landowner commenced clearance of site.
Request made for the LPA to consider retention of pond and cords of
wood. In December 2003 site visited with Local
Member. Operator advised that with
some minor works and landscaping pond could be retained but that the cords of
wood had to be removed. Recent reports indicate that further items
have been brought onto site. There is
therefore a need for a fresh site visit and an assessment if any of the new
activity is development and, if so, is it covered by the existing Notice. Meeting with operator in May 2004 failed
to produce meaningful outcomes and prosecution statement now being produced
with view to prosecution in Magistrate Court for failing to comply with
requirements of notices. |
5. West Billingham Farm Billingham, Newport |
Committee authorised enforcement action
against introduction of upvc windows in Listed Building. 6 months to comply. |
23.4.2002 |
Enforcement Notices issued 7 April
2003. Effective date of 27 May 2003. Compliance date 27 November 2003 Appeal made against Notice on 20 May 2003.
Planning Inspectorate indicated
appeal invalid. Planning application submitted seeking to
retain the UPVC windows with indication that if application refused an appeal
will be lodged. Planning application refused. Appeal submitted with date for Listed Building
Hearing 7 September 2004. |
Site
|
Details
|
Minute/Date
|
Notes/Present Position
|
|||
6. Fort Bouldnor, Main Road, Bouldnor, Yarmouth |
Following refusal of retrospective
planning permission enforcement action authorised against: (a) the unit of
residential accommodation (b) alterations/extensions
and new buildings (c) the use of the
site in connection with training operations. 9 months to comply. |
25.6.2004 |
Enforcement notice issued 22 Nov. 2002
regarding the residential unit. Effective date 15 January 2003. Compliance date 15 October 2003. Enforcement Notice regarding alterations
and extensions to other buildings and the addition of new buildings about to
be issued. LPA approved Lawful Development
Certificate in June accepting “continued use of land and original buildings
as an outdoor activity training centre at Fort Bouldnor”. Report to 11 July
2003 Development Control Committee meeting Members decide to invite (with
prejudice) retrospective application to address only outstanding matter that
is item B in details paragraph. Deadline for submission set at 1 September
2003. Planning application submitted
September 2003, still under
consideration. Date of 15 October 2003 for compliance
with Enforcement Notice on residential
building now passed. Site visited first floor accommodation been
removed, use as permanent residential accommodation ceased as people moved
out but ground floor in use as staff sleeping accommodation. Planning
application submitted seeking temporary permission for this use now under
consideration. |
|||
7. Bembridge Boatyard, Marine Works, Embankment Road, Bembridge |
Enforcement action authorised against
fence adjacent highway and use of land for storage purposes including builders
materials, vehicle repairs and presence of buildings/structures |
25.02.2003 |
Enforcement notice issued dated 19
September 2003 with effective date of 7 November and compliance date of 7
March 2004. Appeal submitted. Inspectors decision letter dated 18 June
2004 dismissed appeals. New compliance date of 18 October 2004 |
|||
8. 34 Mayfield Drive, Newport |
Enforcement action authorised against taxi
business operating from premises. Time period for compliance 3 months |
22.07.2004 |
Enforcement notice issued dated 11
September 2003 with an effective date of 23 October 2003 and a compliance
dated of 23 January 2004. Appeal submitted. Inspectors decision letter date 7 April
2004 dismissed appeal. New compliance date 7 July 2004. |
|||
Site
|
Details
|
Minute/Date
|
Notes/Present Position
|
|||
9. The Boathouse, Blake &
Spencer, Esplanade, Ventnor
|
Enforcement action authorised against use of part of premises for the
preparation of fishing shellfish.
Tim period for compliance is to be
set no later than 31 March 2004 |
12.08.2003
|
Enforcement Notice served dated 8 December 2003 with effective date
of 19 January 2004 and original compliance date of 31 March 2004.
Appeal submitted 12 January 2004. Following consideration of matter at 30
January 2004 Meeting, Members resolved to extend compliance date to 30
September 2004 on basis appeal withdrawn. This proposal accepted by operator.
New
compliance date set
at 30 September 2004 |
|||
10.Land adjacent Embankment Road,
Bembridge
|
Enforcement action authorised against the use of land as car park.
Time period for compliance 2 months. |
23.09.2003
|
Enforcement Notice served dated 7 April 2004 with effective date of
21 May 2004 and compliance date of 21 July 2004.
Appeal submitted, projected target date for decision 4 January 2005. |
|||
11. Medham Village, Medham Farm
Lane, off Newport Road, Northwood
|
Enforcement action authorised.
Failure of developer to comply with that part of a planning condition
which requires highway works.
|
19.11.2002
4.11.2003 |
Following the original Committee resolution in November 2002
discussions took place with the developer and local residents in an attempt
to identify an amicable way forward without the need for the service of the
Notice. These did not result in any
remedy and as a consequence formal Notice served dated 11 September 2003 with
the deadline for compliance of 15 January 2004.
Appeal submitted
against Notice indicating time period given for compliance too short. Further report considered at 4 November
2003 Development Control Committee meeting at which time Committee agreed to
extend compliance period from three to twelve months on basis that developer
withdraws appeal. Further resolution that Officers be
instructed to monitor site over the year, that it will expect full compliance
within the allocated time with any failure leading to consideration of action
through the Magistrates Court. Letter dated 12 November 2003 from
developer confirming appeal withdrawn . New compliance date is 17 October 2004. |
|||
Site |
Details |
Minute/Date |
Notes/Present
Position |
12. Barley Mow Public
House Shide Road, Newport |
Following refusal of retrospective
planning permission for retention of petanque area. 3 months to comply. |
10.12.2002 |
Enforcement Notice issued 30 January 2003. Effective date 14 March 2003. Compliance date 14 June 2003. Further planning application submitted but
invalidated 30 June 2003. Letter sent 30 June, second letter 30
July. Retrospective application remains invalid,
property owner advised remove facility in compliance with the Enforcement
Notice immediately or face potential prosecution action. Use appears to have ceased but surface
remains in place. Site being
monitored to determine if breach of planning control exists. |
13. Land adjoining The Orchard, Undercliff
Drive, St Lawrence, Ventnor |
Enforcement action authorised against
unauthorised alterations to vehicular access and formation of hardstanding. 2 months to comply. |
10.12.2002 |
At the 27 April 2003 Development Control
Committee meeting Members considered a further report on this matter regarding
the question of a legal right to use the new access. Unauthorised access not in use and Members
gave landowner three months to resolve issue regarding use of new
access. Committee to consider
position after that time. Matter considered further at 12 August
2003 Development Control Committee meeting.
Members resolved to pursue the enforcement action. Enforcement Notice served dated 21 October
2003 with an effective date of 5 December 2003 and with a compliance date of
5 February 2004. Appeal submitted against Enforcement
Notice. Enforcement Hearing held 20
April 2004. Inspector’s Decision
Letter dated 27 April 2004 dismissed the Appeal and upheld the Notice with variations. New date for compliance 27 June 2004. Site visited Landowner has complied with
requirements of notice. Case
closed. |
Site |
Details |
Minute/Date |
Notes/Present
Position |
14. Edina, Mill Road, Yarmouth |
Enforcement action authorised for failing
to construct dwelling in accordance with approved plans. Time period for compliance six months from
the service of the Notice. |
14.10.2003 |
Discussion presently underway with Legal
Section on scope and content of Notice. Discussions taken place with applicant and
his agent but to date no remedy acceptable to all parties has been
identified. Intention to proceed and serve Notice. |
15.
Helens Copse, Gate Lane, Freshwater Bay |
Enforcement action authorised against
presence of two shipping containers on the land. Time period for compliance three months. |
14.10.2003 |
Enforcement Notice issued dated 15
December 2003 with an effective date of 2 February 2004 and a compliance date
of 2 May 2004. Appeal submitted before effective date
reached. Hearing took place on 18 May 2004. Inspectors decision letter dated 8 June
2004 dismissed appeal. New compliance date is now 8 Sept. 2004 |
16.
Hawthorn Manor Farm, Chale Green and Sheep Lane Farm, Chale |
Enforcement action authorised against use
of mobile homes as residential accommodation. Time period for compliance 6 months |
04.11.2003 13.07.2004 |
Enforcement Notices issued dated 30
January 2004 with an effective date of 12 March 2004 and with a compliance
date of 12 September 2004. Appeals
submitted before effective date reached. Anticipated 2-3 day Public Inquiry to be
held in January 2004. At 13 July 2004 meeting, Members
considered report noting additional information and resolved to adopt a
strategy that would accept total of 5 caravans at both sites with others
removed. Two LDC applications have now been made and the enforcement notices
have been withdrawn so appeals fall. Both sites to be monitored in accordance
with agreement to ensure removal of unacceptable caravans. |
17.
Three storey building providing retail unit and restaurant on ground
floor with total of 12 flats above, 37 Pyle Street, Newport |
Enforcement action authorised against
developer for failing to construct building in accordance with approved plans
relating to render detail and feature strip and the construction of a low
wall with a change in the footpath level between the road and the building. |
25.11.2003 |
Local Planning Authority had difficulty in
identifying relevant parties on which to serve Notice. These difficulties now subsequently
resolved. Enforcement Notice served dated 2 June
2004 with effective date of 19 July 2004 and compliance date of 19 October
2004. Appeal submitted before effective date
reached. Projected target date for decision 2 March
2005. |
Site |
Details |
Minute/Date |
Notes/Present
Position |
18.
15 Dudley Road, Ventnor |
Enforcement action authorised against
unauthorised car port. Time period for compliance 28 days from
when the Notice takes effect. |
25.11.2003 |
Draft Enforcement Notice prepared. Adjoining householder indicated they will
purchase car port which removes concerns with regard to impact on adjoining
residential property. Subject to satisfactory confirmation of
purchase there will be no need to serve Enforcement Notice. Confirmation of purchase received breach
no longer exists, no need to serve notice. Case
closed. |
19.
Isle of Wight Rugby Football
Club. Footways, recreation ground,
Wootton |
Enforcement action authorised against
failure to comply with condition limiting height of floodlight cluster. Time period for compliance one month. |
25.11.2003 |
Enforcement Notice issued dated 30 January
2004 with an effective date of 12 March 2004 and a compliance date of 19
March 2004. Compliance to be checked. Site checked for compliance and whilst
light cluster slightly above limit considered no further action should be
taken. Case
closed. |
20.
Christian Meeting Room, Buckbury Lane, Newport |
Enforcement action authorised against the installation
of a car park lighting scheme with a time period for compliance of 2 months. |
16.12.2003 |
Enforcement Notice issued dated 22 January
2004 with an effective date of 5 March 2004 and a compliance date of 5 May
2004. Appeal submitted before the effective date
reached with a second appeal against refusal of planning permission. Projected target date for Inspector’s
appeal decision 13 October 2004. |
21. O.S. Parcel 5445, edge of Windgate Copse, Newtown, Isle of Wight |
Enforcement action authorised against
construction of a wooden building. Time period for compliance is 3 months. |
16.12.2003 |
Enforcement Notice issued dated 19 January
2004 with an effective date of 1 March 2004 and a compliance date of 1 June
2004. Appeal submitted before effective date
reached. Projected target date for appeal
Inspector’s decision 4 October 2004. |
22.
Mariners Culver Way, Sandown,
Isle of Wight |
Enforcement action authorised against construction
of a raised decking area and installation of a summerhouse on the decking
area. Time period for compliance is 3 months. |
5.12.2003 |
Enforcement Notice issued dated 20
February 2004 with an effective date of 6 April 2004 and a compliance date of
6 July 2004. |
Site |
Details |
Minute/Date |
Notes/Present
Position |
23. Cats Copse, West View Road,
Cowes. |
Enforcement action authorised against
continued use of land and buildings for paintball games centre. Time period for compliance one month. |
2.3.2004 |
Enforcement Notice served dated 13 May
2004 with effective date of 22 June 2004 and compliance date of 22 July 2004.
Appeal submitted. Projected target date for decision end
January 2005. |
24. Victoria Lodge,
Castle Haven Lane, Niton Undercliff, Ventnor |
The details are Enforcement Action
authorised requiring cessation of use of mobile home, its removal from the
land. Time period for compliance twelve months. |
11.05.2004 |
Enforcement Notice served dated 5 July
2004 with effective date of 23 August 2004 and a compliance date of 23 August
2005. |
25. Cheeks Farm Merstone Lane, Merstone. |
Enforcement Action authorised against
conversion of building to private dwelling and secondly additional works to outbuildings.
Time period for compliance for both notices four months |
11.05.2004 |
Draft Enforcement Notice agreed with
Legal; service imminent. |
26. OS 0091 & OS
0072 land south of Hulverstone Lane Hulverstone |
Enforcement Action authorised seeking removal
of stable block, removal of boats and caravan from the land. Time period for
compliance two months. |
11.05.2004 |
Enforcement notice issued dated 23 June 2004 with effective date of 2 August 2004 and a compliance date of 2
October 2004. Appeal submitted 28 July 2004. |
27. Carpenters Lane,
St Helens |
Enforcement action authorised relating to
the use of land on either side of lane for storage of motor vehicles. Time
period for compliance 3 months. |
11.05.2004 |
Draft enforcement notice being formulated
with Legal. |
28. Part OS Parcel
8700 Land at North
Fairlee Farm, Fairlee Road, Newport |
Enforcement action authorised against use
of land and operating centre for taxi business |
21.05.2004 |
Enforcement Notice served dated 5 July
2004 with effective date of 13 August 2004 and compliance date of 13 August
2005. |
Site |
Details |
Minute/Date |
Notes/Present
Position |
29. Flora Cottage Morton Road,
Brading |
Enforcement action authorised against
formation of vehicular access and further works associated with the creation
of a hardstanding including unauthorised excavations of garden. Time period for compliance 3 months. |
22.06.2004 |
Draft enforcement notice being formulated
with Legal. Planning application submitted seeking to
retain the excavated area which if acceptable could be conditioned to
prohibit any vehicular access. This would remove the need for the service of
any formal notice. Position of planning application to be
ascertained immediately prior to service of any notice. |
215 Notices
Site
|
Details
|
Minute/Date
|
Notes/Present Position
|
1. Kent House, York Avenue, East Cowes |
Authorisation given for the service of a
Notice requiring trailer body to be painted a dark/matt green or brown
colour. Time period for compliance one month. |
1.7.2003 |
Property in flats. Although requisition for information sent
to property this has not been returned and Legal have been trying to
ascertain individual(s) or company who owns building to ensure any Notice
served on the appropriate party. To
date these efforts proved unsuccessful.
Legal currently seeking direction on what to do next. |
2.
Maryland, Colwell Chine Road, Freshwater |
Authorisation given for the service of a
Notice requiring tidying up of garden to property involving removal of a
number of motor vehicles and other items.
Time period for compliance one month. |
2.3.2004 |
Section 215 Notice served dated 23 April
2004 with an effective date of 28 May
2004 and a compliance date of 28 June 2004. Site checked 12 July 2004 some works
undertaken owner indicated outstanding matters to be done within 2 weeks.
Further site visit required 27 July 2004. |
3. 9-13 Pier
Street, Ventnor |
Authorisation given to serve notice
requiring replacement of plywood sheet with glass |
11.05.2004 |
Section 215 Notice served dated 18 June 2004
with effective date of 2 August and a compliance date of 2 September 2004 |
4. 52-58 High
Street, Ventnor |
Authorisation given to serve notice
requiring repairs/improvements to appearance of shop front. |
11.05.2004 |
Section 215 Notice served dated 6 July
2004 with effective date of 20 August 2004 and a compliance date of 20
September 2004. |