PAPER B2

 

 

ISLE OF WIGHT COUNCIL DEVELOPMENT CONTROL COMMITTEE B

TUESDAY 29 APRIL 2003

 

REPORT OF THE STRATEGIC DIRECTOR OF CORPORATE AND ENVIRONMENT SERVICES

 

 

LBC/8854R      Replacement windows, Royal Yacht Squadron, The Castle, Cowes

 

Summary

 

To report on the final outcome of negotiations with the Royal Yacht Squadron regarding the replacement timber windows and the recent inspection thereof.

 

Options

 

1.   To accept the findings of this report and to agree that all the windows which have been replaced as part of the phased programme accepted by this Council, are acceptable, and to agree that this long running saga is finally concluded.

 

Recommendation

 

To accept the findings of this report and to agree that all the windows which have been replaced as part of the phased programme accepted by this Council, are acceptable, and to agree that this long running saga is finally concluded.

 

Background

 

Some Members may recall that it was in April 1991 that the first indication of unauthorised insertion of UPVC windows in this Grade II Star Listed building was brought to the attention of the Council, and since that time it has consumed much time and energy of Officers and consultants to reach a final conclusion on this matter.  It was suggested at that time that within the conservation principles of this Council, UPVC is an unacceptable replacement window in a Listed building.  This has been thoroughly upheld in appeals to 5 May has continued the Council=s 100% record in the refusal of UPVC windows in Listed buildings under application, and also in enforcement for their removal.

 

This case raised many issues, not the least being the contention by English Heritage that perhaps major Listed buildings should be divided down into historic areas, with different gradings on each area.  However, I believe that having addressed this issue in the Royal Yacht Squadron it has proved to be cumbersome and unwieldy and in this particular case will not be proceeded with.  For Members= information the grading of the Royal Yacht Squadron throughout, including all buildings (the 1960=s extension notwithstanding) remains at Grade II Star.

 


Members will no doubt recall the report to the Planning Committee on Tuesday 3 April 2001 when it was reported that the Royal Yacht Squadron had agreed they would insert all the agreed windows, bar the sixteen windows to have been changed under phase 3 of the programme, and which were due to be completed by December 2002.  This was in accordance with the subject of the 1994 Agreement which stated that timber windows had to be inserted to a design agreed with the Council as the Local Planning Authority.  Members may recall that the Council=s Conservation Officer visited the factories of Franklin Window & Joinery Company in Leeds, to agree the type and style of windows that would be provided by them, and which would be suitable in the Royal Yacht Squadron.  A letter to Franklin Window Company of 24 July set out the detailed requirements of the proposed timber windows and these were agreed with the manufacturers.

 

The quotation dated 7 August 2000 for the detailed specification of the windows was accepted by the Royal Yacht Squadron on 18 August 2000, the site sizes were lifted by the manufactures and on week beginning 16 October 2000 manufacture commenced.  During November and December Franklin Windows attended on-site, they removed the offending UPVC windows and inserted the approved timber windows, these were inspected at various intervals along the two months of construction and were found to be perfectly satisfactory.  It was concluded at the meeting that all 33 windows required to be changed under the Enforcement Notice had been carried out properly to the standard required by the Council and returned the main part of the Listed building to its original condition.  As noted at that meeting, there were still sixteen UPVC windows to be replaced under the third and final clause of the 1994 Agreement, they were primarily in the mansard wing with a compliance date for this replacement of December 2002.  It was recommended in the report that Franklin Windows construct and install the sixteen windows to continue both the type and quality of those already fitted.

 

During November and December of 2002 this Authority was advised that the work was being undertaken, and at various intervals through these two months an inspection was undertaken to determine that the quality and the fenestration were acceptable, and I am very pleased to report that on a final inspection on 13 December 1002 the sixteen windows were considered to be perfectly acceptable to the Council.  The quality is still very high, and in a letter to the Squadron comment was made to commend particularly the replacement of the internal architraves and shutter boxes, which contribute in no small measure to the quality of the work.

 

It was also noted at that inspection that two further windows located virtually out of sight under the roof projection and which were not in fact identified within the schedule were also carried out giving a total of eighteen windows undertaken.  Not requested by the Council I would report to Members that these were carried out by the Squadron at their expense and in the spirit of cooperation on this long-running saga, and are to be commended for this action.

 

In the letter of 13 December the final paragraph stated AThis therefore concludes the final phase of all the replacements, and I am happy to confirm that the Squadron has complied in all respects with all sections of the 1994 Agreement.@

 

I am pleased to report that visually the windows in the Royal Yacht Squadron contribute immensely to the character of this commanding and historic building, and I am pleased that the outcome has, after so many years, been satisfactorily concluded.  

 

 

M J A FISHER

Strategic Director

Corporate and Environment Services