Tuesday 20th April 2004
Prestwood Grange Farm, off Smallbrook Lane, Ryde
REPORT OF
HEAD OF PLANNING SERVICES
SUMMARY
To consider a specific option available to this Committee in connection with a dairy operation at the abovementioned farm which is causing disamenity to a number of residential occupiers in the immediate locality.
ACTION
REQUIRED BY COMMITTEE
To give due regard to the merits of serving a Discontinuance Notice (see Appendix), under Section 102 of the Town & Country Planning Act 1990, on the owners of Prestwood Grange Farm in connection with the dairy operation currently taking place on site.
A Discontinuance Notice, or a Discontinuance Order if confirmed, would enable the Council to require the present operation to cease subject to the payment of financial compensation. The Council needs to be satisfied that such action is expedient in the interest of the amenities of the area.
The possible service of a Discontinuance Notice would need to be assessed against a background of various options that have been considered by this Council since the Local Government Ombudsman found maladministration causing injustice in December 1999.
RECOMMENDATION That a Discontinuance Notice is served under Section 102 of the Town & Country Planning Act 1990 on the owners of Prestwood Grange Farm, requiring the use of the farmholding as a dairy operation to discontinue subject to the payment of financial compensation. |
BACKGROUND:
1.
Prestwood
Grange Farm, or Prestwood Farm, is a long-established agricultural holding
situated in open countryside adjacent to a low-density residential area that
was largely developed during the mid twentieth century.
10.
In
February 2002 the Executive was updated on the progress of negotiations with
the landowner and his representatives and advised that part compensation had
been paid to the local residents and estimates had been put forward regarding
the cost of bringing the milking operation on the farm to an end. It was decided that a CPO be made in respect
of the land under Section 226(1)(b) of the Town & Country Planning Act
1990.
11.
Advice
was taken from Counsel in connection with the proposed CPO and it was at this
point that he advised that, in his view, a possible preferred alternative
course of action for the Council was to make a Discontinuance Order under
Section 102 of the Town & Country Planning Act 1990. Subsequently, a decision was taken by Executive
in August 2002 requiring the Development Control Committee to consider the
making of a Discontinuance Order as opposed to a Compulsory Purchase Order.
12.
Throughout
the period that the matter was initially considered, following the outcome of
the appeal and the Ombudsman’s decision, there have been extensive negotiations
and discussions with the owner of the farm, or his agents, conducted by the
Head of Planning Services, as well as extensive monitoring of the situation by
the Environmental Health Manager.
13.
The
present situation can be best summarised in the following terms:-
·
In accordance with the recommendation of the Ombudsman, partial
compensation has been paid to local residents.
While full payment remains an option, it has been previously agreed that
simply complying with the recommendation of the Ombudsman will not resolve the
problem and local people will continue to suffer a loss of amenity,
particularly during the summer months.
·
The Environmental Health Manager and consultants continue to monitor,
investigate and collect evidence in respect of the impact of the dairy
operation on the adjacent residential area.
·
Notwithstanding the efforts of the Head of Property Services, the matter
is unlikely to be resolved by a negotiated settlement in the present
circumstances.
·
An outline planning application submitted by prospective purchasers of
the (part) farm to develop a substantial part of the site for residential
purposes which, if successful, may have helped to resolve the situation, was
refused permission primarily because the land is outside the development
envelope boundary. There was no
appeal. Approval would have been
contrary to the Unitary Development Plan and would have to have been treated as
a departure.
·
If the Council were to serve a Discontinuance Notice, the legal view is
that there are reasonable prospects of success.
·
A considerable period of time has now elapsed since the appeal decision
and the publication of the findings of the Ombudsman and further delay would
not be in the best interests for the landowners or the local residents.
14.
The
Council will give evidence on the level of disamenity suffered by local
residents to support the proposed order.
At this moment in time it would not be appropriate to reveal the full
details of that evidence, however, I am able to confirm that consultants,
acting on behalf of the Environmental Health Manager, have prepared a report
based on the correlation of perceived odour with wind direction at Prestwood
Farm.
15.The Executive Summary of
this report states that observations from Environmental Health staff in 2003
indicate odour emissions from the facility to be intermittent, and on occasions
the odour emissions to be strong. An
appraisal of their meteorological data obtained from the two measurement
sources suggests that there is a correlation between the perceived odour on
Great Preston Road and Smallbrook Lane with wind direction. From the odour observations it was found that
most odours were perceived during periods of low windspeed.
CONCLUSIONS
It is important that Council
now progress the matter and it is apparent that the most appropriate route
seems to be the service of a Discontinuance Notice that, if confirmed, will
address the specific problem and compensate the landowner for the
discontinuation of an authorised operation without the Council having to
purchase the land.
It is worth reiterating that
the reason why the Council has deferred full payment of compensation to local
residents is because this would not provide a solution to the problem. The Council has pursued this goal by
investigating all potential options that would likely to produce a outcome that
would cause a cessation of the use of this part of the holding for dairy
purposes. Members may agree that the
payment of full compensation to residents would only become appropriate when
all other options have been exhausted.
If, for whatever reason, Members
were unable to support the recommendation to serve a Discontinuance Notice,
then, in my view, there should be no further prevarication and unnecessary
delay and the full compensation award should be made to local residents in
accordance with arrangements already agreed by the Head of Property Services
with the District Valuer.
CONTACT DETAILS
Chris Hougham – Development
Control Manager
Tel: (01983) 853565
E-mail: [email protected]
Andrew Ashcroft
Head of Planning Services