REPORT TO DEVELOPMENT CONTROL COMMITTEE –
TUESDAY 15 MARCH 2005
TCP/13798/C – P/01572/04 |
Demolition of shops and flats; 3/4 storey building to form
retail store (Class A1) with 9 flats over; vehicular access & basement
parking (revised plans) (re-advertised application); Island Furnishing, 52 –
58 High Street, Ventnor |
Officer: Mr Hougham, Development Control
Manager Tel: (01983) 825576
Summary
To consider
a request from the applicant’s agent in connection with a specific condition
imposed on the Conservation Area Consent concerning the aforementioned proposed
development.
Background
Members
may recall that the application and a separate application for Conservation
Area Consent (CAC) for demolition of buildings were considered by this
Committee at the meeting held on 7 December 2004. In accordance with the
recommendation Members decided to grant conditional permission. CAC was also
granted on a conditional basis which included a specific condition which
relates to the timing of the demolition of the buildings on site.
The works of
demolition hereby authorised shall not be commenced until a binding contract
for the carrying out of the works redevelopment of the site has been entered
into and planning permission has been granted for the redevelopment for which
the contract provides.
The
reason for the imposition of this condition was to protect the special
character of the area and to prevent the site remaining vacant for a
significant period of time and to comply with Policies B1 to B8 (Listed
Buildings and Conservation Areas) and D1 (Standards of Design) of the Unitary
Development Plan.
A letter
has been received from the applicant’s agent asking the Council, as Local
Planning Authority, to take a view on a specific difficulty that has arisen in
respect of the possible redevelopment of this site and the requirements of the
aforementioned condition.
The
situation can be summarised in the following terms:
·
Developers
wish to develop the site and be open for trading in Spring 2006 and therefore
wish to demolish the existing building as soon as possible.
·
Contract
for the redevelopment of the site cannot be completed until surveyors have made
an accurate assessment of ground conditions which obviously will necessitate
the demolition of the buildings. The agent estimates that there could be a
significant variation in terms of developing cost depending on the results of
this investigation (i.e. up to £200,000)
·
Completion
(i.e. purchase of the site) is likely to take place early next month and the
dilemma is how the developers achieve demolition while providing the Council
with a degree of assurance that the site would be virtually immediately
redeveloped as opposed to being left as open ground for a considerable period of
time.
·
As
evidence of good intentions the agents have pointed out that the developer
would undertake to proceed without any delay and that, in any case, this site
and the adjacent re-development sites, particularly the former Hole in the Wall
will need to be redeveloped at the same time because of practical difficulties
associated with the density of development within an urban location.
The
Development Control Manager decided that this decision should be taken by the
Committee as opposed to officers taking a view under delegated powers.
Financial Implications
None.
Options
1.
Members accept that the prospective
developer has a sustainable argument and agree to suspend any potential
enforcement action in respect of the breach of condition for a period of six
months subject to the developers: ·
Providing
written confirmation of their recognition that they fail to satisfy the terms
of the planning condition by 15 September 2005 they will be in breach of
planning condition which may result in the service of Notice. ·
Prior
to any demolition works taking place on site the developer is required to
submit for approval details of the overall height and decoration of the
temporary hoarding that will be used to screen the cleared site. 2.
Members
accept that the prospective developers have a sustainable argument but are
not prepared to agree to a temporary suspension of any potential enforcement
action and insist that an application is submitted for the removal or
variation of the condition. 3.
Members
do not accept that the developer has a sustainable argument and advise the
developers that if they have difficulty with complying with the condition
they should consider lodging an appeal with the Planning Inspectorate. |
The imposition of the aforementioned condition on
applications for Conservation Area Consent where there is substantial demolition
work in order to facilitate redevelopment of a site is relatively standard
practice when the land is within a designated Conservation Area.
Notwithstanding the poor condition of the existing buildings
on this particular site, it is my view that the Council, as Local Planning
Authority, has adopted a prudent approach designed to protect, if not enhance,
the visual amenity of the area by avoiding an open cleared site within the
streetscene for an indeterminate period of time. Consequently, I take the view
that the imposition of this particular condition was justified.
It is unusual for there to be any problems associated with
the imposition of this condition but in this particular case the existing
buildings cover a large part of the overall site; the buildings are Victorian
(or possibly Edwardian) and are known to include some subterranean rooms and
they are not in a good state of repair. If you combine these factors with
geotechnic conditions which prevail in the locality, Members will probably
agree that the developers will need to demolish the buildings and investigate
the ground conditions before completing a contract for the redevelopment of the
site.
On the assumption that Members accept the position outlined
in the preceding paragraph, the Council needs to establish when agreeing to the
request how the matter should be handled. Strict application of planning law
would necessitate us requesting the applicants to make a formal application for
the removal or variation of this condition. In practical terms it would seem
that the most sensible approach is not to enforce the condition, if the
buildings are to be demolished prior to the completion of a contract for the
carrying of works of redevelopment of the site, for a period of six months.
This concession on the part of the Council would be providing the developers
and their agent understand that if at the end of that period they are unable to
produce a contract for the works then they will be in breach of condition. The
situation also offers the opportunity the overall size (mainly height) and
decoration of any temporary hoarding across the front of the cleared site to be
agreed by officers prior to erection on site.
Recommendation Members
accept that the prospective developer has a sustainable argument and agree to
suspend any potential enforcement action in respect of the breach of
condition for a period of six months subject to the developers: ·
Providing
written confirmation of their recognition that they fail to satisfy the terms
of the planning condition by 15 September 2005 they will be in breach of
planning condition which may result in the service of a Breach of Condition Notice. ·
Prior
to any demolition works taking place on site the developer is required to
submit for approval details of the overall height and decoration of the
temporary hoarding that will be used to screen the cleared site. |
ANDREW ASHCROFT
Head of Planning Services