1.
THE RECOMMENDATIONS CONTAINED IN THIS REPORT OTHER THAN PART 1 SCHEDULE
AND DECISIONS ARE DISCLOSED FOR INFORMATION PURPOSES ONLY.
2.
THE RECOMMENDATIONS WILL BE CONSIDERED ON THE DATE INDICATED ABOVE IN
THE FIRST INSTANCE. (In some
circumstances, consideration of an item may be deferred to a later meeting).
3.
THE RECOMMENDATIONS MAY OR MAY NOT BE ACCEPTED BY THE DEVELOPMENT
CONTROL COMMITTEE AND MAY BE SUBJECT TO ALTERATION IN THE LIGHT OF FURTHER
INFORMATION RECEIVED BY THE OFFICERS AND PRESENTED TO MEMBERS AT MEETINGS.
4.
YOU ARE ADVISED TO CHECK WITH THE DIRECTORATE OF ENVIRONMENT SERVICES
(TEL: 821000) AS TO WHETHER OR NOT A DECISION HAS BEEN TAKEN ON ANY ITEM BEFORE
YOU TAKE ANY ACTION ON ANY OF THE RECOMMENDATIONS CONTAINED IN THIS REPORT.
5.
THE COUNCIL CANNOT ACCEPT ANY RESPONSIBILITY FOR THE CONSEQUENCES OF ANY
ACTION TAKEN BY ANY PERSON ON ANY OF THE RECOMMENDATIONS.
The various documents, letters and other correspondence referred to in the Report in respect of each planning application or other item of business.
Members are
advised that every application on this report has been considered against a background of the implications of
the Crime and Disorder Act 1998 and, where necessary, consultations have taken
place with the Crime and Disorder Facilitator and Architectural Liaison
Officer. Any responses received prior
to publication are featured in the report under the heading Representations.
Members are advised that every application on this report has been considered against a background of the implications of the Human Rights Act 1998 and, following advice from the Head of Legal and Democratic Services, in recognition of a duty to give reasons for a decision, each report will include a section explaining and giving a justification for the recommendation.
1. |
TCP/09568/J P/01877/04 Demolition of redundant farm outbuildings; outline for 'Continuing
Care Community' - a development consisting of a nursing care home, 68 extra
care cottages, 26 extra care apartments, associated specialist indoor
facilities, health care consulting rooms, day care facilities, restaurant, creche,
outdoor recreation/leisure facilities; formation of vehicular access,
pedestrian footpath links & provision of parking Land
adjoining Scotland Farm and properties in Dubbers and, Yarborough Close,
Godshill, Ventnor |
Godshill |
Conditional
Approval |
2 |
TCPL/21027/B P/02088/04 Conversion
of garage into unit of holiday accommodation, (revised scheme) Brookside
Cottage, Main Road, Ningwood, Newport |
Shalfleet |
Conditional
Approval |
3. |
LBC/21027/C P/02304/04 LBC for
conversion of garage into unit of holiday accommodation (revised scheme) Brookside
Cottage, Main Road, Ningwood, Newport |
Shalfleet |
Conditional
Approval |
4. |
TCP/22670/D P/01656/04 Provision
of 5 lighting columns 8.0m high for go-kart track (revised scheme) Land
adjacent Westridge Leisure Centre, Brading Road, Ryde |
Seaview |
Conditional
Approval |
5. |
TCPL/23329/H P/01917/04 Construction
of yacht haven & town pier Section
of foreshore between The Royal Yacht Squadron and opposite the bandstand, The
Parade, Cowes |
Cowes |
Conditional
Approval |
6. |
LBC/23329/J P/01921/04 LBC for
construction of yacht haven & town pier Section
of foreshore between The Royal Yacht Squadron and opposite the bandstand, The
Parade, Cowes |
Cowes |
Conditional
Approval |
7. |
TCP/24514/A P/01983/04 Detached
house with detached garage; formation of vehicular access (aorm)(further
revised scheme) Land
adjacent Ashdown House, Ashlake Farm Lane, Wootton Bridge, Ryde |
Fishbourne |
Conditional
Approval |
8. |
TCP/24579/D P/02580/04 Continued
use of part of premises for the preparation of fish and shell fish Blake
& Spencer, Esplanade, Ventnor |
Ventnor |
Conditional
Approval |
9. |
TCP/25066/B P/01557/04 Retention
of building providing stable, multi-use animal shelter & tack room for
storage of agricultural & forestry tools (revised scheme) Part OS
Parcel 0091 and 0072 south of Hulverstone Farm, Hulverstone Lane,
Hulverstone, Newport |
Brighstone |
Conditional
Approval |
10. |
TCP/25275/B P/02596/04 Demolition
of hotel; residential development comprising a total of 36 dwellings in a
mixed development of houses and flats with associated parking; formation of
vehicular and pedestrian access (revised scheme) Land
adjoining Hill House, Queens Road/2School Green Road/Brookbank/ Brookside
Forge, Brookside Road Freshwater |
Freshwater |
Conditional
Approval |
11. |
TCP/25288/A P/00480/04 Amendments
to approved pair of semi-detached houses ref: TCP/25288 (revised scheme)
(readvertised application) Land
adjacent Rookley Manor, Niton Road, Rookley, Ventnor |
Rookley |
Conditional
Approval |
12. |
TCP/25836/C P/01808/04 Provision
of 14 static caravan bases Thorness
Bay Holiday Park, Thorness Lane, Cowes |
Calbourne |
Conditional
Approval |
13. |
TCP/26052/B P/01400/04 Demolition
of warehouse and workshop; outline for 7 houses and alterations to vehicular
access (revised scheme) (readvertised application) Land
rear of St Leonards - Cornerways, Binstead Road, Ryde |
Ryde |
Conditional
Approval |
14. |
TCP/26467 P/01465/04 Demolition
of Woodington, The Undercliff Drive; landslide stabilisation works, ground
stabilisation, realignment of highway, landscaping & associated works
(scheme 1) 4 sections of land & (additional information) (readvertised
application) From Old
Park Hotel through to and including land west of Beauchamp, The Undercliffe Drive,
St. Lawrence, Ventnor |
Ventnor |
Conditional
Approval |
15 |
TCP/26467/A P/01467/04 Landslide
stabilisation works, ground stabilisation, realignment of highway,
landscaping & associated works, (scheme 2) 4 sections of land &
highway (application to be determined by the Council's Development Control
Committee) (additional information) (readvertised application) From Old
Park Hotel through to and including land west of Beauchamp, The Undercliffe
Drive, St. Lawrence |
Niton |
Conditional
Approval |
16 |
TCP/26498/B P/00063/05 Retention
of single storey side and rear extension; raised deck area and screening as
built 5 Avenue
Road, Shanklin |
Shanklin |
Refusal |
17. |
TCP/26689 P/02181/04 Demolition
of buildings; formation of temporary trailer park 2 industrial
buildings, Castle Street, East Cowes |
East
Cowes |
Conditional
Approval |
18. |
TCP/26732 P/02570/04 Alterations;
1st floor extension to provide additional living accommodation to include
French doors with railings (Revised Plans) Candleshoe
Cottage, Church Road, Cowes |
Cowes |
Conditional
Approval |
1. |
TCP/09568/J - P/01877/04 Parish/Name: Godshill
Ward: Wroxall and Godshill Registration Date: 03/09/2004 -
Outline Planning Permission Officer: Mr. J. Mackenzie Tel: (01983) 823567 Applicant: Mr M Flux Demolition of redundant farm
outbuildings; outline for 'Continuing Care Community' - a development
consisting of a nursing care home, 68 extra care cottages, 26 extra care
apartments, associated specialist indoor facilities, health care consulting
rooms, day care facilities, restaurant, creche, outdoor recreation/leisure
facilities; formation of vehicular access, pedestrian footpath links &
provision of parking land adjoining Scotland Farm and
properties in Dubbers and, Yarborough Close, Godshill, Ventnor, PO38 |
REASON FOR COMMITTEE
CONSIDERATION
The application is a
major submission, the proposal being a departure from the Unitary Development
Plan and there are a number of significant issues to be resolved.
PROCESSING INFORMATION
This application, if
determined at the meeting on the 15 February, will have taken 24 weeks to have
been processed, the delay being due to volume of applications and Christmas
break. In the event that Members accept your Officers recommendation and
resolve to approve the application it will be referred to the Government
Office. This will add further to the processing period.
LOCATION AND SITE
CHARACTERISTICS
The site has an area of
approximately 3.14 hectares, overall dimensions of 180 metres east to west and
a maximum of 220 metres north to south.
The land is presently
open, disused agricultural land, mostly overgrown with a slight fall from east
down to the west and marks the transition from the developed part of Godshill
into the open farm land on the settlement western side.
To the north and abutting
the northern boundary is the cul-de-sac development known as Dubbers, a
development of thirty two storey semi and terraced properties served by the
cul-de-sac linking directly with Newport Road. To the east are further
residential development abuts, the cul-de-sac known as Yarborough Close, a
development of about 50 units comprising bungalows, terraced properties, semi
detached and some maisonettes, accessed again off Newport Road.
To the south of the site
the remaining buildings are Scotland Farm and further to the south west and
west, an open agricultural landscape.
The bulk of Godshill
village lies to the east and south east; the land generally falls in a westerly
direction to a stream which is a tributary of the River Yar eventually emerging
at Bembridge.
A footpath runs along the
eastern boundary linking Dubbers to the junction of West Street with the
Whitwell Road where Scotland Farm presently accesses.
RELEVANT HISTORY
Outline planning
permission was granted for a golf course, hotel, country club, nursing home,
housing (65 dwellings), light industrial units, nature trail and community
facilities, land between Newport Road, Bagwitch Lane and Whitwell Road, west of
Godshill in March 1995. The approval granted included the application site and
much of Scotland Farm including much land to the west but the residential
development and buildings were concentrated in that area immediately abutting
Godshill village, including the application site.
DETAILS OF APPLICATION
The application is
submitted in outline form and seeks permission for the demolition of the
redundant farm buildings and the development of a continuing care community.
Siting and means of access are included for consideration in the proposal.
In summary, the proposed
facilities include:
50 bed en-suite nursing
care home
This part of the facility
would provide elderly care, dementia care, intermediate care, respite care and
palliative care. The care home would also include residents’ lounges, informal
meeting areas and dining areas.
68 close care units and
26 close care apartments
This part of the facility
would provide extra care facilities to residents to maintain a significant degree
of independence in individual units of accommodation. Ten of the 94 units
proposed would be provided for the South Wight Housing Association.
A site manager’s
accommodation and four staff flats
Social and general health
care facilities
These would include:
Reception area/offices
Sitting areas
Coffee shop
Restaurant
Lounge
Shop and hair salon
Spa and physiotherapy
Gym and health fitness
suite
Library
Computer room
Room for
gatherings/meetings/functions
Art/craft room
Visiting
doctors/consultants room
Community health care
Creche
Management office
Interview and meeting
room facilities
Staff facilities
Kitchens
Laundry.
External facilities
These would include:
Sensory garden
Petanque Court
Community Garden
Allotment garden
Public green/landscape
greens
Exercise walk
Residents parking
Visitor parking
Staff car parking
The proposed site layout
plan indicates:
Vehicular access being
achieved directly off Yarborough Close between 24a and 26 Yarborough Close
(currently occupied by the redundant agricultural building).
The construction of the
care complex and the social and health facilities in a cruciform shape in the
western part of the site.
The construction of a
series of close care units and apartments in courtyards with associated car parking
facilities.
Various open areas, a
petanque court and walkways within the site.
The application is
accompanied with details of its proposed operation should planning permission
be forthcoming. It is identified that the focus of the site is based on a
continuing care community which would provide care in a way which responds to
changing care needs and expectations. The proposal has been developed in
consultation with key health and care authorities on the Island including the
Isle of Wight NHS Primary Care Trust, and the Council’s Director of Adult &
Community Services. These are detailed later in this report.
The application is
accompanied by a detailed submission from planning consultants indicating how
the applicant proposes to put in place effective means of controlling and
regulating the development to ensure that it operates as intended. It is
indicated that:-
·
All qualifying residents must be in need of care. All care needs
assessments will be required from an independent source prior to acceptance of
residency.
·
Occupancy will be restricted to persons who are 60 and over, except
occupation by a spouse or partner under the qualifying age if living with the
person requiring appropriate care.
·
The continuing care community will be maintained in perpetuity - a
variety of types of tenure will be offered, but in all cases on termination of
occupation the units shall be surrendered to the operator.
·
The nursing care home and extra care accommodation shall be maintained
as a single planning unit, and sub-division and/or separation will not be
permitted.
·
A green travel plan would be prepared and implemented.
·
A detailed management plan would be prepared and agreed with the Council
to include: -
— preparation, monitoring and implementation of care plans
— all qualifying residents will have access to care packages
— the operator would work with Health & Social Services
authorities on the Island to provide long-term care contracts
—
allocation of extra care units to individual tenants.
DEVELOPMENT PLAN/POLICY
Outside designated
development envelope on Godshill inset of Unitary Development Plan (Development
boundary runs along eastern and north boundaries of the site) western boundary
is shown on UDP Plan as a former railway and Policy TR1 8 applies.
Cl Protection of Landscape Character
G1 Development Envelopes
G5 Development Outside Defined Settlements
Dl Standards of Design
D2 Standards for Development within the Site
D3 Landscaping
D11 Crime and Design
H9 Outside Development Boundaries
H15 Rural Exceptions
U3 Appropriate Location of Education,
Community, Social, Health and Welfare facilities and the Promotion of Sharing
and Dual Use
U9 Residential Care and Nursing Home Accommodation
PPG3 - Housing addresses
the need to create mixed communities of type and size of housing to be built;
the more efficient use of appropriate land, development linked to public
transport and sustainable residential environments. Site is not within an area
of outstanding natural beauty nor is it one designated as a site of special
scientific interest or one of importance to nature conservation.
CONSULTEE RESPONSES
Southern Water have
undertaken a sewer capacity check. There is sufficient foul sewer capacity to
serve the site.
Environment Agency confirms
no objection subject to conditions. Environmental Health Officer/Contamination
recommends conditions if approved.
County Archeologist
recognizes that archaeology is likely to be found on this site and could be of
regional and local importance but recommends conditions if approved.
PARISH/TOWN COUNCIL
COMMENTS
Godshill Parish Council
support the proposal but question the suitability of the means of access to the
site.
THIRD PARTY
REPRESENTATIONS
Isle of Wight NHS Primary
Care support the development based on the principle of independence stating
that the development fits with NHS doctrine regarding elderly health care and
provides much needed accommodation of this type thus relieving pressure on
hospital services.
NHS (St Mary’s Close)
supports the development as it helps to prevent bed blocking.
South Wight Housing
Association support indicating that discussions have taken place with regard to
the provision of affordable housing as part of the provision.
Nine letters of support
from local and Isle of Wight resident applauding the diversification of the
type of care accommodation, stating that examples exist elsewhere and that this
is the best way forward thus filling a gap in the provision of health care for
the elderly.
Twelve letters of objection
from local residents on grounds of inadequate access from Yarborough Close, to
pedestrians, cyclists and children; creating congestion in Yarborough Close
especially with the doctor’s surgery. Creation of a precedence for developments
outside the development envelopes; visual impact; light and noise pollution;
adverse effect on ecology; overburdening the infrastructure; loss of high grade
agricultural land; inadequate drainage. Some writers suggest that access would
be better off West Street.
Island Watch object on
grounds of development outside the development envelope, creation of a
population imbalance in Godshill, that the employment created is not the type
of jobs that which are required.
CRIME AND DISORDER
IMPLICATIONS
Relevant officer has been
given the opportunity to comment but at the time writing no observations have
been received. It is not anticipated that objections on crime and disorder
would be forthcoming but comments on the detailed design may be appropriate at
detailed stage in the event that this application is successful.
EVALUATION
The application raises
several complex matters. In your officer’s opinion there are four main issues
central to the determination of this application as follows:
1. National and local planning policies
2. The sustainability of the site and the use proposed
3. The nature and extent of the health care
facilities incorporated into the proposed development
4.
The impact of the proposed development on the capacity and safety of the
junction between Newport Road and Yarborough Close.
Other factors which are
material to the determination of the application include the impact of the
development on the amenities of surrounding properties, its impact on rights of
way, the impact of the proposal on the general setting and appearance of
Godshill in the wider landscape, and the employment generated. These various
issues are addressed below.
National and local
planning policies
The application site is
adjacent to, but outside the designated development envelope of Godshill as
identified in the Inset Map T of the Unitary Development Plan. As such the
proposal is contrary to Strategic Policies 1, 2 and 3 of the Unitary
Development Plan. In summary these strategic policies indicate that new development
will be concentrated within existing urban areas (SI), will be encouraged on
previously developed land (S2) and that new developments of a large scale will
be expected to be located in Cowes/East Cowes, Newport, Ryde and
Sandown/Shanklin (S3).
In detailed policy terms
the application site conflicts with Policy G1 (it is outside the Godshill
development envelope) and does not comply with the various types of development
which may exceptionally be permitted outside the defined settlements boundaries
(Policy G5).
In more general policy
terms, Policy U9 of the Unitary Development Plan sets out that the development
of new elderly persons’ accommodation, nursing homes and mental care homes will
not be approved unless a variety of criteria are satisfied as follows:
(a) they are of a size which can be
assimilated into the locality
(b) reasonably level access is provided to
and within the site
(c) Safe access for ambulances and cars is
available
(d) There is on-site provision for parking
and turning of staff and visitor
vehicles
(e) There is easy access to public transport
(f) The site is within easy walking distance
of the amenities of the settlement
(g) The building is fit for the purpose for
the specific number of residents.
The proposal complies
with criteria (b), (c), (d), (f) and (g) of this policy. In respect of
criterion (a) (size — assimilation into the locality) the assessment of
compliance is more subjective; and on the one hand is area of the site (3
hectares) is minor in relation to the area within the Godshill development
envelope (xx hectares); on the other hand the potential occupancy of the
development (approximately 250 persons) is significant in relation to the
village population of 1,022. In respect of criteria (e) bus stops on Newport
Road are approximately 200 metres (from Newport) and 300 metres (to Newport)
from the entrance to the site.
Policies H9 and H15 of
the UDP allow for some residential development outside development boundaries
and locally affordable housing respectively. The application includes a limited
degree of affordable housing. However, given the size of the development as a
whole these policies should be given little weight.
Sustainability of the
site and the use proposed
Strategy Policy S3 of the
UDP indicates that major new development will be expected to be located in or
adjacent the main Island towns where the principal services and infrastructure
are located. The sustainability or otherwise of the site and the proposal are
key factors, particularly given the size of the site and the number of journeys
likely to be generated to and from the premises on a daily basis. In supporting
information submitted with the application the applicant indicates that other
locations have been considered including the Polars Care House, Staplers,
Newport, the allocated housing site at Pan, and Whitecroft. It is indicated
that the various sites are not wholly suitable for the type of facilities
proposed at Godshill nor are they readily available. It is clear that the Godshill
site is not as sustainable as would be a location in one of the Island’s larger
towns. Nonetheless, the applicant indicates that the proposed facility is
intended to serve the whole of the Island’s elderly community and that Godshill
is centrally located within the Island with particularly good accessibility to
Newport and Sandown/Shanklin. Similarly, the village is situated on a principal
bus route.
In recognition of these
various matters, the applicant has submitted a draft Travel Plan setting out an
overview of proposals to regulate and control travel movements to the site. The
site would be provided with its own 17 seat minibus (equipped with a tail lift
facility) based on the site with a dedicated driver. It is also envisaged that
a people carrier-type vehicle would be available. The minibus will collect and
deliver staff on a round trip basis, and will make daily visits to town
centres, and regular visits to other facilities such as hospitals, retail
outlets, churches etc. It is also proposed to make available a selection of
pooled cars and electric buggies for short journeys (eg. into Godshill).
The nature and extent of
health facilities offered
The basis of the proposal
has already been set out in the Details of the Application. The type of care
facility proposed on the site is relatively new within the UK, and the
development is based on the Joseph Rowntree Foundation scheme at Hartrigg Oaks,
York. In effect the concept of a continuing care facility incorporates
individual residential/care units with a care home and all other facilities
both operationally and legally. The site would provide:
·
opportunities for older people to lead full and active lives knowing
that care support is at hand if required.
·
specially designed accommodation
·
flexible levels of care
·
dedicated residential and nursing care delivered either in residents own
care accommodation or in the care homes
·
provision of on-site respite care
·
Access to a range of social, educational and recreational facilities.
The nature of the proposed use has attracted a high level of support from health organisations on the Island. The Isle of Wight NHS Primary Care Trust indicate that the proposal supports the wider policy of transfer of care from hospital in-patient settings to care in the community. Similarly, its development would be consistent with the planned reductions in acute hospital (St Mary’s) beds. The Isle of Wight Healthcare NHS Trust also supports the scheme, commenting that it would provide much needed nursing homes provision for the Island, and would prevent further bed blocking. The proposal has the support of the Council’s Strategic Director of Adult and Community Services.
In determining the
application Members need to assess whether the specific nature and purpose of
the proposal is sufficiently important to outweigh the planning policy and
locational objections to the proposed development.
Capacity and safety of
the junction of Yarborough Close and Newport Road
The proposed access into
the site has been raised as an objection to the proposal by several local
residents. A traffic assessment provided on behalf of the applicant concludes
that there is sufficient capacity in the local highway network to cater for the
development. This view is supported by the Council’s Highway Engineer. In
recent discussions on the capacity of the junction of Yarborough Close and
Newport Road to cater for the increased traffic which would originate from this
proposed development, the applicant’s highways consultant and the Council’s
Highways Engineer have agreed for the need for a right hand turn lane into
Yarborough Close in the event that permission is forthcoming.
Impact on surrounding
properties
A detailed layout is
submitted with the application, which seeks permission for the siting of the
various facilities and accommodation in the site. In general terms the proposed
development will not have an unacceptable impact on the amenities of
surrounding properties. Typically, there is a distance of 12 to 15 metres from
the rear of properties in Yarborough Close to the rear of the proposed close
care accommodation units in the eastern part of the site. The equivalent
distance is 18 metres between the properties in the northern part of the site
to the rear of adjacent properties in Dubbers (le to the north of the site).
This impact will be further reduced given the limited height of the individual
units of accommodation. The care homes and social and health facilities are
located to the west of the site, and will be a considerable distance from
existing properties.
Impact on rights of way
A bridleway (GL23) runs
adjacent to the eastern boundary of the site, linking Dubbers with West Street
(to the south). Another bridleway (GL22) passes from West Street to the former
railway station, although this is unaffected by the proposed development. The
route of the former railway line forms the western boundary of the site. Policy
TR18 of the UDP indicates that this and other railway lines should be
safeguarded from development to allow their use for sustainable transport
purposes. In the event that Members were minded to approve the proposal
conditions could be imposed on the consent to control the realignment of GL23,
and to safeguard the western extremity of the site in accordance with Policy TR1
8. Whilst it may be possible to incorporate some form of access through the
south west corner of the site onto GL22, this would be impractical to achieve
by way of condition.
Impact of proposal on the
setting and appearance of Godshill
The application site is
not immediately visible within the village. It is not easily visible from
Newport Road whether approaching the village from the north or from the south
towards West Street. In a wider context the site is open and exposed to the
west, and significant landscaping will be required to reduce an otherwise stark
impact from the open countryside. In more localised terms, the proposed
demolition of the redundant agricultural buildings of Yarborough Close to
facilitate access into the site will improve the amenities of properties in
that immediate locality. This will be enhanced by the creation of open spaces
both to the north and south of the proposed access.
Employment generation
In supporting information
the applicant indicates that the proposed development will support in excess of
120 jobs, which will include managers, nurses, nursing auxiliaries, carers,
administrators, domestics, drivers etc. It is indicated that experience would
suggest that specialist/senior posts are filled from an Island-wide catchments.
The majority of other jobs would be filled from a closer area. The on-site
minibus would be available to transport staff to the site as part of the Green
Travel Plan.
Summary
There are a wide range of
policy and other material considerations for Members to consider in their
determination of this proposal. Your officers suggest that the case is finely
balanced. On the one hand the application site is located in the countryside
and is contrary to strategic and detailed policies in the UDP. This in itself
is sufficient to justify a refusal of the application. Similarly, whilst
Godshill has a range of local facilities, it does not provide the range of
services that are to be found in the four main urban centres on the Island. On
the other hand the proposal is an innovative and well-designed scheme seeking
to cater for older people on the Island in a community care setting and
responding to the wider health care agenda being developed by health
organisations on the Island. In this sense the scheme has attracted
considerable support from the local community. There are no technical or site
specific matters which would specifically prevent the development from coming
forward in an acceptable way and within the context and fabric of Godshill in
general, and the immediate locality in particular.
Having considered the
various matters set out in this report your officers consider that there is
merit in departing from policy and recommending the approval of the proposal.
The scheme accords with the strategic approach of health authorities on the
Island, and will create a continuing care community on the Island which will
provide for the long-term need of elderly people in a creative and embracing
way. To this extent the proposal is sufficiently important to be considered as
an exception to normal policy considerations. The proposal could be
appropriately incorporated into the Godshill environment and would have an
acceptable impact on the amenities of local residential properties. Other
strategic objectives such as the safeguarding of the former railway line would
not be prejudiced by the development of the site. Detailed matters relating to
the management and tenancy of the schemes, and off-site highway improvements
could be covered by a Section 106 Agreement/unilateral undertaking.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission, consideration has been given to
the rights set out in Article 8 (Right to Privacy) and Article 1 of the first
Protocol (Rights to Peaceful Enjoyment of Possessions) of the European
convention on Human Rights. The impact this development might have on the
owners/occupiers of the other properties in the area and other third parties
have been carefully considered. It is considered that the recommendation to approve
is proportional to the social, health, related and economic benefits to the
community and is in the wider public interest. Whilst the recommendation to
approve is contrary to the site specific policies of the Council’s Unitary
Development Plan the reasons for so departing are set out earlier in this
report.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to the material considerations as
described above in the
evaluation section it is felt that although this much needed facility is highly
desirable in concept at, specification and layout, the site is not appropriate
for this use due to its location, due to the scale envisaged and relationship
with the village and other local services and that an exception to the normal constraint
policies of development outside designated development envelopes and in the
countryside is justified. The proposal would therefore be contrary to strategic
and detailed rural development policies contained within the Isle of Wight
Unitary Development Plan.
RECOMMENDATION – APPROVAL
The application is both a
major application and has been advertised as a departure from the development
plan. In these circumstances, and if a local planning authority is minded to
approve the proposal, the application needs to be referred to the appropriate
Government office.
In these circumstances it
is recommended that the Government Office for the South East be advised that
the Council is minded to APPROVE the application subject to the following legal
agreement and conditions.
Legal Agreement to cover:
a) a detailed management
plan on care facilities
b) age and occupancy
controls
c) provision of
affordable housing
d) preparation and
implementation of Green Travel plan
e) off-site highway works
Conditions/Reasons:
1 |
Time limit - outline -
A01 |
2 |
Time limit - reserved -
A02 |
3 |
Approval of the details
of the design and external appearance of the building(s), thereto and the
landscaping of the site (hereinafter called "the reserved matters")
shall be obtained from the Local Planning Authority in writing before any
development is commenced. Reason: In order to secure a satisfactory
development and be in accordance with policies S6 (Standards of Design), D1
(Standards of Design), D2 (Standards of Development Within the Site), D3
(Landscaping), TR7 (Highway Consideration for New Development) of the IW
Unitary Development Plan. |
4 |
The facilities
associated with the continuing care community hereby approved (comprising
associated specialist indoor facilities, health care consulting rooms, day
care facilities, restaurant, creche and outdoor recreation/leisure
facilities) shall be maintained in perpetuity in single ownership and shall
not be sold or disposed separately in any way. Reason: The site is in a
location where commercial enterprises for general public use would not be
approved and where additional traffic supporting such activities would
increase traffic levels to an unacceptable level and in accordance with
Policies G1 and TR7 of the IOW Unitary Development Plan. |
5 |
Details of roads, etc, design and
constr - J01 |
6 |
Details of roads, etc, design and
constr - J02 |
7 |
No dwelling shall be
occupied until the parts of the service roads which provide access to it have
been constructed, surfaced and drained in accordance with the approved
plans/details which have been submitted to and approved by the Local Planning
Authority. Reason: To ensure an adequate standard of highway
and access for the proposed dwellings and to comply with policy TR7 (Highway
Considerations) of the IW Unitary Development Plan. |
8 |
Visibility and sight lines -
J20 |
9 |
Access - junction details -
J36 |
10 |
The development shall
not be brought into use until a vehicle parking layout consistent with the IW
Unitary Development Plan Parking Guidelines has been provided within the
curtilage of the site in a formal manner that shall be submitted to and
approved by the Local Planning Authority and thereafter all of those spaces
shall be kept available for such purposes. The agreed scheme shall be
implemented before the development hereby permitted is brought into use. |
11 |
No building hereby
permitted shall be occupied until space has been laid out within the site,
drained and surfaced in accordance with details that have been submitted to
and approved by the Local Planning Authority in writing for cars and bicycles
to be parked, for vehicles to be loaded and unloaded and for vehicles to turn
so that they may enter and leave the site in forward gear. The space shall not thereafter be used for
any purpose other than that approved in accordance with this condition. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
12 |
No building hereby
permitted shall be brought into use until highway improvements as described
in Conditions 8 and 9 have been carried out in accordance with details to be
submitted and approved in writing by the Local Planning Authority. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Consideration) of the
IOW Unitary Development Plan) |
13 |
Lorry routing -
L19 |
14 |
The surfacing of the
access from West Street, Godshill shall be maintained in a good state of
repair and kept clear and free of mud and debris at all time until completion
of the development hereby approved. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Consideration) of the
IOW Unitary Development Plan) |
15 |
Before any development
commences, details of the arrangements to be made to ensure safe passage of
construction traffic to include for improvement to the existing vehicular
acres and haul road serving the site from West Street, Godshill shall be
submitted to and approved in writing by the Local Planning Authority. All
works included in the approved details shall be carried out before
construction of the development hereby approved commences. Reason: In the interests of highway safety and to
comply with Policy TR7 (Highway Considerations) of the IOW Unitary
Development Plan. |
16 |
Highway safety -
L18 |
17 |
No construction traffic
associated with the development shall travel over Yarborough Close. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Consideration) of the
IOW Unitary Development Plan) |
18 |
Notwithstanding the
provision of the Town & Country Planning (General Development) Order 1995
(or any order revoking or re-enacting that Order) no gates shall be erected
without the prior written consent of the Local Planning Authority. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Consideration) of the
IOW Unitary Development Plan) |
19 |
Prior to commencement
of any development hereby approved, details of the design, construction,
surface water, drainage and signing and lining of a right turn lane plus all
associated works within Newport Road, Godshill at its junction with
Yarborough Close shall be submitted to and approved by the Local Planning
Authority and the development shall not be occupied until the right turn lane
has been provided and completed in accordance with the approved details. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Consideration) of the
IOW Unitary Development Plan) |
20 |
The staff flats hereby
approved shall not be occupied other than by members of staff of the
Continuing Care Community hereby approved. Reason: The site is in a
location where residential development would not otherwise be approved and in
accordance with Policies H4 and H9 of the IOW Unitary Development Plan. |
21 |
No external lighting
shall be installed or operated other than in accordance with a scheme which
has been submitted to and approved in writing by the Local Planning
Authority. Reason: In order to minimise environmental
pollution and in accordance with Policies C1 (Protection of Landscape
Character) and P1 (Pollution and Development) of the IOW Unitary Development
Plan. |
22 |
Foul drainage -
V24 |
23 |
Withdraw PD rights
alterat/extens/etc - R02 |
24 |
The bungalows hereby
approved shall not be enclosed by hedges, walls or fences and no individual
curtilages shall be formed without the prior written consent of the Local
Planning Authority. |
25 |
The route and corridor
of the former railway line abutting the western boundary of the site shall be
kept clear in its entirety and segregated from the site with a boundary fence
and/or hedge details of which shall be submitted to and approved by the Local
Planning Authority prior to the commencement of any development on site. The
agreed means of segregation shall be carried out prior to the development
hereby approved being brought into use. Reason: In the interests of the
amenities of the area and in the interests of maintaining a clear route for
sustainable transport and in accordance with Policy C1 (Protection of
Landscape Character) and Policy TR18 (Railway Lines and Former Railway Lines)
of the IOW Unitary Development Plan. |
2. |
TCPL/21027/B P/02088/04 Parish/Name: Shalfleet
Ward: Shalfleet and Yarmouth Registration Date: 01/10/2004 -
Full Planning Permission Officer: Miss. S. Wilkinson Tel: (01983) 823566 Applicant: Ms R Nihell Conversion of garage into unit of
holiday accommodation, (revised scheme) Brookside Cottage, Main Road,
Ningwood, Newport, Isle Of Wight, PO304NW |
Joint Report - See LBC/21027/C
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
Notwithstanding the
details on the submitted plans, no development shall take place until samples
of materials to be used in the construction of the external surfaces, windows
and doors of the development hereby approved have been submitted to and
approved in wiring by the Local Planning Authority. Development shall be
carried out in accordance with the approved details. Reason: In the interest of the
amenities of the area and to comply with Policy D1 (Standards of Design) and
B2 (Setting of Listed Buildings) of the IOW Unitary Development Plan. |
3 |
The doors and ??
[door/window]?? frames of the building shall be constructed of timber
and shall be painted and thereafter maintained to match those of the existing
building. Reason: To protect the character and appearance of
the existing building and to comply with policies B1 to B8 (Listed Buildings
and Conservation Areas) of the IW Unitary Development Plan. |
4 |
Development hereby
approved shall be used solely as ancillary accommodation to the main dwelling
and bed and breakfast use therein. Reason: The unit of
accommodation is not of a satisfactory standard or in a satisfactory position
in relation to the main house to be occupied separately and would not comply
with D1 (Standards of Design) of the IOW Unitary Development Plan. |
5 |
The unit of holiday
accommodation hereby approved shall not be sold off, leased or otherwise
disposed of separately but shall be retained in one ownership with the
dwelling house known as Brookside Cottages unless the prior consent of the
Local Planning Authority is obtained. Reason: The unit of
accommodation is not in a satisfactory position in relation to the main
dwelling to be occupied separately and would not comply with Policy D1
(Standards of Design) of the IOW Unitary Development Plan. |
3. |
LBC/21027/C P/02304/04 Parish/Name: Shalfleet
Ward: Shalfleet and Yarmouth Registration Date: 02/11/2004 -
Listed Building Consent Officer: Miss. S. Wilkinson Tel: (01983) 823566 Applicant: Mr R Nihell LBC for conversion of garage into
unit of holiday accommodation (revised scheme) Brookside Cottage, Main Road,
Ningwood, Newport, Isle Of Wight, PO304NW |
REASON FOR COMMITTEE
CONSIDERATION
Report requested by local
Member, Councillor Mrs Butchers as she is not prepared to agree to the
application being dealt with under the delegated procedure for the following
reasons:
·
Inconsistency with other decisions in the area - detached annexes
previously refused.
·
Garage is detached from main house and she is concerned that it may be
difficult to resist separation at a later date.
PROCESSING INFORMATION
This is a minor
application, the processing which has gone beyond the prescribed eight week
period for determination of planning applications due to case Officer work load
and the need for Committee consideration.
LOCATION AND SITE
CHARACTERISTICS
Brookside Cottage is
located on Main Road, Ningwood, 200 metres west of the junction with Station
Road. The surrounding residential development is sporadic with a farm to the
west and nursery to the east. Brookside Cottage is a Grade II Listed Building
currently run as an AA Registered Bed and Breakfast. The rear boundary of the
site is separated from the fields to the south by tributaries of the Ningwood
Lake designated as a main river line by the Environment Agency.
RELEVANT HISTORY
TCP/21017/A - An application was refused in July 2004
for the conversion of garage into unit of holiday accommodation and two storey
extension to form replacement garage and additional holiday accommodation. The
reasons for refusal were directly related to the impact of the extension on the
Listed Building and possible impact on the water course and not in relation to
the change of use. The proposal was at that stage contrary to specific policies
B2 (Setting of a Listed Building) and G6 (Development Areas Liable to Flooding)
of the IOW Unitary Development Plan.
DETAILS OF APPLICATION
Consent is sought for
Listed Building Consent and Planning Permission for the conversion of the
garage into a unit of holiday accommodation. The garage is currently attached
to the main house with a wall that also falls within the listing. The existing
garage has a painted green up and over door with dark stained boarding to the
front gable. The application involves the removal of the existing garage door
and its replacement with two windows to the front elevation and a door within
the rear. The proposal would provide a self contained holiday unit in
connection with the operation from the main dwelling house of a Bed and
Breakfast facility.
DEVELOPMENT PLAN/POLICY
Site is located outside
the development envelope as defined on the Isle of Wight Unitary Development
Plan. Relevant policies of the plan are considered to be as follows:
S4 – The countryside will
be protected from inappropriate development.
S6 – Development will be
expected to be of a high standard of design.
G1 – Development
Envelopes for towns and villages.
G4 – General Locational
Criteria.
G5 – Development outside
defined settlements
G6 – Development in areas
liable to flooding.
D1 – Standards of Design
D2 – Standards of
Development within the site.
B2 – Settings of Listed
Buildings.
C1 – Protection of
Landscape Character
C17 – Conversion of Barns
and other rural buildings.
T1 – The implementation
of Tourism and the extension of the sea
T3 – Criteria for
Development to Holiday Accommodation
TR7 – Highway
Consideration for new development
CONSULTEE RESPONSES
The Environment Agency
placed an initial holding objection in relation to the extension on grounds of insufficient
information in order to assess its impact on the tributaries of the Ningwood
Lake. However, following discussions to clarify that the current application
involved no extension and a pure change of use, the holding objection was
removed and a subsequent letter sent confirming no objection to the proposal.
The Area of Outstanding
Natural Beauty Partnership submitted no comment.
Highway Engineer
recommends conditions should the application be approved.
PARISH/TOWN COUNCIL
COMMENTS
Shalfleet Parish Council
objected on grounds that can be summarized as follows:
·
Contrary to Village Design Statement
·
Concerns about access
·
Loss of privacy for neighbouring property
THIRD PARTY
REPRESENTATIONS
One letter of objection was received from neighbouring property with grounds for objection which can be summarized as follows:
·
Noise
·
Increase in traffic
·
Does not comply with Ningwood Village Design Statement “green gaps”
specifically.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder implications
are anticipated.
EVALUATION
Determining factors in
considering this application are whether the provision of rural tourism on an
established tourist site is in line with policies set out in the Unitary
Development Plan.
This application follows
a refusal on the same site for a conversion of a garage into a unit of holiday
accommodation and two storey extension to form replacement garage and
additional holiday accommodation. The application was refused due to the impact
of the extension on the setting of the Listed Building and insufficient
information for the Environment Agency to fully assess the application.
The current application
under consideration has removed the extension element in order to overcome both
objections. The Environment Agency did place a holding objection on the
application for lack of information in regards to the impact of construction
works on the nearby tributary of the Ningwood Lake. However, following
confirmation that the building was to now only be converted and not extended
they removed the objection.
Brookside Cottage is a
Grade II Listed Building. In the previous application Conservation Officer
raised concern that the size of the extension increased the visual dominance of
the garage affecting the setting of the Listed Building as it would have the
appearance of a separate unit rather than an ancillary outbuilding. The simple
conversion of the garage and inclusion of windows replacing the up and over
garage door with matching materials will retain the appearance of an
outbuilding in connection with the main dwelling house. Although we would not
encourage the change of use of outbuildings within isolated rural locations for
self contained units, in this instance there is already a bed and breakfast
business (AA registered) run from this site and the garage is within close
proximity to the main house attached by a boundary wall, thus making
sub-division more difficult. However, any approval can be conditioned
accordingly to retain the unit with the main dwelling house known as Brookside
Cottage.
Concerns have been raised
in relation to noise, linked with both the possible increase in traffic and
additional visitors. Due to the size of the unit and nature of its occupancy,
it is unlikely increases in noise and traffic would be significant enough to
cause unacceptable disturbance to neighbouring and surrounding properties.
The Ningwood Village
Design Statement discusses the protection of “green gaps” between and within
settlements, concerns have been raised that the proposal would impact on green
gaps. However, as there is no new building proposed I do not feel that there
would be any works contrary to those policies within the Ningwood Village
Design Statement or the Unitary Development Plan.
Additional concerns have
been raised regarding the access to the site, however, conditional approval has
been suggested by Highway Engineer.
Objections have also been
raised in regards to loss of privacy to the neighbouring property. However, the site is surrounded by extensive
natural growth and boundary treatment and with all windows at ground floor
level, no overlooking or loss of privacy is anticipated.
An application for the
conversion of a garage to form a holiday unit without any other business use on
site would not necessarily be supported. However, in this instance having
regard to the existence of a business use on site, policies favour the
extension of that use in order to attract more visitors and make a positive
contribution to the rural economy.
Policy T3 (Criteria for
Development of Holiday Accommodation) and Policy T9 (Small Scale rural tourism
development) are particularly relevant to the current proposal and clearly
indicate that the development of holiday accommodation will be acceptable in
principle where, it is associated with another established holiday
accommodation use. Within Policy T9 (c) allowance in made for the change of use
of suitable residential properties in the countryside to hotels, restaurants or
hostels. In this instance, as an establish bed and breakfast is operated from
the site, the change of use of associated garage would improve the present
level of accommodation available on site, making best use of available
buildings on site to extend the holiday season.
When considering all
relevant policies within the Unitary Development Plan and fully assessing the
impact of a change of use of this nature, I consider that due to the existing
bed and breakfast use on site and the degree to which the existing garage is
connected to and associated with the main house, subdivision is unlikely and as
such is in compliance with policies within the Unitary Development Plan, I
consider the application to be acceptable having a minimal impact on the
surrounding area and neighbouring property.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European Convention
on Human Rights. The impacts this
development might have on the owners/occupiers of other property in the area
and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the rights of others it
is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that
such action is proportional to the legitimate aim of the Council’s Unitary
Development Plan and in the public interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I am of the opinion that, due to the established AA registered bed and
breakfast accommodation on site, the conversion of the garage, attached to the
main dwelling house by way of a Listed boundary wall, would comply with policies
set out within the Isle of Wight Unitary Development Plan. This weighed with
the need and demand for additional tourist accommodation and the importance of
tourism to the Island’s economy, the proposal is considered to be acceptable.
RECOMMENDATION – Approval
Conditions/Reasons:
1 |
The works hereby
authorised shall be begun not later than 5 years from the date of this
consent. Reason: As required by Section 18 Planning (Listed
Buildings and Conservation Areas) Act 1990. |
2 |
Notwithstanding the
details on the submitted plans, no development shall take place until samples
of materials to be used in the construction of the external surfaces, windows
and doors of the development hereby approved have been submitted to and
approved in writing by the Local Planning Authority. Development shall be
carried out in accordance with the approved details. Reason: In the interest of the
amenities of the area and to comply with Policy D1 (Standards of Design) and
B2 (Setting of Listed Buildings) of the IOW Unitary Development Plan. |
4. |
TCP/22670/D P/01656/04 Parish/Name: Seaview
Ward: Seaview & Nettlestone Registration Date: 06/08/2004 -
Full Planning Permission Officer: Mr. A. White Tel: (01983) 823550 Applicant: Westridge Racing Provision of 5 lighting columns
8.0m high for go-kart track (revised scheme) land adjacent Westridge Leisure
Centre, Brading Road, Ryde, PO33 |
REASON FOR COMMITTEE CONSIDERATION
The local Member,
Councillor Barry, has requested that this application is reported to Committee
owing to the nature of application and public concern.
PROCESSING INFORMATION
This is a minor
application, the processing of which has taken 28 weeks to date and has gone
beyond the prescribed 8 week period for determination of planning applications
owing to protracted negotiations with applicant and the heavy workload of
Development Control Officers.
LOCATION AND SITE
CHARACTERISTICS
Site is situated behind
Westridge Leisure Centre, immediately south of Cothey Bottom Copse and is
currently being developed with an outdoor go-karting facility.
Area is characterized by
mixed use development comprising of Westridge Leisure Centre itself, Golf Club,
Tesco, industrial and residential at Bullen Village. The latter being situated
some 200 metres away in a northwesterly direction.
RELEVANT HISTORY
TCP/22670/C – P/2500/03 –
Use of land for outdoor go–kart track with building to provide café and
associated facilities; storage building and workshop. Land to rear of Westridge
Leisure Centre. Consent granted subject to a Section 106 Agreement in respect
of a financial contribution in June 2004 in respect of double glazing provision
at Westridge Centre Offices.
DETAILS OF APPLICATION
Consent is sought for a
lighting scheme to be operated in conjunction with the go-karting track.
Members are reminded that the track is subject of a condition in respect of
operating hours stating that karts should only be used on the premises between
09.00 hrs and 21.00 hrs.
This application is
subject of a revised scheme. The latest plans show 5 x 8 metre high flood
lights columns supporting a total number of 13 light heads. Three columns,
comprising of nine light heads, would be situated adjacent the north east boundary
which divides application site from adjoining woodland and fields. The two
other columns would be situated in a more central position on the inside of the
track and would support four light heads.
Proposed scheme has been
designed by a specialist company with brief of concentrating as much light as
possible onto the target area. Each light fitting would offer 1kW of
power. The wattage dictates the number
of lights and height of columns.
Revised plans show that light heads would now face away from the
settlement of Nettlestone and Seaview.
All lights are now shown to face towards the back of Westridge Leisure
Centre or thereabouts.
Proposed columns resemble
typical lamp posts with a galvanised finish.
DEVELOPMENT PLAN/POLICY
Site is situated outside
any development envelope boundary as defined on the IOW Unitary Development
Plan (UDP), but is specifically allocated as a Tourist Development Area. The
following policies are considered to be relevant:
S4 – The Countryside will be protected from inappropriate
development
S6 – All development will be expected to be of a high
standard of design
G1 – Development envelopes for towns and villages
G4 – General Locational criteria for development
G5 – Development outside defined settlements
D1 – Standards of Design
D2 – Standards for development within the site
D14 - Light Spillage
L2 – Formal recreation provision
T1 – Promotion of tourism and extension of season
T2 – Tourism related development
T7 – Site suitable for tourism related development
CONSULTEE RESPONSES
None.
PARISH/TOWN COUNCIL
COMMENTS
Seaview Parish Council
express concern on grounds that lighting in this area is a contentious issue
and that the original plans for lighting contained within the banking appeared
to be far more 'environmentally friendly'.
THIRD PARTY
REPRESENTATIONS
Two letters have been
received from Seaview residents who object on grounds of light pollution and
that siting columns on ridge would impact on landscape character.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
Members will be aware
that consent has recently been granted for an outdoor go-kart track and that
work is now well underway with anticipated completion date of April 2005. In order to maximize the recreation and
tourism benefits of this facility, the applicant proposes a lighting scheme so
that the track can be used during winter evenings and darker conditions.
Although outside of the development envelope boundary for Ryde as identified on the UDP, policy G5 does allow for small scale development ancillary to tourist and recreational development. More specifically, D14 refers to external lighting and states that the following, amongst others, should be considered:
·
Lighting scheme is minimum required for the task
·
Light spillage is minimized, particularly skywards
·
Screened from view from neighbouring countryside.
·
Designed so as not to unreasonably affect neighbouring properties.
The proposed scheme has
been examined thoroughly to ensure that it strikes the balance of providing
minimum lighting required for the task, without impacting unduly on
neighbouring property occupiers or surrounding area in general through light
spillage or visual intrusiveness. It was
suggested to applicant that he consider reducing light columns to ensure that
the proposed scheme would be totally shielded by adjoining trees. However,
lowering columns to 6 metres would have entailed using 400 watt bulbs in order
to minimise glare to drivers. This
would have necessitated some 22 light fittings. This, in my view, would have
resulted in over proliferation of lights on this site.
With this in mind, the
agent maintained his proposal for 5 x 8 metre high columns but has reconfigured
the scheme so that lights would not face in the Seaview/Nettlestone direction.
Furthermore, detailed sections have been submitted showing that the highest
part of certain columns would be almost level with or slightly lower than the
adjoining tree line at Cothey Bottom Copse.
Proposed lighting is
shown as being directed downward onto the target area thereby not spilling
significantly beyond the perimeter of the site or skywards. This is achieved
through setting light head at a certain angle, incorporating light shields and
a symmetric reflector. Site is also well separated from nearest residential
properties either by woodland, field or adjoining employment site. Any
spillage, therefore, would not, in my opinion, impact significantly, if at all,
on nearby residents. In terms of visual impact of lights and associated
columns, given the revised orientation of light heads, intervening natural
growth, relatively high ambient light level in the area and appropriate
condition restricting hours of use, it is my view that the proposed lights
would no be visually intrusive in the landscape.
Taking the above points
into consideration, it is felt that the level of lighting proposed is
reasonable, necessary and minimum required for its intended purpose, and that
the resultant impact through spillage or visual impact would not be
significant. Accordingly, proposal accords with UDP policies, particularly G4,
D1, D2, D14 and C1.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of other property in the
area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the
rights of others it is considered necessary for the protection of the rights
and freedom of the applicant. It is
also considered that such action is proportional to the legitimate aim of the
Council’s Unitary Development Plan and in the public interest.
JUSTIFICATION FOR
DECISION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I consider that lighting scheme as an ancillary development to approved
go-karting track is acceptable in principle.
Following submission of revised and additional information, I am also
satisfied that proposed lighting scheme, being the minimum required for the
go-karting track, would have few implications in terms of light spillage and
would not be excessively intrusive in the surrounding landscape, either in
hours of daylight or darkness.
Accordingly, proposal accords with UDP policies.
RECOMMENDATION - Approval (Revised
scheme)
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
The lighting scheme
hereby approved shall only be operated between 09.00 hrs and 21.00 hrs daily. Reason: In the interests of the
amenities of the area and to comply with Policies G4 (General Locational
Criteria for Development), D1 (Standards of Design), D2 (Standards for
Development within the site) and D14 (Light Spillage) of the IOW Unitary
Development Plan. |
3 |
There should be no
alteration to the lighting scheme or levels of illumination hereby approved
without the express written consent of the Local Planning Authority. Reason: In the interests of
the amenities of the area and to comply with Policies G4 (General Locational
Criteria for Development), D1 (Standards of Design), D2 (Standards for
Development within the site) and D14 (Light Spillage) of the IOW Unitary
Development Plan. |
5. |
TCPL/23329/H P/01917/04 Parish/Name: Cowes
Ward: Cowes Castle East Registration Date: 09/09/2004 -
Full Planning Permission Officer: Mr. A. Pegram Tel: (01983) 823575 Applicant: Mrs P Lewington Construction of yacht haven &
town pier section of foreshore between The
Royal Yacht Squadron and opposite the bandstand, The Parade, Cowes, PO31 |
See joint report under reference
LBC/23329/J.
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
Prior to any work
commencing on site, a full method statement providing details of the
timescales for carrying out of the operations, the means of construction,
delivery and storage of materials and measures to be implemented to ensure
stability of the sea wall has been submitted to and approved by the Local
Planning Authority. Thereafter, works shall be carried out strictly in
accordance with the agreed method statement. Reason: In the interests of the
amenities of the area and the nearby residents and to minimise disturbance to
the candidate special area for conservation in accordance with Strategic
Policy S10 (Designated and Defined Areas) and Policies D1(Standard of Design)
and P5 (Reducing the Impact of Noise) of the Isle of Wight Unitary
Development Plan. |
3 |
No development shall
take place until a full schedule of materials and finishes, including the
colour of the access bridge to the haven and town pier and concrete colour to
be used in the construction of the development hereby permitted has been
submitted to and approved in writing by the Local Planning Authority.
Thereafter, development shall be carried out and maintained in accordance
with the approved details. Reason: In the interests of the
amenities of the area and to comply with Strategic Policy S10 (Designated and
Defined Areas) and Policies G4 (General Locational Criteria for Development),
D1 (Standards of Design), B2 (Settings of Listed Buildings) and B6
(Protection and Enhancement of Conservation Areas) of the Isle of Wight
Unitary Development Plan. |
4 |
Prior to commencement
of any construction works at the site, a programme of measures aimed at
mitigating the impact of construction traffic and requiring delivery by sea
wherever possible, including details and times of vehicle movements shall be
submitted to and approved by the Local Planning Authority. Thereafter, the
delivery of materials and construction of development shall be carried out in
accordance with the approved details. Reason: In the interests of the
amenities of the area, nearby residents and highway safety and to comply with
Policies D1 (Standards of Design), TR7 (Highway Considerations for New
Development) and P5 (Reducing the Impact of Noise) of the Isle of Wight
Unitary Development Plan. |
5 |
Unless the prior
approval of the Local Planning Authority is obtained in writing, works of
construction at the site, other than delivery of materials, shall only be
carried out between 0700 hours and 2000 hours Monday to Friday, 0700 hours
and 1800 hours on Saturdays and not at all on Sundays and recognised bank
holidays. Reason: To restrict to a
minimum the possible noise nuisance from the proposed works and comply with
Policies D1 (Standards of Design) and P5 (Reducing the Impact of Noise) of
the Isle of Wight Unitary Development Plan. |
6 |
Prior to any
construction work commencing on site, a schedule of noisy operations proposed
to be carried out at the site shall be submitted to and agreed by the Local
Planning Authority. Thereafter, those specified noisy operations shall only
be carried out during the period 0900 hours and 1700 hours Monday to Friday
and not at any other time, unless agreed in advance by the Local Planning
Authority. Reason: To restrict to a
minimum the possible noise nuisance from the proposed works and comply with
Policies D1 (Standards of Design) and P5 (Reducing the Impact of Noise) of
the Isle of Wight Unitary Development Plan. |
7 |
Prior to work
commencing on site, details of all lighting, including navigation lights, to
be installed/erected on the haven and town pier hereby approved shall be
submitted to and approved in writing by the Local Planning Authority.
Thereafter, only such approved lighting shall be installed/erected on the facilities
unless otherwise agreed in writing with the Local Planning Authority. Reason: In the interests of the
amenities of the area and to comply with Strategic Policy S10 (Designated and
Defined Areas) and Policies G4 (General Locational Criteria for Development),
D1 (Standards of Design), D14 (Light Spillage) and B6 (Protection and
Enhancement of Conservation Areas) of the Isle of Wight Unitary Development
Plan. |
8 |
No fuel shall be stored
at, or refueling take place within, the haven or at the town pier, unless
required in the event of an emergency. Reason: To avoid possible
pollution and to safeguard the interests of nature conservation in the area
and to comply with Policies P1 (Pollution and Development), P2 (Minimise
Contamination from Development), C8 (Nature Conservation as a Material
Consideration), C9 (Sites of International Importance for Nature
Conservation) and C10 (Sites of National Importance for Nature Conservation)
of the Isle of Wight Unitary Development Plan. |
9 |
Prior to any work commencing
on site, a scheme for the provision of CCTV cameras and lockable gates, or
such other methods considered appropriate to prevent unauthorised access to
the haven and town pier from the shore, shall be submitted to and approved in
writing by the Local Planning Authority. Thereafter, the development shall be
carried out and thereafter retained and maintained in accordance with the
approved details. Reason: To reduce the
opportunities for crime and to comply with Policy D11 (Crime and Design) of the
Isle of Wight Unitary Development Plan. |
10 |
Within two years of the
date of work commencing on the formation of the haven, work shall have
commenced and be substantially completed in respect of the provision of the
town pier, unless otherwise agreed in writing with the Local Planning
Authority. Reason: In the interests of
improving public access to the waterfront and to comply with the aims of the
Cowes Waterfront Supplementary Planning Guidance. |
6. |
LBC/23329/J P/01921/04 Parish/Name: Cowes
Ward: Cowes Castle East Registration Date: 09/09/2004 -
Listed Building Consent Officer: Mr. A. Pegram Tel: (01983) 823575 Applicant: Mrs P Lewington LBC for construction of yacht haven
& town pier section of foreshore between The
Royal Yacht Squadron and opposite the bandstand, The Parade, Cowes, PO31 |
REASON FOR COMMITTEE
CONSIDERATION
Although falling into the
category of a minor application, this proposal raises a number of significant
issues to be considered and has attracted a high level of public interest, both
in support of and objecting to the development.
PROCESSING INFORMATION
This is a minor
application, the processing of which will have taken 23 weeks to the date of
the committee meeting. The processing of the application has gone beyond the
prescribed 8 week period for the determination of planning applications due to
the need to obtain responses from all consultees and case officer workload.
LOCATION & SITE CHARACTERISTICS
Application relates to
area of foreshore at north western end of The Parade and in front of the Royal
Yacht Squadron. The majority of the works will take place below mean low water.
The yacht haven facility would be accessed from the existing walkway in front
of the Royal Yacht Squadron premises and the town pier from existing flight of
steps off The Parade.
The majority of the work
and, in particular, the yacht haven would fall within the area considered to be
part of the setting of Cowes Castle (Royal Yacht Squadron premises) which is a
Grade II* listed building. In addition, proposal would necessitate works to the
steps in front of the property which are also considered to form part of the
listing as curtilage structures. Cowes Castle occupies an elevated position
above the foreshore and forms a landmark building, particularly when viewed
from the sea.
RELEVANT HISTORY
TCP/11829/C/5456 –
Planning permission refused May 1967 for construction of a pier and pontoon
opposite the Gloster Hotel, The Parade on grounds that the proposal would be
seriously detrimental to the amenities and character of the immediate
neighbourhood. The pier/pontoon was shown on submitted plans to be roughly L
shaped projecting some 36 metres from the sea wall.
TCP/11829A/C/6040 –
Planning permission approved August 1968 for construction of jetty, mooring
pontoons and ramp at The Parade. The structure was shown on submitted plans to
be F shaped projecting approximately 40 metres from the sea wall.
TCP/11829B/C/8001 –
Planning permission refused September 1972 for construction of a pier and
pontoon on grounds that proposal would be detrimental to visual amenities of
the area. Submitted plans showed walkway projecting from Parade giving access
to relatively substantial landing stage with overall length of approximately 50
metres.
TCP/11829C/M/414 –
Outline planning permission for pier conditionally approved April 1986.
although seeking outline consent only, siting and means of access were
considered and plans which accompanied submission showed structure virtually
identical to that previously refused
comprising walkway from
Parade providing access to relatively substantial landing stage having overall
length of approximately 50 metres.
In addition to planning
applications detailed above, Cowes Castle has been subject to number of
planning applications and applications for Listed Building Consent in respect
of alterations and extensions, although none are considered to be relevant to
the current proposal.
DETAILS OF APPLICATION
Current proposal
effectively involves two elements, a yacht haven and what is referred to as the
town pier.
The haven would be formed
through the construction of an L-shaped breakwater constructed of concrete
blocks with moulded masonry lines to match the existing harbour walls, which
contain cut and dressed stonework, and moulded concrete. Rock armour would be
placed on the exposed outer face of the breakwater which would be graded half
to three tonne rock of similar bulk to the existing foreshore. Information
which accompanies the submission indicates that this would be imported durable
breakwater rock, for example granite or hard limestone. The breakwater will
extend a maximum distance of 80 metres from the foreshore and would enclose an
area of sheltered water amounting to approximately 3000 square metres.
A set of steps, known as
the Royal Yacht Squadron steps, lead out from the harbour parade wall, over the
foreshore and continue below the water line. These steps presently have a
length of approximately 53 metres and extend into the area which is to be
dredged in the formation of the haven. Therefore, whilst the upper section of
these steps will remain for a distance of approximately 32 metres, the lower
section, the majority of which generally lies below mean low water will need to
be removed. These steps are considered to form part of the curtilage to Cowes
Castle and, as such, form part of the listing.
It is understood that the
haven would provide mooring facilities for the launches operated by the Royal
Yacht Squadron and will facilitate the installation of three pontoons capable
of accommodating around a dozen boats 40 feet in length. Access to the pontoons
would be provided from the existing walkway in front of Cowes Castle by means
of an access bridge. A turret feature and navigation lights would be located on
the outer end of the breakwater. The turret section was originally intended to
echo the castle battlement as well as protecting and signaling the haven entrance.
The town pier would be
created by positioning a floating pontoon with length of approximately 80
metres roughly parallel to the foreshore at a distance of approximately 42
metres from the sea wall. This pontoon would be anchored to the seabed using
cables which, it is understood, are less susceptible to storm damage and remove
the need for a number of heavy vertical piles. However, a smaller landing
pontoon would be positioned immediately adjacent the main pontoon which would
be held in position by four piles and would support the seaward end of an
access bridge providing access to the foreshore via an existing flight of steps
which projects out from The Parade. It is understood that, due to its position
south of the proposed haven, the town pier would also benefit from protection
provided by the breakwater to be constructed to form the haven itself.
The submission was
accompanied by information in support of the proposal, including a design
statement and a document providing additional environmental information. The
design statement asserts that this development will improve the Squadron's
existing facilities for the benefit of club members and local, national and
international yachting events. The document indicates that the first phase of
the project will involve the construction of the haven followed by the
construction of the town pier. It is understood that the haven would, strictly
in the short term, provide berthing facilities for squadron members only while
the town pier would primarily be for eventing/public landing, potentially under
the control of Cowes Harbour Commission. It is not intended that there should
be general pedestrian access onto the breakwater to the haven, other than for
maintenance and servicing, as this is too exposed a location to risk public
access. The structure is designed to be over topped by waves and public access,
even if considered possible, would require a higher and wider structure with
handrails raising the profile still further. It is intended that the town pier
would provide a much more accessible berth for larger vessels. Other steps and
landing points along The Parade would remain available for small boats and
leisure use.
Additional environmental
information is contained in quite a substantial document covering a range of
issues including the need for the facility, dredging requirements and other
environmental issues, particularly the impact of the proposal on the marine
environment in this area, the coastline of which is designated as a candidate
Special Area for Conservation. A copy of the design statement and executive
summary from this document is attached to this report as an appendix. The full
document can be made available on request.
Planning Policy Guidance
Note 20 (PPG20) - Coastline Planning, provides a comprehensive statement of
policies in relation to coastal planning. The guidance note acknowledges that
the coast is an important national resource and that a range of economic and
social activities require coastal locations with certain natural and historic
landscapes and habitats particular to coastal areas. It advises that, against
this background, it is the role of the planning system to reconcile development
requirements with the need to protect, conserve and where appropriate, improve
the landscape, environmental quality, wildlife habitat and recreational
opportunities of the coast. In addition, the PPG acknowledges that the
coastline is dynamic and shaped by powerful natural processes which is varied
in its topography, including cliffs, estuarine marshes and mud flats, coastal
lowlands and sand dune systems, each being subject to its individual set of
natural processes and own special qualities as an environmental, economic and
recreational resource.
In terms of policies for
development that require a coastal location,
PPG20 highlights, under the heading of tourism, that one particular type
of development where there has been a rapid increase in demand in the last 20 years
has been for mariners and other facilities for boat mooring, parking and
launching. It is considered that this demand is likely to continue for the
foreseeable future although such demand varies considerably from region to
region with additional craft each year placing great pressure on existing
facilities. The PPG suggests that, when considering applications for mariners,
the Local Planning Authority should pay particular attention to arrangements
for access and parking and that any associated development should be assessed
separately, on its own merits, taking into account whether it requires a
coastal location. The document advises that public access to the coast should
be a basic principle, unless it can be demonstrated that this is damaging to
nature conservation or impractical and that this applies to both developed and
undeveloped coast.
The development boundary
in this area, as defined on the Isle of Wight Unitary Development Plan, follows
the line of mean low water mark and, therefore, the majority of the site is
located outside the boundary. The coastline in this area is designated as a
candidate Special Area for Conservation (cSAC) and the site immediately adjoins
the designated Conservation Area and Cowes Castle which is a Grade II* Listed
Building. Relevant policies of the Unitary Development Plan are considered to
be as follows:
S6 - All Development will
be Expected to be of a High Standard of Design.
S10 - In areas of
designated or defined scientific, nature conservation, archaeological, historic
or landscape value, development will be permitted only if it will conserve of
enhance the features of special character of these areas.
G1 - Development
Envelopes for Towns and Villages.
G4 - General Locational
Criteria for Development.
G5 - Development Outside
Defined Settlements.
D1 - Standards of Design.
B1 - Alterations and
Extensions to Listed Buildings.
B2 - Settings of Listed
Buildings.
B6 - Protection and
Enhancement of Conservation Areas.
B9 - Protection of
Archaeological Heritage.
C3 - Development of the
Coast Outside of Development Envelopes.
C8 - Nature Conservation
as a Material Consideration.
C9 - Sites of
International Importance for Nature Conservation.
C10 - Sites of National
Importance for Nature Conservation.
L8 - Jettys, Pontoons and
Slipways.
The proposal falls within
the area, the subject of the Supplementary Planning Guidance on the Cowes
waterfront initiative which commenced with Project Cowes. This is considered to
be a vibrant and unique project to secure a vibrant and prosperous future for
the Medina Valley, the aim of which is to attract new investment to provide the
opportunities, facilities and attractions that both local people and visitors
can enjoy. The Strategic Development Framework sets out the vision for Project
Cowes and a detailed programme of new projects. It focuses on a number of key
priorities, identified by local people during the consultation process which,
of most relevance to the current proposal, includes capitalising on and
strengthening Cowes status as an international centre of yachting excellence
and as the ‘home’ of UK sailing.
The SPG identifies five
zones along the Medina Valley characterised by the nature of uses within those
areas. The application site falls within zone 1 which encompasses an area at
the northern end of the Medina estuary, including the existing town centres of
Cowes and East Cowes and their associated waterfronts. These areas are
characterised by town centre, leisure and event activities. Within this area,
the SPG identifies key opportunities including, of particular relevance to the
current proposal, new waterfront access and new marina facilities.
CONSULTEE RESPONSES
Highway Engineer
considers there to be no highway implications.
The Conservation and
Design Team Leader considers that the plans which accompanied the original
submission were lacking in information considered essential before the proposal
could be properly assessed. Therefore, she requested additional information as
follows:
·
Full details, including drawings of the Squadron steps as existing, and
proposed clearly indicating the extent of the steps to be removed and how the
resultant structure would be finished.
·
An elevation of the breakwater from the west showing its relationship to
the listed building (RYS) and its context.
·
A plan showing the area of the proposed bridge head as it exists,
including the angled masonry and details of how that area will be affected by
the proposal as the proposed bridge head details as shown are not adequate in terms
of detail/effect on historic masonry.
·
A copy of a plan of the proposed breakwater and haven in relation to the
existing starboard fairway buoy would provide an understanding of how far and
where the proposal would extend.
The Conservation and Design
Team Leader advises that the planning application appears, on balance, to be
unacceptable in principle regarding its impact on the conservation area and
setting of the listed building(s). She considers that there would be a distinct
change in the character and appearance of the conservation area which will fail
to preserve or enhance. She made a number of observations about the detailing
of the proposal and how this impacted on and was generally unsympathetic to the
listed building and conservation area. Notwithstanding these concerns, she made
a number of suggestions as to how the scheme could be improved. In particular,
she considered that the tower proposed for the outer end of the breakwater was
a sham and would, when viewed from the water, not sit well with the historic
building. It was suggested that there was an opportunity for something more
striking and perhaps modern which might identify the location as more of a
landmark (or seamark). A number of recommendations were made in respect of the means
of enclosure, detailing and colour of structures at the entrance to the haven
from the existing promenade area and in respect of the detailing to the town
pier.
She suggested that the
height and the uncluttered top of the proposed breakwater should not be
increased or added to as this would have an adverse impact on the conservation
area and adjacent Listed Building. Any such proposals would attract a
recommendation for refusal from her. Following a meeting between the
Conservation and Design Team Leader and the applicants agent, the scheme was
amended and further plans and report on the justification for the design
aspects of the proposal was submitted, generally addressing the concerns raised
over the detailing of the proposal.
Councils Ecology Officer
advises that the proposals are located adjacent to and partially within the
Solent Marine cSAC and, consequently, the possibility of a likely significant
effect of the development upon the interest features of the designated area
must be considered. He commented that English Nature have advised the Planning
Authority that the built structures are not likely to have a significant affect
upon the European site but that they will be advising the Marine Consents Unit
of DEFRA, who could be required to issue a dredging licence, that this element
of the work has the potential to cause likely significant effect and would
therefore require an appropriate assessment.
The Ecology Officer
points out that it is the role of English Nature to advise the Planning
Authority, as a competent authority, on the need for an appropriate assessment.
Despite the view expressed by English Nature an appropriate assessment was
carried out, which was confined to the impact of the built development and
concluded that there will be no adverse effect upon the integrity.
Having considered the
information presented with the planning application, English Nature advise that
the built structures themselves are not likely to have a significant effect on
estuary processes and important habitats upstream. Furthermore, the footprint
of the development was not considered likely to have a significant effect on
sub tidal features or sub features of the cSAC. English Nature indicated that,
during construction of the built structures, there is the possibility of some
short term disturbances to fish, although fish communities in general are not
listed as a sub feature of the estuary physiographic feature, although they are
recognised as part of the ecological system. They consider that it is unclear
whether the short term construction impacts on a component of the estuaries
European feature would warrant a significant effect on that feature and
therefore required an appropriate assessment to be carried out.
The Authority is advised
that capital and maintenance dredging are required for construction and use of
the Squadron haven and such dredging is regulated by licence from the Marine
Consents Unit of DEFRA. English Nature were satisfied that all necessary
information to support such an appropriate assessment had been provided by the
applicant. In addition to the impacts on the European designation, the
appropriate assessment should also take into account effect on the physical
processes that support the SSSI habitats further upstream. English Nature were
satisfied that the appropriate assessment carried out by the Council’s Ecology
Officer adequately addressed all relevant issues in this respect.
Environment Agency
initially placed holding objection in respect of the proposal on basis that insufficient
information had been submitted to assess the impact of the development on the
interest features of the European designated site. The agency advised that they
were unable to come to a conclusion regarding the principle of development in
the absence of an appropriate assessment. Following consideration of the
appropriate assessment prepared by the Council’s Ecology Officer, the agency
withdrew their objection to the proposal.
English Heritage
commented that the submitted drawings did not include a plan of the existing
state of the esplanade which, at this point, forms a small battery around the
Royal Yacht Squadron. In addition, they commented that there is also no
historical analysis of the foreshore or any indication of the archaeological potential
and while the proposal does not appear physically to affect features of much
age or consequence, suggested that these issues were explored further.
Following discussions
with English Heritage, the Council’s Planning Archaeologist advises that it will
be necessary for the applicant to submit an appropriate desk based assessment
prior to determination of the application identifying any potential
archaeological interest in this area. A
‘swim over’ survey may be required post decision and prior to any work
commencing on site. It is anticipated that the results of the desk based study
and further comments from the Planning Archaeologist will be available to
report to Members at the Committee meeting.
PARISH/TOWN COUNCIL
COMMENTS
The Town Council supports
in principle the proposal but expressed some reservations regarding the town
pier element indicating that they would wish to see a more attractive Victorian
design for the link span, confirmation that it would be a landing stage only
with no overnight moorings and clarification regarding public access.
THIRD PARTY
REPRESENTATIONS
The applications have
attracted a total of 56 letters objecting to the proposal. Of these, 48 take
the form of a standardised letter relating solely to the effect of the proposal
on recreational fishing in the area. The grounds for objection can be
summarised as follows:
Viewing area on Parade
for public is already congested and extra services to support yacht crews, car
parking and security would deny access to this area.
Impact on outlook to sea
from Parade.
Parade is unique and
important part of Cowes.
Other sites in area
should be enhanced to realise the nautical tourism.
This facility is not
required as adequate marina facilities are proposed as part of the Project
Cowes initiative.
Provision of a proper
pier should be made not a pontoon.
Increased noise,
including sound of halyards, pollution and lack of parking will impact on
amenities of nearby residents.
Project is not
technically feasible.
Submission contains lack
of information regarding public access to town pier and type of vessel able to
use the facility.
Public landing stage
could become gathering point for youngsters.
Development would prevent
continued use of Parade by anglers which, in particular, provides easy access
for children and people with disabilities.
Continued use of Parade
for fishing and mooring of boats would create dangerous conflict.
Whilst short
term/overnight mooring is considered to be acceptable, use by charter vessels
and longer term mooring should not be permitted.
Security of town pier
considered to be a major concern – should be locked at night and off peak with
CCTV provided.
The combination of the
haven and landing facility would be incongruous.
Arrivals and departures
of vessels will increase at all times of day and night, increasing noise and
disturbance to nearby residents.
Increased congestion at
entrance of River Medina creating hazard.
In addition, concerns
raised by individuals in respect of recreational angling, letter has been
received from National Federation of Sea Anglers who, whist welcoming the
proposal on basis that it will enhance Cowes waterfront with respect to
yachting and tourism, raised a number of concerns with regard to impact of
proposal on recreational angling, particularly from the area along The Parade.
However, following discussions between the NFSA and RYS, a further letter has
been received indicated that these discussions have resulted in an agreement and
a way forward for recreational angling in the affected areas which may involve
use of the breakwater and town pier by anglers.
Similarly, letter was
received from the Royal London Yacht Club (RLYC) objecting to the application
and expressing concern with regard to the impact of the proposal on various
aspects of yacht racing in the area. However, it is understood that, following
discussions between the RLYC, the RYS and Cowes Harbour Commissioner, these
concerns have been overcome and the yacht club now withdrawn their objection to
the application.
Letters have been
received from Skandia Cowes, Cowes Yachting and Royal Corinthian Yacht Club
supporting the application with comments which can be summarised as follows:
Haven whilst primarily
for benefit to RYS members will be great assistance to all Cowes yacht and
sailing clubs in the management of major events.
Public landing will provide much needed facilities.
Breakwater will provide shelter to the structure of The
Parade.
Proposal will enhance
harbour entrance and bring more events and visitors to Cowes to the benefit of
the Island economy as a whole.
CRIME & DISORDER
IMPLICATIONS
Following discussions
with the Architectural Liaison Officer, there are considered to be no major
crime and disorder implications associated with the proposal. In general, he
considers that the proposal may raise issues of security for vessels and
personal possessions although this could be addressed by restricting access to
the haven in particular by means of a lockable gate. In general, he considers
that some security devices should be provided such as CCTV. Whilst not strictly
a crime and disorder matter, he expresses concern that public access to the
town quay may result in accidents or people falling into the water placing
pressure on police and other rescue services.
EVALUATION
Main issues relevant to the consideration of this proposal can be summarised as follows:
·
Whether proposal is acceptable in principle.
·
Impact of development on amenities and character of area, specifically
the setting of the conservation area and the impact on the adjacent listed
building.
·
Impact on amenities of nearby residents.
·
Impact on the European designation and wider ecological interests in the
area.
The majority of the work
would take place and resultant structures occupy the area beyond low water
mark, outside the development envelope, as defined on the Unitary Development
Plan (UDP). However, the explanatory text in the UDP in respect of policies
relating to general location of development indicates that they will be
relevant to many development proposals and provide guidance to the locational
constraints or issues which need to be taken into consideration. Other sections
and policies of the plan will also need to be taken into consideration and may,
in certain circumstances, support the principle of development outside the
development envelope.
When considering whether
proposal is acceptable in principle, it is necessary to take into account the
locational constraints associated with the development under consideration and
the need for the chosen location. In this instance, I am satisfied that the
proposed development has an operational requirement dictating its location and
that the proposal falls within a category of development may exceptionally be
permitted. Therefore I am satisfied that the proposal is acceptable in
principle.
From the information
accompanying the submission, it is clear that the facilities to be provided,
and particularly the haven, have been designed to satisfy an operational and
functional requirement whilst minimising the impact of the development on the
surrounding area and the adjacent Listed Building. The rock armour, placed on
the seabed to form the outer face of the breakwater, would have finished height
of 2.01 metres ordnance datum (OD), OD being the highest astronomical tide. The
top of the wave break parapet to the breakwater would be at a height of 2.695
metres OD. To put these levels into context, they need to be compared with
existing levels on The Parade. The report accompanying the submission indicates
that the level of the parade pavement, opposite the Royal London Yacht Club, is
2.285 metres OD and that the balustrading has a height of 1.060 metres above
this giving a height to the top of the balustrading of 3.345 metres OD. This
balustrading is of substantial construction and is a dominant feature on The
Parade. The top of the wave break parapet to the haven would sit approximately
650 mm below the top of the balustrading with only the turret on the outer end
of the breakwater and the pedestrian link bridge projecting higher.
The breakwater has been designed to be over topped by waves, although it will provide safe mooring for vessels under fair to intermediate sea conditions i.e. below force 8. In order to limit the height and impact of the structure, it is not intended to provide public access to the breakwater and this would require a higher and wider structure with handrails, thereby increasing the impact of the development. Notwithstanding these issues, the facility will occupy a prominent location, clearly visible when viewed from both sea and land, and will create a sense of enclosure, impacting on the character of the area. However, whilst it is not disputed that the proposal will impact on the outlook to sea, the design concept for the scheme acknowledges the need to keep to a minimum such impacts. In addition, following discussions between the applicants’ agent and the Conservation and Design Team Leader, further plans have been submitted amending elements of the scheme in order that the development is more sympathetic in terms of existing features in the immediate vicinity, the character of the conservation area and setting of the adjacent listed building. In particular, the following alterations have been made to the scheme:
·
A more simplified approach has been adopted for the tower at the outer
end of the breakwater.
·
The means of enclosure to the pedestrian access at the landward end of
the haven has been altered to reflect existing features in the area.
·
Balustrading is to be returned along either side of the access to the
link span to the town pier to match that along The Parade.
Whilst the proposal will
clearly have a degree of impact on the conservation area and the adjacent
listed building, I consider that these alterations to the scheme result in a
development which is more sympathetic to its surroundings. Given the function
of the development and the character of the area, I do not consider that proposal
would represent an incongruous feature or that the impacts are so significant
so as to be unacceptable.
Existing development on
the south western side of The Parade, opposite the site of the proposed
development, includes residential properties. Concern has been expressed by
residents within these properties regarding the possible disturbance that may
be caused by the proposal. In this respect, I consider that potential sources
of disturbance include the construction phase and the subsequent use of the
completed facility.
In general terms,
potential noise and nuisance generated during the construction phase of a
development is not a matter which normally falls within the control of the
Local Planning Authority. However, in this instance, given the nature of the
operation involved and the volume of material required in the construction of
the haven which could potentially be delivered both by road and by sea, I do
not consider that it would be unreasonable for the authority to seek control,
through conditions should Members be minded to approved the application, the
hours of working and delivering of materials at the site.
A further potential
source of noise and disturbance could arise through activities associated with
the use of the facility. In this respect, I consider that the site is located
in an area where there is a high level of waterborne activity, particularly at
times when events are being held in the area. Such activities obviously
generate a significant volume of waterborne movements, including launches
ferrying people between vessels on off shore moorings and the land. It is also
understand that there are a large number of ‘swinging’ moorings along the area
of The Parade. The information accompanying the submission indicates that the haven
would provide mooring facilities for launches operated by the Royal Yacht
Squadron and the short term moorings for visiting craft, particularly during
events, which would otherwise be moored at permanent facilities either on the
Island or further a field. I am advised that the haven is not intended to
provide long term/permanent mooring facilities for members vessels. Therefore,
I do not consider that proposal would generate a significant increase in
movement of vessels in this area or demand for a high level of car parking in
the area. Having regards to these factors, I do not consider that level of
activity generated by the proposal would have an excessive or unacceptable
impact on the amenities of nearby residents.
The site is located
within the Solent Marine cSAC and, in assessing this proposal, consideration
has been given to the likely affect of the development upon the interest
features of the designated area. The Council’s Ecology Officer has carried out
an appropriate assessment in respect of this proposal in order to identify
whether there is likely to be any significant effects arising from the
development. The appropriate assessment identifies that the interest feature
which would be directly affected by the plan is the estuary's physiographic
feature and that the cSAC is sub tidal at the mouth of the Medina estuary which
was included within the site boundary to protect estuary processes essential to
important habitats upstream. Sub tidal sediment communities are a sub feature
of the estuaries feature. Consequently, the Ecology Officer has identified
these aspects as those which could be affected by the development. Having
identified the special feature of the area and impacts likely to arise through
the development, the Ecology Officer has concluded that none of the changes
associated with the development on its own would give rise to adverse affects
on the cSAC features and that construction should not represent an adverse
affect on the integrity of the Solent Marine cSAC. In addition, in combination
with other plans and projects, available information indicates that
construction is unlikely to contribute to any adverse affects caused by other
schemes. However, he advises that, although no adverse affects on the integrity
of the designated area are predicted, a precautionary approach with regard to
capital and maintenance dredging should be implemented. In this respect, it is
understood that it will be necessary for the applicant to obtain a dredging
licence from the Marine Consents and Environment Unit for the capital and
subsequent maintenance dredging. It is further understood that the process will
also include an assessment of the likely impacts of the development on the
special features of the designated area.
Whilst navigation issues
are not a material planning consideration, this matter has been taken into
account by the Cowes Harbour Commissioner when submitting comments in respect
of an application for a dredging licence. A copy of these comments has been
obtained which indicates that, whilst the proposed haven will project
approximately 65 metres into the western entrance of the harbour, it is clear
of the main fairway and will, therefore, not cause an unacceptable obstruction
to navigation. The Cowes Harbour Commissioner acknowledges that proposal will
also affect the approaches to the various yacht club and Council owned parade
landing steps, although it is understood that he has received no objections in
respect of navigation issues or rights. Cowes Harbour Commission indicate that
they would require both the Royal Yacht Squadron haven and landing pontoon to
be lit, the minimum requirements for which would involve two vertical green
lights on the southern end of the Royal Yacht Squadron breakwater and two
vertical green lights on the southern end of the landing pontoon. I am
satisfied that, should Members be minded to approve the application, the level
of lighting to be provided to this facility can be adequately controlled by
means of a condition of the planning permission.
Concern has been
expressed about the use of these facilities for long term mooring of vessels
and the effect this could have on nearby residents. The information which
accompanies the submission indicates that is intended that these facilities are
required for short term mooring of vessels. Furthermore, it is understood that
the design of the haven would, to a certain extent, limit its use to short term
mooring, particularly during very bad weather conditions (above force 8). In
any event, I do not consider that overnight mooring of vessels at this location
would have a significant or adverse impact on nearby residents or that any
restrictive condition of a planning consent in this respect would be reasonable
or enforceable.
HUMAN RIGHTS
In coming to this recommendation
to grant planning permission, consideration has been given to the rights set
out in Article 8 (Right to Privacy) and Article 1 of the First Protocol (Right
to Peaceful Enjoyment of Possessions) of the European Convention on Human
Rights. The impacts this development might have on the owners/occupiers of the
other property in the area and other third parties have been carefully
considered. Whilst there may be some interference with the rights of these
people this has to balance with the right of the applicant to carry out the
development in the manner proposed. Insofar as there is an interference with
the rights of others it is considered necessary for the protection of the
rights and freedom of the applicant. It is also considered that such action is
proportional to the legitimate aim and in the public interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I do not consider the proposal would have an unacceptable impact on the
character of the area, with particular reference to the conservation area, or
the setting of the adjacent listed building. Furthermore I do not consider that
the use of these facilities and the level of activity likely to be generated by
them would cause excessive or unacceptable impact on the amenities currently
enjoyed by nearby residential occupiers. Furthermore, I am satisfied that the
proposal will not have an unacceptable impact on the special features of the
cSAC or the estuarine processes further south on the River Medina.
RECOMMENDATION – APPROVAL
(Both applications – subject to referral of application for Listed Building
Consent to the Government Office)
Conditions/Reasons:
1 |
The works hereby
authorised shall be begun not later than [5] years from the date of this
consent. Reason: As required by s18 Planning (Listed
Buildings and Conservation Areas) Act 1990 |
2 |
Prior to work
commencing on the partial demolition of the Royal Yacht Squadron steps, as
detailed on the approved plans, details of the method of disposal of the
resultant material together with details of the materials/surface finish to
be used in making good the section of steps to be retained shall be submitted
to and approved by the Local Planning Authority. Thereafter, development
shall be carried out strictly in accordance with the approved details. Reason: In the interests of the
amenities of the area and to protect the character and appearance of the
listed building in accordance with Strategic Policy S10 (Designated and
Defined Areas) and Policies G4 (General Locational Criteria for Development),
D1 (Standards of Design), B1 (Alterations and Extensions to Listed
Buildings), B2 (Settings of Listed Buildings), and B6 (Protection and
Enhancement of Conservation Areas) of the Isle of Wight Unitary Development
Plan. |
3 |
No development shall
take place until a full schedule of materials and finishes, including the
colour of the access bridge to the haven and town pier and concrete colour to
be used in the construction of the development hereby permitted has been
submitted to and approved in writing by the Local Planning Authority.
Thereafter, development shall be carried out and maintained in accordance
with the approved details. Reason: In the interests of the
amenities of the area and to comply with Strategic Policy S10 (Designated and
Defined Areas) and Policies G4 (General Locational Criteria for Development),
D1 (Standards of Design), B2 (Settings of Listed Buildings) and B6
(Protection and Enhancement of Conservation Areas) of the Isle of Wight
Unitary Development Plan. |
4 |
Prior to work
commencing on site, details of all lighting, including navigation lights, to
be installed/erected on the haven and town pier hereby approved shall be
submitted to and approved in writing by the Local Planning Authority.
Thereafter, only such approved lighting shall be installed/erected on the
facilities unless otherwise agreed in writing with the Local Planning
Authority. Reason: In the interests of the
amenities of the area and to comply with Strategic Policy S10 (Designated and
Defined Areas) and Policies G4 (General Locational Criteria for Development),
D1 (Standards of Design), D14 (Light Spillage) and B6 (Protection and
Enhancement of Conservation Areas) of the Isle of Wight Unitary Development
Plan. |
5 |
Prior to any work
commencing on site, a scheme for the provision of CCTV cameras and lockable
gates, or such other methods considered appropriate to prevent unauthorised
access to the haven and town pier from the shore, shall be submitted to and
approved in writing by the Local Planning Authority. Thereafter, the
development shall be carried out and thereafter retained and maintained in
accordance with the approved details. Reason: To reduce the
opportunities for crime and to comply with Policy D11 (Crime and Design) of
the Isle of Wight Unitary Development Plan. |
7. |
TCP/24514/A P/01983/04 Parish/Name: Fishbourne
Ward: Binstead Registration Date: 20/09/2004 -
Reserved Matters Officer: Miss. S. Gooch Tel: (01983) 823568 Applicant: T Jones Development Ltd Detached house with detached
garage; formation of vehicular access (aorm)(further revised scheme) land adjacent Ashdown House,
Ashlake Farm Lane, Wootton Bridge, Ryde, PO33 |
REASON FOR COMMITTEE CONSIDERATION
When consulted under the delegation
procedure the local Member, Councillor Mr E Fox, has requested that the
application is considered by the Committee as he considers proposal is out of
scale with the adjacent properties.
PROCESSING INFORMATION
This is a minor application, the
processing of which has taken 22 weeks to date and has gone beyond the
prescribed 8 week period for determination of planning applications due to
negotiations with the applicant, case officer workload and the request from the
local member for Committee consideration.
LOCATION & SITE CHARACTERISTICS
Application relates to a irregular
shaped area of land north of Ashdown House and is situated on eastern side of
Ashlake Farm Lane which itself is a cul-de-sac leading off north side of Kite
Hill. Application site is located some 200 metres north of junction with main
road. Within the site are various trees some of which are protected with
preservation orders.
RELEVANT HISTORY
TCP/24514 Outline
planning permission granted October 2002 for dwelling on land adjacent Ashdown
House, Ashlake Farm Lane.
DETAILS OF APPLICATION
Reserved matters are now
sought on external appearance, design and landscaping for a detached house and
garage following outline consent granted in October 2002.
Proposed designs display
a large detached property with Georgian style windows and dormer features in
front roof elevation. A typical designed conservatory is proposed to the rear
with a chimney stack feature to the south and portico over main front entrance
door. A double detached garage with dormer features in the front elevation roof
will sit north of proposed house.
Resultant floor space of
proposed detached house excluding the conservatory and garage is 140.70 m2.
Proposal displays accommodation on three floors, the third being located within
the roof space. The detached house will provide six bedrooms, two with
associated bathroom facilities and main communal rooms are all located on the
ground floor.
DEVELOPMENT PLAN/POLICY
Site is located within
the development envelope, as defined on the Isle of Wight Unitary Development
Plan, and is subject to a Tree Preservation Order.
Relevant policies of the
plan are considered to be as follows:
S1 New development
will be concentrated within existing areas
S6 All development
will be expected to be of a high standard of design
S7 There is a need
to provide for development of at least 8,000 housing unit
G1 Development
envelopes for towns and villages
G4 General
Locational Criteria for development
D1 Standards of
Design
D2 Standards for
Development within the Site
D3 Landscaping
H5 Infill
Development
C12 Development
affecting trees and woodland
U11 Infrastructure
and Service Provision
CONSULTEE RESPONSES
Highway Engineer has been
consulted and recommends approval subject to conditions being imposed should
members be minded to approve application.
After liaising with Tree
Officer he requests that detailed fencing zones and specifications, temporary
and permanent access servicing and chronology of site activities are controlled
by condition. More restrictive conditions will need to be imposed to ensure the
longevity of the trees on site.
PARISH/TOWN COUNCIL
COMMENTS
Not applicable.
THIRD PARTY
REPRESENTATION
Three letters of support
were received from local residents which can be summarised as follows:
· Mature oak trees will
screen the property
· Building is not intrusive
or out of scale with other houses in the vicinity
· Proposal is in keeping
with the standard of the existing surrounding properties
Two letters were received from local residents objecting to the application on the grounds which can be summarised as follows:
· Weight and size of
dwelling could affect the water table and there is inadequate drainage.
· Problems with ground
stability.
· Building is out of scale
with the rest of the buildings and would create overlooking.
· Developer should repair
any damage to the lane.
·The copse to the rear of the plot is a red squirrel run and habitat for
wildlife and would have to be cleared to erect such a large building.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications anticipated
EVALUATION
Given outline approval on
this site, determining factors in considering application are whether design,
scale and mass of proposal is appropriate and whether plot can accommodate
development compatible with surroundings without appearing cramped and
intrusive.
Site is located within
development boundary and proposal is considered acceptable in principle.
Proposed design displays a large detached Georgian style property incorporating
a large number of windows with dormer features in front elevation. Negotiations
have taken place to reduce the size of these dormers and a reduction in the
overall number of windows to that previously submitted and a reduction in
length from 15.40 metres to 13.40 metres. Resulting design now appears less
dominant especially when viewing the sectional drawing which shows the existing
ground level being reduced where proposed house will sit.
As there are a number of
protected trees on site following consultation with the Tree Officer they are
of the opinion that to avoid damage to these trees on site a full
arboricultural method statement be agreed prior to any site access. This will
be a condition to ensure the site activities do not affect the health and
stability of the protected trees. They confirm that despite low density
residential development in the area for many years, with care, it should be
possible to conserve them, especially the three protected oaks at the front,
for many more years. I therefore feel it appropriate that development is
allowed subject to fairly stringent conditions to ensure the sustainable
management of these outstanding trees.
Concerns were raised on
the weight and size of the dwelling and its potential affect on the water table
and appropriate drainage arrangements were addressed at outline stage. A condition
was imposed to alleviate this problem and works have been carried out to the
storm water drainage system in 2003.
With regards to problems
with ground stability PPG 14 (Development on Unstable Land) states "the
responsibility for determining whether land is suitable for a particular
purpose rests primarily with the developer" and then goes on to say "
the developer should therefore make a thorough investigation on the assessment
of the ground to ensure that it is stable or that any actual or potential
instability can be overcome by appropriate remedial, preventative or
precautionary measure.
Comments were made by
local neighbours that the developer should repair any damage to the lane,
however, the outline Committee Report noted these concerns. It was explained to
members that these are not planning considerations as it is a private road.
After liaising with the Highways Engineer recommendation for approval was
revised subject to conditions being imposed. There is an additional condition
Highways require in respect of car parking, however this is an application for
landscaping, design and external appearance. Access was considered at outline
stage and therefore a new condition cannot be imposed at this stage.
To the rear of the plot
is a copse which is a red squirrel run and habitat for wildlife and objectors
are concerned that these trees would have to be removed to erect proposed
dwelling. Submitted plans show retention of these trees and condition has been
imposed on outline approval to protect all trees that are to be retained. After
consulting with Ecology Officer in light of the proposed retention of the
majority of trees, he does not believe that the trees to be removed would
impact upon wildlife. The tree report advises some surgery on some limbs of the
three large oak trees and the Ecology Officer has acknowledged that bats may be
present. The removal of these limbs has a real potential to impact on roosting
bats. This is the responsibility of the applicant under the Wildlife and
Countryside Act 1981 and should Members be minded to approve this application,
a letter will be sent advising the applicant of his duty of care.
Taking into account all
the above issues I am of the opinion that as Ashlake Farm Lane exhibits a
sufficient mixture of properties situated in plots of varying sizes the
proposal is acceptable in terms of scale, mass, design and impact on
surrounding residential occupiers.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of other property in the
area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the rights of others it
is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that such action is proportional to the
legitimate aim of the Council’s Unitary Development Plan and in the public
interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I am satisfied that the proposal represents an acceptable form of
development within the development envelope without having excessive or
unacceptable impact on the environment or neighbouring properties and would not
detract from the visual amenities and character of the locality. In view of the above I am
satisfied that the proposal does not conflict with policies of the Isle of
Wight Unitary Development Plan.
RECOMMENDATION - APPROVAL (revised scheme)
Conditions/Reasons:
1 |
The development hereby
permitted shall be begun before the expiration of 5 years from date of the
outline permission or before the expiration of 2 years to the date of
approval of the last of the reserved matter to be approved whichever is the
later. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
2 |
No development shall
take place until details of the materials and finishes to be used in the
construction of the external surfaces of the development hereby permitted
have been submitted to and approved in writing by the Local Planning
Authority. Development shall be carried out in accordance with the approved
details. Reason: In the interests of the amenities of the
area and to comply with policy D1 (Standards of Design) of the IW Unitary
Development Plan. |
3 |
No development shall
take place until details have been submitted to and approved in writing by
the Local Planning Authority of the positions, design, materials and type of
boundary treatment to be erected. The
boundary treatment shall be completed before the building hereby permitted is
occupied. Development shall be carried out in accordance with the approved
details. Reason: In the interests of maintaining the
amenity value of the area and to comply with policy D1 (Standards of Design)
of the IW Unitary Development Plan. |
4 |
All materials excavated
as a result of general ground works including site leveling, installation of
services or digging of foundations, shall not be disposed of within the area
identified red on the submitted plans. The material shall be removed from the
site prior to construction of the dwelling proceeding beyond damp proof
course level or such other time scales as may be agreed with the local
planning authority. Reason: In the interests of
the area in general and adjoining residential property in particular and to
comply with Policy D1 (Standards of Design) of the Isle of Wight Unitary
Development Plan. |
5 |
The access drive
between the protected T2 English Oak and T3 English Oak shall be of a gravel
finish in accordance with the specification laid down in section 5.2, 5.3 and
5.4 of MJC Tree Services Limited report signed 11 September 2004 with such
finish being retained and maintained thereafter. Reason: To ensure the
protection of the trees to be retained in the interest of the amenities of
the area and to comply with Policy C12 (Development affecting trees and
woodland) of the Isle of Wight Unitary Development Plan. |
6 |
Works specified in
paragraph 6.8 of MJC Tree Services Limited reported dated 11 September 2004
shall be carried out and a tree management plan submitted and approved before
occupation of the dwelling hereby approved. Reason: To ensure the
protection of the trees to be retained in the interest of the amenities of
the area and to comply with Policy C12 (Development affecting trees and
woodland) of the Isle of Wight Unitary Development Plan. |
7 |
The proposed access
drive shown on the plan hereby approved shall not be used at any time by
construction traffic and commercial vehicles, including removal vehicles. Reason: To ensure the
protection of the trees to be retained in the interest of the amenities of
the area and to comply with Policy C12 (Development affecting Trees and
Woodland) of the Isle of Wight Unitary Development Plan. |
8 |
Before any development
work starts and before any materials are delivered on site, protective fences
in accordance with Figure 4 of BS5837 must be erected to protect the retained
trees. Where the fence line passes over the proposed drive the fence will be
routed along the side of the drive. No development activities or storage of
materials or vehicles can take place within the fenced off area. Such fencing
to be retained until all building works have ceased on site. Reason: To ensure the
protection of the trees to be retained in the interest of the amenities of
the area and to comply with Policy C12 (Development affecting Trees and
Woodland) of the Isle of Wight Unitary Development Plan. |
9 |
Once development is
complete no activity shall be undertaken at any time on the ground within the
crown spread of protected trees T1, T2 or T3 which involves disturbing the
soil, trenching, temporary or permanent storing or parking of vehicles or
materials, erection of structures, lighting of bonfires, discharge of liquids
or fuels. Reason: To ensure the
protection of the trees to be retained in the interest of the amenities of
the area and to comply with Policy C12 (Development affecting Trees and
Woodland) of the Isle of Wight Unitary Development Plan. |
10 |
No development shall
take place until there has been submitted to and approved in writing by the
Local Planning Authority a scheme of landscaping and works to veteran trees,
which shall include indications of all existing trees and hedgerows on the
land, and details of any to be retained, together with measures for their
protection in the course of development. Reason: To ensure the appearance of the
development is satisfactory and to comply with policy D3 (Landscaping) of the
IW Unitary Development Plan. |
11 |
All hard and soft
landscape works and works to veteran trees shall be carried out in accordance
with the approved details. The works
shall be carried out prior to the occupation of any part of the development
or in accordance with the programme agreed with the Local Planning Authority. Reason: In the interests of the amenities and
character of the area and to comply with policy D3 (Landscaping) of the IW
Unitary Development Plan. |
8. |
TCP/24579/D P/02580/04 Parish/Name: Ventnor
Ward: Ventnor West Registration Date: 16/12/2004 -
Full Planning Permission Officer: Mr. S. Cornwell Tel: (01983) 823575 Applicant: Mr G W Blake Continued use of part of premises
for the preparation of fish and shell fish Blake & Spencer, Esplanade,
Ventnor, Isle Of Wight, PO381JT |
REASON FOR COMMITTEE CONSIDERATION
This application has been
brought before the Committee as the site, the subject of the application, is
included within an area subject of an existing enforcement notice which sought
compliance by 30 September 2004 and is now the subject of deferred Court
action. Furthermore, although Members
considered the enforcement authorisation, the original decision to refuse the
first planning application was taken under the delegation procedure and
consequently the Committee have not had the opportunity to determine the full
detailed merits of the proposal.
PROCESSING INFORMATION
This is a minor
application which will have taken just over eight weeks to determine on the
basis a final decision is made at the Development Control Committee meeting on 15
February 2005.
LOCATION AND SITE
CHARACTERISTICS
Application relates to
eastern part (approximately 25%) of Boathouse which is a single storey building
situated behind properties on the northern side of the Esplanade at Ventnor.
Access to the building is via a passage way which links Esplanade to Marine
Parade. At the southern end of the passage way on either side is the Longshore
Museum and a residential property. To the north of the Boathouse is an open
grass area beyond which is a parking area which has been formed to serve one of
the residential/holiday accommodation properties which lie on the northern side
of Marine Parade. To the east of the site is an open storage area in the same
ownership/control as the remainder of the Boathouse which is used for storage
purposes.
RELEVANT HISTORY
Application for a lawful
development certificate for continued use of the premises for the preparation
of fish and shell fish refused in May 2002 on the ground that the evidence
submitted did not indicate building continuously used over a period exceeding
ten years.
An appeal against this
decision was made but subsequently withdrawn in February 2003.
Planning application for
the use of part of premises for the preparation of fish and shell fish was
refused in August 2003 for the following reason:
“The development has
resulted in an unacceptable odour and pollution nuisance in the locality, and
is therefore considered by the Local Planning Authority to be contrary to
Policies E9 (Employment Development anywhere within settlements) and P1
(Pollution and Development) of the Isle of Wight Unitary Development Plan.
At the 12 August 2003
Development Control Committee Meeting Members resolved to serve an enforcement
notice requiring the cessation of the use of the building known as the
Boathouse and the adjoining land for the preparation of fish and shell fish
with a time period for compliance of 12 months. The enforcement notice was
served and an appeal duly lodged.
The sole ground of appeal
was Ground G (the time given to comply with the notice is too short).
At the Development
Control Committee meeting (Site Inspections) held on 30 January 2004, Members
considered a report relating to the appeal and the time period that this would
involve in reaching an outcome. After some consideration Members resolved to
extend the time period for compliance with the enforcement notice through to
the 30 September 2004 on the understanding that the appeal was withdrawn.
On 1 October 2004 the
premises were inspected and the use was found to be continuing. A prosecution for failure to comply with the
requirements of the enforcement notice was initiated with a first Court Hearing
of 17 December 2004. At that time the case was deferred until March 2005 to
give an opportunity for the current application to be determined.
Although not on this site
the following decision has some relevance to the current application:
At the 22 June 2004
Development Control Committee meeting, planning permission was given for
construction of piled jetty with building over to provide fish processing
facility and retail outlet at a site within the Ventnor Haven facility.
DETAILS OF APPLICATION
Planning permission is
sought to continue the use of premises for the preparation of fish and shell fish
with the applicant indicating that this is required for approximately nine
months. An inspection of the building indicates that there are two steps down
from the entrance door which leads into a short passageway with the boiling pot
and an ice machine located in an area to one side. At the back of the building
is a room containing the work surfaces and sink area where the meat is taken
out of the shells. This room also
includes a number of chiller units where the packed meat is stored before
distribution. The building also contains a cloakroom and WC.
Unlike the previous
application the applicant no longer has access and use of any of the adjoining
open ground to the east.
Letter submitted by the
applicant provides the following information:
·
Catch landed at Ventnor Haven from own boat and this the only source of
supply.
·
Catch transported to Boathouse by pick-up truck.
·
Catch predominantly crab.
·
Main season is September to Christmas, catch is light January to
February with a short Spring run in late March to early May. May is the worst
time of the year for crabs but catches improve through the Summer months.
·
If catch larger than can cook immediately an element is stored at sea in
live pens.
·
Crabs placed in 50 gallon container and boiled for 15 minutes. This
generates little smell which is no more offensive than other food cooking
premises in area.
·
Location of boiler is behind cafés on Esplanade and produces less odour
than fryers in kitchens of cafes on Esplanade which operate all day.
·
Boiler is ventilated by removing wooden shutter.
·
Waste water drained directly into mains drain.
·
Waste crab shells returned to sea and dropped over side.
·
Average daily production is 30 kilograms of crab meat, majority sold
same day, distributed by own vehicle.
·
Building Control Approval now being sought on new facility in haven,
confident new fishery will be up and running in June ready for oncoming crab
season.
DEVELOPMENT PLAN/POLICY
Planning Policy Statement
23: Planning and Pollution Control para 8:
"Any consideration
of the quality of land, air or water and potential impacts arising from
development, possibly leading to an impact on health, is capable of being a
material planning consideration in so far as it arises or may arise from any
land use".
Site lies within the
Ventnor development envelope. No other specific annotation relates to this
area.
Relevant Unitary
Development Plan Policies are as follows:
G10 – Potential conflict between proposed development
and existing surrounding uses.
D1 – Standards
of Design
E9 – Employment
Development anywhere within settlements
TR7 - Highway Considerations for New Development
P1 - Pollution and
Development
CONSULTEE RESPONSES
Principal Environmental
Health Officer:
·
Although this section has received complaints in the past alleging odour
nuisance, our investigations have failed to substantiate the allegation.
The Principal Environment
Health Officer was also asked to comment on repositioning of the boiler inside
the building, to give some comparison between the level of odour from this
operation as opposed to other general cooking activities and finally to comment
on the operation from a health and safety perspective. In response the
following comments have been received:
·
It is possible that the location of boiler within building may have some
slight effect on the reduction of odour. However, adequate ventilation required
by food hygiene legislation and by health and safety legislation likely to
minimize any consequential odour reduction. There may be a psychological effect
on the basis of out of sight out of mind.
·
Regarding comparison between this activity and other cooking
establishment. Shell fish boiling confined to about one hour a day compared to
eight hours or more for a fish and chip shop. Qualitatively of course, the
odours will be different and therefore more or less acceptable to local
residents.
·
Regarding health and safety, can advise officer recently inspected
premises and they comply with current requirements.
Highway Engineer to be
reported.
PARISH/TOWN COUNCIL
COMMENTS
Ventnor Town Council
consider there is no satisfactory reason for the continuing extension of the
temporary planning permission and a further extended period is undesirable.
THIRD PARTY
REPRESENTATIONS
Letters have been
received by five property owners in the locality making the following points:
·
Previous reasons for objection to earlier application still remain.
·
Planning history shows rejection, service of enforcement notice unsuccessful
appeal, extension of enforcement compliance time, failure to comply, Court
date, and new application identical to one rejected in April 2003.
·
Applicant adopting delaying tactics.
·
Council’s acceptance of application tantamount to supporting harassment
the activity causes us.
·
Access via a public right of way, no more than one metre wide which is
subject to regular discharge of cooking fluids along it.
·
Passageway frequently has discarded shell and shell fish waste, left to
decompose causing serious fly infestation and attracts rats. This is a health
hazard.
·
Smells from cooking offensive, especially in summer and this will deter
tourists.
·
Activity results in car parking on double yellow lines at end of passage
way causing hazard to pedestrians and blocking door to residential cottage.
·
There must be more suitable sites.
·
This is a residential area.
·
If approved now would make mockery of planning process.
·
Original refusal just refers to policies E9 and P1. Consider D1 and D10
and TR7 also apply.
·
Fail to understand procedure this third time, applicant requested
planning.
·
75% of the Boathouse is not included in the application.
·
Cooking now takes place indoors. Question if health and safety know.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
Before considering the
determining factors with regard to this application, I believe I should comment
briefly on the planning history and the circumstances surrounding the current
application. The planning history is clearly a material consideration that
should be taken into account in the determination of this application. However,
Members should not allow themselves to be influenced by what has been
interpreted in some of the third party representations as an abuse of the
planning process. Notwithstanding the current status where the applicant has
failed to comply with the requirements of an enforcement notice by an extended
deadline, he has exercised a right to apply and under current legislation the
Local Planning Authority must accept the submission of the application and
determine any application on its merits.
Members should also be
aware that the Town and Country Planning Act 1990 acknowledges that it is
possible to regularise a breach of planning control even where an enforcement
notice has been served by a subsequent grant of consent. Accordingly, the
existence of an enforcement notice does not prevent a review of the case,
particularly if some element has changed.
The determining issues
with regards to this activity are considered to be firstly whether this is an
appropriate location for the activity concerned given the potential impact on
the locality and surrounding properties and secondly, whether there are any
traffic implications. In assessing both
points I will acknowledge the previous determinations and any change in
circumstances.
With regards to the first
point, I consider that the area within which the premises are located is not
solely residential but sits behind a mixed use area on the Esplanade which
includes commercial premises (including several cafes) with some residential
with a mix of residential and holiday accommodation in the properties on the
north side of Marine Parade which are approximately 25 metres away from the
building. Concerning the impact of the operation on the locality, Members
should be aware that this is a relatively small scale operation and comparisons
have been made by the applicant with the café operations that exist on the
Esplanade. In that context, I consider that a significant change in the
operation has been the relocation of the boiler to inside the building. Whilst
I note the comments by the Environmental Health Officer that this may not lead
to a significant improvement in the dissipation of odour I believe that it
would have removed some of the concerns raised by a number of the local
residents relating to the emptying of any water down the passage way. This
cannot take place under the present operation as entry into the building involves
going down two steps. Visits to the site have not resulted in the observation
of any items left in the passage way, which is a further point also raised by
objectors.
During a recent visit to
the site, when stood on Marine Parade I did experience occasional smells from
the premises whilst boiling was in progress but I was also aware of other
cooking odours also being present. Members' attention is drawn to the comments
by the Environmental Health Officer who indicates that complaints alleging
odour nuisance have been received in the past but investigations failed to
substantiate any allegation.
On balance, whilst noting
the changes to the operation, its scale and the site’s proximity to nearby
residential properties I do not consider that there is sufficient evidence of a
substantive nature to justify an objection on the grounds of loss of amenity.
Nor do I consider that the use is unacceptable in this locality having
considered the additional information from the applicant relating to other
commercial premises in the area which also engage in cooking activities.
On the question of the
time period that should be applied to any consent, the applicant has requested
nine months. I am conscious that for a number of reasons the applicant has not
kept to previous timescales and on that basis I am reluctant to set a specific
time with the risk that if the relocation plans do not materialise then we
could end up with a potential enforcement problem in the future. Based on the
assessment outlined above and providing conditions are imposed limiting the
scale of the operation I see no specific need to set a time limit to any
consent other than to seek its cessation when Mr G Blake vacates the building.
This is reflected in the conditions outlined below.
Concerning the second
issue relating to traffic impacts, Members will be aware that the Esplanade
contains a series of traffic control structures. As a consequence I believe
that vehicles will be moving at low speeds only. There is limited parking on
the south side of the Esplanade and should a vehicle park close to the passage
way entrance I believe that this would only be for a short period of time.
Furthermore, this is a situation which I believe commercial properties on the
north side of the road would face at some time or other. On balance, I do not
believe that there is clear evidence of a traffic hazard sufficient to withhold
planning permission. Members will note such a reason did not appear in the
earlier decision to withhold consent.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission, consideration has been given to
the rights set out in Article 8 (Rights to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts this development might have on the
owners/occupiers of other properties in the area and other third parties have
been carefully considered. Whilst there may be some interference with the
rights of these people, this has to be balanced with the rights of the
applicant to continue the operation at the site. Insofar as there is an
interference with the rights of others, it is considered necessary for the
protection of the rights and freedom of the applicant. It is also considered
that such action is proportional to the legitimate aim of the Council’s Unitary
Development Plan and in the wider public interest.
JUSTIFICATION FOR
RECOMMENDATION
I am aware that the
intention is to relocate the business to a purpose built facility in the Haven.
The applicant indicates that work is to start shortly on this building in
anticipation of a relocation by June which reflects the start of the main
fishing season. I intend to update Members on the latest position regarding
this relocation at the meeting.
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I am satisfied that the continued use of this building at the level
which currently exists would not have a detrimental impact on the environment,
neighbouring properties or detract from the visual amenities of the area. In
this regard, I have noted the changing circumstances from the earlier
determinations and that the proposed development complies with the policies as
set out in the Unitary Development Plan.
RECOMMENDATION - Approval
Conditions/Reasons:
1 |
The use hereby
permitted shall be carried on only by Mr G Blake and at the time when he
vacates the premises the use shall cease and the premises shall revert back
to a general storage use. Reason: But for the personal circumstances put
forward by the applicant, the application would not have been approved. |
2 |
Only fish and shell
fish caught by the applicants single boat fishing operations shall be
processed within the building which is the subject of this consent. Reason: To ensure that the
scale of operations remains at a level that does not result in an
unacceptable adverse impact on the surrounding area. |
3 |
Only one boiler shall
be used for the cooking of any fish or shellfish and it should be limited to
a 50 gallon capacity. Any change from
the current boiler shall be agreed in writing with the Local Planning
Authority. Reason: To ensure that the
scale of operations remains at a level that does not result in an
unacceptable adverse impact on the surrounding area. |
4 |
The cooking operations
shall be confined to within the following hours: 0800 to 1800 hours. Reason: To ensure that the
scale of operations remains at a level that does not result in an
unacceptable adverse impact on the surrounding area. |
9. |
TCP/25066/B P/01557/04 Parish/Name: Brighstone
Ward: Brighstone and Calbourne Registration Date: 21/07/2004 -
Full Planning Permission Officer: Miss. S. Gooch Tel: (01983) 823568 Applicant: Mr B Lancaster Retention of building providing
stable, multi-use animal shelter & tack room for storage of agricultural
& forestry tools (revised scheme) part OS Parcel 0091 and 0072 south
of Hulverstone Farm, Hulverstone Lane, Hulverstone, Newport, PO30 |
REASON FOR COMMITTEE CONSIDERATION
When consulted under
delegated procedure the Local Member, Councillor Mrs J Wareham, requested that
the application is considered by the Committee due to concerns raised on the
impact of the building on the landscape, application does not address issues
and policies referred to in the previous appeal and there is no justification
for the building.
PROCESSING INFORMATION
This is a minor
application the processing of which has taken 29 weeks to date and has gone
beyond the prescribed 8 week period for determination of planning application
due to case officer workload and the request from Local Member for Committee
consideration.
LOCATION & SITE
CHARACTERISTICS
Site is located within an
Area of Outstanding Natural Beauty and Heritage Coast. Application site is to
the eastern side of Hulverstone Lane with well established hedgerow/trees which
runs along the western side of the lane. Access to the site is via a five bar
metal gate. Post and wire fence forms other boundaries as the land in the
vicinity appears to have been divided up between a number of owners. Within the
plot exists a typical wooden designed stable with tack room which is
immediately adjacent the field boundary. Located to the south of these stables
is an open fronted a shelter/barn.
Scattered around the site
are various objects not associated with agriculture e.g. disused boats and
personal belongings and at present the stables and open barn/shelter are not
being used for their intended purpose. All of these issues are currently the
subject of an enforcement notice requiring the removal of the stable and floor
slabs.
RELEVANT HISTORY
TCP/25066/A - planning
permission for retention of building providing storage/animal shelter/stabling
for a pony, retention of touring caravan; continued storage of two boats was
refused February 2004 as proposal detracted from the appearance of the site and
failed to protect and enhance the special quality of the landscape designated
as an AONB.
E/25066/C Enforcement
Notice issued dated June 2004 for the permanent removal of the caravan from the
land, removal of all boats from the land, to cease use of the land for storage
purposes.
DETAILS OF APPLICATION
Consent is sought for the
retention of the stable for use as multi use animal shelter and tack room for
storage of agricultural and forestry tools. The applicant is responsible for
the upkeep of surrounding pasture land and the woodlands located to the far
east. The stables would not only be used for horses but when required will be
used for sickly ewes/lambs etc.
With regard to the
current enforcement action in respect of removal of all non-agricultural items
such as boats and personal belongings, the applicant has confirmed he intends
to remove these items.
DEVELOPMENT PLAN/POLICY
Site is located outside
the development envelope, within the Heritage Coast and a landscape designated
as an AONB. Relevant policies of the UDP are as follows:
S4 – The Countryside will be Protected from
Inappropriate Development
G4 – General Locational Criteria for Development
D1 – Standards of Design
C1 – Protection of Landscape Character
C2 – Areas of Outstanding Natural Beauty
C4 – Heritage Coast
C22 – Keeping of Horses
for Recreational Purposes
C23 – Stables and Field
Shelters in the Countryside
P1 - Pollution
CONSULTEE RESPONSES
Environmental Health have
no adverse comment in respect of this application.
AONB advised that whilst
it is regrettable that the sub-division of land has occurred which has resulted
in changed pressures on the landscape, they are of the opinion that it is not
unreasonable to seek approval for a small building to accommodate livestock and
agriculture equipment which is sited to benefit from existing natural
screening.
PARISH/TOWN COUNCIL
COMMENTS
Brighstone Parish Council
note the applicant needs a covered place in which to keep agriculture and
forestry tools, as an owner of land and woodland. They would appreciate if the
storage buildings could be tidied up as well as the whole site and agreed to
proposal.
THIRD PARTY
REPRESENTATIONS
Three letters were
received from local residents objecting to the application on grounds which can
be summarized as follows:
·
Present use is wholly unacceptable
·
If approved, it will set a precedent
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications anticipated.
EVALUATION
Determining factors in
considering application is whether a retention of the buildings has an
unacceptable impact on the countryside and appearance on the surrounding Area
of Outstanding Natural Beauty and Heritage Coast.
Members will recall the
issue of an enforcement notice dated 23 June 2004 for the removal of stable
block and floor slab for the purpose of general storage unrelated to
agricultural use. Enforcement notice was subject of an appeal to the Planning
Inspectorate on 23 July 2004 and a decision is still awaited.
Whilst I acknowledge
there is some question as to the current use of the site and buildings,
consideration needs to be given to the applicants proposed use and not the
existing situation.
Within the applicants
ownership is an area of woodland which has a Protection Order and applicant
confirms that he is responsible for the upkeep of pasture land and the
woodland. Following a Land Registry search, I am satisfied that the land within
the applicant's ownership is of adequate size to allow for the keeping of
horses and multi use animal shelter.
AONB Officer advises that
whilst they are still of the opinion that the sub-division of the land in this
area is regrettable and has resulted in change of pressures on the landscape,
they confirm that it is not unreasonable to seek approval for a small building
to accommodate livestock and agricultural equipment which is sited to benefit
from existing natural screening. They wish to seek removal of the open barn as
the applicant has indicated that the stable and tack room will also act as
storage for agricultural equipment. However, I consider this unreasonable as
there are larger items associated with forestry and maintenance of pasture land
such as a tractor, trailer, field mower etc. that cannot easily be stored
within the stable building.
Concerns are raised on
the present use being unacceptable. However, I can confirm that the current
unauthorised use is being dealt with through enforcement action and this
application is for consideration of an alternative and more appropriate use for
the site. With regards to concerns that the proposal would set a precedent,
each application has to be considered on it own merits.
On balance, I consider
that it is not unreasonable for the applicant to wish to retain the stable and
for the open barn to remain in this location for its intended use, associated
with the tending of he land and keeping of animals thereon, as both buildings
are adequately screened, sensitively sited to avoid harming the visual amenity
of the countryside and set within an appropriate rural location.
HUMAN RIGHTS
In coming to this recommendation
to grant planning permission consideration has been given to the rights set out
in Article 8 (Right to Privacy) and Article 1 of the First Protocol (Right to
Peaceful Enjoyment of Possessions) of the European Convention on Human Rights. The impacts this development might have on
the owners/occupiers of other property in the area and other third parties have
been carefully considered. Whilst there may be some interference with the
rights of these people this has to be balanced with the rights of the applicant
to develop the land in the manner proposed. Insofar as there is an interference
with the rights of others it is considered necessary for the protection of the
rights and freedom of the applicant. It is also considered that such action is
proportional to the legitimate aim of the Council’s Unitary Development Plan
and in the public interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I am satisfied that the proposal represents acceptable development and
is appropriately located within this rural setting. In view of the above I am
satisfied that the proposal does not conflict with policies of the Isle of
Wight Unitary Development Plan.
RECOMMENDATION - Approval
Conditions/Reasons:
1 |
The stables shall only
be used as a shelter for arrivals
kept on the land and for the stabling of horses and the storage of associated
equipment and feed for private recreational purposes only and shall at no
time be used for any trade or business including livery stabling, commercial
equestrian tuition or commercial leisure rides. Reason: The use of the stables on a commercial
basis is likely to lead to an increased use of the premises and generation of
additional traffic which would be detrimental to the amenities of the area
and to comply with policy C22 (Keeping of Horses for Recreational Purposes)
of the IW Unitary Development Plan. |
2 |
Stables - no caravans, etc -
F31 |
3 |
Stables - no outside storage - F32 |
4 |
Stables - no burning of
manure - F33 |
5 |
Stables - no fences/means of
enclosure, - F34 |
6 |
The walls of the stable
block shall be stained, and thereafter maintained in a dark brown colour. Reason: In the interest of
amenities and character of the area and to comply with Policy D1 (Standards
of Design) of the IOW Unitary Development Pan. |
10. |
TCP/25275/B P/02596/04 Parish/Name: Freshwater
Ward: Freshwater Afton Registration Date: 09/12/2004 -
Full Planning Permission Officer: Mr. J. Fletcher Tel: (01983) 823598 Applicant: West Island Developments Demolition of hotel; residential
development comprising a total of 36 dwellings in a mixed development of
houses and flats with associated parking; formation of vehicular and
pedestrian access (revised scheme) land adjoining Hill House, Queens
Road/2School Green Road/Brookbank/ Brookside Forge, Brookside Road Freshwater |
REASONS FOR COMMITTEE CONSIDERATION
This is a major application
requiring determination by the Committee.
PROCESSING INFORMATION
This is a major
application, the processing of which will have taken 10 weeks to date.
LOCATION AND SITE
CHARACTERISTICS
Site, irregular in shape,
having limited frontages onto Brookside Road, Queens Road and School Green
Road. Site takes former substantial area of cartilage of number 2 School Green
Road and the cartilage of hotel premises Brookside Forge on the Brookside Road
frontage. Site adjoins a number of property, namely the cartilage of Brooklands
located on the corner of Queens Road and School Green Road, end of terrace
property Hill House which is one of a group of terraced dwellings which extend
to the south to the junction of Brookside Road with Queens Road. A substantial
area of the eastern boundary and southern boundary the area of the land which
fronts School Green Road abuts a traditional detached dwelling known as
Brookbanks which has a lengthy vehicular access on Brookside Road with the
property itself standing to the west of the food retail premises of
Summerfield.
Application includes and
almost triangular shaped area being set to the south of the bus stop in School
Green Road to west of Somerfield and east of number 2 School Green Road. South
boundary of that area of land abuts the northern boundary of Brookbanks. Site
has gentle falls both towards Brookside Road and School Green Road and has
recently been subject of site clearance.
RELEVANT HISTORY
IN April 2004 a similar
application was approved subject to a Section 106 Agreement covering the
provision of eight affordable housing units in line with Council policy H14 and
a payment of £32,400 (36 x £900) in respect of a contribution of education
facilities and a payment of £10,440 (36 x £290) towards upgrading of local open
space and recreational facilities.
Unfortunately, following
that decision there was a considerable delay in completing that agreement it
was considered that the application should be finally disposed of. This
procedure is carried out under Article 25 (11) of the Town and Country Planning
(General Development Procedure) Order 1995 which enables local planning
authorities to effectively withdraw the application with the Authority taking
no further action on that application.
DETAILS OF APPLICATION
Members are reminded that
proposal is for 36 units split into 4 elements as follows:
·
Element 1 (southern area including frontage onto Brookside Road
consisting of:
3 terraced houses (2, 2
bed and 2, 3 bed)
2 semi detached houses
(1, 2 bed and 1, 3 bed)
1 detached house (1, 3
bed)
2 maisonettes (2, 2 bed)
Total
8
·
Element 2 (located on Queens Road frontage immediately to the south of
southern boundary of property Brooklands and north of property Hill House)
consisting of:
11, 2 bed flats on 2/3
storey block, plots 9-19 inclusive
·
Element 3 (located between the eastern boundary of the curtilage of
property Brooklands and western boundary of Brook Bank) consisting of:
Symmetrical flat block
with central 3 storey element forming bridge over vehicular access including
clock tower with 2 storey wings either side providing:
2, 3 bed units and 1, 2
bed units
Total 3
·
Element 4 (located on School Green Road frontage between Summerfield
Supermarket and number 2 School Green Road) consisting of:
2/3 storey block of 14
flats providing:
11, 2 bed units
3, 1 bed units
Total 14 units
Vehicular access and
parking
Development served by 4.5
metre carriage way access off Brookside Road with splay junction and visibility
splays. Access road serves total of 38 parking spaces dispersed throughout the
site.
Landscaping and footpath
provision
Elements 2, 3 and 4
provided with landscape areas particularly in respect of element 4 which has a
landscaped area which fronts School Green Road immediately to west of
Summerfield Supermarket. Proposal also provides for seating and hard paved
landscaping area for communal use.
Footpath provision is
provided on the western side of the proposed access road and passes through the
proposed seating and hard landscaped area as previously described Footpath
continues in a northerly direction directly adjacent western boundary of Brook
Bank having a width of one metre widening to 1.2 metres and then widening to 2
metres where the path extends through to Scholl Green Road.
Flats are provided with
cycle parking and bin stores appropriately located.
Off site work
Proposal provides for
provision of two pinch points to be located within Brookside Road in the form
of road narrowing island including signage to form traffic calming in Brookside
Road. Proposal also provides for new footbridge to be erected across the brook
linking Brookside Road to the existing footpath which runs along the eastern
side of Brookside Road parallel to the brook.
Boundary Treatment
Because of changes in
level in respect of Element 4 and the adjoining property Brook Bank and number
2 School Green Road, proposal includes for new retaining walls along the
northern boundary of Brook Bank. Provision also made for 1.2 metre high brick
wall along the western boundary of the property Brook Bank and a 1.8 metre high
boundary wall along the eastern boundary of the property Brooklands.
General
Accompanying design
statement emphasizes the following:
Proposal provides for a
good mix of development although accepts the predominance of flats but insures
houses are indicated on the Brookside Road frontage. This results in a
relatively high density of development.
Footpath arrangement
provides opportunity for occupants to gain easy access through the site between
Brookside Road and Scholl Green Road.
Parking provision and its
dispersal of parking throughout the site provides the minimum provision for 1
for 1 with spaces conveniently located relative to the units to which they
serve.
Traditional design
approach has been taken providing a range of dwelling types. Topography of site
dictates new buildings are at various levels with particular reference to flats
which front School Green Road being set down in the ground to reduce impact on
the street scene and to provide better access for pedestrians to the site.
Houses and access road
from Brookside Road follow the gradient of the ground to produce a stepped
arrangement of units.
Queens Road flats design
to step up and way from the adjoining property in part following the ground
levels and in part dug in.
Drainage Engineer have
been involved in terms of drainage scheme with the result that on site
attenuation will be required which will be located to allow vehicular access
off a public place. Apart from the School Green Road frontage land remainder
will drain to Brookside Brook which involves the construction of a new head
wall. It has also been established that there is sufficient capacity in
existing sewers to accept the additional foul drainage.
Previous application
accompanied by a badger report which effectively recognizes badger activity in
the area but not to a degree which that would warrant an objection to the
development. It is suggested the applicant consult with English Nature with a
view to obtaining a DEFRA licence is sought in respect of this matter.
Confirmation has been
received via a letter from Southern Housing Group (Housing Association) who
confirmed their involvement with this scheme to the extent that they will be joined
in to the legal agreement.
DEVELOPMENT PLAN/POLICY
Site within development
envelope boundary.
National policies covered in PPG3 – Housing March 2000 as follows:
·
Provide wider housing opportunity and choice by including better mix and
size, type and location of housing.
·
Give priority to reusing previously developed land within urban areas,
taking pressures off green field sites.
·
Create more sustainable patterns of development ensuring accessibility
to public transport, jobs, education, health facilities etc.
·
Make more efficient use of land by adopting appropriate densities with
30 - 50 units per hectare quoted as being appropriate levels of density with
even greater intensity of development being appropriate in places with good
public transport accessibility such as town centre sites.
·
Emphasis on the need for good quality designs.
·
New housing development should not be viewed in isolation but should
have regard to immediate buildings and wider locality.
·
More than 1.5 parking spaces per dwelling unlikely to reflect
Government’s emphasis on sustainable residential development.
Relevant local plan
policies as follows:
Strategic policies S1, S2, S6 and S7 are appropriate.
Other relevant policies
as follows:
G1 – Development Envelopes for towns and villages
G4 – General Locational Criteria for development
D1 – Standards of Design
D2 – Standards for
Development within the site
H4 – Unallocated
residential development to be restricted to defined settlements
H14 – Locally affordable
housing as an element of the housing scheme.
TR16 – Parking policies
and guidelines
TR7 – Highway
Considerations for new Development
TR6 – Cycling and Walking
U11 – Infrastructure and
Services Provision
U2 – Ensuring adequate
educational, social and community facilities
Reference also made to
housing need survey which whilst acknowledging need for single person
accommodation also identifies ongoing demand for two and three bedroom units to
meet statutory homeless requirements.
Site located within
parking zone 3 which stipulates maximum parking provision of 0-75% of parking
guidelines.
Brookside Road is not
identified as being within a flood plain area.
CONSULTEE RESPONSES
Although the Highway
Engineers comments have yet to be received, proposal is the same as previous
application including traffic calming features in Brookside Road etc. All of
these were subject of discussions with the Highway Department who therefore,
will have no option but to support the proposal subject to condition.
Environment Agency raise
no objection to the proposal being satisfied that the calculations submitted
sufficiently attenuate the rate of discharge from the site and also recommend that applicants confirm
that soakaways have been adequately designed to construct taking into account
the potential fluctuations in ground water level.
Southern Water have not
been consulted however, reference is made to their previous comment which is
itemised as follows:
Surface water should be
kept out of the existing sewer system thus freeing up foul water capacity for
the new development there being no separate surface water sewers in the area.
Southern Water confirms that their records do not indicate any flooding
incidents in the area.
They concluded as
follows: “there seems some uncertainty about the disposal of surface water. We
would not want any highway water discharged into the combined sewers.” Any SUDS
system is not possible to be adopted by Southern Water but they recognize that
this could be the best solution if the soil is suitable.
Council’s Contamination
Officer recommend appropriate conditions should application be approved.
PARISH/TOWN COUNCIL
COMMENTS
Freshwater Parish Council
does not object but would ask that the education grant for each unit be allocated
for local school needs. Consideration should be given to a traffic management
plan and the fact that the development would be on a safe route to schools.
They also feel that the three storey elevation on Queens Road is too over
powering for the area and would prefer to have only two storey.
THIRD PARTY
REPRESENTATIONS
Four letters of objection have been received, three from Queens Road residents and one from Brookside Road resident. Points raised are summarized as follows:
·
Pressures on existing infrastructure with particular reference to
drainage system.
·
Concern that development will exacerbate potential flooding problems.
·
Additional traffic generated by this development will impact on the
local road system to the detriment of road safety.
·
Proposal likely to result in additional pressures in respect of on
street parking, with particular reference to element 2 flat block which faces
Queens Road which may increase those pressures due to the entrance being off
Queens Road.
·
One objector expresses concern at the loss of the hotel premises and the
impact that, that may have on the tourism industry which could further impact
on the viability of local retail businesses.
·
The general height and mass of the centrally located block (element 3)
is considered to be excessive having an over dominant and overlooking affect on
neighbouring property. Reference is also made to the unnecessary clock tower
feature.
EVALUATION
Members will note that
this is an exact repeat of the previous application of April 2004 and because
the proposal exceeds 20 units and in accordance with agreed procedures the
application has to be determined by Committee. The reason the previous
application was "Finally disposed of" by the Authority was that a
judgment was made that the application appeared to be making no progress
despite a number of reminders and on the basis that the Authority simply cannot
allow an application to be held in abeyance indefinitely a not unreasonable
decision was made to finally dispose of the application. This to some extent
has had the desired effect for the applicant has immediately submitted a
similar application, which, because of the limited time period had to be
submitted within an very short period in order to take advantage of a “free
go”.
It is understood that the
matters which have caused delay in respect of the Section 106 Agreement have
largely been resolved and I am advised that Agreement signature should be
quickly achieved. However, recent advice suggests that planning authorities are
able to apply conditions to any consent requiring subsequent completion of a
planning obligation. Such a condition should be worded as a Grampian condition
effectively preventing implementation of any development until a planning
obligation has been completed. I suggest that this application provides a
valuable example of where such a condition can be applied.
In order to remind
Members of these proposals themselves, I summarise the previous evaluation as
follows:
Principal/Density
This application is a
good example of land assembly a procedure which is encouraged within PPG3 with
the site being a brown field urban site in close proximity to the town centre.
In terms of density
because of the predominance of flatted development the density is 80 units per
hectare again not unreasonable given the site’s location close to the town
centre and fully in accordance with PPG3 Advice.
Layout Access and Parking
The original layout was
subject of extensive negotiation which resulted in a reduction from 39 to 36 units.
The various elements of the development pay particular attention to general
characteristics of the area and it was considered that mass and height and
general location of the various elements were acceptable.
Similarly in terms of
access which was subject of negotiations involving the highway department
resulting in the introduction of traffic calming measures and the provision of
footbridge all as previously described. Similarly with regard to the new access
road which has been aligned to serve the potential for further development on
the eastern side but also has been aligned to ensure traffic calming. The road
also provides turning space with reference for space for larger vehicles to
turn and service the site with particular reference to fire appliances and
refuse vehicles.
Block which fronts Queens
Road reflects a continuation of the terraced theme of development. This block
indicates direct access onto Queens Road however, inevitably this could result
in further pedestrian access from the rest of the site. The design of the
footpath however, has been deliberately aligned to discourage that type of
access occurring. Proposal also provides for a metre wide footpath to link to
the existing footpath on the eastern side of Queens Road.
With regard to element 3,
being a block within the car parking area, this provides a link to the main
block of flats on the School Green Road frontage. This block provides only
three units of accommodation although does have a central bridging unit which
stands three storeys high.
With regard to the School
Green Road frontage development, this has been carefully considered to reduce
impact on the property Brook Bank and take advantage of the wider element of
the site by using an L shape. The landscaped area to the east along with the
shape of the unit will create a pleasant visual impact when approaching from
the south east along School Green Road.
Provision of parking
provides for one parking space per unit plus two additional visitors spaces
which is considered acceptable particularly given the majority of units provide
two bedroom accommodation and any occupiers would purchase with the knowledge
there is only one parking space available. Parking spaces have been purposely
split into small groups interspersed with landscaping features to provide a
court yard appearance which can be achieved providing appropriate surface
treatments are applied which can contribute to the visual amenities of the
development.
Finally, the link
footpath through to School Green Road is considered essential to encourage easy
access to the town centre and retail and business facilities. It is considered
unlikely that this will be used only by anybody other than residents of the
site, however there are clearly no guarantees.
Design, mass and impact
Each element has been
traditionally designed with brick finished walls and pitched slated roofs.
Cottage style architecture has been used in respect of the properties on the
Brookside Road frontage with corner aspect being fully acknowledged.
Levels of the site have
also been used appropriately ensuring two storey elements adjacent to existing
terraced cottages particularly in Queens Road.
Use of screen walls along
with obscure glazed lower half of first and second floor windows will be sufficient
to address overlooking concerns.
Flat block which fronts
School Green Road was again subject of extensive negotiations resulting in
reduced height. Also flat block has been deliberately placed in the western
area of the site to reduce impact on detached property Brook Bank. Such height
and mass is compatible with the mainly Victoria buildings opposite the site.
Drainage
Drainage issues have been
satisfactorily resolved evidence by the supporting level from the Environment
Agency. This apart however, I consider appropriate conditions should still be
applied requiring full calculations to be submitted prior to work commencing.
Landscaping
Type of development
results in a considerable amount of hard landscaping however, applicants have
been encouraged to introduce pockets of landscaping within the parking
areas with particular
regard to retaining landscape margins where parking areas abut adjoining
properties.
As already stated parking
areas play an important role in this development in visual terms contributing
to the overall visual appearance of the development. Introduction of seated and
paving areas also contribute to the sense of place and sense of community which
it is hoped, will result from this development. Finally the provision of the
open space area on the School Green Road frontage represents an important area
within an otherwise built up street scene.
Applicants have indicated
use of brick boundary walls where they abut adjoining properties, Brook Bank
and Brooklands. Conditions will also be repeated retaining the existing
boundary walls in School Green Road frontage. Similarly, with regard to bins
stores and cycle parking which is an essential requirement for flatted
developments.
Conditions will also be
applied relating to the submission of a lighting scheme for the car parking
areas with any such scheme ensuring that areas are adequately lit without
causing light spillage problems in respect to adjoining properties.
Financial Contributions
and Provision of Affordable Housing
Since the previous
determination to approve this proposal Supplementary Guidance has been produced
in respect of the affordable housing which if applied to this current
application would require a 30% provision as opposed to the 20% provision which
previously applied. The implications of apply such a percentage requirement
would mean a need for three additional affordable housing units as a proportion
of the development.
Negotiations have been
taking place with the Housing Association as part of the Section 106 process
and virtual agreement has been achieved and therefore I would not wish to
jeopardise that process and therefore jeopardise the viability of the scheme by
applying the 30% provision at this time. A wider aim has to be deliverability
of housing and therefore I consider it is reasonable to apply the original
policy in the UDP to this development given the site’s history. Costings for
the development would have factored in the 20% provision not 30% provision.
Therefore, I recommend no change to the recommendation in terms of provision of
affordable housing provided eight affordable housing units are provided.
I understand that current
negotiations with the Housing Association have agreed the provision of six
rented units with further negotiations needed to ensure a further two units
which may be in the form of shared ownership. I consider that this would be a
reasonable mix on this site.
With regard to the
financial contributions again, changes have occurred in terms of the education contribution
which is now based on levels of capacity in individual areas. At the time of
the previous application the contribution was set at one level ie £900 per
unit. Again, for the same reason as above, I consider the application of the
original figure of £900 per unit to be a reasonable stance in this case again
given the planning history of the site.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of other property in the
area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the rights of others it
is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that
such action is proportional to the legitimate aim of the Council’s Unitary
Development Plan and in the public interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations as described in the
evaluation section of this report, I am satisfied that apart from issues
relating to affordable housing and
financial contributions, the same material considerations are involved all of
which were carefully considered at the time. This is a good example of land
assembly and that this proposal will make a significant contribution to
provision of housing in Freshwater and more importantly also provide affordable
housing. I continue to be of the view that the design, mass and scale are
considered appropriate and this coupled with appropriate drainage solutions
lead me to the view that there should be no change in the approval recommendation.
1.
RECOMMENDATION – Approval
(Subject to Section 106 Agreement covering the provision of eight affordable housing
units in line with the Council’s policy of H14, the payment of £32,400 (36 x £900)
in respect of contribution to education facilities, and payment of £10,440 (36
x £290) towards upgrading of local open space and recreational facilities.)
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
The development
permitted by this planning permission shall not be initiated by the
undertaking of a material operation and defined in Section 56 (4) (a) - (d)
of the Town and Country Planning Act 1990 in relation to the development,
until a planning obligation pursuant to Section 106 of the said Act relating
to the land has been made and lodged with the Local Planning Authority and
the Local Planning Authority has notified the person submitting the same that
it is to the Local Planning Authority's approval. The said planning
obligation will provide for: a) minimum of 8 affordable
housing units b) a sum of £32,400 (36
x £900) to be paid to the Local Planning Authority as a contribution to
education facilities c) the payment of
£10,440 (36 x £290) to be paid to the Local Planning Authority for the
purposes of upgrading local open space and recreation facilities. Reason: To ensure adequate
provision of a) locally affordable housing, b) education facilities and c)
open space and recreation facilities in compliance with Policy H14 (Locally
Affordable Housing as an element of housing schemes and Policy U2 (Insuring
adequate Educational, Social and Community Facilities for the future
population)of the IOW Unitary Development Plan. |
3 |
Construction of the
building(s) hereby permitted shall not commence until a schedule of all
materials and finishes to be used for the external roofing and walls of the
same has been submitted to and approved in writing by the Local Planning
Authority. Thereafter only such
approved materials and finishes shall be used in carrying out the
development. Reason: In compliance with
Policy D1 (Standards of Design) of the IW Unitary Development Plan. |
4 |
No development shall
take place until samples of the materials to be used in the construction of
the external surfaces of the development hereby permitted have been submitted
to and approved in writing by the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In compliance with
Policy D1 (Standards of Design) of the IW Unitary Development Plan. |
5 |
Before the development
commences a soft and hard landscaping scheme shall be submitted to and
approved by the Local Planning Authority.
Such scheme shall specify position, species and size of trees and
shrubs to be planted along with the phasing and timing of such planting, and
shall include provision for their maintenance during the first 5 years from
the date of planting. The scheme
shall also include details of the type, colour and texture of any block
paving and shall ensure that the parking spaces are clearly marked within the
car parking layout. Such hard and
soft landscaping shall be carried out in accordance with the agreed details.
Such landscaping scheme shall include for hedge planting of agreed species along
the landscape margin to rear of parking spaces 21-26 inclusive and 31-34
inclusive indicated on the plan hereby approved. The scheme shall be include
for an agreed long term schedule of management and maintenance
responsibilities which shall be put into place prior to the occupation of units
9-36 inclusive. Reason: To ensure the appearance of the
development is satisfactory and to comply with Policy D1 (Standards of
Design) and D3 (Landscaping) of the IW Unitary Development Plan. |
6 |
No development shall
take place until a detailed scheme including calculations and capacity
studies has been submitted to and agreed with the Local Planning Authority
indicating the provision of a surface water regulation system. Such details shall indicate where appropriate
the location of any surface water attenuation containment proposals and
treatment of outflow into the stream on the southern side of Brookside Road,
with any such outflow indicating methods of flow restraints. The regulation system for the site must ensure
that the run-off from the 1% probability storm is controlled and will
restrict the outflow to that which would have occurred had the site been a
greenfield. The scheme shall include
a maintenance programme and establish ownership of the storage system for the
future, and no dwelling shall be occupied until such an agreed surface water
regulation system has been completed. Reason: To ensure an adequate system of
storm water drainage is provided for the development and to prevent flooding
in compliance with Policy U11 (Infrastructure and Services Provision) and
Policy G6 (Areas Liable to Flooding) of the IW Unitary Development Plan. |
7 |
No surface water
drainage shall discharge into the existing combined sewer in Brookside
Road. Reason: To prevent flooding in compliance
with Policy U11 (Infrastructure and Services Provision) of the IW Unitary
Development Plan. |
8 |
No development shall
take place until there has been submitted to and approved in writing by the
Local Planning Authority a plan indicating the position, design, materials
and type of boundary treatments to be erected in respect of Plots 1-8
inclusive. The boundary treatment
shall be completed before Plots 1-8 are occupied. Development shall be carried out thereafter in accordance with
the approved plans. Such boundary treatment shall include the northern
boundary of the adjoining property Hill House adjacent parking spaces 14 and
15. Reason: In the interests of maintaining
the amenity value of the area in compliance with Policy D1 (Standards of
Design) of the IW Unitary Development Plan. |
9 |
Prior to occupation of
9-22 inclusive, the area set aside for public seating with fountain and
landscaping indicated on the plan hereby approved shall be completed in
accordance with scheme to be agreed with the Local Planning Authority. Such a
scheme shall include management responsibilities and maintenance schedules. Reason: In the interests of the amenities
of the future occupiers of the development in compliance with Policy D1
(Standards of Design) of the IW Unitary Development Plan. |
10 |
Prior to commencement
of work details shall be submitted to and approved by the Local Planning
Authority of the proposed retaining walls along the southern and western
boundaries of the flat block 23-36 inclusive. Such details shall include material finishes and boundary
heights over. Such retaining walls
shall be agreed and thereafter constructed in accordance with those details
prior to occupation of these flats. Reason: In the interests of the amenities
of the neighbouring properties in compliance with Policy D1 (Standards of
Design) of the IW Unitary Development Plan. |
11 |
None of the flats
hereby approved shall be occupied until details of any lighting to be
installed in respect of the car park areas have been submitted to and
approved in writing by the Local Planning Authority. Such lighting schemes shall be carried out
in accordance with the approved details. Reason: In the interests of future
occupiers and adjoining property owners in compliance with Policy D1
(Standards of Design) of the IW Unitary Development Plan. |
12 |
Prior to commencement
of work details shall be submitted to and approved by the Local Planning
Authority of the proposed footbridge on the southern side of Brookside Road
as indicated on the plan hereby approved.
Such details shall include structural details, material finishes,
accurate levels and long term maintenance responsibilities. The bridge shall be constructed in
accordance with those agreed details prior to occupation of any of the
dwellings hereby approved. Reason: In the interests of the amenities
of the area in compliance with Policy D1 (Standards of Design) of the IW
Unitary Development Plan. |
13 |
Prior to occupation of
flat Nos. 25, 26, 27, 28, 29 and 33, the lower half of all south facing
windows within those flats shall be permanently fixed non-opening, and shall
be finished in permanent obscure glazing, all of which shall be retained and
maintained thereafter. Reason: To protect the privacy of the
neighbouring property in compliance with Policy D1 (Standards of Design) of
the IW Unitary Development Plan. |
14 |
Prior to occupation of
flats 11, 12, 17, 13, 14 and 19 the lower half of the north facing windows
within those flats shall be permanently fixed non-opening and shall be
finished in permanent obscure glazing, all of which shall be retained and
maintained thereafter. Reason: To protect the privacy of the
neighbouring property in compliance with Policy D1 (Standards of Design) of
the IW Unitary Development Plan. |
15 |
No development approved
by this permission shall be commenced until a scheme for the disposal of foul
water sewage has been agreed with the Local Planning Authority and no
dwelling shall be occupied until the agreed foul sewage system has been
completed. Reason: To ensure adequate foul water
system is in place in compliance with Policy U11 (Infrastructure and Services
Provision) of the IW Unitary Development Plan. |
16 |
Details of the design
and construction of any new roads, footways, accesses, car parking areas
together with details of the disposal of surface water drainage shall be
submitted to, and approved by, and thereafter constructed to the satisfaction
of the Local Planning Authority. Reason: To ensure an adequate standard of highway
access and drainage for the proposed dwellings and to comply with Policy TR7
(Highway Considerations) of the IW Unitary Development Plan |
17 |
No dwelling shall be
occupied until those parts of the roads and drainage system which serve that
dwelling have been constructed in accordance with a scheme agreed by the
Local Planning Authority. Reason: To ensure an adequate standard of highway
and access for the proposed dwellings and to comply with Policy TR7 (Highway
Considerations) of the IW Unitary Development Plan. |
18 |
Prior to occupation of
the development hereby approved, the roadside boundary of the site shall be
lowered to a maximum of 1 metre in height above existing road level over the
whole frontage and shall be maintained thereafter at a height no greater than
1 metre. Reason: In the interests of highway safety and to
comply with Policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
19 |
Occupation of any of
the residential units hereby approved shall not take place until parking
spaces serving these units are available for use and such spaces shall be
kept available thereafter. Reason: To ensure adequate off-street
parking provision in compliance with Policy TR16 (Parking Policies and
Guidelines) of the IW Unitary Development Plan. |
20 |
The dwelling(s) /
building(s) / development hereby approved shall not be brought into use until
provision has been made within the site for the secure (and covered) parking
of a minimum of (number) bicycles. Such provision shall be made in the form
of ‘Sheffield’ hoops, unless otherwise agreed in writing by the Local
Planning Authority, and shall be retained thereafter. Reason: To ensure adequate
provision for the parking of bicycles and to comply with Policy TR6 (Cycling
and Walking) of the IW Unitary Development Plan. |
21 |
The development shall
not be brought into use until a turning space is provided within the site to
enable vehicles to enter and leave the site in forward gear in accordance
with details to be agreed in writing by the Local Planning Authority. This space shall thereafter always be kept
available for such use. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Considerations) of the
IW Unitary Development Plan. |
22 |
No part of the development hereby
permitted shall commence until there has been submitted to and approved in
writing by the Local Planning Authority: a) A desk-top study
documenting all previous and existing land uses of the site and adjacent land
in accordance with national guidance as set out in Contaminated Land Research
Report Nos. 2 & 3 and BS10175: 2001; and, unless otherwise agreed in writing
by the Local Planning Authority, b) a site investigation
report documenting the ground conditions of the site and incorporating
chemical and gas analysis identified as appropriate by the desk-top study in
accordance with BS10175: 2001 – “Investigation of Potentially Contaminated
Sites – Code of Practice”; and, unless otherwise agreed in writing
by the Local Planning Authority, c) a remediation scheme to
deal with any contaminant including an implementation timetable, monitoring
proposals and a remediation verification methodology. The verification
methodology shall include a sampling and analysis programme to confirm the
adequacy of decontamination and an appropriately qualified person shall
oversee the implementation of all remediation. The construction of buildings
shall not commence until the investigator has provided a report, which shall
include confirmation that all remediation measures have been carried out
fully in accordance with the scheme. The report shall also include results of
the verification programme of post-remediation sampling and monitoring in
order to demonstrate that the required remediation has been fully met. Future
monitoring proposals and reporting shall also be detailed in the report. Reason: To protect the
environment and prevent harm to human health by ensuring that where
necessary, the land is remediate to an appropriate standard in order to
comply with Part 3 (Restoration of Contaminated Land of the IOW Unitary
Development Plan. |
23 |
Prior to occupation of
the flats 9-22 inclusive the 1.8 metre high brick boundary wall which forms
the boundary between the property Brooklands and the application site as
indicated on the plan hereby approved shall be erected and shall be retained
as such thereafter. Such wall shall be finished in materials to be agreed
with the Local Planning Authority. Reason: In the interests of
future occupiers and adjoining property owners in compliance with Policy D1
(Standards of Design) of the IOW Unitary Development Plan. |
24 |
Prior to occupation of
flats 20-22 inclusive the 1.2 metre high boundary brick wall indicated
between Brookbank and the application site shall be erected and shall be
retained as such thereafter. Such wall shall be finished in materials to be
agreed with the Local Planning Authority. Reason: In the interests of
future occupiers and adjoining property owners in compliance with Policy D1
(Standards of Design) of the IOW Unitary Development Plan. |
2. RECOMMENDATION - That letter be sent to applicants requesting the submission of
a construction traffic methodology statement ensuring that site works are
carefully managed to cause least disturbance to local residents and to draw
applicants' attention to the need to address the Party Wall Act of 1996.
The
applicant be advised to consult with English Nature with a view to obtaining a
DEFRA licence in respect of badger
activity.
11. |
TCP/25288/A P/00480/04 Parish/Name: Rookley
Ward: Central Rural Registration Date: 04/03/2004 -
Full Planning Permission Officer: Mr. A. White Tel: (01983) 823550 Applicant: F Stay & Co Amendments to approved pair of
semi-detached houses ref: TCP/25288 (revised scheme) (readvertised
application) land adjacent Rookley Manor, Niton
Road, Rookley, Ventnor, PO38 |
REASON FOR COMMITTEE
CONSIDERATION
Given the contentious
nature of site and previous Committee involvement, it was considered
appropriate to report this application to Members.
LOCATION AND SITE
CHARACTERISTICS
Site previously formed
part of the garden area to Rookley Manor which is situated on the west side of
Niton Road, approximately 150 metres south of its junction with the main
Newport to Shanklin road. Site is irregular in shape, with frontage of
approximately 17 metres and overall depth in the region of 47 metres. Work
commenced on the development soon after the original grant of consent in March
2003, but has stopped at first floor level leaving exposed timber frame in
position.
Northern boundary to
site, which is currently subject to a dispute regarding its exact position, is
defined by a recently erected 1.8 metre high close boarded fence.
Surrounding area can be
described as having a mixed residential character. Immediately to the south is
Rookley Manor which is a two storey stone and slate building which, although
not listed, is a character property fronted by a boundary wall with iron
railings over. To the north is a two storey dwelling of modern appearance.
RELEVANT HISTORY
TCP/25288 - P/2255/02 –
Pair of semi detached houses on land adjacent Rookley Manor. Conditional
consent granted in March 2003 following a Committee site inspection.
It was discovered during
the early stages of construction work that the houses were not being built in
accordance with the approved plans. Firstly, floor level was measured as being
0.9 metres higher than shown on the approved plan. Secondly, development
appeared closer to the northern boundary than that shown on the approved plan.
Developer was therefore advised that such deviations could not be treated as a
minor amendment to the approved scheme, and was invited to make a fresh
application in this respect.
DETAILS OF APPLICATION
Full consent is now sought
for amendments to the pair of semi detached houses approved under TCP/25288.
The amendments in question relate to the finished floor level and position
relative to northern boundary.
Concerning change to
floor level, agent confirms that this has been dictated due to the fact that
sewer connection had to be made at a higher level than originally anticipated.
This resulted in actual floor level being 0.9 metres higher than shown on the
approved plan. To compensate for this increase in floor level, plans show that
0.87 metres of this increase would be accommodated within the fabric of the
houses through reducing eaves and ceiling height. As a result, ridge height
would be little different to that shown on the approved plan.
In terms of position, it
would appear that actual siting does not differ significantly, if at all,
relative to that shown on the approved plan. The discrepancy in this instance
is historical uncertainty as to exact position of northern boundary between
application site and neighbouring property known as Leverets Walk. Agreement
cannot be reached in respect of distance between north facing wall of
development and respective boundary. Depending on the outcome of dispute, the
developer may not be able to comply with access requirements under Building
Regulations and therefore now indicates a door on the front of plot 2 in
addition to the door in the side (north) elevation originally intended as the
principal door. Revised plans also show that the ground floor section of the
north facing wall to plot 2 would be slightly recessed in order to achieve
greater width between flank wall and northern boundary.
Other than slightly lower
eaves level, front door to plot 2 and recessed brickwork mentioned above,
scale, mass and design is shown to be much the same as that approved in March
2003.
DEVELOPMENT PLAN/POLICY
Site is within the
development envelope as designated on the Rookley inset of the IOW Unitary
Development Plan (UDP). The same inset also confirms that the site is within
the AONB. The following policies are considered relevant to the determination
of this application:
S1 - New Development will be concentrated within existing
urban areas
S6 - All development will be expected to be of a high
standard of design
G1 - Development envelopes for towns and villages
G4 - General Locational Criteria for developments
D1 - Standards of Design
D2 - Standards for Development within the site
D3 - Landscaping
H4 - Unallocated residential development to be restricted
to defined settlements
H5 – Infill Development
TR7 - - Highway Considerations for new development
TR16 – Parking Policies and Guidelines
C1 - Protection of Landscape Character
CONSULTEE RESPONSES
Highway Engineer
considers there to be no highway implications.
AONB Officer raises no
objection.
PARISH/TOWN COUNCIL
COMMENTS
Rookley Parish Council
list numerous concerns that were considered at the time of the original
application, but not considered relevant to the determination of this revised
proposal.
Concerns of relevance to the amended proposal can be summarised as follows:
·
Disputed side access is inadequate for disabled access.
·
Proposed roof could be problematical.
·
Plan measurements are inconsistent.
·
The changed position for the dwellings in the current plans is
unacceptable
THIRD PARTY
REPRESENTATIONS
Campaign to Protect Rural
England (CPRE) comment that the fears and objections raised in respect of the
original application have been fully realised since work commenced. Opportunity
is also taken to object to the principle of developing a pair of semi detached
houses on this site. It is also stated that close attention was given to the
original design so that window and door levels matched in a specific way to
corresponding levels of adjoining properties. Although revised proposal seeks
to minimize increase in height by keeping ridge height as low as possible, this
has failed to address the change to window and door positions which no longer
appear proportionate to adjoining properties. As a result, revised proposal
appears completely contrary to the intent of the original plans and of the
wishes of the Development Control Committee and therefore should not be
permitted. There would appear to be no alternative other than to refuse consent
and to require complete demolition. It is suggested that a single dwelling
would be more appropriate for this site.
A total of 24 letters have been received from 17 local residents objecting on grounds which can be summarized as follows:
·
Dwellings are being built higher than approved
·
Destroy ambience of former wildlife retreat.
·
Over dominant relative to Leverets Walk.
·
Developer should be made to build in accordance with approved plans.
·
Wrong position.
·
Inadequate pedestrian access to building, contravening Building
Regulations.
·
Inaccurate plans.
·
Entirely out of place.
·
Plot is too small.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
Site is within the
development envelope for Rookley as identified on the UDP and is subject of
consent for a pair of semi detached houses which are currently under
construction. It is because that two discrepancies were identified during the
early stages of construction that this amended application has been submitted
to regularise the situation.
These discrepancies
relate to floor level and proximity to the northern boundary.
In determining this
application, Members must set concerns regarding principle, over development,
wildlife etc to one side and focus solely on the amendments at hand. Members
will also note that this amended application has generated a considerable level
of local opposition in a similar fashion to the approved scheme. This, however,
should not cloud the issue under consideration, that being whether the
amendments in question would result in a form of development that would be
detrimental to neighbours or surrounding area in general when compared to the
approved development.
Each amendment will be
briefly explained before discussing the merits of these in turn. Firstly, it
became apparent during construction work that floor level is actually 0.9
metres higher than that shown on the approved plans owing to the limited depth
of an underground sewer connection. In
an effort to minimise the physical impact of raising the entire building by the
same amount, the agent has indicated on submitted drawing that 0.87 metres
would be lost within the fabric of the building through reduced ceiling height
and lower eaves level. Window and door heights would inevitably be higher than
shown on the approved plan, but the difference in ridge height would be barely
noticeable.
The second amendment
relates to the position of the houses relative to the northern boundary. The
proposed site plan confirms that the level of separation between development
and adjoining houses to the north and south would be the same, that being 11
metres and 12 metres respectively. This amendment has resulted from a dispute
regarding the position of the northern boundary after the developer had erected
a new fence. The dispute centres around the position of the boundary and
resulting gap between the fence and flank wall of plot 2. The minimum gap that
could result is 0.34 metres, which would not comply with building regulation
requirements for a 0.9 metre wide access to serve the main door in the north
facing wall. The agent therefore proposes to recess part of the ground floor
flank wall in order to widen the access route to the side door and to install a
door in the front elevation as well. He
has also served the requisite landownership certificate on the owner of
Leverets Walk in the event that the neighbour does own a section of land on the
development side of the disputed boundary.
Concerning the amendment
to floor levels, main consideration is whether proposal would appear out of
context in the street scene, either in terms of height or design. Although
floor level has been raised by 0.9 metres, increase in ridge height would be
negligible as agent has adjusted eaves and ceiling heights to compensate.
Therefore, in height terms, proposed amendment would be barely noticeable with
proposed ridge line sitting comfortably between respective height of adjoining
buildings.
In terms of design
implications of this particular amendment, CPRE comment that close attention
was given to window proportions relative to adjoining properties, particularly
Rookley Manor. The approved street scene indicates that both ground and first
floor windows of development would appear much lower than respective windows to
adjoining properties. The proposed street scene indicates that proposed windows
would sit slightly below those at Rookley Manor and slightly above those at
Leverets Walk, almost to the point where window heights differ according to the
sloping nature of Niton Road. Accordingly, I am satisfied that the amendment in
respect of floor level and associated design changes complies with policy D1 of
the UDP in so far as it would respect distinctiveness of the surrounding area
and of a height which would be compatible with surrounding buildings.
The amendment in respect
of the site plan relates to the position of the northern boundary and not the
dwellings. Although proposed dwellings would potentially be within 0.5 metres
of the common boundary, it should be noted that the space between new houses
and Leverets Walk would be the same as approved, i.e. 11 metres. The only
difference in the street scene would therefore be the position of the new
fence.
The uncertainty
surrounding boundary dispute has raised issues in respect of access to the
house on plot 2 as main door is shown as being in the north facing wall.
Initially, agent indicated that part of ground floor flank wall would be
slightly recessed to afford necessary access. This is considered aesthetically
acceptable as plans also make provision for a brickwork corbel on the front
corner which, in my opinion, would be sympathetic to the overall design of the
houses. However, it would now appear that this recessed area may not be
sufficient to satisfy access requirements.
A further revised plan has therefore been submitted showing a door
within the front elevation of plot 2. Again, this is a relatively minor
amendment to the front elevation that, in my opinion, would not undermine the
external appearance of the proposed development.
It is claimed by
objectors, particularly the neighbours at Leverets Walk, that submitted
drawings are inaccurate. Minor
discrepancies were noted following examination of plans and taking levels/measurements
on site, and revised plans were duly submitted to account for this. Although one neighbour continually expresses
concern in this respect, I am satisfied that the latest set of plans before
Members are an accurate representation.
The distance between the building and highway is accurate and the street
scene corresponds with levels taken, finished floor levels and building
height. The exact position of the
northern boundary cannot be shown owing to the ongoing dispute, so the plan
before Members indicates the boundary line as it currently exists. The
appropriate land ownership certificate has been served to account for
uncertainty surrounding dispute. Otherwise, this is a private matter that must
have no influence on the outcome of this application.
Taking the above into
consideration, it is my view that the amendments in question would not result
in development that would appear out of keeping in the street scene or
detrimental to the amenities enjoyed by adjoining property occupiers. Whilst
appearing controversial owing to number of representations received, it must be
borne in mind that development has previously been accepted on this site and
that the differences between that approval and the proposal do not, in my view,
represent a retrograde step. Accordingly, proposed houses in their amended form
accord with policies contained within the UDP.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of other property in the
area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the rights of others it
is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that such action is proportional to the
legitimate aim of the Council’s Unitary Development Plan and in the public
interest.
JUSTIFICATION FOR
DECISION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, it is considered that the proposed amendments would not result in
development that would appear visually intrusive in the street scene or
detrimental to adjoining property occupiers. The increase in floor level has
been compensated for by altering eaves and ceiling heights and the dispute in
respect of the northern boundary is essentially a private matter between the
developer and the owner of Leverets Walk, as the exact position of this
boundary has little bearing on the appearance of the development in the street
scene. Accordingly, this application is before Members with a recommendation
for approval.
RECOMMENDATION - Approval (Revised Scheme)
Conditions/Reasons:
1 |
The dwellings hereby
approved shall be constructed of Hurstwood multi stock bricks under Westland
dark grey Canadian slates, unless otherwise agreed in writing by the Local
Planning Authority. Reason: To safeguard the
amenities of the locality and to comply with Policy D1 (Standards of Design)
of the IOW Unitary Development Plan. |
2 |
The dwellings erected
pursuant to this permission shall include decorative fretwork fascia boards and
bargeboards of similar design to those of the existing Rookley Manor adjacent
and details of the decorative fretwork shall be submitted to and approved in
writing by the Local Planning Authority within one month of the date of this
approval. Reason: To protect the
character and appearance of the adjacent building and to comply with Policy
D1 (Standards of Design) of the IOW Unitary Development Plan. |
3 |
Withdraw PD rights
alterat/extens/etc - R02 |
4 |
Notwithstanding the
provisions of the Town and Country Planning (General Permitted Development)
Order 1995 (or any Order revoking and re-enacting that Order, with or without
modification), no windows/dormer windows (other than those expressly
authorised by this permission) shall be constructed unless otherwise agreed
in writing by the Local Planning Authority. Reason: In the interests of the character and
amenities of the area and to comply with policy D1 (Standards of Design) of
the IW Unitary Development Plan. |
5 |
The windows included on
the north elevation at first and second floors shall be glazed and thereafter
maintained in obscure glass. Reason: In the interest of the
amenities and privacy of the adjoining property occupiers and to comply with
Policy D1 (Standards of Design) of the IOW Unitary Development Plan. |
6 |
No dwelling shall be
occupied until space has been laid out within the site for cars to be parked
and for vehicles to turn so that they may enter and leave the site in a forward
gear in accordance with details to submitted to and agreed in writing by the
Local Planning Authority. Such provision shall be retained thereafter. Reason: To ensure adequate
parking provision in the interests of highway safety and to comply with
Policy TR7 (Highway Considerations) of the IOW Unitary Development Plan. |
7 |
The driveways shall be
constructed of porous materials and shall be retained in that condition
thereafter. Reason: To ensure adjacent
trees are not adversely affected by the driveway and to comply with Policy
C12 (Developments affecting trees and landscape) of the IOW Unitary
Development Plan. |
8 |
Within one month of the
date of this consent, details shall be submitted of a permanent barrier to be
erected around the base of each tree forward of the approved dwellings. None
of the dwellings shall be occupied until such agreed scheme has been fully
implemented which shall be retained and maintained thereafter. Reason: To ensure adjacent
trees are not adversely affected by the driveway and to comply with Policy
C12 (Developments affecting trees and landscape) of the IOW Unitary
Development Plan. |
9 |
The finished ground
floor level of the dwellings hereby approved and the external ground levels
described in the development hereby approved shall be carried out strictly in
accordance with the approved plans. Reason: In the interests of the
amenities of the area and in accordance with Policy D1 of the Isle of Wight
Unitary Development Plan. |
10 |
In this condition
“retained tree” means an existing tree which is to be retained in accordance
with the approved plans and particulars; and paragraphs (a) and (b) below
shall have effect until the expiration of (1 year) from (the date of the
occupation of the building for its permitted use). (a) No retained tree shall
be cut down, uprooted or destroyed, nor shall any retained tree be topped or
lopped other than in accordance with the approved plans and particulars, without
the written approval of the Local Planning Authority. Any topping or lopping approved shall be
carried out in accordance with British Standard 3998 (Tree Work); (b) If any retained tree is
removed, uprooted or destroyed or dies, a replacement tree shall be planted
in the same place, or place to be agreed and that tree shall be of such size
and species, and shall be planted at such time, as may be specified in
writing by the Local Planning Authority. Reason: To ensure the
protection of the trees to be retained in the interests of the amenities of
the area and to comply with Policy C12 (Development Affecting Trees and
Woodland) of the IW Unitary Development Plan. |
11 |
Protection fencing
erected pursuant to condition 14 on TCP/25288/P/2255/02 shall be maintained
throughout the course of the works on the site, during which period the
following restrictions shall apply: (a) No placement or storage
of material; (b) No placement or storage
of fuels or chemicals. (c) No placement or storage
of excavated soil. (d) No lighting of
bonfires. (e) No physical damage to
bark or branches. (f) No changes to natural
ground drainage in the area. (g) No changes in ground
levels. (h) No digging of trenches
for services, drains or sewers. (i) Any trenches required
in close proximity shall be hand dug ensuring all major roots are left
undamaged. Reason: To ensure that trees,
shrubs and other natural features to be retained are adequately protected
from damaged to health and stability throughout the construction period in
the interests of amenity and to comply with Policy C12 (Development Affecting
Trees and Woodland) of the IW Unitary Development Plan. |
12. |
TCP/25836/C P/01808/04 Parish/Name: Calbourne Ward: Brighstone and Calbourne Registration Date: 25/08/2004 -
Full Planning Permission Officer: Miss. S. Gooch Tel: (01983) 823568 Applicant: Park Resorts Ltd Provision of 14 static caravan
bases Thorness Bay Holiday Park,
Thorness Lane, Cowes, Isle Of Wight, PO318NJ |
REASON FOR COMMITTEE CONSIDERATION
When consulted under the delegating
procedure local member Councillor Mrs Wareham requested that the application is
considered by the committee as she raises concerns in respect of over development,
drainage and increased flows, generation of traffic, infrastructure, inadequate
access, and whether the caravans will be legitimately used as holiday
accommodation.
PROCESSING INFORMATION
This is a minor application, the
processing of which has taken 24 weeks to date and has gone beyond the
prescribed eight week period for determination of planning applications due to
case officer workload and the request from the local member for Committee
consideration.
LOCATION & SITE CHARACTERISTICS
Thorness Bay Holiday Park is a
substantial tourist site offering accommodation in static caravans, and chalets
with support facilities adjoining the northwestern coastal slope, immediately
north of South Thorness Farm. The site is divided into two distinctive
sections, the large static caravan and chalet area to the east with a smaller
area of concrete chalets and swimming pool building in the western part of the
site, separated from the main area by an existing landscape belt. To the south
is an existing well established hedgerow beyond which is open farm land to the
south.
RELEVANT HISTORY
TCP/20324/R - Full planning
permission was conditionally approved September 2002 for demolition of 22
chalets and outdoor swimming pool; formation of sixty four static caravan bases
(revised plans).
DETAILS OF APPLICATION
Consent is sought for the provision
of fourteen static caravan bases. Ten of these spaces are located west of the
existing landscape belt and the remaining four will sit south of an existing tarmaced/gravelled
access road. It is also the applicants intention to provide fourteen parking
spaces with associated landscaping. The proposed caravan bases would be located
well within the site, surrounded by existing static caravans.
DEVELOPMENT PLAN/POLICY
Site is located within tourist
development area as defined on the Unitary Development Plan and is within an
Area of Outstanding Natural Beauty and the Heritage Coast. Nodes Point Meadow
(SINC) lies south of application site outside the curtilage of the holiday
camp. Coasted fringe is designated as a Site of Special Scientific Interest,
SINC and is also of European Importance.
Relevant policies of the plan are
considered to be as follows:
S4 The Countryside will be
protected from Inappropriate Development
S6 All Development will be
expected to be of a High Standard of Design
S10 Designated or Defined
Areas/Landscapes
G4 General Locational Criteria
for Development
G5 Development Outside Defined
Settlements
D1 Standards of Design
D2 Standards for Development
Within The Site
D3 Landscaping
D14 Light Spillage
C1 Protection of Landscape
Character
C2 Areas of Outstanding Natural
Beauty
C4 Heritage Coast
C8 Nature Conservation as a
Material Consideration
C9 Sites of International
Importance for Nature Conservation
C10 Site of National Importance
for Nature Conservation
T1 The Promotion of Tourism and
the Extension of The Season
T3 Criteria for the Development
of Holiday Accommodation
T6 Permanent Accommodation
Sites
TR7 Highway Considerations for New
Developments
U11 Infrastructure and Services
Provision
CONSULTEE RESPONSES
The Highway Authority does not wish to
comment on this application as they do not envisage any Highway implications.
Licensing Enforcement Officer
advises that if permission is granted the applicant will need to contact his
department to amend the caravan site licence.
After consulting with the AONB
Officer they raise some concerns that the current arrangement has been squeezed
to accommodate the additional caravan and do have some reservations about the
principle on increasing the number of caravans. They also advise the siting of
the caravans within protected landscape needs to be carefully considered to
ensure that they are not intrusive in the landscape.
English Nature advise that Thorness
Bay is designates as a cSAC, SPA, Site of Special Scientific Interest etc and
is suffering some damage from recreational disturbance - four wheel drive,
trikes and go-karts.
PARISH/TOWN COUNCIL COMMENTS
Calbourne Parish Council strongly
object to this proposal as it would result in inappropriate development of
static caravans in the countryside, detrimental to the visual amenities and
character of the area. The increase in number would cause further density of
the site, lack of privacy and increase in traffic.
THIRD PARTY REPRESENTATIONS
A petition of some 53 signatures has
been received, some of which involving two signatures for one unit/property, on
the inadequacy of the access and by putting down further basis will add to the
problem and cause more traffic congestion.
1 letter of objection received and
the points raised are summarised as follows:
·
Original plan showed a hedge being planted between their house and the
camp
·
Site is now a village of low cost housing and people don't comply with
the eight week occupation restriction
·
Site is already overcrowded.
CRIME & DISORDER IMPLICATIONS
No crime and disorder implications
are anticipated.
EVALUATION
In policy terms, the Unitary
Development Plan seeks to encourage development of holiday accommodation where
such development is associated with an existing permanent accommodation site
and particularly when existing accommodation is upgraded, extension of tourist
season promoted and that the Council is satisfied that development will be
retained for holiday use. Generally speaking Policy T1 (The Promotion of Tourism
and the extension of The Season) promotes and supports tourism provided any
detrimental or adverse impact is minimised.
The site is identified as a
permanent holiday accommodation site and therefore its development will be
acceptable under Policy T3 (Criteria for the Development of Holiday
Accommodation), on the basis that it will be associated with an existing
permanent accommodation site. Should Members be minded to approve the
application, occupancy of the caravans would be limited to holiday purposes by
a condition of the consent.
Of particular importance is Policy
T6 which states that expansion of existing permanent accommodation sites will
be approved providing they adjoin or are directly related to the existing built
facilities, do not detract from their surroundings, enhances the environment or
improves the visual appearance of the site and if new or replacement units are
proposed there design and appearance are appropriate and resultant density of
the site does not adversely affect rural character of the area.
The additional static basis are
located within the site and the proposed layout mirrors the linear
characteristics of nearby units and Policy T6 does allow for expansion where
such development adjoins and, or is directly related to the existing built
facility. Therefore determining factors when considering this application is
whether or not developments meets other criteria, particularly in respect of
visual impact and appearance and appropriateness of new units in terms of
design and resultant density.
The caravans would be located well
within the site and flanked on one side by existing caravans and to the other
by an area of trees, beyond which are further existing caravans. Therefore, I
do not consider that the additional caravans will appear intrusive or will
detract from the character of the area. To ensure this is the case and that the
caravans will be used for holiday purposes conditions will be imposed, should
Members be minded to approve this application, on the occupancy of the caravans,
colour/materials and it will be necessary to ensure that any lighting within
the site is properly controlled. With this in mind I consider proposal would
not have a detrimental impact on the landscape or coastline.
English Nature have advised that
they need to be consulted on any further proposals to increase the holiday camp
but are mainly concerned on recreational disturbances such as four wheel drive
vehicles, trikes and go-karts. These issues are not part of this application
and I do not consider that the proposed development is likely to adversely
impact on the designated area or result in an increased need for coastal
defences in the area.
Concerns were raised on the problem
of accessibility to the site which in the objectors opinion is inadequate and
the proposal would cause more traffic congestions. However after consulting
with the Highways department they do not share these concerns.
A local neighbour comments that
original plans on a previous approval showed a hedge being planted between
there property and Thorness Bay Holiday Park which is outside the application
site and is not part of this application. They also comment that the site is
now a village of low cost housing and people don't comply with the eight week
occupancy restriction. Should Members be minded to approve this application a
holiday occupancy condition will be imposed. With regard to allegations of
non-compliance of previous approvals Enforcement will be made aware of this
matter.
With regard to other concerns that
site is already overcrowded I am of the opinion that as the additional units
are within the centre of the site and are situated in a linear fashion with
spacing which is characteristic of the site, I do not consider refusal on
grounds of over development would be justified.
Turning to the issue of the
increased flows to the existing drainage system, in May 2004 a temporary
planning permission was granted for the siting of w.c/shower block which
expired on 31 October 2004. Issues relating to effluent disposal was also
raised in respect of this application. It was confirmed that Thorness Bay
Holiday Park have a sewage treatment plant and that the final effluent
discharge is laboratory tested on a monthly basis to check for compliance with
the consent standard. The discharge consents are recorded to the satisfaction
of the Environment Agency and the plant is regularly maintained on
recommendations/advice given by Faber Maunsell who are the Environmental
Consultants employed by Park Resorts and that £15,000 was being spent on
upgrading certain elements of the plant. Based on this information I am
satisfied that the sewage treatment plant is capable of accepting the limited
increase in flows likely to be generated from these 14 static caravans.
Overall, although the site is close
to sites of local, national and international nature conservation interest, I
do not believe there would be any adverse impact on the designated sites. I do
not consider proposal represents inappropriate expansion or that any harm would
be caused to the landscape quality particularly when taking into account the
proposed siting of caravan bases, within an existing developed area.
HUMAN RIGHTS
In coming to this recommendation to
grant planning permission, consideration has been given to the rights set out
in Article 8 (Right to Privacy) and Article 1 of the First Protocol (Right to
Peaceful Enjoyment of Possessions) of the European Convention on Human Rights.
The impacts this development might have on the owners/occupiers of the other
property in the area and other third parties have been carefully considered.
Whilst there may be some interference with the rights of these people this has
to balanced with the right of the applicant to develop the land in the manner
proposed. Insofar as there is an interference with the rights of others it is
considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that such action is proportional to the
legitimate aim of the Council's Unitary Development Plan and in the public
interest.
JUSTIFICATION FOR RECOMMENDATION
Having given due regard and
appropriate weight to the material considerations referred to in this report,
and taking into account approved development at the site, I do not anticipate a
significant increase in the number of people likely to visit the site. It will
result in the expansion of a permanent holiday accommodation site identified as
such in the Unitary Development Plan, and providing the caravans are suitably coloured
the impact on the character of the
countryside which is designated AONB and Heritage Coast will be minimal. There
should be no greater disturbance to the nearby which are sensitive for their
ecological importance and there are no sustainable reasons for refusal on
highways or access grounds.
RECOMMENDATION
- APPROVAL
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
The occupation of the
static caravans hereby approved shall be used for holiday purposes only, and not
for permanent residential use. Reason: To ensure that the
static units hereby approved are retained for holiday purposes in accordance
with Policy T3 (Criteria for the Development of Holiday Accommodation) of the
Isle of Wight Unitary Development Plan. |
3 |
The external colour of
the static caravans hereby approved shall be restricted to those colours
indicated within BS6770:1998 (Exterior Colours for Park Homes (Mobile Homes),
Holiday Caravans and Transportable Accommodation Units). Reason: In the interests of the
amenities and character of the area and in compliance with Policy D1
(Standards of Design) and C2 (Areas of Outstanding Natural Beauty) of the
Isle of Wight Unitary Development Plan. |
4 |
External lighting required
in connection with the development hereby approved shall be sited and aligned
so as to ensure minimal disturbance of the character of the area. Details of
location , height and luminance of any external lighting to be provided shall
be submitted to and approved by the Local Planning Authority and such
lighting shall be installed in accordance with the agreed details. No
alterations shall subsequently be undertaken
or additional lighting provided unless the prior written agreement of the Local Planning Authority is
obtained. Reason: To minimise light
pollution in the interests of the amenities of the area in accordance with
Policy D14 (Light Spillage) of the Isle of Wight Unitary Development Plan. |
5 |
The development hereby
approved shall not be commenced until such time as detailed calculations for
the capacity of the sewage treatment plant and any necessary improvements to
the foul water system to ensure continued satisfactory performance in
connection with the increased occupancy at the park have been submitted to
and approved by the Local Planning Authority. Thereafter any necessary
improvements shall be carried out in accordance with the approved details and
a timescale which shall reflect the timing of any increase in occupancy of
the park, to be agreed with the Local Planning Authority. Reason: To safeguard against
contaminations of the environment and in particular the adjacent Site of
Special Scientific Interest and Special Area of Conservation and to comply
with Policy C9 (Sites of International Importance for Nature Conservation),
C10 (Sites of National Importance for Nature Conservation) and P2 (Minimise
Contamination from Development) of the Isle of Wight Unitary Development
Plan. |
6 |
Landscape scheme -
M11A |
7 |
Landscape works
implementation - M30 |
8 |
All materials excavated
as a result of general grounds works, including site leveling, installation
of services or the digging of foundations, shall not be disposed of within
the area identified in red or blue on the submitted plans, unless otherwise
agreed in writing by the Local Planning Authority. The materials shall be
removed from the site prior to the occupation of any of the static caravans
hereby approved. Reason: To ensure satisfactory
long term maintenance of the landscaping of the site/development and to
comply with Policy D3 (Landscaping) of the Isle of Wight Unitary Development
Plan. |
13. |
TCP/26052/B P/01400/04 Parish/Name: Ryde
Ward: Binstead Registration Date: 13/07/2004 -
Outline Planning Permission Officer: Mr. P. Stack Tel: (01983) 823575 Applicant: N W Corbin Ltd Demolition of warehouse and
workshop; outline for 7 houses and alterations to vehicular access (revised
scheme) (readvertised application) land rear of St Leonard’s - Cornerways,
Binstead Road, Ryde, PO33 |
REASON FOR COMMITTEE
CONSIDERATION
Report requested by Local
Member, Councillor Fox, as he considers application raises important issues
concerning highways and potential impact on adjoining residents.
PROCESSING INFORMATION
This is a minor
application, the processing of which has taken 8 months to date. This is
principally due to negotiation and submission of revised plans, the need for additional
information to be submitted by the agent and the request by the Local Member
for Committee determination.
LOCATION AND SITE
CHARACTERISTICS
This irregularly shaped
site is located on southern side of Binstead Hill, almost directly opposite Binstead
Garage and which immediately abuts former Binstead Bakery site which has been
residentially redeveloped. Site presently comprises two large vacant
industrial/commercial buildings which are served by existing access between
properties fronting Binstead Hill.
RELEVANT HISTORY
Application seeking
outline consent for nine houses was refused in March 2004 under delegated
procedure. Reasons for refusal related to excessive density of development
giving rise to overlooking, loss of outlook and having over bearing impact on
surrounding environment. Further reason for refusal related to inadequate and
deficient detail in respect of highway visibility splays and detail in respect
of capacity of existing drainage system to accept additional load.
Resubmission again
seeking outline consent for nine houses was refused under delegated powers in
May 2004. Reasons for refusal again related to excessive density of development
and inadequate detail in respect of drainage systems. Highway reason for
refusal was not included within this decision.
DETAILS OF APPLICATION
This is outline
submission with siting and means of access to be determined at this stage.
Originally submitted
proposal proposed eight houses however, following negotiation scheme has been
revised to scheme for seven houses involving a terrace of five dwellings and
two detached units.
Terraced units will be
located along eastern boundary of site which abuts car park area rear of
Fleming Arms. Two detached units will be located towards eastern half of site.
Development would utilize shared forecourt surface and provide eight off street
parking spaces.
Site will be served by
existing drive which previously served commercial premises between existing
properties fronting Binstead Hill.
DEVELOPMENT PLAN/POLICY
Site is located within
development envelope boundary for Ryde as identified on Unitary Development
Plan.
Relevant Policies are as
follows:
S1 – New development will
be concentrated within existing urban areas.
S2 – Development will be
encouraged on land which has been previously developed (brown field sites).
S4 – Countryside will be
protected from inappropriate development
G1 – Development
Envelopes
G4 – General Locational
Criteria for development
D1 – Standards of Design
H4 – Unallocated
Residential Developments to be restricted to define settlements.
TR7 – Highway
Considerations for new development
E3- Resist developments
for allocated employment land for other uses.
TR3 – Locate development
to minimize need to travel
U11 – Infrastructure and
services provision
CONSULTEE RESPONSES
Contaminated Land Officer
wishes standard condition be imposed concerning site investigation to assess
potential contamination.
Highway Engineer wishes
standard conditions be imposed should consent be granted.
Southern Water have been
consulted on drainage arrangements and their comments are awaited.
PARISH/TOWN COUNCIL
COMMENTS
Not applicable.
THIRD PARTY
REPRESENTATIONS
In respect of original submission six letters were received from local residents and business. Main points of objection are summarized as follows:
·
Proposal represents over development of site
·
Increase in noise
·
Development out of character with locality
·
Loss of trees
·
Inadequate drainage capacity
·
Detrimental impact on highway and pedestrian safety
·
Potential over shadowing of adjoining properties
·
Poor access arrangements
·
Increased disturbance
·
Accessibility for emergency vehicles
·
Boundary treatments
·
Adverse ground conditions
Following revised submission
application re-advertised and seven letters were received from local residents
and business again raising similar issues to those outlined in previous
paragraph.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
Proposal represents
opportunity to provide residential development within previously developed land
within development envelope in sustainable location. In principle therefore,
proposal complies with Central Government advice on housing (PPG3) and relevant
Local Authority UDP guidelines. Whilst proposal does result in loss of former
employment site to which Policy E3 seeks to retain, it is not clear as to the
level of employment site offered in past and in any event loss of employment
land in this location would not compromise overall employment potential of area
and indeed this policy did not figure in previous reasons for refusal and is
not considered appropriate to reach different view on this issue now.
Principle of residential development
has not been questioned in previous refusals issued on this site and proposal
should be looked at in detail in order to assess appropriateness of development
for locality and assess whether or not current revised scheme overcomes
previous reason for refusal relating principally to over development and
insufficient details in respect of drainage.
Development of site with
seven dwelling units would result in density of some 50 units per hectare which
is top end of suggested density guidelines contained within PPG3. Layout is
similar to previously refused scheme and therefore no objection in principle
can be raised to layout. In any event, given orientation of buildings and
distances from adjoining development is not considered that any sustainable
objection can be raised in terms of likely impacts on residential amenity.
In terms of highway and
parking arrangements, site is located within parking zone 3 which requires a
maximum of 75% of normal parking provision and on site provision of eight spaces
complies with zonal requirements. Given Highway Engineer comments refusal on
highway or associated grounds would be unreasonable and in my view
unsustainable on appeal.
In respect of drainage,
capacity check has been carried out by civil engineers acting on behalf
applicant report suggests installation of hydro brake to control rate of flow
into sewer to ensure that it is not greater than the contributing flows.
Further more the amount of surface water flow entering combined public sewer
can also be controlled and the use of hydro brake will in fact reduce rate of
flow entering sewer when development is completed.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of other property in the
area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the rights of others it
is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that such action is proportional to the
legitimate aim of the Council’s Unitary Development Plan and in the public
interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material consideration referred to in this report
I am of the opinion that the application site is capable of accommodating seven
dwelling units as proposed without impacting significantly on neighbouring
properties, highway safety or character of area in general. Proposal is
therefore consistent with relevant policies of the Isle of Wight Unitary
Development Plan.
RECOMMENDATION – Approval (revised scheme)
Conditions/Reasons:
1 |
Time limit - outline -
A01 |
2 |
Time limit - reserved -
A02 |
3 |
Approval of the details
of the design and external appearance of the building(s) and the landscaping
of the site (hereinafter called "the reserved matters") shall be
obtained from the Local Planning Authority in writing before any development
is commenced. Reason: In order to secure a satisfactory
development and be in accordance with policies S6 (Standards of Design), D1 (Standards
of Design), D2 (Standards of Development Within the Site), D3 (Landscaping),
TR7 (Highway Consideration for New Development) of the IW Unitary Development
Plan. |
4 |
Details of roads, etc, design and
constr - J01 |
5 |
No dwelling shall be
occupied until the parts of the service roads which provide access to it have
been constructed, surfaced and drained in accordance with details which have
been submitted to and approved by the Local Planning Authority]. Reason: To ensure an adequate standard of highway
and access for the proposed dwellings and to comply with policy TR7 (Highway
Considerations) of the IW Unitary Development Plan. |
6 |
Visibility splays of x
= 2 metres and y= 90 metres dimension shall be constructed prior to
commencement of the development hereby approved and shall be maintained
thereafter. Reason: In the interests of
highway safety and to comply with Policy TR7 (Highway Considerations) of the
IOW Unitary Development Plan. |
7 |
Notwithstanding the
provisions of the Town and Country Planning (General Permitted Development)
Order 1995 (or any Order revoking and re-enacting that Order with or without
modification), no gates shall be erected other than those expressly
authorised by this permission/other than gates that are set back a minimum
distance of 5 metres from the edge of the carriageway of the adjoining
highway. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
8 |
No part of the
development hereby permitted shall commence until there has been submitted to
and approved in writing by the Local Planning Authority: d) A desk-top study
documenting all previous and existing land uses of the site and adjacent land
in accordance with national guidance as set out in Contaminated Land Research
Report Nos. 2 & 3 and BS10175: 2001; and, unless otherwise agreed
in writing by the Local Planning Authority, e) a site investigation
report documenting the ground conditions of the site and incorporating
chemical and gas analysis identified as appropriate by the desk-top study in
accordance with BS10175: 2001 – “Investigation of Potentially Contaminated
Sites – Code of Practice”; and, unless otherwise agreed
in writing by the Local Planning Authority, a remediation scheme to
deal with any contaminant including an implementation timetable, monitoring
proposals and a remediation verification methodology. The verification
methodology shall include a sampling and analysis programme to confirm the
adequacy of decontamination and an appropriately qualified person shall
oversee the implementation of all remediation. Reason: To protect the
environment and prevent harm to human health by ensuring that where
necessary, the land is remediated to an appropriate standard in order to
comply with Part IIA of the Environmental Protection Act 1990. |
9 |
The construction of
buildings shall not commence until the investigator, identified in Condition No.8,
has provided a report, which shall include confirmation that all remediation
measures have been carried out fully in accordance with the scheme. The
report shall also include results of the verification programme of
post-remediation sampling and monitoring in order to demonstrate that the
required remediation has been fully met. Future monitoring proposals and
reporting shall also be detailed in the report. Reason: To protect the
environment and prevent harm to human health by ensuring that where necessary,
the land is remediated to an appropriate standard in order to comply with
Part IIA of the Environmental Protection Act 1990. |
10 |
No dwelling hereby
permitted shall be occupied until space has been laid out within the site and
surfaced in accordance with details that have been submitted to and approved
by the Local Planning Authority in writing for 9 cars to be parked and for
vehicles to turn so that they may enter and leave the site in forward
gear. The space shall not thereafter
be used for any purpose other than that approved in accordance with this
condition. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
14. |
TCP/26467 P/01465/04 Parish/Name:
Ventnor Ward: Ventnor West Registration Date: 06/07/2004 -
Full Planning Permission Officer: Mr. J. Mackenzie Tel: (01983) 823567 Applicant: Isle of Wight Council - Highway Services Demolition of Woodington, The
Undercliffe Drive; landslide stabilisation works, ground stabilisation,
realignment of highway, landscaping & associated works (scheme 1) 4
sections of land & highway (application to be determined by the Council's
Development Control Committee)(additional information) (readvertised
application) from Old Park Hotel through to and
including land west of Beauchamp, The Undercliffe Drive, St. Lawrence,
Ventnor, PO38 |
See joint report under TCP/26467/A -
P/01467/04
15. |
TCP/26467/A P/01467/04 Parish/Name:
Niton Ward: Chale Niton and
Whitwell Registration Date: 06/07/2004 -
Full Planning Permission Officer: Mr. J. Mackenzie Tel: (01983)
823567 Applicant: Isle of Wight Council - Highway Services Landslide stabilisation works,
ground stabilisation, realignment of highway, landscaping & associated
works, (scheme 2) 4 sections of land & highway (application to be
determined by the Council's Development Control Committee) (additional
information) (readvertised application) from Old Park Hotel through to and
including land west of Beauchamp, The Undercliffe Drive, St. Lawrence,
Ventnor, PO38 |
REASON FOR COMMITTEE CONSIDERATION
The applications are
major submissions by the Council where there are a number of significant issues
to be resolved.
PERFORMANCE INFORMATION
These applications, if
determined by the Committee on 15 February will have taken 32 weeks to process,
the delay being due to outstanding consultations and negotiations.
LOCATION & SITE
CHARACTERISTICS
These applications relate
to four areas of land of varying sizes and irregular shapes located between
Niton village and Old Park in St. Lawrence including approximately 1100 metres
of Undercliffe Drive and land associated on both north and south sides of
Undercliffe Drive and the two applications are submitted following land and
road instability problems encountered through that section between Old Park and
Niton village.
Area 1 relates to that
area east of Stonehams Nursery on the outskirts of Niton village, north of
Puckaster House and the site includes part of the land associated with the
Orchards camping ground and the property formerly known as Beauchamp.
Area 2 is a ‘T’ shaped
tract of land including part of Undercliffe Drive and a tract of land
travelling in a south westerly direction towards the Orchards.
Area 3 is situated to the
north east of Mirables and includes the property known as Woodington.
Area 4 abuts and joins
the east side of area 3, includes approximately 180 metres of Undercliffe Drive
and a large tract of land stretching southwards to wards the coastline and
skirting the north west and west side of Old Park Hotel.
The Undercliffe is
characterised by almost unique features, an inland cliff marking the northern
boundary, beyond which is a plateau of downland and farmland, but whilst to the
south the coastal slope is represented by plateau and valleys with much variation
in the shape and levels of the land. It is generally heavily wooded but
contains some clearings with many springs and rivulets draining the land
towards the coast.
Between Old Park and
Stonehams Nursery there are only a few, sporadically sited but long established
dwellings such as the Orchards, Mirables and the few residential properties at
the eastern end close to areas 3 and 4 which, in the main, are located on the
north side of Undercliffe Drive. Undercliffe Glen abuts area 3 on the south
side of the road and has, itself been affected by the recent landslips.
RELEVANT HISTORY
Planning consent granted
for reconstruction of a new section to Undercliffe Drive for local access and emergency
services use in July 2002. This development has been implemented and relates
directly to area 1 which involved the demolition of Beauchamp House and
Cottage. The route of the new highway is now complete and operational.
DETAILS OF APPLICATION
As previously mentioned
the two applications relate to four areas of Undercliffe Drive and adjoining
land and, essentially, seek consent for the same development, the one exception
being the exact route in area 3 where Scheme B seeks to demolish Woodington due
to the route of the realignment and the Scheme A seeks to avoid Woodington by
routing the new road further to the north, in effect behind the property which
would enable the building to remain.
Works required in
connection with the re-routing are extensive, seeking to reduce the likelihood
of further land slippage. Essentially this is to be achieved by improved land
drainage to remove as much water as possible from the ground, the presence of
which promotes further land movement due to the geomorphological nature of the
land in question.
The realignment of these
parts of Undercliffe Drive is supplemented by the reconstruction and
resurfacing of other sections but, perhaps more importantly, by associated
works including improved drainage as mentioned by land moulding, some tree
clearance, piling, changes to the shape of the land by excavation of some areas
and a supplementation of material in others.
A survey for dormice in
the area has been undertaken which has established that, at this time, no
evidence of dormice has been found. A survey of the area and especially of
Woodington has established a strong presence of bats.
Area 1
This is the area around
and including Beauchamp House and Cottage where the road has already been
diverted and completed includes the installation of a pile array, comprising
300 mm diameter piles over a distance of approximately 95 metres running
parallel to and below the line of the realigned road situated to the north of
Beauchamp House, the installation of a pump house to pump water from the area
to ponds and watercourses to the south. This area also includes the provision
of substantial trench drains in a parallel configuration leading to a headwall
and the same watercourses as previously mentioned. The area above the trench
drains which encompasses the route of the old road is proposed to be regraded
and cleared of woodland; a line of pumped wells situated to the south west of
the area and the former track running in a west to east direction to be
reinstated. In order to improve drainage from the area, at the southern extent
of the site, some 150 metres plus south east of the realigned highway,
watercourses are proposed to be improved so as to improve the efficiency of
taking water away from the whole site.
Area 2
The ‘T’ shaped section
situated approximately 400 metres east of Beauchamp includes a length of
approximately 150 metres of pile array, 300 mm diameter piles installed
parallel to and almost immediately abutting the southern side of the Undercliffe
Drive, the alignment of which is maintained; a 10 metre strip of land on the
northern side and a 15 metre strip of land on the southern side of Undercliffe
Drive is to be cleared of woodland for works and access for approximately 180
metres in length with some of the land regraded following completion of the
works; a line of pumped wells beneath the highway for a distance of about 140
metres with a pumping station located almost centrally in the site with a new
buried drain running in a south westerly direction to a pond with headwall on
its north eastern side with the pond discharging, again in a south westerly
direction towards the shore. The remaining surrounding area, which is
predominantly woodland remains untouched.
Area 3
This is the area to the
west of and including Woodington which includes the realignment of the highway
from the property known as Timber situated at the eastern extent of the site on
the northern side of the original route to a point approximately 400 metres to
the west cutting off a serpentine section of Undercliffe Drive and producing a
smoother slow curving section closer to the cliff. This section includes a 105
metre length of 300 mm pile array and pump house; a 310 metre length of pumped
wells immediately adjoining the northern side of the central part of the
realigned highway, a second line of approximately 170 metres containing pumped
wells running on the northern side of the original road. To the south of the
original route, just to the south west of Woodington, are three sections of
raking piles with a total run of approximately 130 metres situated
approximately 10 to 15 metres from the roadway with the space between them and
the roadway filled and reinforced with earth fill; new drain lines in a radial
form situated to the south of the raking pile run draining land in a southerly
direction to a new headwall and works to improve an existing ditch and stream
which drains the site to the shore. The area to the south of the original road
to be regraded and cleared of woodland for paths through the site are to be
restored and the area between the new and existing routes to be maintained
partly as grassland and partly woodland.
The route ‘A’ is shown on
the plan to spring from a point in the existing Undercliffe Drive approximately
midway in the frontage of the property known as Timber and travelling in a
westerly direction to link about 330m further west with the old route but
travel to the north side of the property known as Woodington with access off
Undercliffe Drive to be retained serving both Woodington and the caravan park
at the Spinnaker.
The alternative option,
route ‘B’ is proposed to spring from Undercliffe Drive approximately two thirds
from the eastern end of the Timber frontage but to be located a little further
south following the demolition of Woodington. The pile array on the northern
side of the original route differs slightly from that of the previous scheme to
account for the realigned highway. Otherwise the details are much the same.
The essential differences
between route ‘A’ and route ‘B’ (option A or option B) is that option A
requires a greater land take from the property known as Timber but allows for
the retention of Woodington; option B involves a smaller land take from Timber
but also requires the demolition of Woodington.
Area 3 involves the most
work, the most tree felling and therefore potentially the greatest visual
impact. Option B is the preferred option involving the demolition of Woodington
with the least land taken.
Area 4
This is the eastern most
of the four locations, situated to the north and west of Old Park Hotel and, as
with the other areas includes significant land drainage works to reduce and
channel water away from the land in a southerly direction to the coast it
comprises a substantial granular buttress just to the south of the Undercliffe
Drive adjoining the property known as Allenmore with several 1 metre wide
trench drains, approximately 4 metres deep at either five of 15 metre centres
draining ground water in a southerly direction into an existing drainage/stream
system which then flows to the coast. It also includes improvements to existing
watercourses. Nearly the whole of the application site is existing woodland and
wholesale clearance is not anticipated. A proportion of the trees are proposed
to be removed to facilitate the installation of the trench drains.
Undercliffe Drive is not
intended to be realigned in this section but it is intended to install a line
of pumped wells on the northern side of the Drive for a distance of
approximately 180 metres.
DEVELOPMENT PLAN/POLICY
None of the sites has any
development plan allocation. All of the sites are within the designated Area of
Outstanding Natural Beauty. Part of area 1 is within the designated SSSI, the
whole of area 2 is within the SSSI. The majority of area 3 is within the SSSI
and a small section of area 4, the southernmost extent of that area is also
within the designated SSSI.
Most of the area within
the Undercliffe is under a Tree Preservation Order or Orders.
The sites are outside any
designated development envelope.
Parts of areas 3 and 4
are located within the Heritage Coast annotation.
The following policies
are considered to be relevant in this instance.
C1 – Protection of Landscape Character
C2 - Areas of Outstanding Natural Beauty
C3 - Development of coast outside the Development
Envelope
C4 – Heritage Coast
C8 – Nature Conservation as a Material Consideration
C9 - Site of International importance for Nature
Conservation
C10 – Sites of National Importance for Nature
Conservation
C11 - Sites of Local Importance for Nature Conservation
C12 – Development Affecting Trees and Woodland
G7 – Unstable Land
G11 - Coastal Development
B9 – Protection of Archaeological Heritage
B10 – Parks, Gardens and Landscapes of Historic Interest
TR12 – The Strategic Road Network
In addition PPG14 –
Development on Unstable Land: Land Slides and Planning refers specifically.
CONSULTEE RESPONSES
Countryside Agency proposes that the
proposals involve possible impacts on the Tennyson Heritage Coastline and in
principle supports the preferred route as it is likely to have to least impact
coupled with the most benefits and comprises the best long-term solution but,
in making such observations stress that artist impressions or 3D views are now
important in determining the scheme. Raises concern over impact on
biodiversity, especially in areas which are to be cleared of woodland. Observes
that there is little prediction of the operational life expectancy and raises
concerns over further maintenance work and over further loss of trees.
AONB Unit point out that the whole
of the area concerned is under an AONB designation and may have significant
impacts but raises specific concerns over –
·
The expected life time of the works
·
They need to conserve the character of the undercliff
·
The design and siting of any engineering structures including areas of
"cut and fill"
·
Implications of landscaping
·
Implications regarding archeology
·
Impacts on rights of way
·
Degree and nature of mitigation
States that the
environmental assessment underplays the significance of AONB and the impacts on
the character of the area suggesting that artists impressions should be
supplied. Raises concerns over any works above ground level and suggests that
the highest design standards for works would need to be incorporated in the
scheme. Raises concerns over the
long-term management of the landscape and encourages the restoration and
reconnection of public footpaths through the area and states that preference
should be for route B, which involves the demolition of Woodington as lesser
works are required to form that route.
Ecological Officer points out that the
proposals are complex with significant implications for habitats and for
protected species and that the sites lie within the designated Compton Chine to
Steep Hill Cove SSSI. advises that he has had close involvement with English
Nature and the authors of the Environmental Statement which has resulted in
incorporation of mitigation measures to minimise impacts. He points out that it is important to
implement the mitigation measures in accordance with recommendations in the
environmental statement.
General comments point
out the need that all site clearance should take place outside the bird nesting
season as defined English Nature as March - August inclusive. No clearance whatsoever should commence
until a survey report for dormice has been received and points out that a
badger's survey will need to be carried out 5 weeks prior to commencement of
works; trees proposed for felling should be surveyed for bats prior to
felling. If any protected species are
encountered during the works the whole works should be halted and advise from
English Nature sought. Protected species in this context is likely to be
nesting birds, bats, badgers, or dormice.
Area 1 at Beauchamp lies
outside the SSSI but preparatory work will require some tree removal and
relocation of bat boxes originally erected as part of the approved first
phase. Work will need to be supervised
by a licensed ecologist to ensure that bats and possibly dormice are dealt with
according to the requirements of the law and that trees, with bat boxes and
other areas of ecological value, are adequately protected during the
construction phrase.
Area 2 around Mirables
involves work entirely within the SSSI but impacts on habitat and species
reliant on pondlands activity are considered to be low and no special measures
are advocated apart from the general principles affecting site clearance.
Area 3 around Undercliffe
Glen is again entirely within the SSSI and constitutes a particular complex
site regarding species and habitats. Both alternative routes cut through a
nature reserve leased by the Isle of Wight Council to the Hampshire & Isle
of Wight Wildlife Trust. Extensive tree
removal is proposed, top soil to be removed to leave a substrate to establish
open grassland. Entrances to a bat hibernation site are to be grilled which
will be vulnerable as result of tree clearance. Survey has shown that
Woodington contains roosts from more than one bat species and therefore if
Woodington is to be demolished on a different licence will be required. Such licence will require that an adequate
alternative accommodation is provided for the bats prior to demolition. One of
the bats is an exclusively house dwelling bat and bat boxes will not provide
adequate mitigation and a building with
a roofed structure will be required in the form of the habitation that is
existing or a new building details of the mitigation measures should be dealt
with within a management plan.
Area 4 ground woodlands
lie outside the SSSI but within a sink and impacts on habitats species reliant
on landslip activity similar to the area, mirrorpools are advocated including
landscaping and provision of bat boxes.
English Nature
The proposal affects land
with important nature conservation interests both within and adjacent to the
SSSI and is in proximity to a possible SAC. English Nature points out the value
of the variety of plant communities and the fact that the Isle of Wight support
approximately 14% of the UK resource of this type of habitat, supporting
nationally scarce plants and includes 8 nationally rare species and 51
nationally scarce species, a factor in the particular shape, form and nature of
the area. Land adjacent to the SSSI also supports assembly of invertebrates and
points out, (as the Ecology Officer did) protected species including bats, badgers,
red squirrel and European protected species of dormice could be present.
English Nature confirm
extensive involvement in the process of the production of the environmental
statement and echo the observations of the County Ecologist and, as a result, advises
that mitigation recommendation in the environmental statement be followed but
that the scope of any planning permission should be sufficiently wide to enable
the mitigation recommended in the report to be implemented.
English Nature has no objection
to the proposed developments subject to the granting of a appropriate licences
where required and recommends conditions be applied accordingly and in order
that all mitigation measures identified are fully implemented. In addition the
developer should produce and agree a costed management plan for creating and
maintaining new habitats for the life of the scheme prior to commencement of
any development.
Ventnor Town Council
Comments that the Town
Council see no reason why planning consent should not be granted.
Niton and Whitwell Parish
Council
Recommend approval.
County Archaeologist
Points out that the
application relates to land within a landscape of archaeological importance;
that the environmental statement draws attention to the importance of the area
of The Undercliff and the high probability of unknown archaeological remains of
local and regional rather than national importance, which must be recorded by
an archaeological watching brief. Also points out that all four of the development
areas contain preserved early 19th Century landscape gardens, houses
and garden structures which are unique to the character of the area of the
Island. In turn these undisturbed landscapes also preserve earlier landscape
features such as woodland banks and field boundaries all of which are local and
regional importance.
County Archaeologist
points out that the application relates to land within a landscape of
archaeological importance; that the environmental statement draws attention to
the importance of the area of the Undercliff and the high probability of
archaeological remains of local and regional rather than national importance,
which must be recorded by an archaeological watching brief. Also points out
that all four of the development areas contain preserved early nineteenth
century landscape gardens, houses and garden structures which are unique to the
character of the area of the Island. In turn these undisturbed landscapes also
preserve earlier landscape features such as woodland banks and field boundaries
all of which are of local and regional importance rather than national
importance. Accordingly recommends conditions be imposed to require access for
recording purposes but in accordance with a programme of archaeological works.
THIRD PARTY
REPRESENTATIONS
Seventeen letters on
behalf of fourteen local residents objecting on grounds of:
·
Sustainability of scheme, questioning costs/benefits of the proposals
·
Increased traffic
·
Changes in water tables, ground water levels and water levels in private
properties.
·
Loss of access to property.
·
Loss of trees and impact of widespread tree clearance resulting in loss
of roots reinforcing the stability of the ground resulting in a destabilization
of the area.
·
Alterations to accesses which would result in loss of visibility and
therefore traffic dangers.
·
Extent of work not enough to protect private property or safeguarding
business interests and questioning responsibility to maintain original access
route to properties.
·
Objections to amount of land take to realign road with resultant defect
that the road would be closer to residential property and its consequent
adverse effects of living conditions through noise and light pollution and
questioning land stability due to the works.
·
Objections to use by heavy vehicles, suggesting that routes should be
limited to a maximum weight limit or size of perhaps a mini bus.
·
Loss of habitat for protected species through loss of trees, overgrowth
or undergrowth and to changes of ecology.
·
Adverse effect on Listed Buildings of a loss of stone walls through the
route and resultant changes in character.
·
Writers call for a public enquiry.
Ramblers Association
Consider that the
proposals could result in new opportunities to establish or re-establish public
rights of way.
Petition
Over 3,000 signatories of
local and predominantly Island residents stating:
1.
Wish to preserve the beauty and continuity of the landscape of The
Undercliffe Drive which is designated as an Area of Outstanding Natural Beauty,
SSSI, Heritage Coast and Conservation.
2.
Fully support the Council in rejecting unnecessary applications for
works to protected amenity trees in this five mile stretch of woodlands along
the Undercliffe Drive
3.
Consider the unnecessary felling of trees in this area of major slippage
to be extremely unwise.
4.
Believe the natural colonization of red squirrels in the area and
presence of other important species of wildlife should not be put at risk by
the actions of landowners who do not understand the ecological importance or
the amenity value of their surroundings for residents, visitor and future
generations.
CRIME AND DISORDER
IMPLICATIONS
Relevant officer has been
given the opportunity to comment but no observations have been received.
However, no crime and disorder implications are anticipated.
EVALUATION
General Background
The Undercliffe Drive
forms a significant component part of the Island’s principal road network and provides
additional utility as a tourist route and affords local access. Although the
Environmental Impact Statement compared the proposed restoration work with the
alternative route via Whitwell, the Environmental Statement concluded that the
Whitwell diversion in its current form is unsustainable in the longer term and
the proposals for upgrading it or identifying a suitable alternative are not
considered to be feasible and would probably involve a Niton by-pass in order
to mitigate adverse effects. It also concludes that, the implications of
restoring the Undercliffe Drive to its previous principal route status, is
considered to be positive in all respects with regard to traffic and
infrastructure issues. This statement also concludes that residents along
Undercliffe Drive will be exposed to elevated traffic level upon completion of
the proposed remedial works but it is pointed out that had the failures not
occurred and the temporary reduction in traffic level imposed by order being
necessary, the levels of traffic using reinstated route would probably been the
same.
In essence the strategic
policy is to restore the Undercliffe Drive to its former status rather than to
find an alternative permanent solution in-land as this would not only require
considerable expenditure to upgrade an in-land route but would also require
considerable expenditure in maintaining local access through the Undercliff. It
should also be remembered that the UDP Policy TR12 states that the Council will
approve proposals which will maintain the effectiveness of the strategic road
network which is presently defined as follows:
f)
All existing “A” Class roads.
The UDP and its policies
contained therein were adopted in May 2001 following a public enquiry.
Some objectors and others
have raised the question of sustainability, ie the long term
costs/benefits/effectiveness of the proposed work to maintain the Undercliffe
Drive as a route open to all traffic. Bearing in mind Council’s policy to
maintain the strategic road network, the decision to expend funds on such works
and its effectiveness over a long term are not a planning issue and I do not
intend to discuss nor pass opinion on them. Having said that, it should be
pointed out that the design life of the current scheme has been stated by the
Council’s consultants as being a period of 50 years and therefore it is
anticipated that the remedial works are a long term option.
Given that the principal
policy considerations are to maintain this “A” class road, the determination of
the details of the scheme will be the determining factors with the effects of
the engineering proposals on matters of acknowledged importance. Whilst not
necessarily exhaustive, those matters include impacts on designated sites; the
loss of trees through the Undercliff, many possible impacts on the ecology and
in visual terms; the impact on various habitats and finally the offsetting of
these impacts by the adoption of mitigation measures and re-landscaping of the
land.
On many instances
planning permission need not be sought by the Highway Authority for works
required for or incidental to the maintenance or improvement of the highway.
This includes land which is outside but adjoining the boundary of an existing
highway. Accordingly, much of the works envisaged fall with “permitted
development” as described by Part 13 of Schedule 2 of the Town and Country
Planning (General Permitted Development) Order 1995. Due to the above and the
fact that substantial amounts of the work envisaged is both outside of the
boundaries of the highway and does not abut the boundary, planning permission
is required, hence the submission.
Members will be aware of
the previous planning permission as detailed above, granted in July 2002 which authorized
the construction of new section of Undercliffe Drive for local access and
emergency use only, the section being at the western end of the Area 1
currently at risk at Beauchamp House and adjacent land. That section of highway
has been installed and is operational although, since its completion there has
been a limitation on its use, preventing the use by heavy through traffic,
limiting its use to temporary access for local and emergency purposes only,
pending the preparation of a long term strategy of the Undercliffe Drive
reinstatement. Members will also be aware that there have been very substantial
ground movements more recently, especially at the Undercliffe Glen location
(Area 3) which has culminated in very substantial landslip clearly visible upon
inspection.
Details of Proposed
Engineering Works
The four areas, the
subject of these applications have been identified as areas of high risk where
intervention is felt necessary to prevent or significantly reduce the
likelihood of further landslide and further breach of the route through the
Undercliffe. Apart from the option to form an alternative route inland, the
options, so far as the Undercliffe Drive is concerned are essentially to do
nothing thus allowing natural forces to continue which will ultimately result
in further failures of the route or to take measures to intervene and “shore
up” and slow down possible ground movements to enable the route to remain open.
Essentially, the proposed
works fall into several categories and the combination of these methods are
intended to be used in the process of the stabilization of the land. The
critical factor in this landslide situation is the continuous removal of
naturally occurring ground water in the landslide area and routing it to the coast
for discharge into the sea. The de-watering of the land at different depths is
intended to improve slope stability by:
·
Direct drainage measures constructed on the landslide slopes which
increase the sheer strength of the slipped material and reduce the pore
pressure along the slip lanes;
·
Drainage up slope of the landslide which will increase the sheer
strength of the soil, assisting in curtailing the propagation of the landslide
up slope, and:
·
Cut off drains located up slope of the landslide to reduce the volume of
groundwater entering the slip.
To be effective these
measures must extend to sufficient depth to affect the slip plane. For
practical reasons they will therefore be most effective in addressing shallow instability.
In detailing the above drainage would be carried out by way of provision of
surface drainage for fast run off gradients to be provided by lined ditches to
prevent introducing water back into the slip. Trench drainage, formed by gravel
filled piped trenches with the installation of deep “cut off” trench drains,
installed towards the rear of the landslide to intercept and prevent ground
water entering the landslide system. Horizontal bored drains drilled into the
slope and lined with perforated pipes sited in arrays and finally by installing
deep watering wells or siphons, used as an alternative to cut off drains and
can either be operated on a pumped system or by siphonage.
Earth works, also used as
an alternative to inhibiting land slippage by re-profiling slopes in landslide
areas by removing material from upper portions thus reducing forces; adding
material to the lower portion of a landslide thereby increasing the restraining
forces and; completely removing and replacing the landslide mass possibly with
a reinforced soil or better drained soil.
Slope retention methods
involve formation of a physical barrier within a landslide, sufficient to hold
the portion of the slope by forming retaining structures including driven sheet
piling or contiguous bored piles forming a wall anchored into underlying and
more stable strata.
Slope reinforcement uses
a variety of means to increase sheer resistance by installing sheer keys or
piles which would require soil to deform around the piles and produce resistance
to movement.
The most drastic part of
the solution is road realignment which clearly means repositioning the route in
order to remove it from an area with immediate landslide hazard.
The design scheme
prepared intends to utilise means appropriate to the circumstances prevailing
in that location, a comprehensive and varied solution to reduce the influx of
water into the landslide area, to speed and channel away water from the
landslide without re-absorption, to support land and reduce the likelihood of
continued landslide and where appropriate to realign the highway away from
areas of impending landslide.
The design scheme has
been produced by Consulting Geotechnic Engineers commissioned by the Isle of
Wight Council to prepare and implement a scheme which is intended to support
the route from further de-stabilisation, but at the same time carrying out the
minimum work necessary to achieve the goal. The works are therefore considered
necessary to achieve the objective of restoring and retaining the A3055 the
Underclife Drive as a major part of the strategic road network on the Island.
Environmental
Considerations
The Undercliffe Drive
passes through an area of high amenity value, the whole of the area contained
within the Area of Outstanding Natural Beauty with much of the application
site's are under designations such as Heritage Coast, SSSI and the eastern
extent within a site designated as and historic garden. The proposed works as
described above includes excavation, piling as well as "cut and fill"
to alter the vertical alignment in accordance with modern road design
requirements.
As substantial areas of
the necessary works are outside of the present road “corridor” trees are bound to
be felled to enable access to the areas to carry out the engineering works. In
the areas of influence of the works, which amounts to about 7% of the
Undercliff area are much of the woodland in these areas will be retained and
protected and although there are a significant number of trees which will be
felled, the replanting of some of these areas will be undertaken as part of the
mitigation and landscaping works proposed after the completion of the
development.
Although there will be
areas cleared of trees, under growth and other vegetation and that some of
these areas will be retained as open grassland, the intention is to replace
many of the trees but in a more diverse landscape including some areas of
grassland which, historically , form part of the character of this area. It
will be necessary for some parts of the landscape to remain open to ensure
maintenance and to secure the effectiveness of the drainage regime, however,
English Nature are firmly of the opinion that more diverse landscape which can
be formed will enrich the habitat for species such as invertebrates.
The proposed mitigation
works and re-landscaping of the area, detailed in the application and the
Environmental Statement have been prepared with close consultation with English
Nature.
Key Material
Considerations
The determining factors
are therefore the desire for and merits of the restoration, realignment and
stabilization works to secure the future of the Undercliffe Drive weighed
against the impacts on the designated sites, Area of Outstanding Natural Beauty
and the impacts on residential property served by the Undercliffe Drive,
weighed against the proposed mitigation measures to safeguard and even enhance
the quality of the landscape and habitats in the area.
Visual Impacts
In visual terms the main
impacts realized will be the loss of preserved trees required to implement the
physical works of excavation and drainage together with the installation of
piling and wells and the extent to which this would adversely affect the Area
of Outstanding Natural Beauty and the Heritage Coast. Approximately 7% of the
whole Undercliff area is likely to be affected by the works and clearly there
will be some impact from tree loss. It is intended that this loss of trees and
undergrowth would be mitigated by replanting trees, shrubs and ground cover in
order to establish more diverse quality of landscape and the Environmental
Statement concludes the visual impact of this tree loss would be minimised. The
proposed works involved, could potentially cause effects on the population of
bats, birds, badgers, squirrels and dormice if any of the above species are
found in the areas.
Few details of street
furniture, signage, road boundaries, stone walls etc. have been submitted but
these will have an impact on the character of the area.
It is proposed to create
a new environment for bats, evidence of which has been found in Woodington, the
property to be demolished. Bats use this property’s roof for roosting and over
wintering hibernation and therefore there is a need to create a new, purposed
built environment for these creatures to ensure their continued colonization of
this area. It addition, bats are known to roost and hibernate in some trees and
therefore replacement habitat by erecting bat boxes and each tree that is to be
felled to be inspected for signs or evidence of bat activity and use before it
is felled.
There is a substantial
bird population in the Undercliff due to the nature of the environment and, once
again, disturbance to birds is likely to occur by the reduction in tree growth.
It is intended that trees be examined not only for evidence of bat use but also
for nesting birds. Unfortunately, the period in which trees must be felled to
avoid the bird nesting season is likely to conflict with the use by bats and,
similarly, the felling of trees to avoid hibernation and roosting of bats is
likely to conflict with the bird nesting season, hence the need for each tree
to be carefully examined to ensure the existence of neither, prior to felling.
The survey work carried
out for the preparation of the Environmental Statement addresses the subject of
badgers and the possibility of sets within the four areas of influence. No
evidence of sets was found, however whilst the area is probably used for
foraging by badgers, the existence of sets even outlying sets can be ruled out
and , of course, if found such a set should not be disturbed or destroyed since
that would constitute a criminal offence. It is proposed that careful re-survey
of the areas of influence, including land abutting, is carried out prior to the
commencement of any works to ensure there are no badger sets. In the event that
a set or sets are found, a licence will need to be obtained from DEFRA before
works can commence.
The presence of red
squirrels has been established but the study has established also that the
importance of this area is not great and of low local value only.
As part of the survey
works a study was carried out to establish the presence of dormice; the study
concluded that there was no evidence of dormice in the area.
It is also an offence
deliberately to kill reptile species such as grass snakes, adders, common
lizards and slow worms. Discovery of such species should be followed by
relocation of such species into suitable release sites before site works can
commence.
Physical impacts
The Undercliffe has a
known history of archaeological finds and the four sites are known to contain
preserved early 19 century landscaped gardens, houses and garden structure
which are unique to the character of the area of the Island. Also there is
evidence of preserved earlier landscape features such as woodland banks and
field boundaries. All of these remains are of local and regional importance
rather than national importance. In addition, it is apparent that the range of
archaeological finds include Paleolithic and Neolithic and Bronze Age finds,
Iron Age settlements and burials, Roman occupation and burials, Medieval
settlements and middens as well as post medieval structures.
The mitigation measures
are detailed within the Environmental Statement which meet with the general
approval of English Nature and with the County Archaeologist who has indicated the
need for a plan of archaeological works to be followed and for a watching brief
as work progresses.
Mitigation
Mitigation measures are deemed
necessary on a wide range of issues many of which have been suggested by
English Nature. The Environmental Impact Statement also include steps to be
taken to counter possible adverse impacts in the areas of archaeology and
architectural heritage; the ecology of the area; relating to traffic and
transportation infrastructure and socio-economic factors and material assets.
The mitigation measures proposed to
be put in hand have been tailored to the individual sites and in the
circumstances prevailing are considered appropriate following the Environmental
Statement and so far as the archaeological and architectural historic heritage
is concerned the proposals involve a watching brief for the recording and
recovery of artifacts, and, if appropriate, recording and preserving in situ
which ever is deemed by the watching archeologist as the appropriate action.
In terms of the ecology of the area,
perhaps the greatest impact would be the clearance of trees where necessary to
carry out the works but there are also areas which are proposed to be cleared
of woodland in order to establish an important and more diverse habitat
important to the status of the area as a SSSI. This includes the clearance and
maintenance of some of the ground habitat to enable invertebrates to
re-establish and thrive in this more diverse habitat. Whilst it is important to
consider also the woodland habitat, the extensive planting and localized
felling to increase the structural diversity of the habitat is also proposed.
Environmental Statement has
recognized the existence of various protected species with surveys having been
carried out and the intention to update such information when the works
commence and continually to monitor a possibly changing situation. Protected
species identified include dormice, bats and birds and especially recognized is
the need to be vigilant regarding the existence of badger sets. DEFRA licences
will need to be obtained in the event that such habitats are found and are
likely to be affected by works in connection with the development. It is also
intended to establish ”no go” areas to prevent inadvertent disturbance or
damage associated with the construction process. Whilst the dormouse survey
already implemented has concluded that there is no evidence of dormice in the
areas, it is clear that there are protected species of bats and birds, reptiles
and possibly badgers so vigilance will be needed to ensure no habitat is
destroyed without having first provided an alternative habitat for such
species.
In this context the erection of a
building to enable bats roosts and hibernation roost be provided as an
alternative to the building known as Woodington, before its demolition, is
proposed. In addition, any tress which are to be felled are to be inspected to
ensure there are no bat roosts or birds nests before the trees are touched and
it is also proposed to install a grill or grills over the caves where bats have
been found to roost and hibernate to ensure intrusion does not occur and
disturb these protected species.
With regard to the traffic and
transportation mitigations, the Environmental Statement makes it quite clear
that the restoration of the Undercliffe Drive to its former principle route
status is considered to be positive, especially when compared to the possible
options of a diversion through Whitwell and Niton including the provision of a
by-pass and other highway improvements. The study acknowledges that residents
along Undercliffe Drive will however be exposed to elevated traffic levels upon
completion of the proposed remedial works but given that the reduction was
temporary and that its consequences were in almost other respects detrimental,
this is not considered to be a significant issue. In other words if the
Undercliffe Drive had not been restricted by land instability, the same levels
of traffic would have been realized in any event. Accordingly, no mitigation
related to traffic levels is proposed.
With regard to the socio-economic
impacts, except for area 3, where the greatest landslip has occurred and where
the road needs to be diverted, no significant adverse impacts on material
assets or the socio-economic environment is anticipated. However, in area 3 the
proposed re-alignment will have significant adverse affects on the properties
know as Woodington and Timber where substantial proportions of their grounds
will be required and, in the case of Woodington House itself, would require
demolition. The mitigation measures required will include the landscaping of
the realigned route. In consequence, Environmental Statement considers that the
remedial works to Undercliffe Drive are expected to reverse those adverse
socio-economic consequences of the recent landslide events over the last few
years and no further impacts are anticipated as a result of the physical works.
Accordingly, no mitigation measures are considered necessary.
CONCLUSION
The Undercliff is an area which is
known for severe land instability but the Undercliffe Drive forms part of the
principal road network throughout the Island which the UDP policy seeks to
retain. The land instability and landslip in the last few years has caused severe
disruption to this route, resulting in a section of highway being realigned and
restored at Beauchamp at the western end of the section, the subject of this
application. The study of the area, expressed in the Environmental Statement
shows that the alternatives to the current proposal to restore and realign the
Undercliffe Drive are two fold. Either the inland route via Whitwell and Niton
could be used but would entail substantial road improvements along its route
and possibly by-pass construction and is felt to be unsustainable. The other
option is to do nothing and allow the route to submit to natural forces thus
accepting an incremental degrading and collapse of the route disrupting not
only local access to individual properties, but also an important part of the
principal road network, especially an element of the “round the Island” route.
The consultants have designed the
scheme which has an anticipated design life of 50 years seeking to restore this
section of the principal traffic route to all traffic and for local access as
well, It is not part of the planning process to determine the sustainability of
this option in economic terms but it is for the planning process to determine
the suitability or otherwise of the detailed scheme, it impacts and mitigation
in the light of the designations of the area and the policies within the
Unitary Development Plan.
Essentially the scheme seeks to
improve the alignment of the highway and stabilizing the land by carefully chosen
geo-technic engineering techniques in order to stabilize and shore up areas
where there is known or likely ground movement and to reduce the risk of
further landslides by dewatering lower strata which is considered to be the
main promoting factor of land slippage.
Extensive physical works within and
adjoining the existing highway corridor will inevitably result in environmental
impacts. It is impossible to install a designed stablisation and drainage
scheme without a degree of land clearance. Determination of the acceptability
of the development will turn on the minimization of such impacts and by the
mitigation of those impacts by the necessary steps to best effect.
The Environmental Statement has been
prepared following much study work and following close consultation with
English Nature who are supportive of the scheme provided that the necessary
mitigation works described in the Environmental Statement are implemented and
maintained thereafter.
The greatest visual impact realized
by the works will be loss of trees. However, contrary to various objectors
observations of clear felling throughout the Undercliff, it is apparent that
only 7% of the Undercliff would be affected by the works and that would be
significantly reduced following replanting and re-landscaping of the area
following conclusion of the works. The recommendation is being made to grant
planning permission for the works described in the application and in the
accompanying statement subject to (amongst others) a condition which prohibits
the commencement of work until a contract/agreement has been concluded for each
of the areas described in the application, the signatories of which shall
include the Council (as applicant), English Nature and any/all land owners
relevant to the area concerned. The agreement/contract will require the Council
to carry out all of the mitigation measures as described in the Environmental
Statement and the continuing maintenance responsibility for the design life of
the scheme overall. It will also require the relevant land owners to permit the
Council to carry out the mitigation works and to implement the continued
maintenance of the scheme and to secure the continued environmental
improvements as describe and agreed with English Nature.
HUMAN RIGHTS
In coming to this recommendation to
grant planning permission consideration has been given to the rights set out in
Article 8 (Right to Privacy) and Article 1 of the First Protocol (Right to
Peaceful Enjoyment of Possessions) of the European Convention on Human Rights.
The impacts this development might have on the owners/occupiers of other
property in the area and other third parties have been carefully considered.
Whilst there may be some interference with the rights of these people this has
to be balanced with the rights of the applicant to develop the land in the
manner proposed. Insofar as there is an interference with the rights of others
it is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that such action is proportional to the
legitimate aim of the Council’s Unitary Development Plan and in the public
interest.
JUSTIFICATION FOR RECOMMENDATION
This is an extremely complex and
complicated development involving many environmental factors. It is a
fundamental policy contained within the UDP (Policy TR12 – The Strategic Road
Network) to “approve proposals which maintain the effectiveness of the
strategic road network which is presently defined as follows:
a)
all existing A class roads”
There is, therefore, a presumption
in favour of the principle of maintaining the A class road network including
Undercliffe Drive. The physical works will inevitably have impacts. However,
bearing in mind the Environmental Statement has been prepared with close
consultation with English Nature the majority of the impacts from ecological
view point have been addressed. There will be visual impacts from new
engineering works and from tree loss but the replanting and landscaping scheme
is felt to be appropriate thus creating a varied and diverse landscape in
ecological terms and consistent with the aims and objectives of the policies
set out within the UDP.
The development is therefore
considered to be consistent with Policies TR12 – The Strategic Road Network; C1
– Protection of Landscape Character; C2 - Area of Outstanding Natural Beauty;
C3 – Development of Coast outside of Development Envelopes; C4 – Heritage
Coast; C8 – Nature Conservation as a material consideration; C9 – Sites of
International Importance for Nature Conservation; C10 – Sites of National
Importance for Nature Conservation; C11 – Sites of Local Importance for Nature
Conservation; C12 – Development affecting trees and woodland; G7 – Unstable
Land; G11 – Coastal Development; B9 – Protection of Archaeological Heritage and
B10 – Parks and Gardens and Landscapes of Historic Interest.
RECOMMENDATION – Approval
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
No development permitted
by this planning permission including any excavation, tree felling or
undergrowth clearance or any material operation as defined in Section 56 (4)
of the Town and Country Planning Act 1990 shall be initiated within any of
the areas 1 to 4 identified on the plans until a binding contract has been
concluded with English Nature and all of the land owners of that respective
area to ensure that mitigation measures and appropriate maintenance
responsibilities are carried out in accordance with a comprehensive scheme of
works, landscaping and continuing management to be submitted to and approved
by the Local Planning Authority. Reason: IN the interest of the
amenities and ecology of the area and in accordance with Policies C1, C2, C3,
C4, C8, C9, C10, C11, C12, G7, G11, B9 and B10 of the IOW Unitary Development
Plan. |
3 |
The property known as
Woodington shall not be demolished until an appropriate replacement habitat
for bats has been provided on a suitable site within the near vicinity of
that building and in accordance with a specification to be submitted to and
approved by the Local Planning Authority. Reason: In the interests of the
ecological value of the habitat and in accordance with Policies C8, C9 and
C10 of the IOW Unitary Development Plan. |
4 |
No trees in any of the
sites identified on the approved plans shall be felled until bat boxes in
such numbers and locations agreed in writing with the Local Planning
Authority have been installed in accordance with a scheme to be submitted to
and approved by the Local Planning Authority. Reason: In the interests of the
ecological value of the habitat and in accordance with Policies C8, C9 and
C10 of the IOW Unitary Development Plan. |
5 |
No trees within the sites
the subject of this permission shown on the approved plans for removal shall
be felled until examined for the presence of bats and their roosts. Should
bats, evidence of bats or their roosts be found, the felling of that tree
shall only be undertaken in accordance with a scheme and timetable agreed in
advance with the Local Planning Authority. Reason: In the interests of the
ecological value of the habitat and in accordance with Policies C8, C9 and
C10 of the IOW Unitary Development Plan. |
6 |
No trees within the
sites the subject of this permission shown on the approved plans for removal
shall be felled until examined for the presence of nesting birds. Should
evidence of active birds nests (including nests under construction, eggs or
dependent young) be found, the felling of that tree shall only be undertaken
in accordance with a scheme and timetable agreed in advance with the Local
Planning Authority. Reason: In the interests of
the ecological value of the habitat and in accordance with Policies C8, C9
and C10 of the IOW Unitary Development Plan. |
7 |
The tree and shrub
planting and seeding of each area as shown in the plans shall be implemented
and completed in the first planting season following completion of the development
works hereby authorised within that area, strictly in accordance with the
details shown in those plans and the environmental statement accompanying the
application. Reason: In the interests of the
amenities of the area and in accordance with Policies C1, C2, C4 and C8 of
the IOW Unitary Development Plan. |
8 |
The materials, finishes
and method of construction to be used in the replacement of the bat roosts as
required by condition 3 above shall be in accordance with a scheme to be
submitted to and approved in writing by the Local Planning Authority prior to
the commencement of work in area 3. Reason: In the interests of the amenities
of the area and in accordance with Policies C1, C2, C4 and C8 of the IOW
Unitary Development Plan. |
9 |
Before works commence
in any of the areas, details of stone walls, street furniture and any other
construction including barriers, fences, retaining structures etc. shall be
submitted to and approved by the Local Planning Authority and, thereafter,
the development shall be carried out in accordance with those details. Reason: In the interests of the
amenities of the area and in
accordance with Policies C1, C2, C4 and C8 of the IOW Unitary Development
Plan. |
10 |
Access for archaeologists -
P22 |
11 |
Site of archaeological
interest - P23 |
12 |
No works associated
with this permission shall commence until a further survey has been carried
out to establish whether or not badgers are present in the area where works
are due to be carried out. Reason: In the interests of the
ecological value of the habitat and in accordance with Policies C8, C9 and
C10 of the IOW Unitary Development Plan. |
13 |
Prior to commencement
of works in a particular area all working areas shall be fenced off with 'Heras'
or similar type fencing to a height of 1.8m and no materials or plant shall
be stored outside of the working areas. Reason: In the interests of the
ecological value of the habitat and in accordance with Policies C8, C9 and
C10 of the IOW Unitary Development Plan. |
14 |
Metal grills in
accordance with a specification to be submitted to and approved by the Local
Planning Authority shall be installed within the entrance to the caves known to
contain bats located in the cliff face before the works hereby approved are
completed. Reason: In the interests of the
ecological value of the habitat and in accordance with Policies C8, C9 and
C10 of the IOW Unitary Development Plan. |
15 |
The Listed gate piers
at the entrance to Old Park shall be protected by the erection of 1.8m high
'Heras' (or similar) fence for the duration of the works and the gate piers
shall be retained thereafter. Reason: The architectural feature/structure to remain
is particularly worthy of preservation and to comply with policies B1
(Alterations and Extensions to Listed Buildings) and B8 (Alterations and
Extensions to non-Listed Buildings in Conservation Areas) of the IW Unitary
Development Plan. |
16 |
The route of the
original road, following the realignment hereby approved, shall be formed
into a public pedestrian right of way in accordance with details which shall
be submitted to and approved by the Local Planning Authority in writing. Reason: In order to enhance the
visual amenities of the area and to improve local rights of way in accordance
with Policies C1, C2 and TR17 of the IOW Unitary Development Plan. |
16. |
TCP/26498/B P/00063/05 Parish/Name: Shanklin
Ward: Shanklin Central Registration Date: 12/01/2005 -
Full Planning Permission Officer: Mr. J. Packman Tel: (01983) 823571 Applicant: Mr & Mrs J Matthews Retention of single storey side
and rear extension; raised deck area and screening as built (application to
be determined by the Council's Development Control Committee) 5 Avenue Road, Shanklin, Isle Of
Wight, PO377BG |
REASON FOR COMMITTEE
CONSIDERATION
This application is before
the development control committee due to the planning history on the site and
the concerns of local member Cllr J Fleming. This application follows a
previous application for the retention of a similar scheme.
PROCESSING INFORMATION
This is a minor
application, the processing of which will have taken nearly 5 weeks to the date
of the committee meeting.
LOCATION AND SITE
CHARACTERISTICS
Application relates to a
semi-detached property within a residential area. The property is located in a
reasonably sized plot that slopes in a southerly direction away from
house. The existing arrangement of
garden already affords a certain degree of overlooking from property to
property looking east. To the western boundary adjoining Milford road there is
a 1.2 metre wall, and on the eastern boundary there is 1.5 metre fence. The
street scene is mixed with a number of different detached and semi detached
properties of different styles, but generally of the same period. The dwelling
to which this application relates is built in a red brick style.
RELEVANT HISTORY
A previous application
(TCP/26498/A) for retention of single storey side and rear extension; raised
deck and screening was presented to committee on two separate occasions and a reduced
scheme was successfully negotiated.
The application was
considered by members on the 26/10/04 in a revised form and was not accepted.
Committee resolved to defer the application to allow opportunity for further
negotiations. A revised scheme with reduced deck area was presented before
committee on the 16/11/04 and planning consent was granted on the 17/11/04
subject to conditions.
Condition 1 stipulated
the removal of a 2.5 x 3.0 metre section of the raised decking closest to
number 7 Avenue Road and the leveling of the ground level beneath to match that
of the existing grass level with a 2 month compliance period which expired on
17 January 2005. Enforcement action by
way of a breach of condition notice is pending the outcome of this revised scheme.
DETAILS OF APPLICATION
Retrospective consent is
sought for the retention of a rear extension and raised decking as built. The
decking includes a scheme of screening on the eastern boundary that includes a
30mm high section of trellising on top of the existing 1.5 metre high fence and
3 large shrubs in pots. The shrubs are all evergreen two of which are Photinia
and one Bay variety. The potted shrubs are between 1.6 and 2.0
metres in height.
DEVELOPMENT PLAN/POLICY
The site is located within
the Sandown and Shanklin development envelope.
Relevant Unitary
Development Plan policies are as follows:
S6 – All development will be expected to be of a high standard of
design
D1 – Standards of design
H7 – Extension and Alteration of Existing Properties
G4 - General locational criteria for development
CONSULTEE RESPONSES
None received.
PARISH/TOWN COUNCIL
COMMENTS
None received.
THIRD PARTY
REPRESENTATIONS
The application has
attracted one letter of objection.
The resident of the
neighbouring property objects to the raised decking on grounds of loss of
privacy and considers screening is totally unacceptable.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
Determining factors are
policy considerations, how the development will impact on the character and
appearance of the area and how the proposal will impact on the amenity of
neighbouring properties.
The design of the
extension and the decking do not significantly impact upon the character of the
dwelling or the street scene. They are of an appropriate design and scale and
the materials match the existing dwelling. The extension does not have any
windows on the east elevation and therefore does not present any loss of
privacy; it has minimum impact on neighbouring amenity.
Both the extension and
the raised decking are contained within the same application.
The focus of this report
relates specifically to the raised decking so attention should be given to
whether the raised decking specifically contributes to a loss of privacy.
A certain level of
overlooking already exists on the site, this is exacerbated by a relatively low
fence on most of the eastern boundary.
The main issue concerns
the degree of visual intrusion and potential noise activity on the decking and
whether this adversely impacts on the amenities currently enjoyed by the
neighbouring property.
It is accepted that the
screening on the eastern boundary would offer a degree of protection and reduce
the potential for overlooking of the neighbouring property but having
considered the overall height of the fence and lack of permanence of the
proposed shrubs grown in pots, I am of the view that this scheme presents an
adverse impact on neighbouring amenity.
In addition and taking account of advice within Circular 11/95 - The Use of Conditions in Planning
Permission and Circular 10/97 Enforcing Planning Control, the Local Planning
Authority would have some difficulty in enforcing the retention of this
planting given its potentially transient nature. Additionally the extent of plant coverage cannot be controlled
and currently does not offer an efficiently satisfactory screening solution.
To conclude, due regard
has been given to the original scheme with officer recommendation for approval
with 1.8m high opaque screen, Members resolution to reduce the size of the deck
and the current scheme. Overriding issue is the resultant impact on
neighbouring amenity and degree of enforceability of current scheme. The
proposal is therefore unacceptable and contrary to Policy.
HUMAN RIGHTS
In coming to this
recommendation to refuse planning permission, consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of the other property in
the area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of the applicant to develop the land in the manner proposed, it is
considered that the recommendation to refuse is proportional to the legitimate
aim of the Council’s Unitary Development Plan and in the public interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations, I am of the view that
the single storey side and rear extension are acceptable in accordance with
Policy, the raised decking and provision of screening as proposed on the
eastern boundary represents an unacceptable form of development.
RECOMMENDATION 1 – Refusal
Conditions/Reasons:
1 |
The construction of the
raised decking and provision of screening in the manner shown on the
submitted plan would result in development detrimental to the amenities and
privacy of the adjoining residential property. The proposal would therefore be contrary to Policy S6 (Be of a
High Standard of Design) and Policies D1 (Standards of Design) and H7
(Extension and Alteration of Existing Properties) of the Isle of Wight
Unitary Development Plan. |
RECOMMENDATION 2
To proceed with the
service of a Breach of Condition Notice to secure compliance with the Planning
Condition imposed on TCP/26498/A.
17. |
TCP/26689 P/02181/04 Parish/Name: East Cowes
Ward: East Cowes North Registration Date: 26/10/2004 -
Full Planning Permission Officer: Mr. A. White Tel: (01983) 823550 Applicant: South East of England Development Agency Demolition of buildings; formation
of temporary trailer park 2 industrial buildings, Castle Street, East Cowes,
PO32 |
REASON FOR COMMITTEE
CONSIDERATION
The local Member,
Councillor Mrs Lloyd, has requested that this application is reported to
Committee as she is concerned about highway implications associated with the
proposal and particularly the ability of lorries to negotiate the roundabout at
junction of Dover Road, Castle Street and Well Road. She is also concerned that
the roundabout could be damaged by lorries as has happened in the past.
PROCESSING INFORMATION
This is a minor
application, the processing of which has gone beyond the prescribed 8 week
period for determination of planning applications owing to the need for
additional information and also the need for Committee consideration.
LOCATION AND SITE
CHARACTERISTICS
Application relates to
two former Westland Aerospace buildings situated on the eastern side of Castle
Street, approximately 30 metres north of the roundabout junction with Well Road
and Dover Road. One of the buildings is two storey in height being constructed
partly of brick and steel cladding. The other is a brick built single storey
structure.
The immediate area is
primarily industrial in character, being the former centre of operations for
Westland Aerospace. There are residential properties nearby at Dover Road and
Well Road, these properties having co-existed with industrial activities and
Red Funnel operations for many years.
RELEVANT HISTORY
None.
DETAILS OF APPLICATION
Consent is sought to
demolish both buildings and to use the land as a temporary trailer park for a
period of five years. It is envisaged that a permanent site for a trailer park
will be identified and finalised during this period as part of the long term
planned regeneration of East Cowes, which may eventually result in the
relocation of Red Funnel’s marshalling yards from their current location.
The proposed temporary
trailer park is regarded as a direct replacement of Red Funnel’s current use of
the slipway in front of the Columbine Works. Red Funnel has been using the
Columbine Slipway for the past 18 months as a short-term holding facility for
trailers, in order to improve the efficiency of its ferry operations. It is
reported that this has functioned well during this period, but the recent
occupation of the Columbine and the Medina waterfront buildings means that it
is no longer appropriate for this use to continue in its current position.
Additionally, it has become apparent that the slipway is fragile and there are
structural problems with it that are being exacerbated by its continued use as
a lorry park. It has therefore been necessary to relocate at the earliest
opportunity.
The proposed temporary
trailer park would contain 13 trailer bays, together with an additional area
for parking of smaller vehicles. The trailer park would comprise of a
reinforced concrete deck and would have a sealed surface. The site would be
drained and include oil interceptors to prevent the pollution of water draining
from the site. The perimeter of the site is shown to be secured by 1.8m chain
link fencing, and gates will be installed at both of the proposed access
points. Existing buildings are currently undergoing demolition and site levels
will remain much the same as they are at present.
The application is
accompanied by a supporting statement which states that the proposed trailer
park needs to be operational for 24 hours a day because much of the trailer
traffic occurs at night; this is because night times are the quietest period
for car traffic, thus providing maximum capacity on the ferries for HGVs. The
typical pattern of trailer movements is up to 120 trailer movements a day
during the week, up to 51 on Saturday and up to 86 on Sunday. The supporting
statement also includes the following table which estimates the usage profile
of the proposed trailer park:
Time period |
Maximum No. of trailers using site |
00:00 |
15 |
03:00 |
20 |
06:00 |
7 |
09:00 |
5 |
12:00 |
2 |
15:00 |
0 |
18:00 |
7 |
21:00 |
9 |
Application is also accompanied
by vehicle sweep diagrams in respect of the roundabout junction at Dover Road,
Well Road and Castle Street. The diagrams are based on a HGV, the largest which
would use the trailer park, and show that vehicles of this size are able to
negotiate this roundabout in one sweep regardless of which direction they are
travelling from.
DEVELOPMENT PLAN/POLICY
Site is within the
development envelope for East Cowes as identified in the Isle of Wight Unitary
Development (UDP), but is not allocated for any specific purpose.
The following policies
are considered relevant to the determination of this application:
S1 - New developments
will be concentrated within existing urban areas.
G1 – Development
Envelopes for Towns and Villages
G4 – General Locational
Criteria of Development
G10–Potential Conflict
between proposed development and existing surrounding uses.
D1 – Standards of Design
D2 - Standards for
development within the site
E3 – Resist the
development of allocated employment land for other uses
TR7 – Highway
Considerations for New Development
TR9 - Encourage the provision of improved transport
facilities
TR10 – Cross Solent ferry
Links
TR11 – Traffic Management
Schemes for ferry terminals
P1 - Pollution and Development
U11 - Infrastructure and Services Provision
CONSULTEE RESPONSES
Highway Engineer
recommends conditional approval.
Environment Agency raise
no objection subject to a condition in respect of site drainage in order to prevent
pollution of water environment.
Environment Agency were considering the details of the drainage scheme
and interceptors at time of writing this report. Comments will be reported at Committee if received, otherwise can
be controlled by way of condition and discharged as appropriate.
PARISH/TOWN COUNCIL
COMMENTS
East Cowes Town Council raise no objection but ask for the following points to be taken into consideration:
·
Lorries driving down Well Road on the way to the trailer park will have
difficulties turning around the flower bed situated at the bottom of Well Road.
If the application is approved then the Town Council has no objection if the
flower bed is removed to ease the turning circle.
·
It is strongly recommended that notices be placed directing lorries to
the trailer/night park by the agreed route.
THIRD PARTY
REPRESENTATIONS
Isle of Wight Society
makes the following observations:
·
Question whether the proposed underground works would interfere with a
Southern Water pipeline that was laid a few years ago.
·
Proposed 1.8 metre high fence and gates would be unsightly.
·
Question whether existing stretch of planting along the highway boundary
would be retained.
Seventeen letters received, of which 15 are in the standard format from different residents, expressing concern in respect of the following:
·
No information given as to length of time that temporary lorry park
would be required.
·
Insufficient information in terms of how site would be accessed.
·
Concern that right hand turn from Well Road into Castle Street is not
possible for an articulated lorry owing to brick roundabout, therefore meaning
that lorries would travel via lower York Avenue, Ferry Road and Phoenix Yard
and potentially disturb local residents.
·
Visual impact, being just as ugly as the redundant industrial buildings.
One letter submitted
drawing attention to hazardous processes and activities that took place from
buildings to be demolished.
One letter received expressing
support on grounds that proposed site constitutes the most sensible location
and is an appropriate use of this redundant industrial site.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
The need for trailer
parking facilities is well documented and has arisen through a combination of
an increase in commercial flows to and from the Island, changes to operational
practices that improve the efficiency of ferry operations and planning
restrictions that prevent the use of the existing marshalling yards for trailer
storage. Red Funnel has been using the Columbine slipway over the past 18
months as part of its new arrangement to improve the efficiency of its freight
handling operations. Columbine was an ideal short term solution owing to its
proximity to the ferry terminal but no longer suitable owing to structural
defects to the slipway and re-occupation of building. The application site,
being some 150 metres from the ferry terminal, has therefore been identified as
an interim solution pending the outcome of major regeneration proposals for
East Cowes.
Determining factors in
respect of this proposal relate to policy, highway implications and potential
disturbance to local residents.
Although not allocated
for any specific purpose, site does form part of the industrial centre of East
Cowes and has been used as such for many years. As proposed trailer park is not
considered to be an employment use in the recognised sense, Policy E3 of the
UDP is considered relevant. This policy aims to resist development of
employment land/buildings for other uses unrelated to employment, but does list
five exceptions to this. Once such exception is where there is an identified
need for the proposed use and no other suitable site is available.
The need for a trailer
park is proven and is considered essential in order to effectively manage
commercial traffic flows to and from the Island. The site is also considered to
be in a suitable and sustainable location, being a short distance from the
ferry terminal and within a recognised commercial area. There are certainly no
better sites currently available. I am therefore satisfied that proposal would
comply with recognised exception to Policy E3. Also, bearing in mind the
identified need for a trailer park together with nature of surrounding area, it
is considered that proposal is well sited to help address the traffic and
marshalling problems associated with the Island’s cross Solent ferry terminals
and therefore accords with the intentions of Policy TR11.
Policy TR10 specifically
refers to cross Solent ferry links and states that associated developments will
be approved where adequate access can be achieved to the existing transport
network. Policy TR7 is also relevant in this respect. The highway implications
associated with this development are of concern to local residents. In
particular, whether the trailers are capable of negotiating the roundabout
junction at Well Road, Dover Road and Castle Street, potentially resulting in
HGVs using residential streets of East Cowes if turning circle at roundabout is
too tight. In this respect, agent has submitted vehicle sweep diagrams showing
that HGV's could negotiate this roundabout in one motion regardless of which
direction they are travelling from. This information has been closely examined
by the Highway Engineer who is satisfied that the submitted diagrams are an
accurate representation and confirms that this roundabout could be used without
causing a hazard or obstruction to other highway users. As such, there is no
reason to believe that vehicles would have to travel via lower York Avenue,
Ferry Road and the Phoenix Yard which, in any event, would provide a far less
efficient route than Well Road. Also,
Phoenix Yard is subject of a condition restricting use by commercial vehicles
to between hours of 0800 and 2100.
Accordingly, proposal accords with Policies TR7 and TR10 of the UDP.
In terms of visual
impact, whilst proposed 1.8 metre high enclosure is not ideal, it must be borne
in mind that area is industrial in character with buildings of little
aesthetical value and that proposal is for a temporary period of five years, at
which time the future of this site as part of major regeneration proposals will
be more certain.
Regarding drainage
implications, surface water run off is unlikely to intensify bearing in mind
that much of the site is currently hard surfaced. Environment Agency has been consulted and raise no objection
subject to a condition in respect of site drainage, in order to ensure that
appropriate connections are made to oil interceptors. The Agency were considering a drainage scheme at the time of
preparing this report. In the event
that the proposed scheme has not been agreed before Committee consideration,
then an appropriate condition would suffice to ensure that drainage scheme is
accepted prior to work commencing.
Concern has been expressed regarding difficulties that Southern Water
may have encountered a few years ago whilst laying a new pipeline immediately
outside of site. This concern should
have no bearing on the outcome of this application, but I do recommend that a
covering letter be issued with the decision notice drawing this concern to the
attention of the developer. Taking the above points into consideration, it is
considered that proposal accords with Policy U11.
To summarise, the need
for a trailer park is proven and the proposed temporary site is considered to
be suitable both from a highways and general amenity point of view. Accordingly,
proposal accords with Development Plan Policy.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy) and Article 1 of the First Protocol
(Right to Peaceful Enjoyment of Possessions) of the European Convention on
Human Rights. The impacts this development might have on the owners/occupiers
of other property in the area and other third parties have been carefully
considered. Whilst there may be some interference with the rights of these
people this has to be balanced with the rights of the applicant to develop the
land in the manner proposed. Insofar as there is an interference with the
rights of others it is considered necessary for the protection of the rights
and freedom of the applicant. It is also considered that such action is
proportional to the legitimate aim of the Council’s Unitary Development Plan
and in the public interest.
JUSTIFICATION FOR
DECISION
Having given due regard
an appropriate weight to all material considerations referred to in this
report, I consider that the proposal is essential to help address the traffic
and marshalling problems associated with cross Solent ferry terminals and that
the proposed site is most suitable to serve this purpose. Accordingly, proposal
accords with policies contained within the UDP.
RECOMMENDATION 1 - Approval
Conditions/Reasons:
1 |
Time limit - full -
A10 |
2 |
No development shall take
place until details have been submitted to and approved in writing by the
Local Planning Authority of the positions, design, materials and type of
boundary treatment to be erected. The boundary treatment shall be completed
before the use hereby permitted is brought into use. Development shall be carried out in
accordance with the approved details. Reason: In the interests of maintaining the
amenity value of the area and to comply with policy D1 (Standards of Design)
of the IW Unitary Development Plan. |
3 |
Development shall not
begin until details of the design, surfacing and construction of any new
roads, footways, accesses and HGV parking areas, together with details of the
means of disposal of surface water drainage therefrom have been submitted to
and approved in writing by the Local Planning Authority. Development shall be
carried out in accordance with the approved details. Reason: To ensure an adequate standard of highway
access and drainage for the proposed dwellings and to comply with policy TR7
(Highway Considerations) of the IW Unitary Development Plan. |
4 |
The temporary trailer
park shall not be occupied until the means of vehicular access thereto has
been constructed in accordance with the approved plans. Reason: To ensure adequate access to the proposed
development and to comply with policy D1 (Standards of Design) of the IW
Unitary Development Plan. |
5 |
The use hereby permitted
shall not commence until space has been laid out within the site and drained
and surfaced in accordance with drawing number 14926/100/006, 005 and SD228
for 13 HGVs to be parked and the vehicles to turn so that they may enter and
leave the site in a forward gear. The space shall not thereafter be used for
any purpose other than that approved in accordance with this condition. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
6 |
The trailer park hereby
approved shall only be used as a holding facility for trailers that are
associated with marshalling activities at Red Funnel Ferry terminal. Reason: This application has been approved on the
basis of an identified need and to comply with Policy E3 (a) of (Resist
development of allocated employment land for other uses) of the IOW Unitary
Development Plan. |
RECOMMENDATION 2 - That decision notice is accompanied by a
covering letter highlighting concerns raised in respect of difficulties
experienced by Southern Water.
18. |
TCP/26732 P/02570/04 Parish/Name: Cowes
Ward: Cowes Castle East Registration Date: 07/12/2004 -
Full Planning Permission Officer: Mrs. H. Byrne Tel: (01983) 823594 Applicant: Mr & Mrs Sandell Alterations; 1st floor extension
to provide additional living accommodation to include French doors with
railings (Revised Plans) Candleshoe Cottage, Church Road,
Cowes, Isle Of Wight, PO318HA |
REASON FOR COMMITTEE
CONSIDERATION
Report has been requested
by local member, Cllr M O Morgan Huws as he considers the proposed development conflicts
with the policies regarding scale and mass and that it represents
overdevelopment on the site.
PROCESSING INFORMATION
This is a minor
application, the processing of which will have taken 10 weeks to the date of
the committee meeting. The application has exceeded the prescribed 8 week
period for the determination of planning applications due to the need for
committee consideration.
LOCATION AND SITE
CHARACTERISTICS
Application relates to a
modest cottage occupying a small plot within the newly extended Cowes
Conservation Area. Properties in the immediate locality are in quite close
proximity to each other and mutual overlooking is in evidence. The flank and
rear wall of the cottage form the boundaries of the site, the remaining
boundaries are defined by a 1.8 metre high brick wall.
Immediate locality
consists mainly of modest Victorian dwellings in varying plot sizes.
The Property has
previously been extended at the side by means of a single storey flat roofed
extension. The application indicates that this flat roof has previously been
used as a roof terrace.
RELEVANT HISTORY
None
DETAILS OF APPLICATION
Original submission
included provision of a balcony at first floor level. However balcony has been omitted,
the first floor extension has also been reduced in size.
Consent is now sought for
alterations to the front elevation of the property to include the replacement
of patio doors with two sets of timber French doors, the insertion of a new
timber front door and replacement timber window. There will also be an
additional window at 1st floor level on this elevation as a result
of the proposed first floor extension, which will extend 3.3 metres out over
the existing flat roof extension, to include French doors in the east elevation
with railings across the opening. Consent is also sought to clad two elevations
of the building in ‘Eternit’ weatherboard.
DEVELOPMENT PLAN/POLICY
Site is located within
the development envelope and the recently extended Conservation Area. Relevant
Policies of the Unitary Development Plan are as follows:
S6 – All development will be expected to be of a
high standard of design
D1 – Standards of design
B6 – Protection and enhancement of conservation
areas
H7 - Extension and alteration of existing
properties
G4 - General locational criteria for development
B2 – Settings of listed buildings
C12 - Development
Affecting Trees and Woodland
CONSULTEE RESPONSES
Conservation Officer considers
proposal to have little or no impact on the character or appearance of the
conservation area and on that basis does not wish to comment further.
PARISH /TOWN COUNCIL
COMMENTS
Cowes Town Council
objected to the original scheme on the grounds that the position of the
proposed balcony would be too intrusive and would affect the privacy of
neighbouring properties. No further comments in respect of the revised scheme
have been requested.
THIRD PARTY
REPRESENTATIONS
The application has
attracted eleven letters of objection from nine properties, the details of
which are summarised below:
·
Extension will affect view, light and privacy to neighbouring properties
and presents significant harm and intrusion, overbearing and causing loss of
amenity.
·
Impact on Conservation Area and adjacent Listed Buildings.
·
Balcony intrusive, loss of privacy, noise generation.
·
Inaccuracies in submitted details and plans, also relating to previous
use as balcony and adjacent trees.
·
Density of development is high, overdevelopment, out of character.
·
Concern regarding future arrangement of accommodation.
·
Impact on trees and lack of landscaping.
·
Proposed materials out of keeping.
CRIME AND DISORDER
IMPLICATIONS
No crime and disorder
implications are anticipated.
EVALUATION
Determining factors in
considering this application are the size, design and form of the proposal in
relation to the existing and surrounding properties, the impact on neighbouring
amenity, the impact on the character of the area and whether the proposal
maintains or enhances the character of the built environment and Conservation
area or affects the setting of the nearby Listed Buildings.
The property currently
has a large flat roof extension which is not in keeping with the existing style
of property. The proposal seeks to add a first floor extension extending 3.3
metres from the existing first floor over the existing flat roof and to clad
the building on two elevations with ‘Eternit’ weatherboard. There is a variety
of building materials and finishes in the area and therefore this material is
not considered to be out of keeping.
With regard to third
party comments relating to inaccuracies in the submitted details, the
application has been assessed on merit, taking into account site
characteristics. Furthermore, it is not anticipated that the trees in the
adjacent garden will be adversely affected.
Concern regarding future
arrangement of internal accommodation cannot be reasonably enforced by planning
condition.
The revised first floor
extension will respect the visual integrity of the host building and the
provision of inward opening French doors with railings across the opening and
reduced glazing, minimises the potential for overlooking and loss of
privacy. The scale of the proposal is
acceptable in relation to the original dwelling and presents no adverse impact
on the designated Conservation Area or nearby Listed Buildings. I am satisfied
that the revised scheme has overcome the issues regarding loss of privacy and
dominance.
HUMAN RIGHTS
In coming to this
recommendation to grant planning permission consideration has been given to the
rights set out in Article 8 (Right to Privacy and Article 1 of the First
Protocol (Right to Peaceful Enjoyment of Possessions) of the European
Convention on Human Rights. The impacts
this development might have on the owners/occupiers of other properties in the
area and other third parties have been carefully considered. Whilst there may be some interference with
the rights of these people this has to be balanced with the rights of the
applicant to develop the land in the manner proposed. Insofar as there is an interference with the rights of others it
is considered necessary for the protection of the rights and freedom of the
applicant. It is also considered that such action is proportional to the
legitimate aim of the Council’s Unitary Development Plan and in the public
interest.
JUSTIFICATION FOR
RECOMMENDATION
Having given due regard
and appropriate weight to all material considerations referred to in this
report, I am satisfied that the revised proposal represents an acceptable form
of development having minimal impact on the neighbouring properties, street
scene and character of the area.
RECOMMENDATION – APPROVAL
Conditions/Reasons:
1 |
The development hereby
permitted shall be begun before the expiration of 5 years from the date of this permission. Reason: To comply with
section 91 of the Town and Country Planning Act 1990. |
2 |
The development hereby
permitted shall be constructed using only the materials, details of which are
shown on the approved plans or in accordance with details to be agreed in
writing with the Local Planning Authority. Reason: In the interests of the
amenities of the area and to comply with policy D1 (Standards of design) of
the Isle of Wight Unitary Development Plan |
3 |
The roof area adjacent
bedroom 1, as shown on the approved plans, shall not be used as a balcony,
roof garden or similar amenity area without the grant of further specific
permission from the Local Planning Authority. Reason: In the interests of
the amenities of the adjoining neighbours and to comply with policy D1
(Standards of design) of the Isle of Wight Unitary Development Plan. |
4 |
Notwithstanding the
provisions of the Town and Country Planning (General Permitted Development)
Order 1995 (or any order revoking and re-enacting that Order, with or without
modification), no windows/dormer windows (other than those expressly
authorised by this permission) shall be constructed in the south east
elevation of the property. Reason: In the interests of
the character and amenities of the area and to comply with policy D1
(Standards of Design) of the Isle of Wight Unitary Development plan. |
ANDREW
ASHCROFT
Head of Planning Services