ADDENDUM REPORT FOR CONSIDERATION BY DEVELOPMENT CONTROL COMMITTEE AT THEIR SITE VISIT 13 AUGUST 2004
TCP/10558T/P00713/04 |
RESIDENTIAL
DEVELOPMENT OF 29 HOUSES AND A BLOCK OF 4 FLATS; FORMATION OF VEHICULAR
ACCESS AND PARKING PROVISION (AORM), LAND ON CORNER OF HEATHFIELD ROAD AND
COLWELL ROAD, FRESHWATER |
Report required following list of concerns raised by
local Member which relate to the following:
1.
Explore
possibility of discharging drainage from the proposed development into
refurbished private foul sewer, which currently serves Heathfield Close
development.
2.
Assurance
that the new bus shelters are of a design which provide weather protection and
are lit at night.
3.
Introduction
of some mechanism to ensure site construction traffic does not use the vicinity
of Heathfield Close during construction works.
4.
Assurance
that traffic calming methods are introduced both in Heathfield Road and at the
junction of Colwell Road with Heathfield Road to reduce speeds of traffic when
entering from Colwell Road.
5.
30 mph speed
limit be re-sited further to the east to accommodate the repositioned bus stop.
6.
Assurances
that the substantial treed southern boundary is to be retained in the interests
of reducing overlooking.
7.
Re-consultation
with Education Department to establish their support for the contribution with
particular reference to pre-school provision at All Saints Primary School.
The issues will be addressed in order as follows:
1.
Further
consultation taken place with Southern Water who confirm that whilst they do adopt
private sewers their preferred option would always be that such sewers were
accessible via public highway or public open space to which vehicular access
would be possible at all times. In terms of the current situation the
applicants have employed the services of a professional drainage engineer and
the solutions being proposed are acceptable to Southern Water and the
Environment Agency and therefore the Planning Authority could not insist that
this development discharge drainage into a private sewer on the basis that this
may be a method to ensure that sewer is formally adopted. Certainly the failure
of the applicants to discharge their drainage into the private sewer could not
be sited as a reason to refuse the application which is the ultimate test. It
is also important to note that Southern Water have stated that “there are no
records of flooding from the sewer in the vicinity of this site.” It is
emphasized that the existing combined sewer in Colwell Road is being required
to accept additional foul drainage from 33 units with a surface water drainage
having been designed to be attenuated to ensure flows are set at a same level
as that which would be discharged from the virgin site.
The issue of any future adoption of the
private sewer which serves Heathfield Close is therefore outside the remit of
the current planning application and I can only suggest that residents of the
Close could make their own approach to Southern Water who no doubt would
consider it on its merits.
2.
Reference
made to suggested Condition 9 which seeks that “such bus stops shall be
constructed in accordance with detail to be submitted to and agreed by the
Local Planning Authority.” This condition could be reinforced to make specific
reference to the bus stops being suitably weatherproofed and lit.
3.
The issue of
control of site and construction traffic is a matter which cannot be dealt with
under the auspices of planning conditions or legal agreements. Reference is
made to Circular 11/95 (The use of conditions in Planning Permissions) which
specifically advises that conditions are not an appropriate means of
controlling the rights of passage over public highways with this being on the
grounds of difficulty to enforce. The document advises that it may be possible
to encourage drivers to follow preferred routes by posting site notices to that
effect or by requiring them to use a particular entrance to or exit from the
site. Only where it is absolutely essential to prevent traffic from using
particular routes could controls be introduce and this would need to be done
under the Road Traffic Regulations Act of 1984 not the planning legislation.
I suggest a letter be sent to the
applicant advising they ensure that both construction works and particularly
construction traffic is carefully managed to cause minimal disturbance to local
residents.
4.
Have carried
out further consultations with Highway Engineer (Keith Jolliffe) who would
support the introduction of traffic management proposal involving prioritized
works which would essentially introduce ‘Give Way’ signs which would give
preference to one direction of traffic over the other direction of traffic. A
system not dissimilar to that being used in Newchurch. This could be covered by
way of, either a condition or form part of the Section 106 Agreement.
With regard to re-engineering the junction
of Colwell Road and Heathfield Road by introducing a tighter radius the highway
engineer considers this would be inappropriate having and effect on the free
flow of traffic along Colwell Road. He would therefore not be in a position to
support such a proposal.
5.
Issue of
changes to the 30 mph speed limit would need to be dealt with under separate
procedures through the Highway Department.
6.
Reference is
made to Condition 10, which could be further reinforced to cover the specific
retention of the trees along the southern boundary. It is also important to
note that the submitted revised plan indicates trees to be retained along the
southern boundary. I am therefore satisfied that this issue is and can be covered
robustly.
7.
Further
consultation has taken place with the Education Department who I understand
could not justify and therefore could not support the obtaining of an education
contribution on the grounds of lack of provision. It is important to appreciate
financial contributions need to satisfy key tests to be sustainable. As the
Education Department is not indicating that this development will have an
impact on school capacity then there is no justified requirement to mitigate a
problem which has not been identified. The key tests are similar to those which
would apply to condition and therefore any such request for a financial
contribution would fail the two most important of those tests being “fairly and
reasonably related in scale and kind and directly related to the proposed
development’” In this case I can do no more than accept the advice obtained
from the Education Department and without their support it would be
unreasonable to apply such a requirement.
Education Officer considers it would be
difficult to justify requiring a contribution towards pre school provision at a
time when primary school roles are falling away. It is also suggested that as a
basic principle education contributions where appropriate should cover the
provision of education facilities for children of statutory school age.
Crime and Disorder
Implications
I am fully satisfied that had the relevant officer
considered a specific comment was necessary, he would have done so. The
relevant officer is given the opportunity to comment on all applications and
would have raised issues had he identified specific concerns. (Crime Prevention
Officer currently on leave).
In general terms the shared surface cul de sac
designs automatically provide good quality surveillance an important requirement
in the process of planning and crime. Also Plot 12 has been deliberately
arranged to overlook the footpath link to the proposed bus stop, which again
accords with crime prevention policy. Appropriately located street lighting
will also play a role in making these areas safe places to live with the
important aim to ensure that residents take ownership of the development as a
community.
Changes to Recommendation
Condition 9 to be amended with an additional sentence
as follows:
“Such bus stops shall be suitably weather
proofed and lit which shall be retained as such thereafter.”
Condition 10 to amended to include the following
sentence:
“Any such plan and particulars shall
ensure retention of trees along the southern boundary and where appropriate
along the western and northern boundaries where they abut Heathfield Road and
Colwell Road.”
No change in approval recommendation.
1.
Subject to a
Section 106 Agreement covering the provision of 7 on site affordable housing
units in line with Council’s policy H14, payment of £9,570 (33 x £290) towards
upgrading of local open space and recreational facilities, the funding of total
costs or the carrying out of works in relation to the provision of two pelican
crossings in Colwell Road, in positions to be agreed and the provision of
traffic management proposals involving prioritized works within Heathfield
Road, the setting up of a management company to ensure long term maintenance of
the drainage infrastructure proposals which serve plots 1 – 7 inclusive and 16
– 33 inclusive.
2.
That a
letter be sent to developers suggesting they ensure both construction works and
particularly construction traffic is carefully managed to cause minimal
disturbance to local residents.