Committee SOCIAL SERVICES, HOUSING AND BENEFITS
SELECT COMMITTEE
Date 6 JUNE 2002
Title SUPPORTING PEOPLE
IMPLEMENTATION PROGRAMME
REPORT OF THE STRATEGIC DIRECTOR OF SOCIAL SERVICES
AND HOUSING
1. SUMMARY
This report updates the Select
Committee of the implementation of the Supporting People Programme.
It provides an updated
Implementation Plan and Action plan and identifies the DTLR targets, which have
been met. It provides information on
the progress made on tackling the areas, which were been identified by the DTLR
following the January milestone report, as causing concern (i.e. Housing
Benefit and IT systems)
The report also advises members of
forthcoming issues e.g. charging for support services, which is recognised
nationally as being a contentious issue.
Members will have to approve the local charging policy in September.
2. BACKGROUND
On 6th March 2002 this
committee received my report, which outlined the Supporting People Programme
and raised the concerns of the DTLR regarding the implementation programme.
A further report was requested by
committee to advise members of the progress made and to respond to the areas in
the implementation programme where the DTLR have expressed concerns.
Following the results of the
January DTLR milestones and the visit from the SP Implementation team at the
DTLR, there have been numerous measures put in to place to ensure that the
implementation of the programme is carried out efficiently and effectively.
3. STRATEGIC
ISSUES
The Local Authority through the
Supporting People Team will be the key people driving forward the local
authority implementation strategy pre and post April 2003. They will: -
v
Take the active role in linking the Supporting People
strategy into other programmes and initiatives
v
Develop partnerships and enable the programme to be
developed in their own and neighbouring areas
v
Pull together the necessary information to allow the
Supporting People Programme to be maintained and expanded
v
Create, service and co-ordinate the Strategic Core Group and
Inclusive Forum
v
Write and lead the consultation, implementation and
monitoring processes of the Supporting People Strategy
v
Undertake the tendering, contracting, payments, monitoring
and review process for existing and future services
v
Provide the DTLR with required returns for funding both the
administrative structure and Supporting People services
v
Identify policy implications for Select Committee to
consider and recommend to cabinet
4. ISLE OF
WIGHT’S PERFORMANCE
The DTLR is monitoring the
performance of each 154 lead Councils in implementing this programme. Each Council is assessed against milestones
set by the DTLR every 3 months. In
October 2001 the Isle of Wight was assessed as having achieved only 59% of its
targets, this improved by January to 75%.
However, there was evidence
showing that we were struggling to maintain the required pace of
implementation. The DTLR identified the
completion of the map of all support services (supply mapping) and the
preparations required for implementing a new IT system to support the business
functions of Supporting People as being areas of specific concern.
A further report was requested by
select committee to set out our progress in these and other areas so that
elected members can monitor closely our performance.
Appendix 1
This shows a more robust project
plan (implementation phase).
Appendix 2
This is an action plan showing how
the key tasks will be achieved, the expected outcomes, any risk or
inter-dependency with other tasks, the responsible person/group and status.
The project plan and action plan
are working tools and are subject to constant review and change
Appendix 3
This is a local project
management tool and is the framework that the Supporting People Project
Manager uses in the day-to-day management of the programme. Strategic Core Group (SCG) milestone reports
are produced each 6 weeks and are a reporting tool for the SCG.
This is subject to regular review
and amendment.
5. KEY
TARGETS IDENTIFIED AS AREAS OF CONCERN BY DTLR
a. Supporting
People Information Technology (SPIT)
Action Point/Recommendation
arising from DTLR visit in Jan 02 |
Action Taken to date |
Tasks outstanding |
Establish appropriate ICT
governance and ownership with the authority |
David Price appointed as senior
supplier on SPIT Project Board.
Project board chaired by director of social services and housing and
David Martin appointed as SPIT Project Manager |
Formal sign off of start up
(1-2days) and Project initiation (1 – 2 weeks) |
Corporate representation on the
SP SCG should be established as a matter of urgency |
As above |
None |
IT resources from within
Corporate ICT function should be involved directly with SPIT to perform the
next level of analysis required to confirm the chosen solution and to ensure
that it fits appropriately with the authorities strategic direction |
Decision will be made by SPIT
project Manager with technical input from various ICT staff and approved by
project board |
Placing of order for SP stand
alone IT package |
As a matter of urgency the SPIT
project should be formally recorded and authorised within the Corporate IT
function as a priority project for the forthcoming year |
Formal documentation using
Prince2 methodology |
None |
Consideration should be made as
to how the resources required to define and deliver SPIT are obtained and
managed. Careful consideration should
be given to funding corporate ICT resources for this activity rather than
alternative routes |
Advantages of using corporate
ICT for these functions already decided |
ICT specialist staff need to be
given some idea of when and for how long they will be needed for |
The development estimate on
ACCISS system should be ratified, both in terms of the requirements currently
understood and the charging guidance |
SP system no longer dependent on
ACCISS |
None |
If a review of available SP
package solutions is to be undertaken then this should be led by corporate IT
with input from the SP team in terms of its system requirements |
Completed – Agreement to
purchase a stand-alone SP package. |
None |
b. Supply
Mapping
One of the
key tasks for SP teams is to compile a complete “map” of all support and care
services in their area. This is an
involved process as every service and/or scheme must be identified and visited
to ensure that their service/scheme are mapped. The supply mapping process goes behind the service and identifies
all current and future funding so that sufficient money will be made available
when the DTLR “size the SP pot” and to produce a needs analysis for the SP
strategy.
Action Point/Recommendation |
Action Taken to date |
Tasks outstanding |
Supply Mapping a little behind –
homeless provision and Abbeyfields schemes of particular concern |
Supply mapping almost complete. |
Some small registered care homes
(SRCH) unable to make the decision with regard to change of services until
they have received an inspection from NCSC.
Therefore, SP unable to map fully |
Project Plan needs to be more
robust |
More robust project and action
plans developed |
None |
Potential losses from HB may
lead to some pressure to reduce efforts to develop and improve support
services on the island |
Providers encouraged to revisit
support costs breakdowns. SS&H & health encouraged
to maximise HB by breaking down their current provision to determine THB
eligible elements |
SS&H to identify worker to
separate care and support and transfer to THB |
Shadow Strategy |
Consultation for 1st
draft of shadow strategy finished. 2nd draft available 6.6.02 |
None |
6. MILESTONES
The DTLR required a further
quarterly milestone report for 12.4.02.
This was completed and submitted to DTLR as requested. Appendix 4 is a
copy of the report received by DTLR in answer to the milestones.
The Isle of Wight received a score
of 92.42%
The DTLR stated that they no
longer have concerns regarding our programme for implementation.
7. FUTURE
DEVELOPMENTS
a. Charging
The Islands Supporting People
Commissioning Body (CB) – made up of commissioners from the 4 strategic
partners, shall determine a policy for charging SP service users and for
reducing or cancelling charges for those service users who may not have the
means to pay. This policy will need
member approval prior to being submitted to the DTLR.
Supporting People Grant will be
paid to local authorities by the DTLR net of an assumed charging income.
The CB’s policy on charging will
include
1. A
policy on exempting schemes from charging
2. A policy on reducing or
cancelling charges to service users in non-exempt schemes who may not have to
means to pay by the application of a means test (MT)
3. A policy for reviewing
the outcome of a MT following a request from a service user and for dealing
with complaints
The SP charging policy will comply
with the DoH Guidance on “Fairer Charges” which applies to day care, domestic
help, personal home care, and equipment and adaptations, with necessary
amendments.
8. SHADOW
STRATEGY
The Supporting People Shadow
Strategy is currently under consultation with service providers, service users
and service referrers. It will be
bought to this committee on 4th September for approval prior to
being submitted to the DTLR by the end of September.
9. FINANCIAL
IMPLECATIONS
After April 2003 the CB will have
to produce the 5-year plan, which will include the capital and revenue budgets
as well as funding details of Cross Authority Group Services. This will be co-ordinated and owned by the
Administering Authority (AA) and will need the approval of elected members.
The Local Authority will act as
the AA for the SP programme.
Primarily, the financial plan
seeks to address how the service delivery will be funded from the various
available sources of capital and revenue including the SP Grant.
All potential sources of funds for
revenue as well as capital are analysed and where necessary “in principle”
commitments are entered in to. The
primary focus is on services funded by SP Grants, but other revenue funding
streams will also frequently match this.
Capital budget identifies sources
and application of funds towards capital needs – new buildings and remodelling.
The development of new schemes is
funded mainly through Social Housing Grant (SHG) through the Housing
Corporation’s Approved Development programme (ADP) and local authority
SHG. Other sources of capital funds
include New Deal For Communities (NDC and Single Regeneration Budget (SRB)
Financial plans will be prepared
by the CB, the formal planning and ownership of the budget, and the programme
as a whole, rests with the AA who should be involved at every stage.
10. RECOMMENDATIONS
That the select committee
elect a Supporting People “Champion” to work with the Supporting People Team
That the Supporting People
Project Manager produces a draft charging policy for select committee in
September 2002
Contact Point : Yvonne May, 824278
C WADDICOR
Strategic
Director of Social Services and Housing
TASK |
STATUS |
START
DATE |
COMPLETION
DATE |
IMPLEMENTATION STAGE
|
|||||||||||||||||||||||||||||||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept 02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Task 1
Transitional Housing Benefit |
|||||||||||||||||||||||||||||||||||
Monitor take up of THBS |
ongoing |
1 April 02 |
30 Dec 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Liaise with Housing Benefits |
Ongoing (monthly) |
29 Jan 02 |
|
|
|
|
|
* |
|
* |
|
* |
|
* |
|
* |
|
* |
|
* |
|
* |
|
* |
|
* |
* |
* |
* |
* |
* |
* |
* |
||
Expand THBS |
Ongoing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Maintain THBs data using DWP
spreadsheet |
ongoing |
Nov 01 |
Feb 03 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 2 Strategy |
|||||||||||||||||||||||||||||||||||
Map links to all other
strategies and identify joint areas of working |
Ongoing |
|
13 April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Establish links with
commissioning managers in SSD |
Completed |
|
1 April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept
02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Establish links with
commissioning managers in Health |
Completed |
|
1 April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Establish links with
commissioning managers in Probation |
Completed |
|
1 April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Develop overall project Plan for
the implementation of SP |
Completed but ongoing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Visit existing schemes |
ongoing |
|
10 May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Review TOR for CSG & IF
following guidance |
|
1 Nov 01 |
30 Aprill 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Agree vision for shadow strategy |
|
Nov 01 |
30 April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Submit shadow strategy &
annual plan to DTLR |
|
|
mid Sept 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Produce options and strategies
for meeting need |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 3
Supply Mapping |
|||||||||||||||||||||||||||||||||||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept
02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Complete provider SP3 workshops |
Completed |
1 Feb 02 |
1 March 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
SP1 & 2 data migrated onto
SPINTLS |
Completed |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
SP3 provider visits |
ongoing |
1 mar 02 |
10 May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
SP3 fortnightly reports |
ongoing |
|
10 May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Identify service gaps |
|
1 Mar 02 |
10 .may 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Produce options and strategies
for meeting need |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 4
SPIT |
|||||||||||||||||||||||||||||||||||
Obtain agreement for preferred
option from CSG |
Completed |
|
6 Mar 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Appoint SPIT project Manager |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Agree Project Management
Arrangements |
|
6 March 02 |
30 May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept
02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Source the market |
ongoing |
6 Mar 02 |
14 April |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Supoplier approved by CSG |
|
|
17 April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Revise SPIT plan with risks & contingencies |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Commission software, hardware
and workstations |
|
|
29 May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Confirm integrity of data (FiDO,
SX3 etc) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
IT solution installed |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Commence testing |
|
Oct 02 |
Mar 03 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 5
Administration Arrangements |
|||||||||||||||||||||||||||||||||||
Agree administrative team
structure (staffing) |
|
|
Oct 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Agree location of Administration
team |
|
|
Nov 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept 02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Recruit and train additional
staff |
|
Nov 02 |
Feb 03 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Administration team trained and
in situ |
|
|
Mar 03 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 6 Shadow Strategy
|
|||||||||||||||||||||||||||||||||||
Produce Shadow Strategy &
annual plan |
|
|
1 June 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Consult and incorporate feedback |
|
June 02 |
Aug 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Obtain CSG approval |
|
|
21 Aug 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Obtain CB agreement |
|
Aug 02 |
Sept 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Submit to DTLR |
|
|
1 Sept 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 7 Cross Authority Arrangements
|
|||||||||||||||||||||||||||||||||||
Review TOR for CAG in light of
guidance |
Ongoing |
April 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Produce CA shadow strategy and
annual plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept
02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Complete service specifications
for all CA services |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Determine total funding amount
for interim CA contracts |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Agree 100% interim CA contracts
with providers |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 8
Interim Contracts |
|||||||||||||||||||||||||||||||||||
Identify existing systems |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Identify what is needed for SP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Consult with contracting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Agree key principles of contract |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Agree administrative and
staffing arrangements |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Develop appropriate systems |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept
02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Draw up interim contracts |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 9 Accreditation & Best Value
|
|||||||||||||||||||||||||||||||||||
Identify existing systems |
|
Mar 02 |
May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Plan how BV will take SP into
account services from April 02 |
|
May 02 |
Jul 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Produce scheme visit schedule |
Linked to SP3 data collection |
Feb 02 |
10 May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Undertake programme of scheme
visits |
Ongoing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 10 Payment & Financial Systems
|
|||||||||||||||||||||||||||||||||||
Determine internal financial
management systems |
|
April 02 |
June 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Develop systems and draw up
interim contracts |
|
May 02 |
June 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Identify services where clients
will be charged |
|
April 02 |
May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
4 Feb 02
|
18 Feb
02 |
4 Mar 02 |
18 Mar
02 |
1 April
02 |
15 April
02 |
29 April
02 |
13 May
02 |
27 May
02 |
10 June
02 |
24 June
02 |
15 Jul
02 |
29 Jul
02j |
12 Aug
02 |
26 Aug
02 |
9 Sept
02 |
23 Sept
02 |
14 Oct
02 |
28 Oct
02 |
11 Nov
02 |
25 Nov
02 |
9 Dec 02 |
23 Dec
02 |
6 Jan 03 |
20 Jan
03 |
3 Feb 03 |
17 Feb
03 |
3 Mar 03 |
17 Mar
03 |
31 Mar
03 |
||
Develop local charging policy |
|
April 02 |
May 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Obtain CB & CSG approval on
charging policy |
|
June 02 |
Jul 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Collect charging data |
|
Jul 02 |
Oct 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Migrate charging data |
|
Aug 02 |
Oct 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Review “pot” size with DTLE |
|
Dec 02 |
Feb 03 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Confirm contract value with
providers following agreement from DTLR |
|
Jan 03 |
Feb 03 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
PAY PROVIDERS |
SP day |
1 April |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Task 11 User Involvement
|
|||||||||||||||||||||||||||||||||||
Consult with users |
Ongoing |
Mar 02 |
Jul 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
1st meeting of user
consultation group |
|
Aug 02 |
Aug 02 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
Isle of Wight Supporting People Programme Action Plan
Major Task Heading |
Main Sub-Tasks |
Detail |
Expected Outcome(s) |
Risk and/or Interdependency |
Period |
Who is responsible ® Involved
(I) |
Status |
|
Start |
Finish |
|||||||
Task 1.
THB |
·
Monitor take up of THB ·
Liase with housing benefits ·
Expand THBS ·
Maintain THBS data using DWP spreadsheet |
·
Regular liaison meetings ·
Fortnightly reports ·
Appointment of additional project officer(s) with
specific task ·
All THBs claimants to be entered onto data
base/spreadsheet |
·
Full awareness of the take up of THB ·
Preparation for “Sunset” arrangements complete ·
In line with DTLR milestones |
·
Additional project officers not appointed ·
HB do not use DWP spreadsheet |
3/03 |
31/3/03 |
·
® HB & YM ·
(I) SP team |
On
target |
Task 2. Strategy |
·
Map links to all other strategies ·
Identify areas of joint working ·
Establish links with commissioning managers in SSD ·
Establish links with commissioning managers in
Probation ·
Establish links with commissioning managers in
Health ·
Develop overall project plan for SP implementation ·
Visit existing schemes/services ·
Review TOR for CSG & IF in light of guidance ·
Agree vision for shadow strategy ·
Submit shadow strategy & annual plan to DTLR ·
Produce options and strategies for meeting need |
·
Identify local strategies ·
Make links to ensure SP reflected ·
Maintain links and developments ·
Specific joint commissioning plans to be developed ·
Link in with SP3 data collection ·
Agree how and when to involve members ·
Produce shadow strategy and annual plan |
·
Vision on how SP will be implemented on Island ·
How SP will contribute to the delivery of other
local strategic priorities and needs ·
Set out how SP will consult, decide and move
forward with the work plan locally ·
Provide for the first annual plan |
·
Supply mapping not completed on target ·
Needs analysis incomplete ·
Consultation not completed on time |
3/02 3/02 April 02 June 02 |
4/02 End 3/02 Aug 02 Sept 02 Aug 02 |
® YM (I) SP team partners &
stakeholders ® YM ® YM ® CSG/YM ® YM ® YM |
Complete Ongoing Ongoing Complete Ongoing |
Task 3
Supply Mapping |
·
Provider awareness/training ·
SP1 & 2 data migrated onto SPINTLS ·
SP3 provider visits ·
SP3 data monitoring ·
Identify service gaps ·
Produce options and strategies for meeting need ·
Verify SP3 financial information |
·
Programme of provider workshops ·
SP3 fortnightly reports ·
Obtain SMHG, THBs IS and PAGS information to verify
provider info |
·
Stakeholders aware of SP (SP3) requirements ·
SPINTLS enabled ·
Collection and initial validation of data ·
Initial verification complete |
·
Reluctance by stakeholders to engage |
3/02 3/02 3/03 3/02 3/02 |
3/02 3/02 10/5 6/02 4/02 |
® YM (I) SP team (I) Stakeholders/providers |
Completed Completed Ongoing Ongoing Ongoing |
Task 4.
S.P.I.T. |
·
Obtain agreement on preferred IT option ·
Appoint SPIT manager ·
Agree project management arrangements ·
Source the market ·
Supplier approval ·
Revise SPIT plan ·
Commissioning process ·
Confirm integrity of data ·
IT solution installed ·
Commence IT testing |
·
CSG approval ·
Partnership with ICT ·
Obtain CSG approval ·
Software, hardware and workstations ·
Fido, SX3 and ACCISS ·
User testing |
·
Permission to source the market ·
IT project manager appointed ·
SPIT plan on target ·
IT solution commissioned and installed |
·
Unable to appoint ·
Unable to appoint SPIT project manager |
3/02 3/02 5/02 3/02 4/02 4/02 10/02 12/02 12/02 |
6/3/02 5/02 5/02 4/02 4/02 5/02 11/02 12/02 3/03 |
® SCG (I) YM (I) ICT dept ® CSG |
Completed |
Task 5.
Administration Arrangements |
·
Agree administrative arrangements ·
Administration team enabled |
·
Agree administrative team structure ·
Agree location of administration team ·
Recruit and train staff |
·
Supporting People administrative arrangements
prepared for 1/4/03 |
·
Difficulty in recruitment ·
Unable to secure premises ·
SPIT not on schedule |
11/02 3/03 |
12/02 |
® YM & SCG (I) SP team |
|
Task 6.
Shadow Strategy |
·
SCG agreement on shadow strategy and annual plan ·
Submit to DTLR |
·
Produce shadow strategy ·
Produce annual plan ·
Consultation with stakeholders, users and partners ·
Obtain CSG approval ·
Submit approved document to DTLR |
·
Shadow strategy and annual plan |
·
Supply mapping incomplete ·
Consultation “slippage” |
6/02 7/02 9/02 |
6/02 8/02 9/02 |
® CAG ® YM |
SP3 data collection ongoing |
Task 7.
Cross Authority Arrangements |
·
Review TOR ·
Produce CA strategy & annual plan ·
Determine funding ·
Agree CA contracts |
·
In light of guidance ·
Complete service specification of CA services ·
Determine total funding amount for interim contract
value ·
Agree 100% of interim contracts with CA providers ·
Verify information with Hsg Corp etc |
·
CA shadow strategy and annual plan ·
CA interim contracts prepared ·
Funding requirement identified |
·
Supply mapping inaccurate/incomplete |
3/02 6/02 7/02 |
4/02 8/02 9/02 |
® CAG ® SP team/contracts SSD |
TOR completed Other work ongoing |
|
Task 8. Interim Contracts |
·
Identify existing systems ·
Agree key principles of contract ·
Agree administrative process/arrangements ·
Develop systems |
·
Consultation with SSD contracting section |
·
Agreement on where contracting will sit and how
managed |
·
Supply mapping incomplete ·
Unable to recruit staff ·
IT systems not enabled |
3/02 5/02 5/02 6/02 |
4/02 6/02 6/02 8/02 |
® YM/SCG/SSD (contracts) (I) IF |
|
|
Task 9.
Accreditation & BV |
·
Identify existing systems ·
Integration of SP in BV process ·
Scheme visits |
·
Consult with BV review team ·
Plan schedule of scheme visits |
·
Accreditation and BVR prepared in readiness for
steady state |
·
Schedule of scheme & service reviews incomplete ·
Supply map incomplete ·
Staffing levels wrong |
4/02 6/02 1/03 |
6/02 3.03 3/03 |
® YM/ BV officer |
Partially completed |
|
Task 10. Payment & Financial Systems |
·
Identify internal management systems ·
Develop systems and draw up interim contracts ·
Identify services and clients who will be charged ·
Agree local charging policy ·
Review “pot” allocation with DTLR ·
Confirm contract value with providers ·
PAY PROVIDERS |
·
Identify existing methods of payment ·
Identify SP requirements ·
Develop appropriate payment policy/procedure ·
Consult and inform about new system ·
Set up payments for April 2003 ·
Identify services which will be charged ·
Obtain CSG approval on local charging policy ·
Collect charging data ·
Migrate charging data ·
Confirm contract value with providers following
agreement from DTLE |
·
System for paying providers ·
Local charging policy agreed ·
Local charging procedure developed and implemented ·
Charging data collated and migrated to SP systems ·
Contract value confirmed |
·
SP3 data inaccurate ·
Delay in charging guidance from DTLR ·
Slippage in charging consultation and/or approval ·
|
3/02 5/02 6/02 8/02 12/02 1/03 |
5/02 6/02 8/02 9/02 2/03 2/03 1.4.03 |
® YM/SCG/CB |
Completed Ongoing |
|
Task 11.
User Involvement |
·
Agree consultation framework ·
Incorporate into action plan |
·
Devise and obtain agreement on the local plan for
user involvement ·
Facilitate meetings |
·
User involvement strategy |
·
Delays in consultative process |
4/02 |
7/02 |
® YM/ Spteam |
Ongoing |
|
APPENDIX 3
28th May Milestone
Report
This is an
internal project management tool to monitor the implementation of the
Supporting People Programme.
A milestone
report will be produced for each strategic core group meeting so that progress
can be tracked.
The shading indicate
a “self assessment” of progress to date
Green Task on target, no problems
Amber Small element of concern
Red Concerns achieving task on time
Task No. |
Sub-task |
Detail |
Task Owner |
Target Date |
Status |
1 |
Expand THB |
Work with stakeholders to maximise
THB claims |
AA |
23.12.02 |
Ongoing but on target |
1 |
DWP database maintenance |
Maintain THBs data using DWP
database |
YM Hsg B |
31.3.03 |
Ongoing |
2 |
Produce options & strategies
for meeting need |
Link to SP3 data collected Produce 1st draft of
shadow strategy for consultation |
YM |
June 02 |
Started Completed |
2 |
Visit schemes |
Visit all existing schemes and
services to familiarise SP team with sector |
YM AA |
10.5.02 |
Completed |
2 |
Review TOR of SCG & IF |
Following October guidance a
review of the TOR is required and SCG roles identified |
YM |
29.4.02 |
Completed |
3 |
Provider SP3 awareness |
Series of seminars to advise
providers on the next stages of supply mapping and how to complete SP3 |
YM AA |
4.3.02 |
Completed |
3 |
SP3 data collection |
Visits to providers to complete
SP3 and accreditation documentation |
YM AA |
10.5.02 |
Completed |
3 |
SP3 reports |
SPINTLS generated reports to
monitor progress of data collection |
AA |
Fortnightly |
Enabled And ongoing |
3 |
Needs analysis |
Identification of service gaps
via SP3 data |
YM |
10.5.02 |
Ongoing |
4 |
SPIT project management
arrangements |
SCG to agree SPIT project
management arrangements |
YM JP SCG |
10.5.02 |
Completed – SCG agenda item for
approval |
4 |
Appoint SPIT technical manager |
In consultation/partnership with
IoW council ICT dept |
YM |
10.6.02 |
Completed ahead of schedule
(29.4.02) |
4 |
Revise SPIT plan |
Revise SPIT plan to take account
of new information – submit to DTLR |
JP YM |
29.4.02 |
Completed |
4 |
Confirm integrity of data |
Fido, SX3, ACCISS |
DM YM |
01.10.02 |
Ongoing |
6 |
Produce shadow strategy |
1st draft available
for consultation |
YM |
10.6.02 |
Completed ahead of schedule |
6 |
Shadow strategy consultation |
Distribute to service providers,
service users, commissioners, Inclusive Forum, needs groups. |
YM |
11.6.02 |
Completed ahead of schedule |
7 |
Review TOR for CAG |
Review TOR for CAG in light of
guidance. Guidance not yet published
– DTLR “slippage” |
YM CAG |
13.5.02 |
Completed |
7 |
Produce CA shadow strategy &
annual plan |
Identify CA services and include
in CA plan |
YM CAG |
23.9.02 |
Ongoing |
7 |
Complete service specification
for CA services |
CA interim contracts prepared |
YM |
14.10.02 |
Not yet started |
7 |
Determine CA funding |
Determine total funding for
interim contract value of CA services |
YM |
25.11.02 |
Not yet started |
8 |
Administrative & staffing
arrangements |
Agreement of administrative and
staffing arrangements for interim and steady state |
YM HB/DC |
27.5.02 |
Agreement not yet reached |
8 |
Identify existing systems |
Consult with SSD contracting |
YM |
1.4.02 |
Ongoing |
8 |
Identify SP requirements |
Examine and compare SSD
contracts with SP contract template |
YM Hbetts |
6.5.02 |
Started and ongoing |
8 |
Consult with contracting |
Refer to above |
YM HBetts |
31.3.03 |
Ongoing |
8 |
Develop appropriate systems |
Systems developed for production
of IC |
YM HB/DC |
15.7.02 |
Agreement not yet reached |
9 |
Identify existing systems |
Identify which providers are
already accredited with an approved organisation and which will need early
review |
YM |
10.5.02 |
Not yet completed |
9 |
Produce scheme visit schedule |
Produce a schedule of visits to
every service and scheme to determine priority for BV & SP review |
YM |
31.3.03 |
Not yet completed |
9 |
Undertake schedule of visits |
As above. NB – all providers will be
visited when collection SP3 and accreditation data (task3) |
YM AA |
31.3.03 |
Initial visits ongoing |
10 |
Determine internal financial
management systems |
Assurance that SP funding is
totally ring fenced and only SP authorised personnel can access |
YM Kerry H/DC |
27.5.02 |
Assurance not yet given |
10 |
Develop systems and draw up IC |
Develop policy & procedure
for all financial/payment transactions |
YM |
23.9.02 |
Ongoing |
10 |
Identify services for charging |
Identify all services where
charging is appropriate |
YM |
13.5.02 |
Final Charging guidance not yet
available |
10 |
Develop charging policy |
Using DTLR guidance develop a
LOCAL charging policy |
YM |
27.5.02 |
Final Charging guidance not yet
available |
10 |
SCG approval of charging policy |
Obtain CSG approval for charging
policy – agenda item at SCG meeting 10 July |
YM |
10.7.02 |
Final Charging guidance not yet
available Not yet started |
10 |
Identify CLIENTS for charging |
Identify which clients in a
service will be subject to charging |
YM |
01.10.02 |
Final Charging guidance not yet
available |
11 |
Consult with users |
Develop user
consultation/communication strategy |
YM |
29.7.02 |
Ongoing |
APPENDIX 4
Name of Authority: Isle
of Wight Council
Thank you for the return of your
April 2002 Milestones. We have now assessed the information provided and attach
the feedback on your return together with the points awarded. We hope that you
find the assessment useful – should you have any comments on this feedback,
please e-mail them to [email protected]
by 10th of May 2002.
Note that the total number of points for a section is not always equal to the sum of all points achievable for the questions within the section.
Comments
|
Score 28 or Over Excluding IT Scores Section C (IT
feedback will be sent out separately by CGEY) Following the submission of your
April Milestones it is evident that you are driving forward the SP programme
within your area and that you are achieving the milestones which have been
set by the DTLR. We feel confident that you will achieve readiness by 1st
April 2003 should you continue to maintain your current progress. |
APPENDIX 5
Glossary of terms
Glossary of terms |
|
|
|
Accreditation |
Formal way of confirming your
organisation meets the required standard |
Annual statement |
This is produced annually by the
CB for submission to the DTLR. It
contains the detail behind the shadow strategy/5 year strategy and
communicates variations since the strategy was first submitted |
BVR |
Best Value Review – these are
undertaken by LA’s to ensure that their services are the best value they can
possibly be – quality for money etc.
Supporting People BVR’s could be carried out at the programme level,
at the service level, cutting across all client groups or by way of any
appropriate variation |
Block Contracts |
The purchase of support services
for more than one person, usually in advance of the service being delivered |
Client group |
A classification applied to a
person according to their support needs.
A person may fall into a number of such classifications |
CB |
Commissioning Body – This is a
partnership of the LA, health and probation services. The CB may not be formally constituted but
will have terms of reference which defines its roles and responsibilities |
Cross Authority issues |
Matters relating to a service
that cross local authority boundaries, including assessing need and supply
for services strategic planning, funding, monitoring reviewing and
decision-making |
DTLR |
Department of Transport, Local
Government and the Regions – the governing body for the SP Programme |
DWP |
Department of Work &
Pensions – formally DSS. |
FSS |
Floating Support Scheme – a
support service which is not linked to a specific property but can be applied
in a range of situations/locations |
Himp |
Health Improvement Plans –
jointly developed by the health partnership |
Interim Contract |
Formal document between SP
programme and the provider to show what services are offered and to make sure
that the provider receives payment for the services they intend to deliver |
PCT |
Primary Care trust – formed from
the health authority on 1.4.2001 |
PI’s |
Performance indicators – these
are there measures by which service\e providers will be monitored |
PAGs |
Probation Accommodation Grants –
a grant by the home office to probation to fund accommodation and support for
ex-offenders |
Provider |
Organisation providing housing
related support services |
Scheme Review |
Scheme reviews are the mechanism
by which LA’s will manage the transition from existing service provision to
the new patterns of service delivery |
Shadow strategy |
This is produced in place of the
5 year strategy in the interim phase |
SMHG |
Supported Housing Management
Grant – money given by the housing corporation to housing associations to
develop schemes |
SP |
Supporting People |
Spot Contracts |
The purchasing of support
services for individuals, usually on an emergency basis |
Steady State |
This refers to the period when
all LA’s and service providers have been fully transitioned to the SP
Programme |
Sunset Day |
6.4.03 – the official day that
THBs will cease |
Supply Mapping |
The process by which information
on current service provision is captured |
SP day |
1.4.03 – the cut off point for a
number of activities which will kick start the SP programme |