PAPER C

 

 

                                                                                                                Purpose : for Decision

                        REPORT TO THE EXECUTIVE

 

Date :              4 JUNE 2003

 

Title :               WIGHT LEISURE EXTERNALISATION

                       

REPORT OF THE PORTFOLIO HOLDER FOR TOURISM AND LEISURE

IMPLEMENTATION DATE : 16 June 2003

 

SUMMARY/PURPOSE

 

1.                  To consider the future of the project to externalise Wight Leisure in the light of the recommendations made by Mr Tony Hall from the Institute of Public Finance, following his review of the process adopted in the project.

 

BACKGROUND

 

2.                  It is now 12 months since the Wight Leisure Best Value Review (BVR) was accepted by the Executive with a recommendation to transfer the services provided by the Council through Wight Leisure to a Not for Profit Distributing Organisation (NPDO).  This aspiration was first considered by the Council in 1997.

 

3.                  Given the amount of time having elapsed since the recommendation of the BVR was approved, it was thought prudent to ask an independent “third party” to review the process and provide guidance to the Council to enable it to make a judgement that the work completed to date provides a sound basis for externalisation.

 

4.                  Tony Hall from the Institute of Public Finance has now completed this work and delivered his final report to the Council.  The Executive Summary of the report is attached as annex 1 to this report.  The main recommendations of the report are:-

 

(a)               That the project in its present form should cease with immediate effect because:

 

·        The process has become flawed and a number of irregularities seriously impair its successful conclusion.

·        An evaluation of the WLL initial proposal would in normal prudent procurement conventions disqualify WLL on two key financial criteria:

·        No satisfactory evidence of fund raising capacity and funding (see

 

 

·        paragraph 4.3.7.7);

·        Financial robustness and financial management capacity as a new undertaking without apparent access to reserves in the short-term (see paragraph 4.3.7.8).

 

(b)               If the project is to restart then the Council must establish a new and robust project and project plan and project protocols to effect  a completion driven by a multi disciplinary Project Board.  This Board should be led by a Strategic Director.

 

(c)               Before the project recommences the Council should implement two further recommendations: -

 

(i)                 The Council should initiate an enquiry into the irregularities that have arisen during the course of the project

(ii)               A further review is essential to establish exactly why the and how the organisational deficiencies that have come to light during this review happened and to determine how to prevent them in the future.

 

5.                  In arriving at these recommendations Tony Hall made a comparison between the systems and processes adopted by the Council in the project and a model by which he felt the project may have been successfully concluded.  This model has been used successfully in similar projects elsewhere, although is not the only model that could be used.

 

6.                  The Council’s approach to the project has been based on advice received in 1998, and accepted by the then Policy Committee.  The approach has been modified and re-shaped with each subsequent decision taken in respect of the project.

 

7.                  Whilst both approaches have significant similarities, there are two crucial areas of difference:-

 

7.1      In Tony Hall’s view the Council should have prepared a specification setting out its expectations of the NPDO in “managing its leisure services”.  This would have allowed the NPDO to produce a business plan to match and be judged against the Council’s expectations rather than a plan which delivered the NPDO’s expectations first and the Council’s requirements second.

 

7.2             The board of the new NPDO, early on in the process, again in Tony Hall’s view, should have been established using the independent board members only.  This would have allowed those responsible for the running of the NPDO in the future to be involved in the decision-making processes that would shape its future.  This would have also ensured a greater clarity of client and contractor roles within the Council, and possibly improved the decision-making processes in these roles.  The board would have had a duty to challenge the business plan under development.

 

8.                  Should the Council choose to recommence the project, then the establishment of a Project Board would seem a sensible proposal to prevent any future organisational difficulties.  Such a board would own and direct the project on behalf of the Council, it would be an intelligent client processing and receiving advice from external advisors, receive progress reports from the Project Manager and ensure the appropriate dissemination of information across the Council.

 

9.                  Tony Hall’s recommendation is that the Project Board should be chaired by an Executive Director, the Strategic Director of Education and Community Development would be the most appropriate and comprise senior representation from the Council’s finance and legal departments and the Project Manager.  It is felt that it would also be beneficial to include a representative from the Property Services department and also the Leader, Deputy Leader and Portfolio Holder for Tourism and Leisure.  The Managing Director and senior officers of Wight Leisure will also need to attend the Board as necessary.

 

10.             The Project Board will ensure that appropriate protocols are agreed in order to ensure probity is ensured throughout the process.

 

11.             The Project Board will also ensure that any assumptions underlying both the decisions taken in the light of this report and decisions taken on previous occasions are challenged.

 

12.             The role of the Project Manager, in Tony Hall’s model for delivery is seen as pivotal to the success of the project.  The Project Manager will need to be the key point of contact between the Council and the NPDO.  All information passed between the two parties, including that provided by Wight Leisure – the Council department, should be via the Project Manager.  It would be appropriate for the Head of Community Development and Tourism to fulfil this role for the Council.

 

STRATEGIC CONTEXT

 

13.             One of the aspirations of the Community Strategy, under the theme of improving access to services and facilities, is to, “encourage physically and/or mentally stimulating activities as a route to staying healthy and a foundation for a full and active life”.

 

14.             The Council’s own key objective of improving health, housing and the quality of life for all identifies the promotion of healthy living as a being of particular importance and lists, “encouraging the uptake of physically and mentally  stimulating activities as a route to staying healthy and leading a full and active life” as a key priority.

 

15.             Working, “with the tourism industry to promote the Island as an all-year holiday destination, particularly seeking to develop sustainable tourism initiatives and improving standards of customer care in the industry”, is a particular priority for the Council within the context of its objective to encourage job creation and economic prosperity.  The development of the Island as one of the UK’s leading tourist and leisure destinations is also a relevant aspiration within this objective.

 

16.             Services provided by Wight Leisure and the areas for improvement identified in the Best Value Improvement Plan can be clearly seen to link with these themes, objectives and aspirations of the Community Strategy and the Corporate Plan.

 

CONSULTATION

 

17.             In completing his report for the Council, Tony Hall has interviewed a number of people connected with the project.  The list of interviewees is included in the Appendices to his report and is summarised below:-

 

                        Isle of Wight Council:

 

·        Head of Community Development and Tourism

·        Head of Legal and Democratic Services

·        Head of Property Services

·        Corporate Finance Manager

·        Managing Director of Wight Leisure

·        Finance and Administration Manager, Wight Leisure

 

                        Independent Advisers:

 

                        Representatives from:-

 

·        Leisure Partners

·        Leonie Cowen & Associates

·        PMP Consulting

 

                        Isle of Wight Economic Partnership

 

·        Partnership Development Manager

·        Area Regeneration Director

 

FINANCIAL/BUDGET IMPLICATIONS

 

18.             It is estimated that the externalisation of Wight Leisure to a NPDO would save in the order of £145,000 per annum.  This is almost all due to the NPDO being able to claim mandatory rate relief (at 80%) on the National Non-Domestic Rates of the Council owned premises it would utilise.  There is also a small VAT benefit included in this total “saved” amount.

 

19.             Previous discussions and resolutions have determined that this saving could be used to fund the best value improvement plan and continuous improvement in the services.  One area identified for improvement in the Best Value Review having been the fabric and structure of the Council’s leisure buildings.  The review identified three principal costs in this regard:-

                       

                        Essential Facility Works                      £898,000

                        Desirable Facility Works                     £417,000

                        Development Opportunities £3,900,000

 

The Council having allocated £351,000 towards these works from its anticipated capital receipts in 2002/03.

 

20.             The major financial criteria agreed for the transfer being that it should be at, “no additional cost to the Council”.  In his report, Tony Hall has suggested that the Council may wish to review this criteria in the context of its newly developed medium term financial plan. 

 

21.             The less tangible benefits of the externalisation have been previously identified as the ability of the NPDO to access funding streams for service development that are not available to the Council.  The ability of any NPDO to achieve this is largely dependent on the project in question and the funding streams approached.

 

22.             Since 1998 the Council has allocated through the Committee system a total of £70,000 to procure independent advice in respect of the externalisation.  The fact that such an amount has been allocated to the realisation of the project is indicative of the on/off nature of it across 3 successive Councils since 1996.

 

23.             The cost implications of restarting and then completing the project are not yet fully known and would need to be identified very early on by a newly formed project group.  The costs are also dependent on the scale of any newly proposed transfer.  It would seem that the costs will fall into 3 main areas;

 

·        Completion of legal documentation

·        Preparation of Council aspirations (specification)

·        Grant assistance to the new board of the NPDO for it to procure advice and respond to the Council’s aspirations

 

            This may come to in the order of £40,000 total, but this figure needs confirmation and would be reduced if the preparation of the Council’s aspirations could be achieved through an internal secondment.

 

24.             The Monitoring Officer and Chief Financial Officer intend to undertake a short investigation designed to establish:

 

·        The amount and legitimacy of spending on this project to date

·        Whether any recommendations can be made to the Council in relation to either the corporate or service specific management of the externalisation process.

 

LEGAL IMPLICATIONS

 

25.             In coming to a decision about the externalisation of Wight Leisure, Members must be assured that the decision is reasonable, discharges the fiduciary and best value duties of the Council and establishes a structure which will ensure the delivery of the strategic objectives of the Council over an extended period of time. Tony Hall’s brief was to provide a report that would set the context in which this decision could be considered. 

 

26.             The Council’s powers to proceed with the transfer of the services have been clearly set out in previous reports.  The core legislative provision empowering the transfer being Section 19(3) Local Government (Miscellaneous Provisions) Act 1976.  This is an especially narrow power and one which has been extensively litigated, therefore demanding that the Council is cautious in the actions taken to deliver the transfer.  The extent to which the Local Government Act 2000 supplements the s19 power remains to be tested in the courts.

 

OPTIONS

 

1.         Stop the project in its present form with immediate effect.

 

2.         Restart the project, using a revised process, to externalise Wight Leisure to a management developed NPDO.

 

3.         Restart the project using a revised process, looking first at various externalisation vehicles including a currently trading NPDO (via a tendering process) and other models previously discounted by the Best Value Review.

 

4.         Keep and continue to manage the services, “in-house” for a period of at least 2 years pending exploration of options for future service delivery.

 

5.         A Project Board, with terms of reference reflecting paragraphs 8 to 12 inclusive, as described in this report, be established to oversee the externalisation process in a new project.

 

6.               To endorse the actions of the Monitoring Officer and Chief Financial Officer (set out in paragraph 24).

 

EVALUATION/RISK MANAGEMENT

 

27.             If the project is allowed to continue in its current form then it is unlikely that the Council will be able to come to a reasonable decision that the work completed to date provides a sound basis for externalisation.

 

28.             Option 1 is consistent with the findings of the Best Value Review although it would be prudent for the Project Board to revisit these findings to confirm their relevance some 12 months after their publication, and also within the context of the Council’s medium term financial plan.

 

29.             One of the main concerns raised in the Audit Commission’s inspection of Wight Leisure was that the delivery of the Best Value improvement plan was reliant on the externalisation of Wight Leisure to an NPDO.  No other options considered in the Best Value Review were thought to have the same capacity to deliver as this one.  Any decision which therefore seeks to deviate from that model will need to be made in the context of the capacity to deliver the improvement plan.

 

30.             The extended time for which externalisation has been an aspiration of the Council has contributed to the staff of Wight Leisure feeling at the least unsettled and certainly frustrated.  A guaranteed period of reflection as set out in option 4 may serve to reinforce the Council’s commitment to ensuring the long term sustainability of Wight Leisure’s services and their consequent employment.  However, this would need to be set against the uncertainty of not knowing what would happen at the end of that period.

 

RECOMMENDATIONS

 

31.             That options 1, 2, 5 and 6 be adopted. 

 

BACKGROUND PAPERS

 

32.             Report by Tony Hall dated 23rd May 2003.

 

33.             Wight Leisure Best Value Review, May 2002.

 

34.             Audit Commission Inspection of Wight Leisure, October 2002.

 

Contact Point :           John Metcalfe / John Lawson

 

D PETTITT

Strategic Director

Education and Community Development

J FLEMMING

Portfolio Holder for

Tourism and Leisure

 

 


 

EXECUTIVE SUMMARY

Introduction

            Scope of the Review

                             To examine interfaces and communications channels with a view to recommending ways of overcoming impasses in negotiations, paying particular attention to:

                   Clarification regarding Westridge development capital funding;

                   The extent to which development costs are structured in accordance with Section 19 of Local Government (Miscellaneous Provisions) Act 1976;

                   To ascertain that there is common understanding of the business plan submitted on behalf of Wight Leisure Limited (WLL);

                   To resolve any remaining questions about the basis of proposed performance indicators in WLL business plan;

                   To resolve client/contractor relationships.

            Layout of Report

                             Section 2 deals in detail with both the terms of reference and approach to the review and includes a brief history of the Externalisation Project.

                             Section 3 considers the nature of the project and proposes a process and protocol that is known to have worked for other local authorities in the conduct of similar projects.

                             Section 4 provides an account of the findings of the review.

                             Section 5 details 16 conclusions that arise from the review.

 

 

Recommendations

            Externalisation Project

                             The project should cease with immediate effect for the following reasons:

                   The process has become flawed and a number of irregularities seriously impair its successful conclusion.

                   An evaluation of the WLL initial proposal would in normal prudent procurement conventions disqualify WLL on two key financial criteria:

·     No satisfactory evidence of fund raising capacity and funding (see paragraph 4.3.7.7);

·     Financial robustness and financial management capacity as a new undertaking without apparent access to reserves in the short-term (see paragraph 4.3.7.8).

                   If the Council is minded to re-start the project it must establish a prudent project plan and related protocols.  An outline model is given under Section 3 of the report. It is the view of the author that the project should not re-start before the corporate issues recommendations that follow have been implemented.

            Corporate Issues

                             The Council should initiate an enquiry into the irregularities that have arisen during the course of the Externalisation Project.

                              A further review is essential to establish exactly why and how the organisational deficiencies that have come to light during this review happened and to determine how to prevent them in the future.

 

Summary of Conclusions

1.3.1      The Externalisation Project is seriously flawed and compromised due to lack of effective process and protocol.

1.3.2      Recent corporate engagement in the project has been dysfunctional due to the lack of a Project Board to direct the project.

1.3.3      The dissemination and exchange of information within the Council is poor, and a review of strategies and processes should be undertaken as quickly as possible.

1.3.4      There are indications that expenditure may have been incurred for purposes which the Council has no powers to incur expenditure.

1.3.5      There has been no substantive commitment from Isle of Wight Economic Partnerships to allocate SRB funding to the Westridge project in its current form.