PAPER C1

                                                                                                                Purpose : for Decision

                        REPORT TO THE EXECUTIVE

 

Date :              3 DECEMBER 2003

 

Proforma :      TO CONSULT ON A POOLED BUDGET WITH THE PRIMARY CARE TRUST IN THE MANAGEMENT OF REIMBURSEMENT AROUND DELAYED DISCHARGES FROM HOSPITAL

 

REPORT OF THE PORTFOLIO HOLDER FOR SOCIAL SERVICES AND HOUSING

 

IMPLEMENTATION DATE : 1 APRIL 2004

SUMMARY/PURPOSE

 

1.                  Attached is a paper (App. 1) that sets out the proposed local process for implementing Reimbursement for Delayed Discharges on the Island.  This paper has already been considered and endorsed by the Primary Care Trust Executive Committee and considered by the Isle of Wight Healthcare NHS Trust Operational Board.

 

2.                  To agree a pooled budget for Reimbursement of Delayed Discharges and Intermediate Care between the Primary Care Trust and the Social Services and Housing Directorate is constructed using a Section 31 Agreement for a period of 3 years to take effect from April 2004.

 

3.                  To endorse the approach taken with the Free Nursing Care pooled arrangement s and support the extension of this for a further 3 years from April 2004, subject to a final evaluation.

 

BACKGROUND

 

4.                  The background to the Community Care Delayed Discharges Act is set out in sections 1 – 4 of Appendix 1.  The Act places new duties on local authorities to ensure patients in an acute hospital bed are discharged into the community within appropriate timescales or the local authority will be liable for reimbursement of care which would constitute a fine of £100 per day.

 

5.                  The objective of the new legislation is to encourage partnership working, and a proactive cross agency approach to the prevention of delays.  The proposed pooled budget would be a combined Primary Care Trust and Social Services & Housing Commissioning budget that will be used to target the causes of delays.

 

STRATEGIC CONTEXT


 

6.                  This is a national development which local authorities and health economies have to implement fully by January 2004.  The Directorate of Social Services and Housing has always worked closely with health partners to prevent delays and the development of Intermediate Care Services has featured in both Service Plans and Local Delivery Plans.  The partnership work which underpins the implementation of the new legislation is also recognised in the Statement of Intent and the endorsed action plan.

 

CONSULTATION

 

7.                  The Joint Protocol which supports the local implementation of the legislation is currently being consulted on.  The new legislation was consulted on nationally.

 

FINANCIAL/BUDGET IMPLICATIONS

 

8.                  The existing pooled budget for Free Nursing Care amounts to roughly £5.7m over a three year period. The new pooled budget would be set up using existing allocated resources between health and social care.  Liabilities for each organisation will be set out in a ‘Section 31’ partnership agreement that will need to be signed by each organisation. The details of the current budgetary allocation to the Social Services & Housing Directorate for reimbursement is approximated below.

           

Current Commitment

2004/5

2005/6

2006/7

 

 

 

 

Delayed Discharges

308K

225K

150K

Intermediate Care

300K

309K

318K

 

608K

534K

468K

 

These figures are provided as indicative amounts but are dependent upon grants and changes to legislation and government targets.

 

LEGAL IMPLICATIONS

 

9.                  The partnership agreement will be set up within Section 31 of the Health Act 1999 and the Partnership Regulations.

 

OPTIONS

 

10.             The Council has two options:

 

·                     To establish a pooled budget with the Primary Care Trust.

 

·                     To keep separate budgets for Reimbursement and Intermediate Care.

 

EVALUATION/RISK MANAGEMENT

 

11.               The aim of setting up a pooled budget with the Primary Care Trust is to ensure that the new funds allocated to the Local Authority can be used to invest in services to prevent delays rather than pay reimbursement.  By having a pooled budget, the Primary Care Trust will claim funding back from the Isle of Wight Healthcare NHS Trust if reimbursement should apply and put the funds back  into the pool.  The Primary Care Trust will be able to do this because it already pays for an average number of delays in the services it commissions.  By working together both organisations can maximise the benefits for service delivery.  If there is no pool of resources, additional delayed discharge funding is more likely to be used for the payment of reimbursement rather than used pro-actively to invest in services.  The management of risks will be via the partnership agreement.

 

 

RECOMMENDATIONS

 

12.             That the Executive agree a pooled budget for Reimbursement of Delayed Discharges and Intermediate Care between the Primary Care Trust and the Social Services and Housing Directorate is constructed using a Section 31 Agreement for a period of 3 years to take effect from April 2004.

 

13.             That the Executive endorse the approach taken with the Free Nursing Care pooled arrangement s and support the extension of this for a further 3 years from April 2004, subject to a final evaluation.

 

BACKGROUND PAPERS

 

 

14.             HSC 2003/009:LAC (2003)21: The Community Care (Delayed Discharges etc) Act 2003

Discharge from Hospital, pathway process & practice

            Health & Social Care Joint Unit & Change Agent Team 2003

Department of Health web site: http//www.doh.gov.uk/reimbursement/ddgrant.htm

 

ADDITIONAL INFORMATION

 

15.             Implementing Reimbursement for Delayed Discharges paper (Appendix 1)

 

 

Contact Point :           Gillian Baker, Deputy Director Of Commissioning & Partnerships

                                    Isle Of Wight Primary Care Trust & Social Services

                                    Tel: 01983 535 419

                                    Email: [email protected]

 

 

S WELLER

Head Of Adult Services

G KENDALL

Portfolio Holder for

Social Services and Housing

 

 


 

 

Appendix 1

Isle of Wight Primary Care Trust

Isle of Wight Directorate of Social Services

 

 

IMPLEMENTING REIMBURSEMENT FOR DELAYED DISCHARGES

NOVEMBER 2003

 

 

1.         Background

           

1.1  Proposals for Reimbursement for delayed discharges were made by the government following evidence presented at the National Beds Enquiry.  This showed that delays in discharge were usually the result of poor bed management, with lack of attention to discharge planning, and a failure of communication between health and social care systems.

 

1.2  The aim behind the Community Care (Delayed Discharges etc) Bill in April 2003 was to introduce a financial incentive to ensure patients receive the right level of care, in the right place, at the right time.  The government has concentrated on delays in transfer from acute care, however the aim is to extend to other parts of the system.

 

2.         The Objective of the New Legislation

 

·        To end widespread delays by 2004.

 

·        To encourage partnership working within the scope of the Health Act 1999.

 

·        To provide effective, timely, safe and appropriate transfer of patients our of acute hospital beds and promote the independence of older people in particular by creating incentives to discharge from the institutionalising effects of acute inpatient care.

 

·        To encourage a proactive approach to the prevention of delays.

 

·        To encourage cross agency and inter-disciplinary working in support of effective discharge in a whole systems approach.

 

3.         Requirements of the Act

 

3.1   The Delayed Discharges Act places new duties on both local authorities and NHS trusts in relation to discharge planning and community care arrangements.  These commenced on the 1st October 2003.

 

3.2   There is a specific duty on NHS trusts, to notify the relevant local authorities as soon as it becomes apparent that a patient receiving acute care may require community services upon discharge.  There are exemptions, these include patients receiving mental health care, learning disabilities services, rehabilitation, maternity services and GP led care.

 

3.3   From 1st October 2003, NHS trusts should be notifying the Social Services in accordance with jointly agreed operating procedures.  The necessary infrastructure should be in place in readiness for full implementation from January 2004.

 

3.4   Social Services departments have 3 working days to implement appropriate discharge following notification that the patient is medically fit and when the multidisciplinary team have determined the patient is safe for discharge.

 

3.5   Acute Trusts also need to notify Social Services of any changes in the patient’s readiness for discharge, such as deterioration in the patient’s condition.

 

3.6   Agreements between the PCT, Social Services and the IWHCT need to be in place before actual reimbursement takes place in January 2004.

 

4.         Funding Arrangements & Expenditure

 

4.1   £100 million of new funding is to be transferred from central NHS funds to local authorities in each full year of the scheme, to enable local authorities to tackle these delayed discharges.  This follows the distribution of £300 million building care capacity grant to local authorities in October 2001.

 

4.2 To further support this work, the Department of Health is launching the Access and Systems Capacity grant, this will provide a further £170 million to local authorities 2003/2004.  The national scale of charges has been agreed at £100 per day of delay.

 

4.3   Locally, £152,000 has been allocated to the Isle of Wight Social Services & Housing Directorate for the remainder of this financial year to support the introduction of the bill.  (This will be increased for the full year effect in 2004/05).

 

4.4  It should be noted, that there is no rigid guidance on the use of this funding.  However, there is an expectation that funding may be invested proactively to support arrangements that operationalise, the management/prevention of delayed discharges and also provide a reserve to cover the costs of reimbursement should these be incurred.

 

4.5  The Steering group has directed how the current budget should be spent and decisions have been taken to strengthen the infrastructure and support services to minimise probability of delays.

 

·        The Hospital Care Management Team will receive additional resources to ensure there are sufficient Care Managers to be allocated to wards in order to appropriately assess patients and put care packages together.

 

·        There will be a part time Finance Officer who will track all the notification process on behalf of both Health and Social Care.

 

·        Investment has gone into additional Nursing Home beds.

 

5.         Local Implementation of the New Arrangements

 

5.1   A cross agency Steering Group has been established, and two subgroups were formed.  One to deal with Finance and the other to develop policy and procedure.

 

5.2   A draft protocol has been produced and will be put into practice during November 2003 to test its effectiveness.  This protocol, which sets out organisational arrangements, roles and responsibilities, is for consultation. Comments should be given to Conal Grier c/o PCT at Whitecroft by the end of November 2003, ready for a final document to be produced in December 2003.

 

            In summary the protocol addresses the key requirements as set out below:

 

·        Accurate screening for discharge of all hospital admissions – both elective and emergency

 

·        Identification of high risk patients where there is a probability of delay to promote proactive discharge management

 

·        Systems through which to agree delays

 

·        Systems through which to manage reimbursement

           

5.3 The Steering group has had to consider and resolve a number of issues:

 

·        The IWHCT has counted rehabilitation beds within its stock of acute beds for the SITREP return.  Under the new legislation reimbursement only applies to delays from acute beds and rehabilitation beds are an exclusion from this.  SITREP returns will now only reflect delays from acute beds for reimbursement.  However data will continue to be collected on delays from all areas, and equal importance will be given to resolving delays from wherever they occur.

 

·        It is also recognised that following the local bed census, a reconfiguration and redesignation of beds within St Mary’s will take place in early 2004.  This will need to be reflected in the protocols and SITREP returns.

 

·        The philosophy behind the Delayed Discharges Bill is to encourage partnership working to prevent delays.  The focus of the new money is to use it for investment to prevent delays.  It is clear double funding of the acute sector should not occur and therefore PCT’s should amend Service Level Agreements.  This is currently being considered.  The PCT will use any funding reclaimed to be reinvested in services to prevent delays for 2003/04.

 

6.         Risk Analysis

 

6.1   Homecare - When the Steering Group started reviewing the implementation of the guidance in early summer, the main area of risk for delays was lack of nursing home capacity.  10 new beds in the nursing home sector, which have been developed through support of the Intermediate Care Capital Scheme, are currently available and have been block purchased between the PCT and Social Services.  However, recent exacerbation of the problems within the Homecare Market and shortage of carers is now a new real risk in supporting discharge.  Social Services have an action plan to address this and further investment to support this sector is required.

 

6.2  The Bed Census report has recently highlighted a significant number of patients who do not need to be in hospital and could be cared for in the community.  These are not people who are counting as delays in the SITREP returns as discharges dates have not been agreed.

 

6.3   Through the introduction of more effective discharge planning significantly more patients will be identified for earlier discharge, the full impact of this for Social Services has not been modelled.  Changes in current practice within the hospital will impact on Primary and Social Care, and new community beds and homecare support will be required.  The lead-time for developing additional support in the community should not be underestimated and bed closures at St Mary’s will need to be managed in tandem with development of community services.

 

7.         Proposed Way Forward

 

7.1  Pooled Budgets - The whole health and social economy has a vested interest in ensuring that the new funding available for reimbursement of delayed discharges is used effectively to prevent delays.

 

7.2   It is therefore proposed that a pooled budget is set up from April 2004.  This recommendation is in the action plan and timetable, which has been agreed by ISG as part of the statement of Intent.  The pooled budget would be a combined PCT and Social Services budget for both Intermediate Care and Delayed Discharges and would be used to commission Intermediate Care services and other services required to avoid delays.

 

7.3   The initial proposals for a pooled budget are that it should contain:

 

-         Funding for NHS Nursing Home beds

-         Funding for Independent Living Resource Centre beds

-         Funding for Intermediate Care Team

-         Funding for the Homecare Rapid Response Team

-         Funding allocated for Reimbursement of Delayed Discharges

-         Funding reclaimed by the PCT as a result of reimbursement to avoid double counting in the acute

 

The Joint Commissioning Team would manage the budget.

 

7.4   As with other pooled budgets, a partnership agreement would be drawn up between the PCT and Social Services and agreement will be reached on a tripartite basis to include the IWHCT on how the additional reimbursement funding for 2004/5 can be used most effectively to avoid delays.

 

7.5   Protocol - Following consultation on the Draft Joint Protocol, a new protocol will be drawn up and however it is envisaged that this will be a iterative process and continue to be developed.

 

7.6   Delayed Discharge Policy - The Delayed Discharge Policy is currently being amended to reflect the requirements of reimbursement.

 

7.7  Training and Awareness - Training Sessions for nursing staff will be available in November and a number of Awareness Sessions will be put on for both Health and Social Care Staff.  A wider stakeholder session will also be set up and discussions have already been held with interested groups such as Age Concern.

 

7.8  Media relations will be considered by the Steering Group and proposed press releases will be developed.

 

CONCLUSION & RECOMMENDATION

 

8.1       The Local Authority and Primary Care Trust are asked to approve the proposal to set up a pooled budget for commissioning Intermediate Care Services including Delayed Discharge funding.

 

8.2       Both organisations and the IWHCT are asked to consult on the draft protocol for agreement to be reached in December 2003, ready for full implementation January 2004.

 

 

 

Gillian Baker

October 2003