PAPER E1

 

                                                                                                              Purpose : For Decision

                        REPORT TO THE EXECUTIVE

 

Date :              3 NOVEMBER 2004

 

Title :               PROCUREMENT OF THE ISLE OF WIGHT SUPPORTING PEOPLE TEAM SUPPORTING PEOPLE INFORMATION TECHNOLOGY (SPIT) SYSTEM

                       

REPORT OF THE PORTFOLIO HOLDER FOR ADULT AND COMMUNITY SERVICES

 

IMPLEMENTATION DATE : 15 November 2004

 

 

SUMMARY/PURPOSE

 

1.                   In the light of the operational decision not to proceed with implementation of the current Supporting People IT System, to determine to purchase an alternative system and to waive Contract Standing Orders in order to do so.

 

BACKGROUND

 

2.                   The Supporting People IT system, supplied by OLM Ltd and called CareSupport, was implemented during Autumn 2002 and nominally went live on 1st April 2003, following completion of data migration from the interim SPLS (SPINTLS) system. However, the process of migrating data and configuring the OLM system did not achieve a functional system.  Although the system continued ‘live’ from that date, it was to all intents and purposes unusable and was therefore not handed over to the team as a fit for purpose system.

 

3.                   As the system was not considered operational SP team efforts were directed towards the launch of the Supporting People project whilst waiting for OLM to deliver a useable product.  An illustration of this is that it was incapable of producing any useful Reports. Use of the system was confined to entry of Client, Provider etc. details, as system output was extremely limited.

 

4.                   By autumn 2003 the system had fallen into disuse. SP Team members were unable to use it as a working tool and believed that the system was essentially dysfunctional.  Problems included inability to get output from the system, login problems, different versions of the application on different PC’s, and lack of DBA/Application admin resource.

 

5.                   A review of the project was carried out in December 2003, remedial work was carried out in spring 2004, and the system made useable as a data repository for SP clients, providers, contracts, etc by 1st April 2004.  The review process however highlighted the lack of any obvious business advantages to the team of using the system, particularly as the system is not capable of implementing the new (“Phase II”) requirements imposed nationally on SP teams by the Office of the Deputy Prime Minister.

 

6.                   A Supporting People Information Technology (SPIT) project board was initiated, chaired by the Head of Housing and Community Support Services, comprising representatives from the Supporting People Team, central IT, Social Services IT and Internal Audit.  Successive SPIT project boards (spring, summer 2004) identified the purchase of an alternative system for the SP team as the best way ahead.

 

7.                   There is clear evidence that OLM works best in environments where the Supporting People software is operated in conjunction with a main social care suite.  The Council has chosen instead to introduce SWIFT as the main Social Services software package.  The result is that OLM’s SP package in a stand-alone capacity is cumbersome, lacks flexibility and also lacks functionality.  The experience of this council is also mirrored in other authorities which have procured the stand alone SP package.  They too, have largely migrated to other suppliers.

 

8.                   Possible alternative systems to OLM have been evaluated.  Two, the SWIFT system (as currently being implemented by Social Services) and the SPOCC system, from Oxford Computer Consultants, were shortlisted. Social Services IT and the SP Team reviewed these systems and agree that the SPOCC system is the most suitable for the SP Team.

 

9.                   This position has been reached having had full regard to the current functionality offered by both SWIFT and SPOCC, a full financial appraisal and the views of the system users.  It also recognises that at present, the SPOCC system is best set up to be able to cope with imminent changes within the SP regime.

 

10.               Implementation has also been a significant factor, with SPOCC offering a much quicker implementation process.

 

11.               Appendix 1 is an assurance report endorsing the purchase of the SPOCC system as a result of the evaluation described above. Appendix 2 sets out the business case for the purchase of a Supporting People IT system.

 

12.               Clearly, the process of procuring a suitable system for SP has not been without problems.  There are lessons from which the Council can learn and benefit future procurement exercises.  It is therefore suggested that the Executive request that the Resources Select Committee add to their work program an enquiry into how the initial procurement failed to deliver it’s objectives, and to make recommendations to the Executive in relation to similar future procurements.

 

CONSULTATION PROCESS

 

14.       The Supporting People Steering Group, Supporting People IT Project Board and the SWIFT Project board have been kept fully informed of problems associated with implementation of the CareSupport System, the review process, and the proposal by the SP IT Project board to replace CareSupport with SPOCC.

  

STRATEGIC CONTEXT

 

15.             The Supporting People regime is a statutory requirement by central government. From its inception, the government, via the ODPM has set out a very prescriptive regime which it has required to be followed completely.  This includes methods of reporting and performance management.  Further detailed amendments to this regime are in the process of being introduced later in 2004 which demands the provision of information through an electronic system to a central data depository run by the ODPM.

 

16.             In reference to this, the ODPM have recently written to the council, indicating that our future administration grant may be threatened if we are unable to resolve the computer system in the near future.


 

CONSULTATION

 

17.       The Supporting People Steering Group, Supporting People IT Project Board and the SWIFT Project board have been kept fully informed of problems associated with implementation of the CareSupport System, the review process, and the proposal by the SP IT Project board to replace CareSupport with SPOCC.  IWC Audit have been fully involved in the review process.  A report from IWC Audit is appended.

 

FINANCIAL/ LEGAL, CRIME AND DISORDER IMPLICATIONS

 

17.             Cost of the proposed replacement system and exit from the existing contract can be met from existing budget reserved for implementation of an IT system for the SP team.  A fully costed business plan is attached to this report as Appendix 2.

 

19.             The implication for IWC’s Adult and Community Services Directorate and the Supporting People strategy is that an improved quality of service can be expected, government targets for provision of service performance indicators will be met, and government funding for IWC’s Supporting People initiative on the Isle of Wight will be secured.

 

LEGAL IMPLICATIONS

 

20.             It is expected that exit from the existing contract can be achieved by agreement with the current contractor and without financial penalty.

 

21.             The power to procure such an IT system is incidental to the primary functions of Supporting People. There is a statutory obligation to achieve and demonstrate best value, and a constitutional requirement for the Executive determine whether to waive Contract Standing Orders, on a recommendation from the directors Group.

 

OPTIONS

 

22.             In addition to the recommendations there are two options:

 

·        Continuing with the current ad hoc arrangements. This is not offered as a recommendation for the reasons set out in the business case at Appendix 2.

 

·        Delaying implementation of the system until a full procurement exercise has taken place. There is not an active market in the supply of suitable software solutions and the delay and cost of a competitive procurement exercise would not result in the purchase of a more cost effective system.

 

EVALUATION/RISK MANAGEMENT

 

23.             The Council has a responsibility to ensure best value in relationship to both resource expenditure and service delivery.  In this instance, there is clear evidence that a waiver of standing orders achieves both objectives.

 

24.             The need to implement an effective data management system is unquestionable.  Action will be taken by the ODPM if this is not in place quickly.  Following in-depth analysis by appropriate officers, it is clear that the OLM system originally commissioned does not deliver our requirements.  It is also clear, that of other systems on the market, the SPOCC system is currently best placed to offer the required functionality.

 

25.             There is a real danger that further delay in implementing a new system will result in short term impact, through the ODPM withdrawing money from the council on the basis that we are not delivering our agreed outcomes.  Of equal concern, there may be longer term damage when the Supporting People inspection is conducted in 2005.

 

RECOMMENDATIONS

 

It is recommended that the Executive:

 

1.      Waive Contract Standing Orders

 

2.      Authorise the Head of Housing and Community Services to negotiate the purchase of a Supporting People IT system from SPOCC

 

3.      Request the Resources Select Committee add to it’s work programme an enquiry into the initial procurement of the Supporting People IT System appears not to have delivered its objectives, and to make recommendations to the Executive in relation to similar future procurements.

BACKGROUND PAPERS

 

SPIT Project Board Business Case V3/5, SPIT Review Project – Product Completion (22/7/04)

 

 

APPENDICES ATTACHED

 

Appendix 1 Report by Ken May, IWC Audit, on SPIT Project Board recommendation to purchase SPOCC from OCC Ltd.

 

Appendix 2  SPIT Project Board Business Case V3/5, SPIT Review Project – Product Completion (22/7/04)

 

Contact Point :           Martyn Pearl, F 823061 e-mail [email protected]

           

 

 

 

MARTYN PEARL

Head of Housing and Community Services

GORDON KENDALL                                   Portfolio Holder for Adult and Community Services

 

 

 


Appendix 1

 

Assurance report on the decision to select the OCC Ltd system “SPOCC”

 

Introduction

 

This report was requested at the SPIT Review Project Board on 22nd July 2004 following the decision to select the SPOCC system from OCC Ltd.  This decision was the culmination of the review that was conducted to identify the most appropriate solution for the needs of the Supporting People team headed by Yvonne May.  The purpose of this report is to give assurance that the decision was properly made, supported by an adequate audit trail.

 

Conclusion

 

We conclude that the decision was properly made and that there is an appropriate audit trail to substantiate the process leading up to the decision to select the SPOCC system.  This is qualified only to the extent that a number of tasks remain outstanding, which are listed in the Board minutes for the meeting on 22nd July 2004, and these need to be completed satisfactorily.  This report does not endorse the product selected, the SPOCC system, it is only to be taken as assurance that the decision to select the product was properly made and evidenced.

 

The Key Factors

 

In arriving at the decision to select the SPOCC system the following key factors needed to be taken into account and duly considered:

 

q        In making this decision, the Board effectively made the decision to abandon the current OLM CareSupport system, recognising that this represents a significant sunk cost without material realised benefit

q        In selecting the SPOCC system, additional costs will be incurred to integrate the system with the new SWIFT system (in due course), costs that would not have been incurred if the SWIFT SP module had been selected

 

However, the key deciding factor was the “fitness for purpose” of the system and the ability of the users to realise the benefits of moving to a computerised system from the largely manual system that is currently in place.  The assessment of the functionality of the options presented showed that the SPOCC system is the better system from the users’ point of view (and to that extent, the customers’ also).  We conclude that the principal basis for the decision was sound

 

We conclude that the factors listed above, and a number of others, including, for example, the capacity of the SP Team to implement any of the solutions, were duly considered.

 

Appropriate consideration was given to the issue of “interoperability”.  Whilst there is no immediate need to interface the two systems, there will be a need in time.  The ability of the SPOCC and SWIFT systems to “talk” to each other was demonstrated to the satisfaction of the respective users and due consideration was given to the cost of the development of the interface (largely a SWIFT cost), particularly in light of the need to interface other systems with SWIFT in due course.

 

The key risks associated with each implementation option were identified and assessed together with the mitigation actions to manage the risk, with assigned responsibility.  Our recommendation, in the light of the decision, is to restate/refresh the risk register for the option selected and to ensure that the actions identified to manage the risks are built into the implementation plan.

 

For further information, please contact me on extn 3046.

 

Ken May

ICT Auditor