PAPER E
Purpose: for Decision
REPORT
TO THE EXECUTIVE
Date : 10 SEPTEMBER 2003
Title : PUBLIC CONVENIENCE CLEANSING
AND MINOR MAINTENANCE CONTRACT
REPORT OF THE PORTFOLIO HOLDER FOR SUSTAINABLE
DEVELOPMENT, ENVIRONMENT AND PLANNING POLICY
IMPLEMENTATION
DATE : 22 September 2003
1. To make a
decision in relation to the award of the Public Convenience Cleansing and Minor
Maintenance Contract.
2. The Council’s current Islandwide Public
Convenience Cleansing contract commenced in November 1998. The contract covers
the cleansing and minor maintenance of 77 public conveniences located
throughout the Island. The contract was awarded to Coastline Cleaning Company,
based on the most economically advantageous tender received. The contract
length was for five years with an ability written into the contract to extend
the term by up to one year. The contract is now in its fifth year and
terminates on 2nd November 2003. The option to extend by up to one
year was not taken up.
3. To allow a new contract to commence on 2nd
November 2003, procedures have been followed in accordance with the Council’s
‘Best Practice Guide to the Process of Contract Letting‘ and in particular the
European Union Procurement legislation. Tenders were invited from a select list
of 6 contractors who met Financial, Health and Safety and other criteria
following receipt of 8 expressions of interest questionnaires. Tenderers were
required to submit tenders for both a three and six-year term, with the potential
for a maximum of a three year extension. A total of 4 tenders were received for
which detailed tender analyses have been prepared. A précis is given below.
Contractor |
Tender Total - 3 Year Contract |
Tender Total -
6 year Contract |
Contractor A. |
278,327.03 |
263,282.03 |
Contractor B |
309,303.21 |
309,303.21 |
Contractor C |
354,297.11 |
354,297.11 |
Contractor D |
441,333.82 |
422,382.60 |
4. Each tenderer also provided the level of
resources to be deployed on the contract and which would form part of the
tender evaluation exercise. The following is a summary of the time and
operatives to be deployed on the contract for the various parts of the year
(Winter, Summer, Peak Summer):
Contractor |
Winter |
Summer |
Peak Summer |
Contractor A. |
1 Sup,5 F/T, 4 P/T 289 Hours P/W |
1 Sup, 5 F/T, 6 P/T 395 Hours P/W |
1 Sup,7 F/T 6 P/T 505 Hours P/W |
Contractor B |
2 Sup,5F/T 3 P/T 382 Hours PW |
2 Sup, 7 F/T 2 P/T 466 Hours PW |
2 Sup, 12 F/T 2 P/T 739 Hours PW |
Contractor C |
1 Sup,5 F/T 2 P/T 232 Hours PW |
1 Sup,7 F/T 3 P/T 340 Hours PW |
1 Sup,8 F/T 6 P/T 562 Hours PW |
Contractor D |
3 Sup,4 F/T 4 P/T 340 Hours PW |
3 Sup,9 F/T 4 P/T 589 Hours PW |
4 Sup,10 F/T 4 P/T 628 Hours PW |
5. The above times do not include for head
office time but do include for overtime and additional time to cover special
events that are specifically referred to in the new contract.
6. As stated
above, contractors were asked to provide alternative tenders for both a three
year and six year contract period. Although the service is predominantly labour
based this gave the opportunity for each Contractor to consider maximising
capital investment in plant and equipment to maintain a high level of service.
Only Contractors A & B have indicated that there would be a reduction in
the annual cost of the service if awarded a six year contract instead of a
three year contract at the outset.
Contractor A submitted the lowest tender for both contract periods
tendered.
The select
committee last received an update report from the task group on 26th
September 2002.
8. The work of the task group is ongoing and has
focused on various areas where there is clearly:
Ø Duplication of
facilities by geographical proximity
Ø Where toilets
could be offered to town or parish councils or other
authorised bodies
Ø Where it can be
demonstrated that facilities are underutilized
Ø Where toilets are
beyond economic upgrading or repair
Ø Where there are
specific concerns as to their long-term viability
Contractor |
Tender Total - 3 Year Contract |
Tender Total -
6 year Contract |
Contractor A |
290,327.03 |
275,282.03 |
11. The tenders
also include a contingency allowance of 2% of the tender total that provides
scope to vary the levels of service to be provided. In addition the new
contract allows for variations of 15% in either cost, number of public
conveniences cleansed, floor areas cleansed etc without the need to renegotiate
rates or the contract. This flexibility allows for the potential transfer /
closure programme of toilets currently envisaged.
12. As in the
previous contract, cleansing frequencies are based on winter, summer and peak
summer frequencies, with a number of public conveniences being closed during
the winter period. The frequencies are based on the ability to maintain a good
level of cleanliness. Additional cleansing is also provided for key events,
including Cowes Week. The contingency allowance does allow some flexibility to
carry out additional cleansing when required. Incorporated within the tender is
also a locking and unlocking service.
13.An assessment of delivery options was considered
prior to undertaking the procurement exercise. Given the existing stock of
public conveniences, the slow and phased programme of rationalisation and the
health and safety, crime and disorder and asset management consequences of
ceasing to maintain to at least minimum standards, ceasing maintenance was not
seriously considered.
14. As stated above, initiatives are under way to
find partners able to take on
responsibility for individual units. This will only represent a limited
and gradual diminishing of the burden that falls upon the local authority. This
trend is anticipated by building in variation to service volumes without
penalty.
15. In house provision was not pursued as an option.
Given the well established market for commercial provision of these services,
in house provision would have to be the result of a competitive process and it
is unlikely that an in house bid would be commercially competitive. In addition it was concluded that there are
avoidable significant risks involved with carrying out the service in house due
to the labour intensive nature. With respect to partnering, the Executive have
already taken a decision to pilot this approach initially in Schools
Maintenance and is not current policy to undertake partnering in this service
area until that pilot has been evaluated.
16. Although future consideration could be
made for aggregation with office and beach
cleaning, the timing of the letting of these contracts has not coincided, preventing
aggregation in this cycle.
17. Public
Convenience Cleansing is consistent with the strategic objectives contained
within the corporate plan and in particular: -
Improving health, housing and the quality of life.
Protecting the Islands natural environment.
In addition, other supplementary objectives are
addressed: -
Promoting
health and wellbeing.
Promoting
independence.
Social
inclusion.
Improving
access to services.
Targeting
greatest need.
A
responsive Council.
Raising
the image and profile of the Island.
18.
Extensive
consultation has been undertaken both through the Town and Parish Protocol, and
the Environment and Transport Select Committee Task group work in respect of
public convenience provision and cleansing standards. Consultation has also
taken place with disabled groups. This process is ongoing as part of the Task
Groups deliberations.
19.The current annual cost of the service included in
the budget for 2003 - 04 is £238,750. Inflation will raise this to
£244,750 in the budget for 2004 – 05. If the tendered specification service is
adopted and the contract awarded to Contractor A for an initial 6 year period,
as recommended, then the annual cost would increase to £263,282 and produce a
current annual budget deficit of £24,532. If the 9 public conveniences omitted
from the original tender are reinstated the annual cost of the service would
increase to £275,282.03, and produce a budget deficit of £36,532. If the
contract is awarded to Contractor A for an initial 3 year period for the
tendered specification the annual cost would increase to £278,327 producing a
budget deficit of £39,577. This deficit would increase to £51,577 if the 9 public conveniences omitted from the
original tender were reinstated.
20.
For both initial contract periods the stated sums will increase by the
Retail Price Index (RPI) on an annual
basis.
Items within the contract, which would significantly affect the tendered sum, are summarised below: £
Reduce the Summer cleansing frequency to same
as Winter 25,594
21. Without a locking/unlocking service
this will likely result in an increase in
vandalism and associated maintenance
costs. Previous experience has indicated that this is the case although cause
and effect are difficult to measure and
quantify.
1) To Award the contract to Contractor A for
all 77 public conveniences for: -
i) A three year term costing £ 290,327
ii) A six year term costing £ 275,282
Subject to additional funding being made
available corporately.
2) To close the 9 identified public conveniences
not included in the tender before 2nd November 2003 and award the
contract for 68 conveniences to Contractor A for:-
i) A three year contract
costing £ 278,327
ii) A six year contract
costing £ 263,282
Subject to additional funding being made
available corporately.
3) To reduce the level of cleaning to Winter
frequencies for the Summer period and to include the Peak Summer frequency
enhancements for all 77 public conveniences and award the contract to
Contractor A for:-
i) A three year contract
costing £ 250,718
ii) A six year contract
costing £ 237,176
Subject to additional funding being made
available corporately for 3(i).
4) To negotiate a
Service Level Agreement on the best possible terms with the shortlisted contractors
for a budgeted sum of £244,750 per annum for: -
i) A three year
period.
ii) A six year period.
5) To negotiate with the existing contractor to extend the current contract for a further 6 or12 months.
23.In
the current financial climate it is not viable to pursue an option with a cost
in excess of budgeted cost without identifying other services that can be cut
to accommodate the additional cost. The viable options are, therefore limited
to:
i.
3(ii) a six year contract with contractor as set out in option 3(ii)
ii.
negotiating a
service level to a fixed price, as in option 4, or
iii.
negotiating an extension to the existing contract to
allow for future levels to be clarified, and for service planning and budgeting
processes to be completed.
exercise that option.
RECOMMENDATIONS That the Head of
Engineering Services, in consultation with the Portfolio Holder, be given a
specific delegation to pursue and agree a contract under whichever of options
3 (ii), 4) ii), or 5, delivers as closely as possible the objectives of the
original specification. |
Specification and
invitation to tender
Tenders (exempt from disclosure
under paragraph 8 and 9 of schedule 12 Local Government Act 1972)
Contact
Point : Steve Boswell 01983 823732
email: [email protected]
STEVE
MATTHEWS Head
of Engineering Services |
T M BUTCHERSPortfolio Holder for Sustainable Development, Environment and Planning
Policy
|