PAPER B
Purpose : For
Decision
Committee :
EXECUTIVE
Date : 10 SEPTEMBER 2002
Title : RESPITE CARE HOME FOR CHILDREN
WITH A DISABILITY
1.
SUMMARY/PURPOSE
1.1 To update Members on the current position
with regard to this project and to seek agreement to proceed on the basis
outlined in the report.
2.
BACKGROUND
2.1 A report on this matter was presented to
the Executive on 23 April 2002.
Briefly, this project concerns the building of a new residential respite
care home for children with a disability to replace the current facility at
Cowes, which is owned and operated by the Isle of Wight Healthcare Trust.
2.2 Members will recall that considerable
work has been undertaken to a stage where Detailed Planning Permission and
Building Regulations Approval have been obtained. The scheme assumes the
involvement of a private sector partner in achieving the necessary capital
investment.
2.3 The 23 April report outlined an approach,
which Members endorsed, to deal with identified legal constraints under Section
22 of the Local Authorities (Capital Finance) Regulations 1997. Legal advice
indicated that certain conditions would need to be complied with in order to proceed:-
·
A development agreement incorporating a building contract, which
provides for repayment of costs over a specified period
·
A facilities management lease to a registered landlord, to maintain the
fabric and running of the building with a licence to an operator
·
A Contractual Agreement with an operator to provide the care service
2.4
Work has been undertaken in the intervening period to progress
matters:-
·
Preparatory legal work has been undertaken to develop the necessary
contract documentation, including a Building Contract; Lease to a Registered
Social Landlord and a License to allow the operation of a service.
·
Expressions of interest from Registered Social Landlords have been
invited. A qualifying submission has
been received from South Wight Housing Association and is currently the subject
of detailed discussion.
·
The Council’s consultants Drivers Jonas (Chartered Surveyors) have been
commissioned to assist with the marketing process and identification of
suitable
·
potential developers for this project.
Fees of £12,000 would become payable upon securing a suitable Developer
and these have been included in the estimated costs of the scheme.
·
Advice received has recommended that the marketing process be
undertaken in one operation commencing in mid-September.
·
A period of eight weeks would allow for detailed proposals to be
developed by prospective developers.
·
The aim would be to select and agree a contract with a developer by the
end of the year.
·
The Executive of the Isle of Wight Healthcare NHS Trust have been
briefed on progress and have confirmed the capital commitment to the project
arising from the proceeds of the current building.
·
Work is being undertaken to draft the necessary Service Level Agreement
for the provision of the service in the new building.
·
Plans and details of the scheme are available should Members request
them and will be displayed at the meeting.
3. FINANCIAL
IMPLICATIONS
3.1 The total cost of the scheme is now
estimated to be £1.33m and currently approved resources include:-
132,000 Isle of Wight Council, Capital
Programme
157,460 Social Services & Housing
2001/02 contribution
207,665 Social Services & Housing
2002/03 contribution
50,000 Education Directorate commitment
125,000 IW Healthcare Trust
Contribution from capital proceeds
£672,125
3.2 A capital finance bid under the Joint
Investment Plan for Learning Disability was submitted earlier this year
and the project has been successful in gaining a grant allocation of
£250,000. This will increase the
resources available or committed to £922,125.
The grant will assist in absorbing some of the anticipated increase in
development costs arising from the delays to the scheme. However, it may be prudent to assume that
any shortfall will continue to reflect rising costs. The final structure of the funding will be dependent on the
financial arrangements with the developer.
3.3 As part of the
process to seek a potential developer it will be necessary to indicate in the
draft contract potential options for structuring financial proposals. This
financial structuring will allow a developer to structure the cost to the
Council of paying back the outstanding costs of constructing the building over
the determined period of up to 20 years, with an initial capital payment. The outstanding payment for the
construction of the building would then be paid to the Developer by the Council
in phased payments over a set period of time.
4. RECOMMENDATIONS
4.1 The
Committee note the content of this report and endorse the continuation of the
process in accordance with Section 22 of the Local Authorities (Capital Finance)
Regulations.
4.2 Endorse
the proposal in terms of the procurement of a suitable Developer and the
proposed capital funding arrangement as outlined.
4.3 Agree
to receive a further report in November setting out the detailed contract
arrangements.
5. BACKGROUND PAPERS
Executive papers 18 January 2001
Social Services & Housing Select Committee 21 December 2000
The Local Authorities (Capital Finance) Regulations 1997
Contact Point : Jimmy Doyle,
( 520600
C WADDICOR Strategic Director Social Services and Housing |
R MAZILLIUS Portfolio Holder for Social Services and Housing |