    Capital Budgets/Payments:            
  Gross 2003-04 & 2004-05 2004-05 2004-05 2004-05 2004-05 2004-05 2004-05 2005-06
CAPITAL PROJECT SUMMARY Costs Earlier Original Revised Actual Commitment Variance Predicted Exp Outturn Var Estimate
  £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Major Schemes      
Military Road 4,013 3,920 0 93 123 10 -40 93 0 0
Ryde Interchange 5,560 0 0 95 1 0 94 95 0 5,465
Undercliff Drive 12,880 203 0 0 829 45 -874 900 -900 11,777
                     
Sub-total Major Schemes 22,453 4,123 0 188 953 55 -820 1,088 -900 17,242
       
Maintenance Schemes      
Strategic Corridors 2,111 2,092 0 19 1 18 0 19 0 0
Structural Maintenance of Principal Roads 1,270 24 1,600 1,246 556 409 281 1,046 200 200
Surfacing 82 81 0 1 1 0 0 1 0 0
Recycling 338 316 0 24 22 0 2 22 2 0
Bridge Structures, Assessment & Maintenance 1,920 500 1,340 1,420 313 121 986 720 700 700
Drainage Schemes 165 0 170 166 40 25 101 150 16 15
Capitalised Maintenance Schemes 1,061 833 0 228 195 0 33 228 0 0
Adverse Weather Works 1,477 542 260 932 105 630 197 800 132 135
                     
Sub-total Maintenance Schemes 8,424 4,388 3,370 4,036 1,233 1,203 1,600 2,986 1,050 1,050
       
Integrated Transport Schemes      
Newport Town Centre Traffic Management 560 533 0 26 4 23 -1 27 -1 0
Pedestrian & Footway Improvements 2,076 1246 560 833 264 207 362 600 233 230
Safe Routes to Schools 804 109 600 695 457 10 228 650 45 45
Safety Schemes 1,350 460 560 888 358 103 427 650 238 240
Cycleways 817 597 200 220 35 0 185 100 120 120
Public Transport Infrastructure 913 303 575 607 70 21 516 250 357 360
Traffic Calming/Speed Reduction 359 209 140 156 11 7 138 75 81 75
Walking Schemes 119 19 100 100 79 20 1 100 0 0
                     
Sub-total Integrated Transport Schemes 6,998 3,476 2,735 3,525 1,278 391 1,856 2,452 1,073 1,070
       
Other Highways Expenditure      
Ventnor Ground Investigation 577 303 0 275 39 0 236 39 236 235
Grant Funded Schemes 213 -94 0 307 325 2 -20 307 0 0
Advance Highways Design 60 5 150 55 5 0 50 55 0 0
Purchase of Vehicles 40 21 0 19 19 0 0 19 0 0
Residual Scheme Costs 241 165 50 61 73 2 -14 76 -15 0
Funding from Slippage 0 0 905 0 0 0 0 0 0 0
                     
Sub-total Other Highways Expenditure 1,131 400 1,105 717 461 4 252 496 221 235
                     
TOTAL 2004/05 HIGHWAYS PROGRAMME 39,006 12,387 7,210 8,466 3,925 1,653 2,888 7,022 1,444 19,597
     
Funding    
Supported Capital Expenditure - LTP   6,305  
2 Year SCA - Clay Shrinkage   688  
Resources Carried Forward From Previous Year   913    
Grant Funding   216  
Other Contributions   69  
SCA - Ground Investigation   275  
Capital Receipts                    
TOTAL FUNDING OF HIGHWAYS PROGRAMME       8,466            
 
Sustainable Development, Environment and Planning Policy Portfolio
       
    Capital Budget/Payments:    
  Gross 2003-04 & 2004-05 2004-05 2004-05 2004-05 2004-05 2004-05 2004-05 2005-06
CAPITAL PROJECT SUMMARY Costs Earlier Original Revised Actual Commitment Variance Predicted Exp Outturn Var Estimate
  £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Coast Protection      
Seaview Duver Road 3,944 3,738 206 206 75 5 126 206 0 0
Castle Haven 5,218 2,458 2,760 2,760 2,568 3 189 2,760 0 0
Strategic Monitoring Study 184 29 155 155 47 0 108 155 0 0
Other Minor Coastal Projects 103 0 0 103 163 0 -60 103 0 0
Coastal Emergency Works 200 0 100 100 59 0 41 100 0 100
                     
Sub-total Coast Protection 9,649 6,225 3,221 3,324 2,912 8 404 3,324 0 100
       
Waste Disposal      
Waste Disposal Projects 205 112 93 93 29 0 64 93 0 0
                     
Sub-total Waste Disposal 205 112 93 93 29 0 64 93 0 0
                     
TOTAL 2004/05 ENVIRONMENT PROGRAMME 9,854 6,337 3,314 3,417 2,941 8 468 3,417 0 100
     
     
Funding    
Supported Capital Expenditure             36  
SCE - Seaview Duver - 65% Grant             72  
SCE - Castle Haven - 75% Grant           690  
SCE - Strategic Monitoring           155  
Grant Funding         2,243  
Other Contributions             28  
SCA - Waste Disposal             93  
Capital Receipts           100  
                     
TOTAL FUNDING OF ENVIRONMENT PROGRAMME             3,417            
Major Variances Since the Previous Report
Supplementary Budget
Following representations to the Government Office for the South East by the Council's Coastal Manager, the Council has been awarded an additional £275,000 Supplementary Credit
Approval for investigatory work on the potential landslip problem at Ventnor. There is no time limit on when the SCA must be used.
Military Road Scheme
It is anticipated that the apparent overspend on the Military Road project will have been resolved prior to the year end by recovering the amount from the contractor in respect of works
which were not completed to the standard expected.
Ryde Interchange
Funding approval for the full scheme is contingent upon all relevant statutory procedures being completed and final approval by Ministers. In the interim it has been necessary to approve
a budget from available resources in advance of scheme approval in order to allow the project to progress to the planning stage. Currently it is anticipated that works on the project may
commence in the autumn of 2005. A retrospective adjustment will be sought to allow the preliminary costs incurred to be charged against the project budget, once approval is received.
Undercliff Drive
Funding approval for the full scheme is contingent upon all relevant statutory procedures being completed and final approval by Ministers. In the interim it has been necessary to approve
a budget from existing resources in advance of scheme approval in order to allow design works, site investigation and landslip monitoring works to proceed. The project is very near to
receiving planning approval and, subject to final discussions with English Nature, it may be possible to draw down £1.5 million to allow works to commence during March 2005. A
retrospective adjustment will be sought to allow the preliminary costs incurred to be charged against the project budget, once approval is received
Bridge Structures, Assessment and Maintenance
Approval of £750,000 was received for the Ryde St John's Road Bridge Strengthening scheme as part of the 2004-05 settlement. The main element of this project will now be carried out
during 2005-06, hence there is a need to carry forward sufficient budget to allow the project to proceed in that year.