Committee: ENVIRONMENT
AND TRANSPORT SELECT COMMITTEE
Date: 28
AUGUST 2002
Title: SERVICE
PLANS AND PERFORMANCE INDICATORS
REPORT OF
THE STRATEGIC DIRECTOR OF CORPORATE AND ENVIRONMENT SERVICES
SUMMARY / PURPOSE :
This report summarises information on the 2002/03 Service Plan for Engineering Services together with information and commentary on past performance in 2001/02.
Service Plans have been prepared to a standard format for all major service areas within the authority. The Plans contain a range of information including :
Following preparation of a
Corporate Plan (draft approved for consultation at Executive on July 2nd
2002), a revised Service Plan format is to be introduced for the next financial
year – this will ensure that service activities directly link to the approved
corporate goals.
The Council also collects a
diverse range of information regarding service performance through both
national and local Performance Indicators (PIs) which are published each year
in the Best Value Performance Plan (BVPP). In the 2001/02 BVPP, a “traffic light” system has been introduced to
classify PIs by the following categories :
Attached to this
report (Annex 1), members will find summary information for the following
service areas :
·
Road Safety
·
Development Control
·
Rights of Way
·
Highway Maintenance
·
Coastal Management
·
Traffic Management
·
Transportation
·
Street Lighting
·
Highway Design
·
Waste Disposal and Grounds
Maintenance
·
Car Parking
The information provided in Annex
1 includes :
Members should note the following
:
·
By giving priority to the
implementation of the Best Value Improvement Plan, this will allow the Engineering
Services Department to achieve a sustained improvement in service delivery.
·
The Improvement Plan will address
the following areas:-
1. Departmental role in the Corporate Plan.
2. Communications with Elected Members, Town and Parish Councils and the
public.
3. Implementation of Service Strategies.
4. Staff Development.
5. Performance Management.
6. Procurement.
·
Delivery of the Capital Programme
rates almost as high a priority as implementing the Best Value Improvement
Plan.
·
If the Capital Programme is not
delivered then future funding will be adversely affected.
·
Staff are the Department’s most
valuable asset and the importance of recruiting, training, maintaining and
developing its workforce is not underestimated. Although included in the Improvement Plan, the importance of
attaining “Investors in People” warrants the separate inclusion of this aim.
·
With the advent of E-government
the preparation of a departmental ICT Strategy is essential.
·
The “front line” staff provide
the face of the Council and it is recognised that customer focus improvements,
including training, should form part of the departmental aims for this year.
Members are invited to comment
upon the Service Plan. Areas for enquiry may include :
Also attached to
this report (Annex 2), are the Performance Indicators for the Select Committees
areas of responsibility. These have been categorised into the 4 “traffic light”
groupings described earlier.
The following comments should be
noted :
1.
Better than average and
improving
The excellent results for the Waste Management Indicators BV82a and 82b, along with BV91, endorse the fact that the Isle of Wight Council is a high achieving authority in the top 25% for recycling nationally. This is no doubt due to the innovative Integrated Waste Management Contract.
2.
Better than average but
worsening
The closure of the Resource Recovery Facility at Forest Road, Newport for improvement work, has reduced the percentage of waste producing power and increased the tonnage to landfill. This in turn has affected BV82a and 82b. Production at the plant is increasing and this should be reflected in the 2002/3 Indicators.
Nationally the quantity of household waste produced is rising by 3% and
BV84 mirrors this rise on the Island.
BV88, which relates to missed collections of household waste, is only
2.74 collections per 100,000 worse for 2001/02 than 2000/01 and this should
also be looked at in the context that the Isle of Wight Council has only
one-third of the missed collections experienced by the average Council.
Examining the Performance Indicators for highway maintenance and street
lighting the fact that BV93, 95 and 105 are being deleted for 2002/03 and that
BV96, 97 and 100 have been amended in the same year it is becoming very
difficult to obtain meaningful comparison figures.
A change in the method of calculating BV97, which relates to the
condition of non-principal roads, has led to the increase in the Indicator
value.
The speed of response to damaged roads and pavements within 24 hours
has risen from 88% in 1999/000 to 97.3% in 2000/01 and the drop to 97% in
2001/02 is statistically insignificant.
BV99c(i), 99c(ii) and 99d(ii), relating to numbers of road accident casualties,
have increased but with the small overall numbers involved they are not
statistically reliable. Notwithstanding
this fact the reduction of accidents rate a priority and a draft Road Safety
Plan is at present out to consultation.
3.
Worse than average but
improving
With an
annual increase in Landfill Tax and the Integrated Waste Management Contract
linked to RPI BV87 is rising. Mainland
authorities are also experiencing similar rises in the cost of waste disposal.
4.
Worse than average and
worsening
Since the statistics to calculate BV85 for 2001/02 are not yet available, it cannot be stated whether this cost of street cleansing Indicator is worsening. However with costs rising, as in BV87 above, it can be expected to increase.
BV86,
relating to the cost of waste collection, showed a downward trend between
1990/00 and 2000/01 and the figures for 2001/02 are awaited. However, increased Landfill Tax Charges will
no doubt put up costs for all authorities.
It is disappointing that road accident casualties are rising, as shown in BV99a(ii), 99b(ii) and 99d(i), but as previously mentioned the statistics must be treated with caution, due to the small sample. It is considered that the measures outlined in the draft Road Safety Plan, once implemented, will assist in reducing accidents.
There is no doubt that BV102 (local bus passenger journeys per year)
was affected by the reduction in tourists due to the foot and mouth
restrictions in 2001. A draft bus
strategy has been written with the intention of introducing measures to
increase bus usage.
The value of performance indicators is recognised as a means of identifying some importance aspects of our service delivery. At present the area of Highways and Transportation only utilises National Best Value Performance Indicators, but several of these have been deleted or amended, which makes comparisons year on year difficult. Also, there are no appropriate Indicators for parts of the service. Both the Car Parks and Coastal Management Sections use Local Best Value Performance Indicators and the Highways and Transportation Section is now moving in this direction.
Under the auspices of the County
Surveyors Society, the Highways and Transportation Departments of nine South
East Counties have joined together to form SECSIG (South East Counties Service
Improvement Group). Nine Theme Groups
have been set up to establish and exchange details of working methods and
processes along with agreeing Local Performance Indicators across a range of
activities. The original theme groups
consisted of:
(a)
Road Safety
(b)
Network Management
(c)
Maintenance
(d)
Parking
(e)
Highway Development Control
(f)
Waste Management
(g)
Sustainable Transport
(h)
Highway Construction Projects
(i)
Business Support
The Local Performance Indicators
set up and compared between authorities are shown in Annex 3 and the Isle of
Wight Council will be submitting their data for 2001/02 by the end of November.
This will allow comparison with the other members of SECSIG.
It is considered that both the
Sustainable Transport and Business Support Theme Groups have completed their
work and they are being replaced with the following Theme Groups:
(a)
Customer Focus and Performance Management.
(b)
Local Transport Plan.
The Customer Focus and Performance
Management Theme Group is to be led by the Isle of Wight Council and the first
meeting will be held on 11 September 2002.
Both these groups will introduce new Local Performance Indicators.
In conjunction with the County
Surveyors Society, the National Best Value Benchmarking Scheme has been set up.
At present this scheme covers a range
of Indicators related to highway maintenance (see Annex 4 for details). These are based on the requirement of the
“Delivering Best Value in Highway Maintenance Code of Practice”. The Isle of Wight Council has recently
joined this Group and once we submit our data, which we intend to do by
November 2002, charts will be made available highlighting our performance in
relation to other highway authorities nationally. As part of this scheme other modules, to cover strategic
planning, transportation, the environment and economic development are being
developed.
Building Software Limited have
also set up two Best Value Benchmarking Clubs one for “Highway Design” and one
for “Highway Works”. Several South and
South Western Counties are members of these.
The value of the Isle of Wight Council joining is at present being
appraised.
Even with the regional and
national initiatives mentioned above, it may still be necessary to develop
additional Local Performance Indicators in consultation with our
stakeholders. It is, however, essential
that we do not identify too many and inappropriate Indicators. Further work is therefore necessary, in
conjunction with our regional colleagues, to define our Performance
Indicators. A deadline has been set of
December 2002 so that the data feed can be started in March 2003 and the
indicators brought into use for 2003/2004.
None as a direct result of this
report.
That the Committee : 1.
Consider and comment
upon the Service Plan 2.
Consider and comment
upon the Performance Indicators for the service and identifies priority
areas for improvement
Best Value Performance Plan,
2001/02
Contact point : Malcolm Smith F 823777
M J A FISHER
Strategic Director of Corporate and Environment Services
ANNEX 1 : SERVICE PLAN
|
|
PERFORMANCE INDICATOR AND SOURCE |
PERFORMANCE |
BENCHMARKING |
|||
|
ACTUAL 01/02 |
TARGETS 02/03 |
OTHER TARGETS & DATES |
COMPARATIVE PERFORMANCE (DATE) |
SOURCE OF COMPARISON |
BV82a - Percentage total tonnage
of household waste arisings which have been recycled. |
21.97% |
23.3% |
|
10.0% (00/01) |
NUB Group |
BV82b - Percentage of total
tonnage of household waste arisings which have been composted. |
6.56% |
4.1% |
|
2.1% (00/01) |
NUB Group |
BV82c - Percentage of total
tonnage of household waste arisings which have been used to recover heat,
power and other energy sources. |
6.07% |
20.4% |
|
0.0% (00/01) |
NUB Group |
BV82d - Percentage of total
tonnage of household waste arisings which have been landfilled. |
64.5% |
52.1% |
|
87.5% (00/01) |
NUB Group |
BV84 - Kg of household waste collected
per person. |
559.03 |
518 |
|
550.5 (00/01) |
NUB Group |
BV85 - The cost per square
kilometre of keeping relevant land and relevant highways for which the
Authority is responsible clear of litter and refuse. |
To be confirmed |
Deletion 02/03 |
|
£55,805 (00/01) (Note: excludes area of beaches) |
NUB Group |
BV86 - The cost of waste
collection per head. |
To be confirmed. |
£38 |
|
£30.00 (00/01) |
NUB Group |
BV87 - Cost of waste disposal per
tonne for municipal waste. |
To be confirmed |
£42 |
|
£38.85 (00/01) |
NUB Group |
BV88 - Number of collections
missed per 100,000 collections of household waste. |
37.86 |
Deletion 02/03 |
|
£98.62 (00/01) |
NUB Group |
BV91 - BVPP Percentage of
population in the authority=s area which are served by kerbside collection of recyclable or
within 1 km radius of a recycling centre. |
90.66% |
Amended 02/03 |
|
8 87.3% (00/01) |
|
BV91 - BVPP from 02/03 Percentage
of population resident in the authority=s area served by a kerbside collection of recyclables |
Not yet in place. |
48.5% |
80% by 04/05 |
|
NUB Group |
BV93 - BVPP Cost of highway
maintenance per 100 km travelled by a vehicle on Principal roads. |
To be confirmed |
Deleted 02/03 |
|
£0.36 (00/01) |
NUB Group |
BV94 - BVPP Cost per passenger
journey of subsidised bus services. |
£0.40 |
Deleted 02/03 |
|
£0.88 (00/01) |
NUB Group |
BV95 - BVPP Average cost of a
working streetlight. |
To be confirmed. |
Deleted 02/03 |
|
|
NUB Group |
BV96 - Condition of Principal
roads. |
8.3 |
Amended 02/03 6.0 |
|
10.5 (00/01) |
NUB Group |
BV97 - BVPP Condition of
non-Principal roads |
4.2 |
Amended 02/03 |
|
10.2 (00/01) |
NUB Group |
BV99a(i) - BVPP Number of road
accidents casualties per 100,000 population. Pedestrians - killed/seriously
injured. |
12.36 |
17.82 |
|
12.185 (00/01) |
NUB Group |
BV99a(ii) - BVPP Number of road
accident casualties per 100,000 population.
Pedestrians - slight injuries. |
71.01 |
56.79 |
|
37.76 (00/01) |
NUB Group |
BV99b(i) - BVPP Number of road
accident casualties per 100,000 population.
Pedal cyclists - seriously injured/killed. |
3.09 |
12.31 |
|
6.46 (00/01) |
NUB Group |
BV99b(ii) - BVPP Number of road
accident casualties per 100,000 population.
Pedal cyclists - slight injuries. |
34.64 |
42.29 |
|
31.25 (00/01) |
NUB Group |
BV99c(i) - BVPP Number of road
accident casualties per 100,000 population.
2 wheeled motor vehicle users - seriously injured/killed. |
21.63 |
17.24 |
|
12.16 (00/01) |
NUB Group |
BV99c(ii) - BVPP Number of road
accident casualties per 100,000 population.
2 wheeled motor vehicle users - slight injuries. |
44.81 |
43.98 |
|
29.96 (00/01) |
NUB Group |
BV99d(i) - BVPP Number of road
accident casualties per 100,000 population.
Car users - seriously injured. |
52.53 |
36.66 |
|
33.27 (00/01) |
NUB Group |
BV99d(ii) - BVPP Number of road
accident casualties per 100,000 population.
Car users - slight injuries. |
279.65 |
268.69 |
|
268.13 (00/01) |
NUB Group |
BV99e(i) - BVPP Number of road
accident casualties per 100,000 population.
Other vehicle users - killed/seriously injured. |
3.94 |
4.2 |
|
4.96 (00/01) |
NUB Group |
BV99e(ii) - BVPP Number of road
accident casualties per 100,000 population.
Other vehicle users - slight
injuries. |
17.77 |
26.24 |
|
25.0 (00/01) |
NUB Group |
BV100 - BVPP Number of days
temporary traffic controls or road closure on traffic sensitive roads caused
by local authority roadworks per km of traffic sensitive roads. |
2.22 |
Amended 02/03 |
|
1.08 (00/01) |
NUB Group |
BV100a - BVPP from 02/03 Number
of days temporary traffic controls or road closures on traffic sensitive
roads caused by local authority roadworks per km of traffic sensitive roads. |
Not yet in place |
2.0 |
0.4 by 04/05 |
n/a |
|
BV100b - BVPP from 02/03 Number
of days temporary traffic control or road closure on traffic sensitive roads
caused by utilities roadworks per km of traffic sensitive roads. |
Not yet in place |
2.0 |
0.4 by 04/05 |
n/a |
|
BV102 - BVPP Local bus service
(passenger journeys per year). |
5.8m |
6.9 m |
7.1 m by 04/05 |
6.5m (00/01) |
NUB Group |
BV105 - BVPP Damage to roads and
pavements. |
97% |
Deleted 02/03 |
|
93% (00/01) |
NUB Group |
BV165 - BVPP Percentage of
pedestrian crossings with facilities for disabled people. |
96% |
Amended 02/03 94% |
97% by 04/05 |
n/a |
|
BV178 - BVPP The percentage of
total length of footpaths and other rights of way which were easy to use by
members of the public. |
94% |
95% |
95% by 04/05 |
n/a |
|
PERFORMANCE ACHIEVEMENTS
During last 12 months |
Achievements 1. Better information service to the public - web pages,
signs and roadworks notification cards to residents. 2. Improved public consultation. 3. Better response time to correspondence. 4. Increase in staffing resources. 5. Setting up of "Call Centre" to take all
incoming highway related telephone calls. 6. Performance management systems introduced including
letter tracking, contractor response time monitoring and check on follow-up
phone and letter responses. 7. Improved inspections and monitoring of statutory
undertakers - now generating more income. 8. Improved safety inspection regime - maintaining
frequencies. 9. Met the spend profile (Capital) maintenance schemes. 10. Completed CVI survey of all Principal and non-principal
roads, together with deflectograph survey of Principal roads. 11. Insurance claims risk focus system now in place. 12. Preparation, tendering and award of Islandwide Street Cleansing
Contract, annual cost ,1.14 million. Obtained additional annual funding from
Council at budget meeting. 13. The award of the Islandwide Grounds Maintenance Contract. 14. The completion of the Lynnbottom Restoration Contract. 15. Introduction of safety audits. 16. Introduction of inspection regime for highway retaining
walls. 17. Launch of IW Centre for the Coastal Environment website
(www.coastalwight.gov.uk). 18. Completion of coast defence strategy study for IW
North-East coast and commence Strategy Study for Sandown Bay. 19. Submission of application for ,3 million coast protection scheme
at Seaview Duver to DEFRA and receipt of planning consent for ,2.4 million scheme for Ventnor
Harbour. 20. Preparation of the Local Government Association National
Coastal Action Plan. 21. Achievement of High Level Target requirements to DEFRA for
first year targets. 22. Appointment as Chairman of the Coastal Groups of England
and Wales for third year and of SCOPAC for eighth year. |
23. Successful completion of Interreg 2 project leading to
Rights of Way Strategy 2001-6. 24. Add to cycleway infrastructure. 25. Production of Annual Progress Report for Traffic. 26. Development of Islandwide parking strategy. |
|
Over last 1 to 3 years Achievements 1. All Primary and Middle schools now have one or more
cycling initiatives/training each year.
46 Primary, 16 Middle. 2. Implementation of GIS and PMS systems. 3. Computerisation of Traffic Regulation Orders onto GIS
database. 4. Introduction of database for highway bridges. 5. Introduction of consultation procedures for major
schemes. 6. Rationalisation of car park ticket machines and tariff
boards. 7. Introduction of car park staff uniform, which reflects
corporate identify. 8. Increase in excess charges being issued. 9. All car park staff undertaken Violence and Aggression
Training Course. 10. Six year extension of Integrated Waste Management Contract
with improved recycling/diversion rate in excess of 50% of Domestic Waste. 11. Award and completion of ,1.4 million in EU grants from EU LIFE Environment and
other funding programmes. 12. Completion of North-East Coast of the Isle of Wight Coastal
Defence Strategy Study and commencement of Sandown and West Wight
Strategies. 13. Completion of major renovation programme at the Isle of
Wight Coastal Visitors' Centre with the assistance of grants amounting to
approximately ,350,000. 14. Appointment of Coastal Manager as Chairman of the Coastal
Groups of England and Wales since 2000 and Chairmanship of SCOPAC since
1995. 15. Chairmanship of the Organising Committees for the
"International Conference on Instability - Planning and
Management" (IW 2002) and the Institution of Civil Engineers Coastal
Management Conference (2003). 16. Completion of coast protection schemes at Seagrove Bay,
Seaview and Wheeler's Bay, Ventnor (total value ,2.5 million). 17. Complete and disseminate Rights of Way Strategy. 18. Complete and disseminate revision of definitive map 2000. 19. Production of Local Transport Plan. 20. Introduction of bus priority schemes. 21. Introduction of first 20 mph zones. |
|
SERVICE AIMS, OBJECTIVES, TASKS AND TARGETS
SERVICE AIM /OBJECTIVE |
TASKS |
TARGETS AND DATES |
RESPONSIBLE OFFICER |
DIRECTORATE OBJECTIVE TO WHICH
THIS TASK CONTRIBUTES |
a. Implement Best Value Action Plan. |
Please refer to Best Value Improvement Plan for details |
All |
||
b. Delivery
of annual programme as set out in the Local Transport Plan and Capital
Programme subject to annual reviews. |
1. Implement Capital Programme. 2. Produce Annual Progress Report. 3. Report progress to Environment & Transport Select
Committee. 4.
Monitor/evaluate schemes to
ensure compliance with LTP objectives. |
1. 31 March 2003. 2. 28 June 2002. 3. Monthly 4. Continuous with monthly report. |
1. Project Managers identified in Capital Programme Scheme
list. 2. Chris Wells 3. Head of Service 4. LTP monitoring officer. |
All |
c. Investors
in People. |
1. Undertake Personal Development Plans for all staff. 2. Provide IIP
training/ workshops for all staff. 3. Gain IIP
award. |
1.
31 July 2002. 2. 31 July
2002.. 3. 1 November
2002. |
1.
All Managers/ Supervisors. 2. Head of
Service. 3. Strategic
Director, Heads of Service, Managers and staff. |
|
d. ICT
Improvements. |
1. Prepare an ICT strategy for the next 3 years to achieve
e-government and service objectives. |
1. 30 November
2002 |
1. Principal Officer Support Services. |
The provision of High Quality
Professional Services for the whole of the Council. Support to Elected Members and
the democratic process. |
e.
Customer Focus Improvements. |
1. Provide customer service training for all relevant staff.
2. Adhere to the corporate service standards. |
1. 1 November 2002. 2. April 2002.
Monthly monitoring and reporting by Principal Officer, Support
Services. |
1. Principal
Officer Support Services. 2. Head of
Service. |
Support to Elected Members and
the democratic process. The provision of high quality
professional services for the whole of the Council. |
ANNEX 2 :
PERFORMANCE INDICATORS
BV 82a Percentage of total tonnage of household
waste arisings which have been recycled.
BV 82b Percentage of total tonnage of household
waste arisings which have been composted.
BV 91 Percentage of population in the authority’s
area which are served by a kerbside collection of recyclables or within one
kilometre radius of a recycling centre.
BV 94 Cost per passenger journey of subsidised
bus services.
BV 99e(ii) Number
of road accident casualties per 100,000 population: Other vehicle users ‑ Slight injuries
BV 82c Percentage of total tonnage of household
waste arisings which have been used to recover heat, power and other energy
sources.
BV 82d Percentage of total tonnage of household
waste arisings which have been landfilled.
BV 84 Kg of household waste collected per head.
BV 88 Number of collections missed per 100,000
collections of household waste.
BV 93 Cost of Highway maintenance per 100
kilometres travelled by a vehicle on principle roads
BV 95 Average cost of maintaining streetlights.
BV 96 Condition of principal roads.
BV 97 Condition of non-principal roads.
BV 99c(i) Number of
road accident casualties per 100,000 population: 2 wheeled motor vehicle users ‑ Killed/seriously injured
BV 99c(ii) Number
of road accident casualties per 100,000 population: 2 wheeled motor vehicle users ‑ Slight injuries
BV 99d(ii) Number
of road accident casualties per 100,000 population: Car users ‑ Slight injuries
BV 100 Number of
days temporary traffic controls or road closure on traffic sensitive roads
caused by local authority road works per kilometre of traffic sensitive roads.
BV 105 Damage to
roads and pavements.
BV 87 Cost of waste disposal per tonne for
municipal waste.
BV 99a(i) Number of
road accident casualties per 100,000 population: Pedestrians ‑ Killed/seriously injured
BV 99b(i) Number of
road accident casualties per 100,000 population: Pedal Cyclists ‑ Killed/seriously injured
BV 99e(i) Number of
road accident casualties per 100,000 population: Other vehicle users ‑ Killed/seriously injured
BV
85 The cost per square
kilometre of keeping relevant land, and relevant highways for which the
authority is responsible, clear of litter and refuse.
BV 86 Cost of waste collection per household.
BV 99a(ii) Number
of road accident casualties per 100,000 population: Pedestrians ‑ Slight injuries
BV 99b(ii) Number
of road accident casualties per 100,000 population: Pedal Cyclists ‑ Slight injuries
BV 99d(i) Number of
road accident casualties per 100,000 population: Car users ‑ Killed/seriously injured
BV 102 Local bus
services (passenger journeys per year).
Theme
Group |
Theme
Local Performance Indicators |
1. Road Safety |
1.
KSI casualties per 100,000 population. |
|
2.
Slight casualties per 100,000 population. |
|
3.
Pedestrian KSI casualties per 100,000 . |
|
4.
Pedestrian slight casualties per 100,000. |
|
5.
Pedal cyclists KSI casualties per 100,000. |
|
6.
Pedal cyclists slight casualties per 100,000. |
|
7.
Motorcycle KSI casualties per 100,000. |
|
8.
Motorcycle slight casualties per 100,000. |
|
9.
Car users KSI casualties per 100,000. |
|
10.
Car users slight casualties per 100,000. |
|
11.
Other KSI casualties per 100,000. |
|
12.
Other slight casualties per 100,000. |
|
13.
Child KSI casualties per 100,000. |
|
14.
Child slight casualties per 100,000. |
|
15.
Young driver KSI casualties per 100,000. |
|
16.
Young driver slight casualties per 100,000. |
|
17.
Older road users KSI casualties per 100,000. |
|
18.
Older road users slight casualties per 100,000. |
|
19.
KSI per million vehicle km on principal roads. |
|
20.
Slight casualties per million vehicle km on
principal roads per 100,000 |
2.
Network Management |
None at present. |
3.
Maintenance |
1.
Number of insurance claims received/100km of local
authority network over a financial year. |
|
2.
Number of insurance claims repudiated/100km of
local authority network over a financial year. |
|
3.
% length of footway maintained in a financial
year. |
|
4.
% revenue allocation spent on planned footway
maintenance. |
|
5.
% principal network with skid resistance above
investigatory level. |
|
6.
% length of carriageway network receiving planned
maintenance. |
|
7.
% revenue budget allocation spent on planned
carriageway maintenance. |
|
8.
% revenue budge allocation spent on planned
maintenance. |
|
9.
% road network receiving precautionary salting. |
|
10.
Cost of winter maintenance salting per salted km. |
|
11.
Proportion of budget expended on reactive
maintenance. |
|
12.
Maintenance spend /100km of highway network
(principal and local county roads). |
4. Parking |
1.
Proportion of local parking plans consistent with
LTP policies. |
|
2.
Proportion of major development proposals which
include parking restraint measures. |
|
3.
Percentage of parking tickets waived following
representations or rejects on appeal. |
5. Highway development Control |
1.
% responded within 14 days. |
|
2.
% of highway recommendations accepted. |
|
3.
% land charges responded within local targets. |
|
4.
% highway land records responded within local
targets. |
|
5.
Number of appeals dismissed on highway grounds as
a proportion of total number of appeals which include highway reasons for
refusal. |
|
6.
% refusals resulting in an appeal. |
|
7.
Value of contribution/works at time of agreement
compared to capital programme. |
|
8.
Total road length completed under S38 Agreements. |
|
9.
% vehicle operator licences upheld. |
6.
Waste Management |
1.
Municipal waste disposal cost per tonne. |
|
2.
Cost per capita. |
|
3.
Household waste kg per capita. |
|
4.
Household waste recycled %. |
|
5.
Household waste recycled in WDA area %. |
|
6.
Household waste composted %. |
|
7.
Household waste composted in WDA area %. |
|
8.
Household waste incinerated %. |
|
9.
Household waste incinerated outside WDA area %. |
|
10.
Household waste landfilled %. |
|
11.
Household waste landfilled outside of WDA area %. |
|
12.
Household waste diverted from landfill %. |
|
13.
% of WDA area covered by hazardous waste disposal
facility. |
|
14.
Household clinical waste kg per capita. |
|
15.
Abandoned vehicle cost per 1,000 people. |
|
16.
Abandoned vehicles number per 1,000 people. |
|
17.
Waste growth % per annum. |
|
18.
% of people satisfied with CA sites. |
|
19.
% of waste recycled at CA sites. |
|
20.
CA site management cost per tonne. |
|
21.
Haulage of CA waste per tonne. |
|
22.
Disposal of CA waste cost per tonne. |
|
23.
CA site availability number per 100,000 people. |
7.
Sustainable Transport |
1.
km of cycle route constructed per year. |
|
2.
% trips by cycle. |
|
3.
% trips by walking. |
|
4.
Bus punctuality. |
8.
Highway Construction Projects |
1.
Contract award cost to contract final cost %. |
|
2.
Construction period at award to actual
construction period %. |
|
3.
Estimated design and supervision costs to final
design and supervision costs %. |
|
4.
Final fees to final works cost %. |
9 Business Support |
Health and Safety |
|
1.
Number of accidents. |
|
2.
Number of accidents reported to HSE Staff. |
|
3.
Staff turnover. |
|
4.
Cost per head of training. |
|
5.
Amount of training per head. |
|
6.
% sickness rate. |
Annex 4
Reference |
Performance
Indicator |
SA1 |
% of routine safety inspections undertaken by the
Authority’s inspectors and completed within the time limits set by the
Authority. |
SA1-1a |
Number of actionable defects identified per km of road
network. |
SA2 |
% of principal road network with a skid resistance above
the investigatory level. |
SA2-2a |
% of principal road network awaiting priority treatment
for skid resistance. |
SA2-2b |
% of principal road network measured for its skid
resistance annually. |
SA3 |
The average length of time in repairing street light
faults and compare with the Authority’s policies and objectives |
SA3-3a |
Number of faults generated by inspectors (annually) |
SA3-3b |
Number of faults reported by users (annually) |
SA3-3c |
Number of repairs completed within specified time limits
(annually) |
SA3-3d |
Number of repairs completed outside specific time limits
(annually) |
SA4 |
% of the lighting stock that is life expired. |
SA4-4a |
% column replacement. |
SA4-4b |
Total number of columns |
SA5 |
% of third party claims repudiation rate over the
previous three years. |
SA5-5a |
Number of claims over previous three years. |
SE1 |
Average length of time in executing non-safety actionable
repairs in the highway and compare with the stated objectives of the
Authority’s policies. |
SE1-1a |
Number of repairs effected within specified time limits
(annual) |
SE1-1b |
Number of repairs effected outside specified time limits
(annual) |
SE1-1c |
Number of Category 1 repairs – BVP1 105 |
SE2 |
% of the major road work schemes which overrun the
published completion dates. |
SE3 |
Assessment of the overall condition of the highway
network by inspection on an annual basis using NRMCS (Index number) |
SE4 |
% score of user satisfaction by conducting an annual survey
through representative sample. |
SE5 |
% of occasions that all precautionary salting routes were
completed before the formation of ice. |
SE5-5a |
% of occasions that the precautionary salting was
completed within the Authority’s timescales. |
SU1 |
Percentage of the annual expenditure for reactive
maintenance of running surfaces compared with the annual expenditure for
programmed structural maintenance. |
SU1-1a |
Highway Maintenance Budget Outturn (£) |
SU1-1b |
Reactive Maintenance Budget Outturn (£) |
SU1-1c |
Structural Maintenance Budget Outturn (£) |
SU2 |
Annual road length resurfaced with low noise road
surfaces (km) |
SU2-2a |
Annual length of roads resurfaced (km) |
SU2-2b |
% length of noise reducing schemes as % of the network. |
SU3 |
The cost (value) of recycled road construction material
that is incorporated into maintenance works (£). |
SU3-3a |
Lengths of carriageway reconstructed annually by category
– total (km) |
SU3-3b |
Lengths of recycled carriageway constructed annually by
category – total (km) |
SU3-3c |
Average cost of reconditioned carriageway using
traditional materials (£/km) |
SU3-3d |
Average cost of reconditioned carriageway using recycled
materials (£/km) |
SU4 |
The outturn cost of winter service salting pre salted
kilometre (£/km) |