PAPER E
Purpose
: for Decision
REPORT
TO THE EXECUTIVE
Date : 19 NOVEMBER 2003
Title : HIGHWAYS
CAPITAL PROGRAMME
REPORT OF THE PORTFOLIO HOLDER FOR TRANSPORT
- TAKEN UNDER RULE 15 URGENCY PROVISIONS
IMPLEMENTATION
DATE: 1December 2003
1. To approve the
following changes to the Highways Capital Programme:
2. This report does not
appear on the forward plan and is being taken as an urgent item under Rule 15
Access to Information Procedure Rules.
It did not appear on the forward plan for November 2003-February 2004,
published in October 2003 because the severity and magnitude of the shrinkage
cracking has increased significantly over the last few weeks. It cannot wait until the publication of the
next forward plan (for December 2003-March 2004) because urgent repair works
are needed to restore highway safety and prevent accelerated deterioration of
the road structure.
3. None.
Several sections
of the Island’s highway network have suffered extensive
shrinkage
cracking and deformation arising from the drought conditions of the 2003
summer. The dry conditions have reduced
the moisture content of underlying shrinkable clays, resulting in subsoil
shrinkage and damage to carriageway surfacing.
The scale of the
problem has been assessed at £1.6 m and a large number of remedial schemes are
necessary to mitigate the effects of the clay subsoil shrinkage across the
Island. The works have been prioritised
in view of the shortage of available funds and costed. Budget estimate for the urgent high priority
remedial work which can be achieved is £600,000.
Further remedial
work will be necessary at several other sites next financial year. This is likely to have an adverse effect on
the Council’s LTP obligations.
Representatives from the Government Office for the South East (GOSE)
have been invited to the Island to view the scale of the drought damage to the
highway network and to discuss the Council’s requirement for additional capital
funding.
The highways
maintenance revenue budget has historically always been set at a low base,
although it must be acknowledged that the Council is still spending at 13%
above the highway maintenance FSS of £3.818m in the current financial year.
This year the high demands on the budget have made it necessary to capitalise
£100, 000 of appropriate work to ensure the availability of revenue funding for
reactive maintenance to the end of the financial year.
6. Ventnor Haven
Project
The Ventnor haven
project was completed in early August 2003.
The original estimated cost of the project was £2,070,000. Funding for the project was obtained from
the government’s Single Regeneration Budget Round 2 (£1,240,000) together with
a fixed contribution from Defra as coast protection grant aid (£235,000) with
the remainder being funded by the Council.
The final cost
for the project, comprising construction works, investigations and studies and
contract supervision is £2,476,953; this follows the conclusion of negotiations
with the contractor this week. The
budget shortfall is £406,953, which takes account of the sharing of the
additional construction costs over and above the ‘target cost threshold’; a
condition of the contract. However a
significant part of the scheme required environmental and geotechnical
investigations which will aid the development of the IW Undercliff Coastal
Defence Strategy Study which is grant-aided by Defra. This will save consultancy fees to the value of £30,000 on the
Study and will allow a reduction in the fees expenditure on the haven project
of the same amount. The net additional
expenditure is, therefore, £376,953.
As part of the
Council’s contribution to the capital cost of the sum a sum of £100,000 was
approved from land sales / leases achieved by 31 March 2004. A lease for regeneration of a site on the
Eastern Esplanade has been made for the sum of £100,000 but this will be paid
in five annual instalments of £20,000.
The principal
additional items of expenditure were :
·
The payment of a 20% tax on rock armourstone as part of the
government’s Aggregate Sustainability Levy; this amounted to approximately
£88,000; an increase of 4.2% on the overall project cost.
·
Additional rock armourstone required due to depressions and soft areas
of seabed; it was not economic to arrange barge transport for the additional
rock and, therefore, it had to be imported by road at a higher unit cost;
weather-related costs, removal of
accumulated silt during construction phase and other minor amendments to
contact specification - £194,548 (net tender cost increase of 10.5%); an
increase of 9.3% on the overall project.
·
Additional costs for technical studies and environmental mitigation
work required by English Nature and the subject of planning conditions -
£124,405 (less £30,000 described above) leaving £94,405; an increase of 4.5% on
the overall project budget.
The Ventnor haven
scheme was first approved for SRB funding in 1996. Protracted negotiations over environmental issues following the
designation of the coastal waters off Ventnor as part of the South Wight
Maritime Special Area of Conservation meant that the scheme was held up for
nearly four years pending resolution of these issues to the satisfaction of
English Nature. Environmental
mitigation was finally resolved in early 2002 / 03. Resulting planning conditions required the translocation of reef
boulders from beneath the footprint of the harbour arms and within the haven to
an alternative location in order that the various species of seaweed and
lichens could be adequately safeguarded; the Council is required to monitor
performance of the environmental scheme for the next five years. The project supervision and environment
management elements required a significantly greater input than envisaged.
If the scheme had
not proceeded last autumn the Council would have been required to repay to the
Government’s Challenge Fund the costs of technical investigations, environmental
studies and detailed design fees totalling nearly £400,000, incurred between
1995 / 96 and 2002 / 03. The haven
scheme is already making a significant contribution towards the regeneration of
the town of Ventnor.
The Coastal
Manager is actively pursuing opportunities for additional funding to assist in
mitigating the shortfall but further resources cannot be guaranteed at this
stage. For this reason the Head of
Engineering Services is seeking contingency funding from the Capital Programme.
In order to
accommodate the unforeseen pressures on the highways capital budget as outlined
above, the delivery of a number of capital schemes within the Highways Capital
Programme will need to be deferred to next financial year 2004/2005. The
deferred schemes have been identified in accordance with the Council’s Priority
Ranking Assessment methods and will all receive high priority
for 2004/2005 .
Even before
considering the recent and ongoing effects of subsoil shrinkage due to the
drought conditions, the condition of the Island’s highway assets was well below
standard. Current levels of funding
will not make it possible to achieve the national objectives of arresting the
decay of the network by 2005 and removing most of the maintenance backlog by
2011.
There is a high
national demand for conventional capital funding for highway maintenance, as
all responsible local authorities endeavour to address their maintenance
backlog. It is considered essential
that areas of additional funding are identified, with the potential to deliver
better value for money in order to halt the deterioration of the Island’s
highway assets.
Many local authorities
are now exploring areas of additional funding for highways management projects,
particularly PFIs. In this context, an
outline PFI business case is currently being prepared for the Isle of Wight
Council by consultants Mott MacDonald and this is being funded from existing
budgets then a full business case will need to be part of a tendered exercise.
9. Specialist advice has been obtained
from other similarly affected Local Authorities and from contractors
experienced in highway remedial works. This is in order to establish the full
range of remedial works being undertaken elsewhere, and whether there are any
innovative and cost effective solutions or proprietary treatments that will
provide appropriate solutions to the problems being experienced.
10.
Additional
Requirements £
Urgent Remedial Works 600,000
Ventnor Haven Contingency Requirement 400,000
Capitalisation of Revenue Work 100,000
£1,100,000
Deferral of Capital Schemes 880,000
Military Road Savings 220,000
£1,100,000
The
council has a duty to maintain the highway and can be liable for failure to so
do. The recommended amendments to the capital programme are the result of
applying a risk analysis to existing planned works and the newly emerging need
to repair cracking.
The
contingency for Ventnor Harbour represents contractual obligations to the
various contractors necessary to deliver the scheme.
11.
(b)
To amend the proposed changes to the Highways Capital
Programme.
12. It is recognised that an alteration to
the approved 2003/2004 Highways Capital Programme involving deferral of a
significant number of capital schemes to the following financial year might
affect the Council’s ability to achieve the targets and objectives set out in
the LTP. This in turn might adversely
affect future LTP capital settlements.
As previously mentioned, representatives from the Government Office for
the South East (GOSE) have been invited to the Island to view the scale of the
required remedial works and to discuss the Council’s requirement for additional
funding.
RECOMMENDATIONS 13. That
option (a) is approved. |
14. Report to Informal
Executive. 30 July 2003.
15. Appendix A. List of urgent remedial schemes for sites affected by clay
shrinkage and heave.
16. Appendix B. Required adjustments to the Capital Programme to accommodate
urgent remedial schemes
S MATTHEWSHead of Engineering Services |
E FOX Portfolio
Holder for Transport |
REMEDIAL WORKS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ROAD NAME |
TOWN |
AREA |
CLASS |
BUDGET ESTIMATE |
|
|
|
|
|
|
|
Ashey Road |
Ryde |
2 |
C |
75,000 |
|
Beaper Shute |
Brading |
3 |
A |
2,500 |
|
Brading Road |
Ryde |
3 |
A |
7,000 |
|
Carters Road |
Ryde |
2 |
C |
10,000 |
|
Clarence Road |
Wroxall |
5 |
B |
20,000 |
|
Fairlee Road |
Newport |
8 |
A |
5,000 |
|
Forest Road |
Newport |
8 |
A |
5,000 |
|
High Street |
Whitwell |
5 |
C |
18,000 |
|
Leeson Road |
Ventnor |
5 |
A |
7,000 |
|
Main Road |
Brighstone |
6 |
B |
15,000 |
|
Main Road |
Havenstreet |
2 |
|
95,000 |
|
Medina Way |
Newport |
8 |
A |
7,000 |
|
Newport Road |
Godshill |
5 |
A |
5,000 |
|
Newport Road |
Ventnor |
5 |
B |
15,000 |
|
Quarry Road |
Ryde |
2 |
|
5,000 |
|
Rew Street |
Gurnard |
1 |
C |
20,000 |
|
Rowborough Lane |
Brading |
3 |
A |
15,000 |
|
Sandown Road |
Bembridge |
3 |
B |
5,000 |
|
Smallbrook Lane |
Ryde |
2 |
C |
37,500 |
|
Station Road |
St Helens |
3 |
B |
5,000 |
|
Stroud Wood Road |
Ryde |
2 |
C |
17,000 |
|
Whiteoak Lane |
Porchfield |
7 |
C |
12,000 |
|
Whiterails Road |
Newport |
1 |
C |
60,000 |
|
Yarmouth Road |
Shalfleet |
7 |
A |
120,000 |
|
Park Road Wootton 17,000
TOTAL 600,000
APPENDIX B
Sandown Road, Lake
Bridges and Structural Maintenance
Horringford
Ponda Rosa Bridge
Park Road, Wootton
Rights of way signing
High Street, Wootton
The Mall, Brading
High Street, Ventnor
A3055 Lake Hill/Fairway
Upton Road, Ryde
Canteen Road, Whiteley Bank
Hunnyhill-Parkhurst Road Bus Link
Unallocated less over commitment
Chimney Steps/Leeson Road
Baring Road Traffic Calming
Advance Design Unallocated
Design, Ryde High Street