PAPER C
ENVIRONMENT AND TRANSPORT SELECT COMMITTEE- 20
AUGUST 2003
BEST VALUE REVIEW - CONSULTANT'S
PROGRESS REPORT ON HIGHWAYS AND TRANSPORTATION IMPROVEMENT PLAN
HEAD OF ENGINEERING SERVICES
REASON FOR SELECT
COMMITTEE CONSIDERATION
Resolved at the Environment and Transport Select Committee of 24 June
2003, that the contents of the Consultant’s progress report be reported to this
Committee meeting.
ACTION REQUIRED BY THE SELECT COMMITTEE
To receive the Consultant’s progress report
on the Highways and Transportation Best Value Improvement Plan.
BACKGROUND
The Improvement Plan was well received by the Audit Commission’s Best
Value Inspectors when the Highways and Transportation Service was re-inspected
in September 2002.
Good progress has been made in implementing the Improvement Plan. However, the availability of resources has a
major impact on the Department’s ability to deliver and therefore, careful
monitoring is essential to ensure that adequate progress is maintained. To assist in this process the Consultant
that helped with the external challenge to the Improvement Plan has been requested to undertake an audit on
progress. Details of his report are as
follows :-
1. The purpose of the
Audit was to check the extent to which the Highways and Transportation Best
Value Improvement Plan is being delivered.
Before the audit took place, a series of actions contained in the Plan
was agreed with the Head of Service for investigation.
2. Discussions were
held with Steve Matthews, Malcolm Smith, Phil Hayward, Peter Taylor, Nick
Gallin, Steve Boswell, Chris Wells and Helen Gaches on the 3 and 4 June. Everyone was very co-operative, spoke openly
and gave generously of their time.
1. Of the 31
findings, which emerged from the discussions with senior staff, five of the
planned actions had been changed, mostly due to Corporate initiatives. There is therefore, a real risk that
progress will become bogged down to the detriment of service delivery because
of the breadth and competing pressures of Corporate work.
2. Corporate initiatives
identified as having an affect on the Improvement Plan include:
3.
Findings
relating to areas where progress has been better than anticipated in the
Improvement Plan are:
4.
Additionally,
good progress has been made with some other initiatives that were not
specifically highlighted in the Improvement Plan:
5.
Progress is
broadly on schedule for the Department’s two major management initiatives –
gaining IiP status and the introduction of an accredited Quality Management
System.
6.
The Department
is about to produce its first quarterly report for the Departmental Management
Team on the performance indicators.
This is a key step and needs to be encouraged. DMT will need to satisfy itself about the robustness of the data
and systems that underpin the performance measures and will need to set
realistic, but challenging targets for the measures.
7.
Progress is
being made towards a Private Finance Initiative (PFI) approach to asset
maintenance and a report on this is soon to be taken to the Executive
Committee. Because of this new
important strategy, the term highway maintenance contract has had to be
extended with the two existing contractors.
8.
Areas to watch
and concerns:
1.
DMT reviews
progress in implementing the Improvement Plan quarterly and sets revised
priorities and targets where slippage has occurred or new activities intervene.
2.
The Department
needs to be more proactive in adjusting the scope and timescale of some
Corporate initiatives to better suit its own imperatives.
3.
Consideration
is given to the organisational and staffing issues referred to in paragraph 8.
4.
The Department
continues to examine the possible application of a PFI approach to asset
maintenance and development, not least because of its pioneering experience
with the integrated waste contract.
Because this is a difficult procurement arrangement to deliver, other
short-term opportunities to improve existing contractual practices should not
be put on hold.
RELEVANT PLANS,
POLICIES, STRATEGIES AND PERFORMANCE INDICATORS
The Highways and Transportation Best Value Improvement plan.
CONSULTATION
PROCESS
Not necessary at this time.
FINANCIAL, LEGAL,
CRIME AND DISORDER IMPLICATIONS
None at present.
APPENDICES
ATTACHED
None.
Audit
of the Highways and Transportation Best Value Improvement Plan by M Sharpe.
Contact Point :Malcolm Smith, Policy and Strategy Manager, F 823777
e-mail [email protected]