Transport Capital Summary Report with Comments - to end February 2004

COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

A3020 Strategic Corridor - Newport to Cowes

8HGA   A3020 CTNSC - Carriageway Works   £0       £0  £718,550 £722,330  £0      -£3,780

8HGB    A3020 CTNSC - Footway Works   £0       £0  £59,771   £62,421  £0      -£2,650

8HGC    A3020 CTNSC - Bus Infrastructure Works   £0       £0  £25,000   £28,717  £0      -£3,717

8HGD    A3020 CNTSC - Street Lighting Works   £0  £0      £20,543  £13,124          £0  £7,419

8XC1    Cowes-Newport Strategic Corridor £650,000  £11,135          £0  £7,521 £0 -£7,521

Total for Group  £650,000 £11,135  £823,864 £834,113  £0       -£10,249

A3021 Strategic Corridor - Newport to East Cowes

8H6H    Advce Desgn Newport to Cowes and E Cowes £0       £0  £0      £2,586  £0  -£2,586

           Cor

8HG1    A3021 ECTRC SC - Carriageway Works   £0       £0  £167,444 £161,382  £0      £6,062

8HG2    A3021 ECTRC SC - Footway Works  £0  £0      £27,729  £21,096    £7,186  -£553

8HG3    A3021 ECTRC SC - Street Lighting Works   £0  £0      £14,695  £7,317 £0 £7,378

8HG4    A3021 ECTRC SC - Bus Infrastructure Works   £0       £0  £5,326 £5,887  £215   -£776

8XC2    East Cowes to Racecourse SC - DO NOT USE  £500,000 £234,807  £0      £0       £0  £0

Total for Group  £500,000 £234,807  £215,194 £198,268  £7,401    £9,525

A3054 Strategic Corridor - Newport to Ryde

8H50    A3054 RTNSC - Carriageway Mtce (Inc A-Skid)       £0  £0      £26,222  £31,764          £0  -£5,542     Works complete.

8H51    A3054 RTNSC - Footway Mtce (Inc T-Paving)  £0      £0  £1,533  £2,065 £0   -£532  Works complete.

8H52    A3054 RTNSC - Street Lighting £0       £0  £0      £625    £0  -£625

8H53    A3054 RTNSC - Wootton Bridge   £0       £0  £0      £617    £0  -£617  Complete.

8H54    A3054 RTNSC - Newport Tunnels Graffiti  £0  £0      £409  £1,764 £409      -£1,764  Tunnel 1 complete

Total for Group  £0                £0  £28,164   £36,835  £409     -£9,080

A3054 Strategic Corridor - Newport to Yarmouth

8H60    NTYSC - Yarmouth Bridge (Phase 3 of 5)    £0  £0      £44,788  £42,026       £868  £1,894

8H61    NTYSC - Bettyhaunt Lane £0  £0      £2,653  £1,373 £0  £1,280  Complete

8H62    NTYSC - Carriageway Maintenance      £0  £0      £5,717  £186   £5,717    -£186     Complete

03 March 2004  Page 1 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

8H63    NTYSC - Footway Maintenance      £0  £0      £1,950  £1,537 £1,950    -£1,536  Complete

Total for Group  £0                £0  £55,108   £45,122  £8,534    £1,452

Newport Town Centre Traffic Management

8XY1    Newport Town Centre Traffic Mngmnt   £0  £0      £423,705  £312,686 £192,936  -£81,917

Total for Group  £0                £0  £423,705 £312,686  £192,936 -£81,917

Ventnor Ground Investigation

8XT1    Ventnor Ground Investigation      £0  £0      £0       £0  £195   -£195

Total for Group  £0                £0  £0                £0  £195       -£195

A3055 Undercliff Drive Diversion Works

8XU1    Undercliff Drive - Beauchamp House   £0       £0  £50,350   £56,084  £0      -£5,734  Main contract complete. Additional works & further

                        investigations

Total for Group  £0                £0  £50,350   £56,084  £0        -£5,734

Structural Maintenance of Principal Roads

8HW1   Advance Design-Undercliff Dr 0304 £0       £0  £150,000 £171,994  £0      -£21,994

8XBK    98/99 - A3055 Military Road Project  £1,850,000  £0      £2,753,422  £2,514,193  £41,546 £197,683  Work commenced 6 Jan 03.

Total for Group  £1,850,000      £0  £2,903,422  £2,686,187  £41,546 £175,689

Structural Maintenance Of Carriageways

8H1C    01/02/03 A3055 Sandown Road Lake £150,000  £0      £2,827  £2,826 £0      £1

8HY1    Dover Street Ryde       £0  £0      £3,000  £1,145 £0 £1,855

8HY2    Medina Way Newport    £0  £0      £2,345  £159   £0 £2,186

8HY3    Mill Hill Road Cowes     £0  £0      £3,000 £64  £0      £2,936

8HY4    Niton Road Niton     £0       £0  £3,000 £0       £0  £3,000

8HY5  Whitehouse Road Newport          £0  £0      £3,000  £6,334 £0 -£3,334

8HY6    Residential Bus Routes       £0  £0      £3,000  £2,749 £0   £251

8HYA   Newport Quay Resurfacing  £0      £0 £18,400  £18,400          £0  £0

8XP2    00/01/02 A3055 Broadway Sandown - Widening          £0  £0      £0    £702  £0      -£702

Total for Group  £150,000        £0  £38,572   £32,379  £0         £6,193

03 March 2004  Page 2 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

Surfacing

8H6G  Carriageway Overlays-Ryde & E Cowes  £0       £0  £15,003   £11,530  £3,403 £70

Total for Group  £0                £0  £15,003   £11,530  £3,403        £70

Insitu Recycling

8H2A    01/02/03 Great Preston Road Ryde (Part)       £0  £0      £29,878  £6,856 £23,467   -£445

8H2C    01/02/03 Minerva Road East Cowes  £0       £0  £332   £0    £332  £0      Complete. Commitment = retention

8H2D    01/02/03 Lamorbey Road / James Avenue Lake     £0       £0  £860   £0    £860  £0      Complete. Commitment = retention

8H2G    01/02/03 Newnham Lane Binstead (West End)     £0       £0  £663   £0    £663  £0      Complete. Commitment = retention

8H2J     01/02/03 Union Rd / St Johns Rd / George St   £0  £0      £1,170  £0  £1,170 £0  Complete. Commitment = retention

8H2L    01/02/03 Rowlands Lane Havenstreet North End      £0       £0  £512   £0    £512  £0      Complete. Commitment = retention

Total for Group  £0                £0  £33,415    £6,856  £27,005    -£446

Bridges & Structural Maintenance

8H1H    01/02/03 Chilton Chine     £0  £0      £989  £1,052 £0   -£63

8H1J     01/02/03 Horringford £30,000  £0      £5,767  £3,029 £5,919    -£3,181

8H1L    01/02/03 Wroxall  £20,000 £0  £21,500    £6,375  £13,834   £1,291

8H1M    01/02/03 Gurnard £41,000 £0  £58,323   £13,845  £40,019   £4,458

8H1N    01/02/03 Caesars Road Newport          £0  £0      £1,500  £1,563 £0     -£63  Complete

8H1P    01/02/03 Betty Haunt Lane Newport          £0  £0      £2,490  £1,405 £0  £1,085  Complete.

8H1Q    Blacklands Bridge (part insurance credit) £0  £0      £1,838  £1,437 £0    £401  Complete.

8H1R    01/02/03 Calbourne Lower Mill       £7,000  £0  £13,500    £1,213  £5,671 £6,616

8H1V    01/02/03 Islandwide Bridges - Maintenance    £0  £0      £9,084  £6,268 £828  £1,988 Ongoing

8HR1    Church Lane Ryde-Retaining Wall Emerg Works  £9,000 £0 £38,500  £38,362       £750  -£612

8HR2    St Albans Steps Ventnor-Retaining Wall  £20,000          £0  £21,200   £21,076  £486   -£361

8HR3    Kite Hill Wootton - Retaining Wall Works  £9,000  £0      £12,100  £10,444       £242  £1,413

8HR4    Duver Rd Bridge St Helens - Investigation Wk  £5,000 £0  £5,900  £5,648 £0   £252

8HR5    Ashey Rd Ponda Rosa Bridge - Safety Fencing  £41,000          £0  £5,921 £1,790  £3,571 £560

8HR7    Structural Maintenance - Bridges £49,000 £0  £44,416   £14,623  £24,663   £5,130

8HR8    Structural Maintenance - Retaining Walls  £19,000          £0  £5,000 £3,160  £0  £1,840

8XND    00/01/02 Afton Bridge Freshwater - Reconstrt         £0  £0      £706 £738  £0      -£32  Complete. Snagging prog April 2003

8XNG    00/01/02 Park Rd Wootton Bridge and Rd Imprv    £0       £0  £45,431   £35,537  £0      £9,894  Ongoing consultation, land acquisition

03 March 2004  Page 3 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

8XNH    00/01/02 Alresford Rd Footbridge Shanklin  £0      £0 £18,453  £16,749       £359  £1,346

8XNK    00/01/02 Islandwide Structural Bridge Mtce     £0       £0  £0      £815    £0  -£815  Ongoing

8YF1    Ryde St Johns Road-Bridge Strengthening    £0  £0      £7,290  £0  £7,250 £40

Total for Group  £250,000        £0  £319,908 £185,128  £103,592 £31,187

Pedestrian Improvements

8H0B    01/02/03 Pelican Crossings  £0      £0  £2,798  £367   £2,798    -£368

8HM2    Islandwide Dropped Crossings  £50,000          £0  £63,357   £31,022  £2,427 £29,907

8HM3    Fiveways Junction - Ryde  £50,000          £0  £22,500    £1,227  £13,650   £7,623

8HM4    Rights of Way Signing      £0  £0      £17,000  £18,499          £0  -£1,499

8HM5    Newport Road Lamorbey - Merrie Gardens  £0  £0      £57,000  £6,325 £47,692  £2,983

8HM6    Eddington Road Nettlestone £0  £0      £63,500  £1,298 £34,387  £27,815

8HM7    Ashey Road / Upton Road (Ped. Improvements)   £0  £0      £17,000  £1,058 £0 £15,942

8HM8    Baring Road Cowes - New Footway          £0  £0      £67,602  £17,050          £0  £50,552   Ongoing consultation-start delayed to end March/early April

8HM9    High Street Wootton - New Footway          £0  £0      £1,300  £664   £0   £636

8HMA   The Mall Brading (Footway / Buildouts)         £0  £0      £4,100  £398   £0 £3,702

8HT1    Yarbridge Cross, Brading (Ped. Phase)     £0  £0      £27,500 £0  £0      £27,500

8HT2    High Street / Madeira Road Ventnor (Ped X) £0  £0      £3,700  £0  £0      £3,700

8XC9    Road Crossings 2003-04 DO NOT USE  £110,000        £0  £0      £0       £0  £0

8XP0    00/01/02 Anglesea St/George St Ryde - Crosing          £0  £0      £0  £3,523  £0      -£3,523  Being designed in-house

Total for Group  £210,000        £0  £347,357 £81,432  £100,955 £164,970

Footway Improvements & New Footways

8H0M    01/02/03 Alverstone Road Apse Heath Footway          £0  £0      £795   £80  £0      £715  Complete

8H0P    01/02/03 Gustars Shute Calbourne - Footway          £0  £0      £5,008  £3,720 £750 £538  Complete

8H0R    01/02/03 Eddington Road St Helens - Footway  £0      £0 £36,324  £34,899   £17,395  -£15,969

8HM1    Footpath Link Improvement Works   £0       £0  £8,570 £8,570  £0  £0

8XC6    Walking Schemes - DO NOT USE      £500,000  £0      £545    £0  £0      £545

8XN0    00/01/02 N.Walk Ryde - Footway - Phase 1  £0      £0  £3,559  £4,081 £8,203    -£8,725

8XN2    00/01/02 Newport Pedestrianisation Study    £0       £0  £668   £0       £0  £668

8XNA    00/01/02 Clarence Rd Wroxall - Footway  £0      £0       £0  £0      £3,199    -£3,199

8XNC    00/01/02 Upper High St Bembridge-Footway          £0  £0      £25,000  £956   £0 £24,044

03 March 2004  Page 4 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

Total for Group  £500,000        £0  £80,469   £52,305  £29,546 -£1,383

Safety

8H3G    01/02/03 Carpenters Rd Beaper Shute Brading £0       £0  £21,425   £21,425  £0      £0

8H3T    01/02/03 Visibility Improvement at Junctions         £0  £0      £0  £4,370  £0      -£4,370

8H3W   01/02/03 North Road / High Street Shanklin   £0  £0      £5,330  £5,321 £51  -£41

8H6K    Safety Camera Partnership-Capital  £0      £0       £0  £33,272    £1,655  -£34,927   Spend will be covered by grant yet to be received.

8HH1  Greenmount Primary School - Ryde    £30,000 £0  £11,665   £12,161  £0      -£496

8HH2    Nine Acres Newport          £0  £0      £44,000  £3,673 £15,600  £24,727

8HH3    St Boniface / St Wilfrids Ventnor £0  £0      £44,000  £2,096 £0 £41,904

8HH4    Oakfield Primary School   £0  £0      £44,000  £2,169 £0 £41,831

8HH5    Broadlea Primary Lake     £0  £0      £30,000  £9,285 £0 £20,715

8HHA    Shalfleet Primary Ningwood  £0      £0 £30,000  £2,159 £0 £27,841

8HHB    Advance Design - Safe Routes to Schools  £0      £0 £25,000  £0      £0 £25,000

8HP1    B3395 Culver Parade / Yaverland Road  £50,000          £0  £50,000   £23,433  £20,982   £5,585

8HP2    A3056 Hale Common / Fighting Cocks   £50,000          £0  £50,000    £3,837  £5,379 £40,784

           Crossroad

8HP3    Mersley Down / Knighton Shute    £50,000 £0  £105,000 £17,902  £0      £87,098

8HP4    A3055 Lake Hill / The Fairway £0       £0  £5,783 £1,838  £0  £3,945

8HP5  Briddlesdord Road / Havenstreet Road  £0      £0 £15,000  £5,074 £20,000   -£10,074

8HP6    Melville Street / Dover Street Ryde       £0  £0      £12,000  £4,089 £9,999    -£2,088

8HP7    Upton Road Ryde        £0  £0      £3,832  £1,807 £0 £2,025

8HP8    A3054 High Street / Station Road Wootton    £0  £0      £1,000  £325   £0   £675

8HP9    A3020 Blackwater Road / Shide Road       £0  £0      £1,000  £475   £0   £525

8HPA    Canteen Road Whiteley Bank  £0      £0  £3,000  £3,166 £0  -£166

8HPB    A3054 Forest Rd junction with Gunville Rd £0  £0      £33,000  £13,638   £15,590  £3,772

8XC3    Safe Routes to School - DO NOT USE  £220,000        £0  £0      £0       £0  £0

8XC7    Local Safety Schemes 2003-04  - DO NOT USE      £300,000  £0      £0       £0  £0      £0

8XL5    99/00 Brambles Corner Freshwater -LSS £0  £0      £0    £920  £0      -£920

8XLB    Fairlee Rd Junction works  £0  £0      £67,000 £0  £0      £67,000

8XLK    99/00 Afton Rd btwn Wilmington Lane/Broad Ln   £0  £0      £4,100  £0  £0      £4,100

8XLR    99/00 Princes Rd jnctn with Avenue Rd Fwater  £0       £0  £2,700 £0       £0  £2,700

8XLT    99/00 Nettlestone Green Seaview          £0  £0      £5,000 £92  £0      £4,908

8XLW   99/00 Upper Green Rd adj.Sunnyside St.Helens         £0  £0      £0  £1,016  £0      -£1,016

03 March 2004  Page 5 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

8XLY    99/00 Minor Junction Improvements - Islandwd          £0  £0      £5,000  £2,375 £0  £2,625  Complete

8XR3    00/01/02 Traffic Regulation Orders  £0       £0  £34,501   £31,732  £72     £2,697  Ongoing

8XR4    00/01/02 A3021 Whippingham Rd - Refuges           £0  £0      £1,460  £1,460 £0      £0

Total for Group  £700,000        £0  £654,796 £209,109  £89,328 £356,359

Cycleways

8H05    01/02/03 Newport to Sandown Cycle Route    £0       £0  £233,897 £214,076  £16,403    £3,418  Project operational June 2003

8HK1    2003-4 Wootton High St cycle by-pass    £0  £0      £12,846  £11,926          £0  £920

8HK4    2004-04 Petticoat Lane Cycle Path        £0  £0      £0 -£4,866  £0      £4,866

8HK5    2003-04 Medham Cycle Route    £0       £0  £0      -£500   £0  £500

8XC5    Cycling Schemes 2003-04 - DO NOT USE  £175,000        £0  £0      £0       £0  £0

8XMT    99/00 Cycle priority     £0  £0      £0    £148  £0      -£148

8XNN    00/01/02 Wootton - Ryde Cycle Route      £0  £0      £0      £77  £0      -£77

Total for Group  £175,000        £0  £246,743 £220,861  £16,403  £9,480

Public Transport Provision

8H08    01/02/03 Study for Bus Priority Measures £0  £0      £13,801  £13,920          £0  -£119

8H09    01/02/03 Bus Shelters     £0  £0      £10,431  £10,431          £0  £0

8H1A    01/02/03 Upgrade Bus Stops & Hardstanding  £0  £0      £2,002  £3,527 £0 -£1,525  Complete

8H1B    01/02/03 Ryde Interchange  £0      £0    £412  £695   £0   -£283  Complete

8H40  Sandown/Shanklin - Park & Ride Facilities           £0  £0      £3,949  £835   £4,401    -£1,287

8H5A    PTII - Islandwide Bus Routes  £0       £0  £2,782 £2,782  £0  £0      Complete. Commitment = retention

8H5B    PTII - Gt Preston Rd Ryde £0  £0      £2,923  £302   £0 £2,621

8H5C    PTII - Carpenters Rd St Helens  £0       £0  £25,000   £20,960  £1,969 £2,072  Commenced 6 January 2003

8H5D    PTII - Melville St Sandown         £0  £0      £1,083  £0  £1,083 £0  Complete. Commitment = retention

8H5E    PTII - Mayfield Rd Ryde £0  £0      £19,823  £21,311       £100  -£1,588  Commenced 6 January 2003

8HH6    Bus Gate Mayfield Rd - Ryde  £80,000          £0  £120,500 £14,870  £3,650 £101,980

8HH7    Hunnyhill - Parkhurst Road Bus Link      £70,000 £0  £13,503   £11,427  £0      £2,076

8HH8    Sandown Rail Station - Disabled Access £0  £0      £10,000 £0  £0      £10,000

8VE2    Rural Bus Challenge         £0  £0      £0       £0  £95,364  -£95,364    Costs will be covered by grant yet to be received

8XC4    Bus Infrastructure 2003-04 - DO NOT USE      £90,000 £0  £0      £0       £0  £0

8XPF    00/01/02 Park & Ride Cowes - Additional Funds  £0      £0 £31,831  £31,941          £0  -£110

8XPK    00/01/02 Bus Priority Measures         £0  £0      £148   £77  £0      £71

03 March 2004  Page 6 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

Total for Group  £240,000        £0  £258,188 £133,078  £106,567 £18,543

Traffic Calming / Speed Reduction

8XPR    00/01/02 Traffic Quiet Cells,Ryde        £0  £0      £164,601  £160,330 £14,634  -£10,362  Substantially complete.

Total for Group  £0                £0  £164,601 £160,330  £14,634 -£10,362

Drainage

8H28    01/02/03 Castle Road Carisbrooke      £0  £0      £3,160  £1,965 £0 £1,195

Total for Group  £0                £0  £3,160      £1,965  £0         £1,195

Highways Maintenance Capitalisation

8H1U    Leeson Rd Ventnor (Emergency Works)  £0      £0       £0  £190   £0  -£190

8H4R    Capitalised carriageway Repairs £0       £0  £73,800   £74,026  £0      -£226

8H4T    Capitalised Drainage          £0  £0      £17,918  £17,918          £0  £0

8H4V    Capitalised Footway Improvements    £0  £0      £8,282  £8,283 £0     -£1

8H6B    Coppins Bridge Reconstruction   £0  £0      £3,455  £3,779 £0   -£324  Complete. Retention due Feb 2004.

Total for Group  £0                £0  £103,455 £104,196  £0          -£741

Advance Highways Design for 2003/05

8H6A    Alpine Rd Ventnor £0       £0  £866   £834 £696  -£664

8XD4    Advance Design for 2004/5 schemes-DO NOT   £210,000        £0  £179,605        £0  £0      £179,605

           USE

Total for Group  £210,000        £0  £180,471     £834  £696   £178,941

Adverse Weather Works

8H4D    Chimney Steps/Leeson Rd Bonchurch £60,000  £0      £6,494  £557   £3,902  £2,035

8HY8    Struct Mtce - Princ Rds - due clay shrinkage  £0      £0  £249,999 £164,124  £94,093  -£8,218

8HY9    Struct Mtce -Ord Rds - due clay shrinkage  £0      £0  £250,000 £158,117  £94,271  -£2,388

Total for Group  £60,000          £0  £506,493 £322,798  £192,266 -£8,571

Other Schemes

8H4H    Design - High St Ryde Upgrade Pedest Area     £0       £0  £70     £106    £0  -£36

8H4J     Design - Old Rd E.Cowes (Footway)        £0  £0      £0  £1,631  £0      -£1,631

03 March 2004  Page 7 of 8


COST          COST CENTRE 2003/04

CENTRE      DESCRIPTION  ORIGINAL   ACCRUALS     REVISED   ACTUAL   COMMIT  BUDGET

CODE  BUDGET  2002-03  BUDGET  SPEND    -TED  LEFT                     

8H6J     Retaining Wall Works - Alpine Rd Ventnor       £0  £0      £30,431  £28,975       £441  £1,015

8H6L    Heart of Pan - Road junction improvements    £0  £0      £19,678  £15,245       £162  £4,271

8HX1    Sandrock Rd - Slipped carriageway reconstruc        £0  £0      £35,000  £25,074    £1,519  £8,406

8HX2  Briddlesford Rd 03-04 Surfacing RHill to Lyn        £0  £0      £43,000  £42,469    £3,230  -£2,699

8HX4    Ryde Gateway Scheme - SRB funded      £0  £0      £0       £0  £34,553 -£34,553

Total for Group  £0                £0  £128,179 £113,500  £39,905 -£25,226

Roads + Transport Total  £5,495,000  £245,942  £7,580,617  £5,805,598  £975,322 £799,697

03 March 2004  Page 8 of 8