PAPER B

 

 

Committee:            ENVIRONMENT AND TRANSPORT SELECT COMMITTEE.

 

Date:               19th DECEMBER 2002.

 

Title:                INTEGRATED WASTE MANAGEMENT CONTRACT – UPDATE ON THE OPERATION OF THE RESOURCE RECOVERY FACILITY (RRF) AND ADJOINING POWER PLANT AT FOREST PARK, NEWPORT.

 

                        REPORT OF THE HEAD OF ENGINEERING SERVICES

_________________________________________________________________________________

 

SUMMARY / PURPOSE

 

To report on the current closure of the Power Plant Operation located at Forest Park, Newport, and the potential implications to the Council.

 

BACKGROUND

 

The Council’s Integrated Waste management contract commenced in October 1997, and was groundbreaking in that it was the first truly Integrated Waste Contract of its type in the UK, and was also the first of its type under the provisions of the Governments Private Finance Initiative (PFI). This has allowed major investment to be made in the Islands waste management infrastructure. Under the PFI the Council also receives PFI credits of approximately £1.5m per annum. The contract is currently one of the largest currently operated by the Council. The contract was awarded to Island Waste Services (IWS) who were specifically set up to operate the contract. They are a fully owned subsidiary of Biffa Waste Services Limited.

 

The contract covers many service areas including waste collection; waste treatment; waste disposal, including landfill development, operation, restoration and monitoring; recycling including composting and backdoor and kerbside collection of recyclables; civic amenity site development and operation; and the operation of a Resource Recovery Facility (recovery of recyclables and fuel production).

 

The main thrust of the contract is the diversion of waste from landfill. High targets were set which were well in excess of the average recovery rates being achieved nationally, and which after year 5 of the contract increases incrementally by 1% on an annual basis. The current annual target is 30%. Diversion of waste from landfill has many advantages to the Council both financially and environmentally.

 

The original contract length was twelve years. The Council extended the contract by six years in the year 2000. The current contract will end in October 2015. Part of the basis of this extension was to allow IWS to make capital investment in the existing Waste Derived Fuel Plant, to convert it into a Resource Recovery Facility that would produce a partially densified floc fuel from the same feedstock as was processed by the WDF plant but which would also produce additional fuel from wastes that were un-processible through the existing WDF plant pelletisisation system. This increased the throughput and effectiveness of the plant, and hence diverted more waste from landfill. The existing power plant facility adjacent to the RRF facility also had to be converted to be able to accept the floc fuel. This is operated by another company, Combined Heat and Power (CHP) / Ener-G, with whom IWS have a separate contract for the supply of floc fuel. Works to modify the WDF plant commenced in January 2001. Since becoming fully operational earlier this year recovery rates have increased significantly, and have on a number of occasions exceeded 50%, which was the desired outcome of the revised process. The average recovery rate for year 5 of the contract exceeded 49%

 

However, on the 31st October 2002, the power plant operation was closed and ceased to accept any of the floc fuel production from the RRF plant, following a prolonged period of discussions and negotiations between IWS and CHP concerning various operational and other issues. In the short term it is unlikely that the power generation facility will come back on line. It has therefore become necessary for IWS to source alternative markets for the floc fuel.

 

Alternative markets for the fuel do exist on the mainland, although the transport logistics of such an operation do create problems. Island markets have also been investigated, but found not to be viable. An outlet has already been established in Lincolnshire and investigations are currently ongoing for an alternative site in Wiltshire. Loads have already been sent on a trial basis to the Lincolnshire outlet with great success as far as the combustion process is concerned.

 

At the present time the new tipping cell at Standen Heath landfill is being brought into use and will require approximately 8,000 tonnes of soft waste to be placed in the base as a protection blanket. This was a programmed event and would have required waste to be diverted from the RRF plant in any case.

 

In the short term waste will continue to be processed at the RRF plant with a target of two loads of floc daily being transported to the mainland (approximately 40 tonnes). The remainder will be used on the landfill site, initially as a soft protection layer, and then for disposal. Extraction of steel and aluminium will continue at the RRF facility and the fine rejects from the plant will continue to be processed through the in-vessel composter at Lynnbottom. Plant and equipment has been sourced, including two walking floors and five bulk carriers, which will be used in the short term to transport floc to the Lincolnshire plant.

 

Negotiations are currently being undertaken by IWS for the installation of a baling press. This will make the handling of the floc fuel easier and more economic for export to the mainland. In addition the quantity that can be delivered on a daily basis can be increased to approximately 55 tonnes. The machine will also be capable of baling cardboard for recycling rather than converting it to fuel or disposing of it to landfill. This will also improve the performance and efficiency of the main processing plant without its modification, and therefore not compromise operations in any way should the energy from waste plant be re-commissioned in the future.

 

It is expected that in the short term with approximately 40 tonnes of floc fuel being delivered to the mainland that recovery rates will remain at or above 40% in line with the average recovery rates to date. With a baling process in place, and an increased tonnage being delivered, recovery rates will increase to be more in line with recent recovery rates.

 

However, IWS have indicated that they are committed to the principle of an energy from waste plant on the Island, and have indicated that it is their intent to submit a planning application for construction of their own state of the art unit to replace the existing energy plant.

 

STRATEGIC CONTEXT

 

Waste management and recycling form part of the innovative Private Finance Initiative scheme and are consistent with the Corporate Plan objectives.

 

 

 

 

FINANCIAL IMPLICATIONS

 

Within the contractual arrangements with IWS they are required to meet recycling targets for each year of the contract. If IWS had only met their contractual target of 30% recycling for the current contract year the cost of landfill tax to the Council would have been £682,500, based on a landfill tax charge of £13 tonne, and 52,500 tonnes of waste being landfilled. However, IWS achieved a much higher recycling rate of 50%, which resulted in a saving to the Council of £97,500 in landfill tax charges (i.e. landfill tax charges reduced to £585,000). The closure of the Power Plant is likely to result in a recycling rate of 40%, still some 10% in excess of the contractual obligation. This will result in the savings to the Council being reduced to approximately £48,750, based on current landfill tax rates, and tonnages of waste being processed.

 

LEGAL IMPLICATIONS

 

None

 

EVALUATION / RISK MANAGEMENT

 

The apportionment of risk benefit is clearly defined in the PFI agreement. The closure of the plant will not give any greater risk than at present.

 

 

RECOMMENDATIONS

 

That this report is noted and that further reports be brought back to this committee as required providing updates.

 

BACKGROUND PAPERS

 

None

 

Contact Point: Steve Boswell Tel: 823732

 

 

 

 

                                                                        STEPHEN MATTHEWS

                                                                        Head of Engineering Services