To provide members with an update on the Economic Development Best Value Improvement Plan.

 

ACTION REQUIRED BY SELECT COMMITTEE

 

Members to note the actions taken to date.

BACKGROUND

 

The Best Value Review of the Economic Development service of the Council was carried out at the end of 2001 and the Improvement Plan was finalised in March 2002.  At that time the Council’s Economic Development Unit was seconded to the Isle of Wight Economic Partnership (IWEP), which was undergoing a major restructuring.

 

In April 2002 the Council’s Economic Development Unit returned to the Council and in November 2002 was subsumed into the new Policy Unit as part of the Council’s restructuring process.  As a result of these changes much of the Best Value Improvement Plan has been overtaken by events and the consequent changes in roles and responsibilities.  However, some of the key achievements are as follows:

 

IWEP Recovery Plan and Activities

 

Service Improvement Issue 1 – Establishing a sustainable delivery structure;

 

Service Improvement Issue 2 – maintaining and improving performance;

 

            Aim 1: Building competitive business;

            Aim 2:Creating a culture of innovation;

            Aim 5: Regenerating our deprived neighbourhoods;

            Aim 6: Regenerating our Rural Communities;

 

Service Improvement Issue 3 – Establishing an effective monitoring and evaluation framework

 

·         Ref 1-IWEP was successfully restructured and is now operating on a sound financial basis.

·         Ref 2 - An audit of IWEP was carried out by Ernst and Young, paid for by SEEDA, giving the company a clean audit report, thus allaying concerns regarding possible financial irregularities in the past running of the organisation.

·         Ref 31,32,33, 36, 37, 38, 40, 41 - The Council have entered into a new Service Level Agreement (SLA) with IWEP for the period 1 April 2002 to 31 March 2003, which has now been finalised.  IWEP are the main delivery agency for economic development activity on the Island.  Their main activities are the delivery of regeneration programmes for the Island (including SRB, Rural Development Programme and Leader +); marketing and inward investment, management of the innovation centre and enterprise hub.  The SLA provides for regular structured monitoring of the activities and performance of IWEP to this Committee.


·         Ref 19 - The Cowes development strategy is now well under way with Project Cowes.  IWEP are taking a lead on this but are working closely with the Council’s Planning department.

 

Area Investment Framework

Service Improvement Issue 1 – Establishing a sustainable delivery structure

 

Ref 5 - he Area Investment Framework (AIF has been developed for the Island and is now being used as a tool to help prioritise projects seeking external funding, including those developed by the Council.

 

External Funding Service:

Service Improvement Issue 1 – Establishing a sustainable delivery structure

 

Ref 6, 30, 34 - The Council’s external funding service has been established:

·         two members of staff

·         development of a funding web page on the Council’s web-site which is available to everyone.

·         Work in starting on establishing a network of project offices in each service section to help identify and work up projects and the associated funding applications.  These will be facilitated and supported by the external funding staff

 

Central Research Unit

Service Improvement issue 2 – Maintaining and Improving performance

 

Ref 11, 12 - A research and information service is now provided as part of the activities of the restructured Corporate Policy Unit.

 

Staff Training and Development

Service Improvement issue 2 – Maintaining and Improving performance

 

Ref 10, 18 - With the return to the Council, the relevant staff now come under the Council’s protocol for training and performance review.  The Policy and Communication Unit are working towards the Investors in People award.

 

Tourism

Aim 3: Developing the tourist industry

 

Ref 23 - Tourism strategy, which formed part of the Economic Development plan is now subject to a separate investigation exploring the potential for externalising the service.  This is being led by the Council’s Tourism and Community Development service which is currently responsible for Isle of Wight tourism.

 

Learning Partnership

Service Improvement issue 2 – Maintaining and Improving performance

            Aim 4: Improving skills and education

 

Ref 24, 25 - The IoW Learning Partnership is active and provides a key focus for the learning agenda.

 

Successful Projects

Service Improvement issue 2 – Maintaining and Improving performance

            Aim 4: Improving skills and education

 

Ref 28 - The EU Territorial Employment Pact project was successfully delivered, bringing £170k funds to IWEP.

Ref 30 - Over £1.3m ESF funding has been approved for the Island between May and Sept 2002.

 

Outstanding issues in the Development Plan will be addressed in conjunction with IWEP through the SLA.

 

RELEVANT PLANS, POLICIES, STRATEGIES AND PERFORMANCE INDICATORS

 

Economic Development Best Value Improvement Plan, March 2002.

The IWEP are delivering the following PSA targets over the period 1.4.03 – 31.3.06 on behalf of the Council as part of their SLA:

·         Increasing employment on the Isle of Wight by the creation of 100 new jobs and assisting 6 new and expanding companies.

·         Increasing the number of workless people over 50 years old getting sustained jobs by 120.

 

CONSULTATION PROCESS

 

As part of the Best Value review process the following activities were undertaken:

·         Internal stakeholder consultation with IWP staff – 20 interviews

·         External stakeholder consultation – 80 questionnaires

·         MORI citizens panel – 1,700 Isle of Wight residents

·         Economic Development Challenge Day – attended by over 50 stakeholders

·         Series of meetings including the BV Project Group and Appraisal Group.

·         One-off meeting and discussions with key stakeholders eg Planning, IW Tourism< Members of Economic Development Select Committee, Heads of Paid Service.

 

FINANCIAL IMPLICATIONS

 

Under the SLA the Council gives IWEP £104,000 plus seconded staff costing £75,000 per year to IWEP for delivery of Economic Development services.  In addition the Council has the cost of its own staff and associated overheads incurred through economic development activity.

 

LEGAL IMPLICATIONS

 

The Council has a contractual obligation under the SLA between the Council and IWEP.

 

APPENDICES ATTACHED

 

The Economic Development Best Value Improvement Plan is attached at Appendix 1

 

BACKGROUND PAPERS

 

Economic Development – Best Value Review (March 2002)

Economic Development – Best Value Review – Summary Report (March 2002)

Contact Point : ,          John Bentley

                                    Head of Corporate Policy and Communications

                                    Ext 3346

 

 

JOHN BENTLEY

Head of Corporate Policy and Communications


Appendix 1

ECONOMIC DEVELOPMENT BEST VALUE REVIEW PLAN

           

 SERVICE IMPROVEMENT ISSUE 1  -  ESTABLISHING A SUSTAINABLE DELIVERY STRUCTURE

Ref:

ACTION

TARGET DATE

LEAD

 

1

 

 

 

 

 

2

 

 

3

 

 

4

 

 

 

 

 

 

 

 

Fully implement IWEP Recovery Plan to establish the agency on a sound and stable financial footing.   Central to this is a “federal” delivery model which establishes the IWEP as the delivery arm of the service and the Council as the body responsible for advising the Board on strategic and developmental issues.

 

As part of the Recovery Plan, an audit of IWEP is to be undertaken by Ernst and Young

 

Three year funding strategy to be developed for IWEP to access additional external resources

 

Case to be developed for additional Council support for the service as part of the 2003/04 budget process.   This will include investigation of the potential for additional funding and further staff secondments.

 

 

April 2002

 

 

 

 

 

May 2002

 

 

 

September 2000

 

 

 

September 2002

 

 

IWEP board & Management team

 

 

 

 

Danny Fisher

 

 

 

John Bentley

Mike King

Liz Wood

 

John Bentley

 

 


 

Ref:

ACTION

TARGET DATE

LEAD

 

5

 

 

 

 

 

 

 

 

 

 

 

 

6

 

7

 

Area Investment Framework (AIF) to be developed for the Island.   The AIF will be a diagnostic tool which matches needs to planned resource expenditure across the public, private and voluntary sectors.   The resulting “gap analysis” will support bids for external funding to deliver the Island Regeneration Strategy.   The AIF will provide

the basis for development of a bidding strategy to secure the necessary external resources to deliver the Regeneration Strategy.

 

“Funder-finder” service to be developed to maximise the levels of external funding secured.   This will provide a co-ordinated information and support service for the public, voluntary and private sectors.   To include provision of information, training programme, consultancy support and bid writing service.

 

Partnership Protocol to be developed to ensure effective multi-agency working and liaison with the new Local Strategic Partnership.

 

 

 

 

July 2002

 

 

 

 

 

 

 

 

 

 

 

 

September 2002

 

June 2002

 

John Bentley

Liz Wood

 

 

 

 

 

 

 

 

 

 

 

John Bentley

 

John Bentley

 


SERVICE IMPROVEMENT ISSUE 2 – MAINTAINING AND IMPROVING PERFORMANCE

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

8

 

 

9

 

 

 

 

10

 

Whole Service

 

Island Regeneration Strategy to be reviewed in light of new Community Plan

 

Marketing and Communications Strategy to be developed to improve public awareness of the service.   Particular attention to the use of the Council and IWEP web sites and links with the Council’s Policy and Communications Officer

 

Personal Development Plans to be developed/agreed with all service staff on an annual basis

 

 

 

 

 

 

 

 

 

December 2002

 

 

Sept. 2002

 

 

 

 

June 2002

 

 

 

 

 

 

 

 

 

 

John Bentley

 

 

Mike King

 

 

 

 

John Bentley

Mike King

Liz Wood

 

 

 

 

 

 

 


Ref:

ACTION

TARGET DATE

LEAD

 

11

 

 

 

 

 

 

 

    12

 

 

    13

 

 

 

 

 

 

 

 

 

Review to be undertaken investigating scope for establishing a Central Research Unit (within the Council’s Economic Development Unit) to provide a “one stop” information and research service.   This would support bid development activities and provide a resource to support policy and service development.

 

2 IWEP research staff have been transferred to the Council Economic Development Unit as part of the IWEP reorganisation. Funding for the posts is to be secured through research consultancy work to generate external income.

 

EU and Brussels Office strategy to be developed to clarify aims and means of achievement.

 

Dec. 2002

 

 

 

 

 

 

 

March 2003

 

 

July 2002

 

 

John Bentley

 

 

 

 

 

 

 

John Bentley

 

 

John Bentley

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

14

 

 

 

15

 

 

16

 

 

 

17

 

 

 

18

 

AIM 1: Building competitive businesses

 

Inward Investment and Marketing Strategy to be developed setting out the target sectors and means by which the IWEP will seek to market business opportunities on the Island.

 

Sites/Premises Strategy to be developed to ensure ability to meet anticipated business needs

 

Ambassador Scheme to be developed aimed at equipping key business and public figures with the skills/information to promote business opportunities on the Island.

 

Client Management Protocol to be developed to ensure consistent approach to the handling of potential investors by Council, IWEP and Business Link staff

 

Training programme to be developed for staff and councillors – planning training for IWEP staff, investor handling for planning officers, the development process for members.

 

 

 

 

 

 

 

September 2002

 

 

 

December 2002

 

 

September 2002

 

 

 

May 2002

 

 

 

June 2002

 

 

 

Mike King

 

 

 

Mike King

Paul Airey

 

Mike King

 

 

 

Mike King

Paul Airey

 

 

Mike King

Paul Airey

 

 

 

 

 

 

 

 

 

19

 

 

 

 

 

 

 

Cowes Development Strategy to be prepared utilising the international status of the town brand and realising development potential.

 

 

 

 

 

July 2002

 

 

 

Mike King

 

 

 

 

 

 

 

 


 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

20

 

 

21

 

   

22

 

 

 

 

 

AIM 2: Creating a culture of  innovation

 

Marketing Strategy for the Enterprise Hub will be developed as part of the proposed Inward Investment Strategy (Ref. 14).

 

Proposals to be developed for a satellite Enterprise Hub facility to provide further high tech incubator space.

 

Composites Development Plan to be drafted as a policy framework for development of this key sector.

 

 

 

 

 

 

 

 

 

 

September 2002

 

 

 

 

 

May 2002

 

 

 

 

 

 

 

Mike King

 

 

Mike King

 

 

Mike King

 

 

 

 

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

23

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AIM 3:  Developing the tourist  industry

 

Tourism Strategy to be developed with a focus upon:

 

·         Action to raise the Island profile as a distinctive destination.

·         Action to broaden the market base and lengthen the season

·         Action to enhance the status of tourism on the Island

·         Action to improve the range and quality of accommodation

·         Action to improve the quality of the visitor experience.

·         Action to improve employment prospects within the industry

·         Action to improve our key resorts

 

The Strategy will also examine the staff and resource requirements to deliver it including an investigation of the need for organisational changes within the Council.

 

 

 

 

September 2002

 

 

 

Tim Addison

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

24

 

 

 

 

 

25

 

 

 

 

 

26

 

27

 

AIM 4:  Improving Skills and Education

 

The Council will assume the “host agency” role for the IOW Learning Partnership, with the Manager reporting to the Assistant Director for Education.   This will support an all-age approach to the learning agenda.

 

The Council and IWEP will continue to actively support the Learning Partnership. Priorities include delivery of the Basic Skills Action Plan, Learner Feedback projects and EoP issues.

 

The Council and IWEP will seek to agree a compact with the Learning and Skills Council to ensure that the LSC Strategic Plan meets the needs of the Island and provides the basis for a joint approach to improving skills and education.

 

The Council and IWEP will actively support implementation of the IW College Recovery Plan.

 

 

 

 

 

 

January 2002

 

 

 

 

 

On-going

 

 

 

 

 

September 2002

 

On-going

 

 

 

David Pettitt

 

 

 

 

 

John Bentley

Liz Wood

 

 

 

 

John Bentley

Janet Stevens

John Bentley

Mike King

Liz Wood

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

28

 

 

 

 

 

29

 

 

 

30

 

The Council and IWEP will complete delivery of the EU Territorial Employment Pact project which seeks to establish a partnership approach to employment and labour market planning.

 

Proposals for a customised investor training package will be developed as part of the Inward Investment Strategy (Ref 14)

 

As part of the proposed Area Investment Framework (Ref. 5) and Funder-Finder (Ref 6) service, proposals will be developed to maximise the levels of ESF funding secured to support training initiatives.

 

 

 

 

 

 

 

 

 

 

 

July 2002

 

 

 

 

 

September 2002

 

 

 

September 2002

 

John Bentley

 

 

 

Mike King

 

John Bentley

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

 

31

 

 

 

32

 

 

 

33

 

 

 

 

 

AIM 5:  Regenerating our deprived  

              neighbourhoods      

 

The IWEP will continue to deliver the SRB programmes on the Island.   Performance in this area is excellent and fully complies with the management and audit requirements of SEEDA.

 

The IWEP will continue to develop sustainable mechanisms to support on-going community regeneration.   The setting up of community development trusts is the preferred model.            

 

The Council and IWEP will actively support delivery of the Island Social Exclusion Strategy through delivery of SRB, RDP, Healthy Living and Leader+ programmes.

 

 

 

 

    

 

 

 

 

On-going

 

 

 

On-going

 

 

 

On-going

 

 

 

 

 

 

 

 

Liz Wood

 

 

 

Liz Wood

 

 

 

Liz Wood

John Bentley

 

 

 

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

34

 

 

As part of the proposed Area Investment Framework (Ref 5) and Funder-Finder (Ref 6) service, proposals will be developed to maximise the levels of funding secured to support area regeneration projects.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

July 2002

 

 

John Bentley

 

 

 

 

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

 

35

`

 

36

 

 

 

37

 

 

 

38

 

 

39

 

AIM 6:  Regenerating our rural

               Communities

 

Review to be undertaken of the executive support arrangements for the IWEP Rural Issues Group.

 

The IWEP will continue to deliver the Rural Development Programme for the Island.   Performance in this area is excellent and fully complies with the management and audit requirements of SEEDA.

 

Arrangements will be put in place for the IWEP to deliver the recently secured funding under the EU Leader+ programme aimed at rural regeneration.

 

The IWEP will support delivery of the recently secured funding under SEEDA’s Market Towns programme.

 

As part of the proposed Area Investment Framework (Ref 5) and Funder-Finder (Ref 6) service, proposals will be developed to maximise the levels of Countryside Agency funded secured to support rural regeneration.

 

 

 

 

 

 

 

Sept. 2002

 

 

On-going

 

 

 

April 2002

 

 

 

On-going

 

 

July 2002

 

 

 

 

Liz Wood

John Bentley

 

Liz Wood

 

 

 

Liz Wood

 

 

 

Liz Wood

 

 

John Bentley

 


 

SERVICE IMPROVEMENT ISSUE 3 – ESTABLISHING AN EFFECTIVE MONITORING AND EVALUATION FRAMEWORK

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

 

 

40

 

Whole Service

 

Revised Service Level Agreement (SLA) between Council and IWEP to be drafted.   The SLA will set out the nature/extent of the Council’s contribution to the IWEP (staff and finance) and the authority’s requirements in terms of service delivery and working practices.   Particular attention will be placed upon:

 

  • Establishing a Council/IWEP Protocol for reporting back to the Council and sharing information.
  • The requirement for the IWEP to actively support implementation of the BV Improvement Plan.
  • Financial monitoring arrangements.
  • Establishing a Code of Conduct for IWEP staff and Board directors.

 

 

 

 

 

 

 

May 2002

 

 

 

John Bentley

 

 

Ref:

ACTION

TARGET DATE

LEAD

 

41

 

 

 

 

 

 

 

 

 

 

 

 

42

 

 

43

 

 

Monitoring and Evaluation Strategy to be drafted to support assessment of both outputs and outcomes.   Key elements of the Strategy to include:

 

·         Clear standards/targets to be set for IWEP activities.

·         Development of Benchmarking Club to facilitate on-going comparative assessment.

·         Monitoring emerging best practice in use of Performance Indicators.

·         Identification of rolling programme of service activity reviews including the carrying out of SRB evaluation

 

 

Economic Development service to be fully incorporated into BVPP for 2003/04.

 

Annual Work Programme to be prepared for the Council and IWEP elements of the service setting out details of activities and standards/targets to be achieved.   This will assist in achieving a better balance between stakeholder expectations and resource availability.

 

 

September 2002

 

 

 

 

 

 

 

 

 

 

 

 

December 2002

 

 

April 2002

 

John Bentley

 

 

 

 

 

 

 

 

 

 

 

 

 

 

John Bentley

 

 

John Bentley

Mike King

Liz Wood