SUMMARY / PURPOSE:
This report summarises information
on the 2002/03 Service Plan for Economic Development service together with
information and commentary on past performance in 2001/02.
Service Plans have been prepared
to a standard format for all major service areas within the authority. The
Plans contain a range of information including :
Following preparation of a
Corporate Plan (draft approved for consultation at Executive on July 2nd
2002), a revised Service Plan format is to be introduced for the next financial
year – this will ensure that service activities directly link to the approved
corporate goals.
The Council also collects a
diverse range of information regarding service performance through both
national and local Performance Indicators (PIs) which are published each year
in the Best Value Performance Plan (BVPP). In the 2001/02 BVPP, a “traffic light” system has been introduced to
classify PIs by the following categories :
Attached
to this report (Annex 1), members will find summary information for the
following service areas :
The
information provided in Annex 1 includes :
Members
should note the following :
Members
are invited to comment upon the Service Plan. Areas for enquiry may include :
As there have been no Performance
Indicators previously set for the Economic Development Service it was not
possible to measure performance against these when the Best Value review was
carried out. However, under Section 7
of the Service Plan targets have been set for the current year and Section 8
identifies non-numeric achievements and areas for improvement.
None as a direct result of this
report.
Best
Value Performance Plan, 2001/02
RECOMMENDATION
That
the Committee : 1.
Consider and comment upon the Service Plan 2.
Consider and comment
upon the Performance Indicators for the service and identify priority areas
for improvement |
Contact
Point : Lesley Williams, Acting Head of Economic Development; Ext 3797
Alan Kaye
Head of Paid Service
ANNEX 1 : SERVICE PLAN
7. STATEMENT OF PERFORMANCE 1
NUMERIC INDICATORS, TARGETS, STANDARDS AND COMPARISONS
PERFORMANCE INDICATOR AND SOURCE |
PERFORMANCE Note: No Performance Indicators previously set |
BENCHMARKING Note: No Nationally Agreed Framework available |
|
ACTUAL 01 / 02 |
ESTIMATE 02/03 |
TARGET (& DATE) |
COMPARATIVE PERFORMANCE (DATE) |
SOURCE OF COMPARISON |
Review of Island Regeneration Strategy in light of
Community Plan |
|
1
Revised Strategy |
December
2002 |
|
|
Revise Service Level Agreement between Council and IWEP |
|
1 new SLA |
September 2002 |
|
|
EU and Brussels Office Strategy reviewed |
|
1
strategy |
December
2002 |
|
|
EU
funding approved for the Isle of Wight |
£1.2m |
£850k |
March
2003 |
|
|
Total
value of Research Consultancy contracts won |
£105,000 |
£50,000 |
March
2003 |
|
|
Development
of Funder-finder service to maximise levels of external funding to support
economic development activities |
|
Service
defined and resources identified and in place |
December
2002 |
|
|
8. STATEMENT OF PERFORMANCE 2
NON NUMERIC PERFORMANCE STANDARDS, SIGNIFICANT
ACHIEVEMENTS OR AREAS FOR IMPROVEMENT
During
last 12 months |
Achievements.
Despite a period of
major organisational changes in the IWEP staff continued to deliver an
effective service including: ·
Successful
Leader + bid (£2.5m grant funding) ·
Help
in accessing over £1.7 m ESF funds for the Island ·
Successful
winning and executing over £105k of commercial consultancy work, including
some key sector skills work that has led to the development of projects for
the Island in the composites sector ·
Continued
delivery of a valuable information service both regarding European issues and
statistical information and analysis |
Areas
for Improvement. Three
main areas for improvement were identified in the Best Value Review carried
out in March 2002: ·
Establishing a sustainable organisational structure
for service delivery (of economic development services) ·
Maintaining and improving performance in service
delivery ·
Establishing effective monitoring and evaluation
arrangements In
addition the following are considered in need of improvement: ·
Communication
with both internal departments and external organisations ·
Promoting
“success stories” of achievements ·
Ensuring
that funding approved is spent ·
Quality
of projects submitted for funding and quality of their delivery ·
Ensuring
that environmental considerations permeate ALL aspects of economic
development activities |
Over
last 1 to 3 years |
Achievements.
Establishment of Isle
of Wight Partnership (regeneration partnership for the Isle of Wight) whose
main achievements have been: ·
A
number of notable new investment projects attracted to the Island creating or
safeguarding over 1,000 jobs ·
Establishment
of an Innovation Centre on the Island which will be the focus for a
“composites cluster” ·
Significant
new development at Somerton, Cowes with over 7,000sq m of new industrial
floor space ·
Expansion
of a number of existing businesses.
SP Systems have established a purpose built headquarters in St Cross,
Newport; Pascall Electronics have similarly expanded into a new building in
Ryde ·
Success
in accessing over £20m UK and EU regeneration funding since 1996 to support a
range of comprehensive regeneration initiatives and training projects
throughout the Island ·
Successful
delivery of SRB and RDP regeneration programmes for which funding has been
granted. |
Areas
for Improvement. ·
Communication
with both internal departments and external organisations ·
Promoting
“success stories” of achievements ·
Ensuring
that funding approved is spent ·
Quality
of projects submitted for funding and quality of their delivery |
11. SERVICE AIMS, OBJECTIVES, TASKS AND TARGETS
SERVICE AIM /OBJECTIVE |
TASKS |
TARGETS AND DATES |
RESPONSIBLE OFFICER |
DIRECTORATE OBJECTIVE TO WHICH THIS TASK CONTRIBUTES |
a. The
creation and safeguarding of employment |
1.Assist
in the development of projects to support employment / training 2.Help in identifying and accessing funding to
support training and employment projects 3. Continue sector skills research to identify key
areas of employment opportunities 4. Encourage / work with the LSC, Business Link
and the Enterprise Company to continue services for business support to the
Island |
1. Ongoing 2. Ongoing 3. Ongoing 4. Ongoing |
1 All staff 2 Head of Economic Development , EU Unit 3 Policy and Research Manager 4 Head of Economic Development |
1 1,2 and 4 2 1 and 4 3 1 and4 4 1,2 and 4 |
b.
Maximise benefits from EU and UK funding opportunities |
1. Continue providing support for ESF funding –
seminars / workshops / newsletter / one-to-one advice and guidance 2.Develop funder-finder service to enable this
service to be extended to non-EU funding 3.Encourage partnership working to avoid
duplication of effort in projects 4 Promote information on success stories 5 Encourage better quality projects and better
quality of delivery through workshops and promotion of best practice |
1 Ongoing 2 Service defined, resources
identified by December 2002 3 Ongoing 4 Ongoing 5 Ongoing |
1 Principal European Officer, EU
Officer 2 Policy and Research Manager / European Officer 3 Head of Economic Development 4 Head of Economic Development (all staff to contribute) 5 Head of Economic Development , Prinicipal EU
Officer, EU Officer |
1 1,2,4 2 All objectives 3 All Objectives 4 All Objectives 5 All Objectives |
c. Maximise potential to influence UK and EU
policies for the benefit of the Island |
1 Respond
to relevant consultations both directly and through associations such as the
Islands Commission, LGIB etc 2 Play an active part in the lobbying activities of associations
such the Islands Commission which
benefit the Island by attending conferences, participating in joint
activities 3 Ensure that the message sent in response to
different consultations is consistent |
1 As required – dependent on
external bodies (eg EU Commission, UK Government etc) 2
Islands Commission
Conference – May 2002 CPMR conference 0 Sept 2002 3 Ongoing |
1 Head of Economic
Development 2 Principal European Officer 3 Head of Economic
Development |
1 provides support to all objectives 2 provides support to all objectives 3 provides support to all objectives |
D Ensure that as far as possible the tenets of
environmental sustainability permeate through all economic development
activities. |
1 Encourage
environmental awareness in all project development work (a requirement of ALL EU funding already) 2 Lead by
example by ensuring the Economic Development Unit adopt these principals as
far as possible (eg use both sides of paper, recycle envelopes, turn of
lights and PCT when not needed etc) 3 Assist
the IWEP in the drawing up of their environmental policy (a requirement of
the TEP project) 4 Ensure that this principal is incorporated in the SLA
between the IWEP and the Council |
1 Ongoing 2
Ongoing 3
July 2002 4 September 2002 |
1 All Staff 2
All Staff 3
Principal European
Officer 4 Head of Economic Development |
1 Contributes to all objectives – in particular 1,3,5,6. 2 3 Contributes
to all objectives – in particular 1,3,5,6. 4 Contributes to all objectives – in particular 1,3,5,6. |
ANNEX 2 : PERFORMANCE INDICATORS