RURAL DEVELOPMENT PROGRAMME
QUARTERLY
MONITORING REPORT
QUARTER 2, (2002/03)
Progress against Key Indicators.
Partnership, Management and Administration |
Review of all management systems in line with DETR guidance and new output requirements by July 2002. |
Management systems reviewed in line with DETR guidance and output tables being adjusted for second half of year.
Strategy & Programme Co-ordination |
Formal reporting mechanisms through the Rural Management Group in place by July 2002. |
Rural Management Group in place and quarterly reports will be distributed and discussed at Rural Issues meetings.
Leverage Private Public Total |
£265,508 £162,500 £428,008 |
Planned Private Sector Leverage £265,508
Actual
Private Sector Leverage £303,546
Debit OR Credit £38,038 credit
Planned Public Sector Leverage £162,500
Actual
Public Sector Leverage £302,174
Debit OR Credit £139,674 credit
RDP expenditure defrayed |
£ 117,801 |
Actual RDP expenditure defrayed £164,212
No 4 Farming Futures |
Links established with Leader+ Project Officer and joint meetings to develop action plan to stimulate project development to support farm diversification and farming developments by September 2002. |
Links with Leader+ established and development worker network set up to
discuss mechanisms to address farm diversification at local and regional
levels.
No 5 Meeting the needs of Rural Businesses |
Interviews with key stakeholders for feasibility of establishing air links to the Island completed by September 2002. Joint working with other Rural programme officers to develop action plan to stimulate project development to meet the needs of Rural Businesses by September 2002. |
Discussion has taken place to request Leeds University to undertake the feasibility study.
Regular network meetings of IWEP, IWC, RCC and Island Volunteers established to review the delivery of RDP, MTI, Leader+ and Vital Villages.
Progress has also been made with the scoping exercise involving the Farm Advisor and other rural activities, to share information and to develop joint actions
No 6 Meeting Community Needs
|
New community based database in place; training needs analysis completed for community trainers and support mechanisms in place for town co-ordinators and village clerks by September 2002. |
New Community Database established through project based at West Wight Information Centre.
Capacity building workshops have been developed and are scheduled to commence in Q3 in Sandown.
A community capacity building portfolio has been developed, through the network mentioned in 5 above and is now available to all organisations.
Parish clerks training/options will be discussed during October.
No 7 Protecting and Enhancing the Island’s Rural Environment |
Links established with Leader+ programme and mapping exercise to establish gaps in achieving the objectives of this theme under the Rural Strategy by August 2002. Restructuring and relaunch of Sustainable Tourism Forum by September 2002. |
All projects in RDP and Leader+ listed to establish links / joint working practices and gaps. Outcome to be discussed at next Rural Issues Group meeting.
Meetings have been held between the Assistant Director of Community and Development and ITIA to discuss the way forward for the Sustainable Tourism Forum.
The re-launch is now scheduled for November 2002.
No 8 Outputs |
3.6 jobs created; 440 counselling sessions completed and 3030 people advised
by September 2002. |
6.1 jobs created
449 counselling sessions
4056 people advised
Signature: Name: [BLOCK CAPITALS] |
|
Position: Date: |
SRBII ‘ALTOGETHER WIGHT’
QUARTERLY
MONITORING REPORT
QUARTER 2 YEAR 7 (2002/03)
Progress against Key Indicators.
Partnership, Management and Administration |
Completed
Statement of Grant Expenditure to Auditors by September 2002. |
Completed Statement of Grant Expenditure to Auditors by first week in October.
Leverage Private Public Total |
£14,500 £147,000 £161,500 |
Planned Private Sector Leverage £14,500
Actual
Private Sector Leverage £42,663
Debit OR Credit £28,163 credit
Planned Public Sector Leverage £147,000
Actual
Public Sector Leverage £53,659
Debit OR Credit £93,341 debit
Public Sector leverage down due to delay in Ventnor Harbour project.
SRB expenditure defrayed |
£137,890 |
Actual SRB expenditure defrayed £121,000
Ventnor Harbour Scheme delayed, but will start second week of November
2002.
No 8 RDP[S02] |
Review
of all management systems in line with DETR guidance and new output
requirements by July 2002. |
Management systems reviewed in line with DETR guidance and output tables being adjusted for second half of year.
No 10 Ventnor Harbour |
Commencement of construction of harbour arms by
May 2002. Complete rock deliveries
by Aug 2002. |
Project was on hold
pending DEFRA approval, (now approved 24/10/02.) Considerable progress has been made in the quarter in
implementing the construction phase. Project went out to tender in June, lowest
tender was returned within budget and the contractor has been notified of the
intention to appoint him for the construction phase which will now start on 4
November 2002.
No 14 (a)
Baseline Data (b)
Evaluation |
(a) Socio-economic
analysis completed and fed into AIF by April 2002. (a)
AIF in place and being used by Local Strategic Partnership and Isle of Wight
Economic Partnership in the planning process by July 2002. (b)
External consultancy commissioned to carry out evaluation of all SRB
programmes by Aug 2002. |
(a) Completed and document available. Draft copy has been circulated to LSP and IWEP and comments are being fed back for final document to be produced – November 2002.
(b) Contacts for suitable consultants being collated from other SRB areas.
Outputs |
10
Jobs created by Sept 2002 [1A(i)] 2
New business starts in Innovation Centre by Sept 2002 [2A] |
1A(i) – 15 jobs created
2A – 2 new businesses in Innovation Centre
Signature: Name: [BLOCK CAPITALS] |
|
Position: Date: |
SRBIV ‘BUILDING A
COMMUNITY BRIDGE TO EMPLOYMENT’
QUARTERLY
MONITORING REPORT
QUARTER 2 YEAR 5 (2002/03)
Progress against Key Indicators.
No1 Partnership, Management and Administration |
Completed Statement of Grant Expenditure to Auditors by September 2002. |
Completed Statement of Grant Expenditure to Auditors by first week of October.
No3 Leverage Private Public Total |
£401,500 £269,500 £671,000 |
Planned Private Sector Leverage £401,500
Actual Private Sector Leverage £375,503
Debit OR Credit £25,997 credit
Planned Public Sector Leverage £269,500
Actual Public Sector Leverage £452,629
Debit OR Credit £183,129 credit
No4 SRB expenditure defrayed |
£75,000 |
Actual SRB expenditure defrayed £130,281
No 7 Overcoming
Barriers (a) Ladders (d) Cowes Extension College |
(a) Marketing initiative for Ladders Project in place by
Sept 2002. (d) Publication of black and white cards using student photos by April 2002. (d) Preparation of new after
school programme to introduce Arts workshops for the community by August 2002 |
(a) The Ladders project has been successful in
stimulating sufficient interest within the community to justify the provision
of new resources for adult basic skills learning in the Cowes and East Cowes
areas. Two new resources have now been
set up to deliver adult learning opportunities. The Isle of Wight College have started to provide weekly free
classes in East Cowes Library and Community Solutions have set up a Community
Learning Centre in Cowes, providing free basic literacy/numeracy and basic
computing courses (copies of advertising for both resources attached to this
Report). The project has been
successful in its aims to stimulate community activity and provide sustainable
provision to meet the community needs.
(d) Photocards have now been
published.
Arts workshops including jazz, textiles & photography, have been introduced into
the after-school programme. They will be enhanced further by ‘Awards for All’
funding.
No 19 Leisure for Youth(a)
HECK [Help East Cowes Kids] |
(a) Annual General Meeting by Sept 2002. |
(a) The project's AGM took place on 11th September 2002.
Evaluation |
External consultancy commissioned to carry out evaluation of all SRB programmes by Aug 2002. |
Contacts for suitable consultants being collated from other SRB areas.
Outputs |
16 Business Starts by Sept 2002 (2A) 525 Young people benefiting from projects to promote social development by Sept 2002. [1J] |
2A – numbers being confirmed.
1J – 587 young people benefiting.
Signature: Name: [BLOCK CAPITALS] |
|
Position: Date: |
QUARTERLY
MONITORING REPORT
QUARTER 2 YEAR 4 (2002/03)
Progress against Key Indicators.
Partnership, Management and Administration |
Completed Statement of Grant Expenditure to Auditors by September 2002. |
Completed Statement of Grant Expenditure to Auditors by first week of October.
Leverage Private Public Total |
£79,500 £118,250 £197,750 |
Planned Private Sector Leverage £79,500
Actual Private Sector Leverage £56,647
Debit OR Credit £22,853 debit
Planned Public Sector Leverage £118,250
Actual Public Sector Leverage £303,266
Debit OR Credit £185,016 credit
SRB expenditure defrayed |
£142,500 |
Actual SRB expenditure defrayed
£238,515
No1 Capacity Building 1j Wight 2B Heard |
(j) Evaluate
year one of the project development plan, including sustainability by
September 2002. |
An
evaluation report was produced by the project's Co-ordinator in August 2002
covering the project's first year of operation. The report detailed progress and outcomes against agreed
milestones and how the project intends to develop and achieve future
sustainability.
No 2 Community Development2c Salisbury Way 2d Brading Community Development 2i One Stop Feasibility Study |
(c) Exit Strategy developed and put in place by June 2002. (d) Move to new, larger premises complete by June 2002. (i) Study completed and information disseminated by August
2002. |
(c) The work currently being undertaken by
this project will be picked up by SWHA through Housing Officers, Tenants
Participation Officers or Caretakers ensuring sustainability.
(d) The
Centre opened on 2nd September with demand far in excess of
estimates. Official opening to be held in October 2002.
(i) Study has been completed and disseminated to all relevant people and organisations.
No 3 Disaffected Youth3b VYPER 3d
Youth Arts Base |
(b) Additional volunteers trained and peer mentoring schemes
established by Sept 2002 (d) Move into stage one of
building by June 2002. |
(b) Additional volunteers have been recruited and training will be
completed in October 2002.
(d) Furniture is currently being moved into the
building and Stage 1 will be open by the end of October 2002.
No 4 Community Safety4c
Interact 4d Domestic Violence Co-ordinator |
(c) Review and report of goals achieved by
young people by September 2002. (d) Recruit and train staff by June 2002.
[Team Manager post] |
(c) This has been achieved in September 2002.
(d) A
further recruitment exercise on 30th September was successful in
appointing a Team Leader with the applicant due to take up post on 28th
October 2002.
No 6 Support for Older Persons 6b
Outreach Support for
Older Persons |
(b) Establish Age Resource Desks on Mobile Service and E.
Cowes office by August 2002 |
The East Cowes
Outreach office is established, opening one morning a week and is located
adjacent to the Age Concern shop in the town centre. The Age Resource desks are a point to access a comprehensive
database containing details of local and national organisations that provide
social and leisure activities, benefits information, etc. for older members of
the community. The database is in the
process of being developed and updated from the existing local information
given. In addition, further research of
the potential client base and a questionnaire is underway to ensure the target
population needs are met.
Evaluation |
External consultancy commissioned to carry out evaluation of all SRB programmes by Aug 2002. |
Contacts for suitable consultants being collated from other SRB areas.
Outputs |
9 Jobs created by Sept 2002 [1A(i)] 103 Training weeks delivered by Sept 2002 [1E] |
1A(i) – 14.3 jobs
1E – 219 training weeks delivered
Signature: Name: [BLOCK CAPITALS] |
|
Position: Date: |
SRBVI ‘RYDE 2000’
QUARTERLY
MONITORING REPORT
QUARTER 2 , YEAR 3 (2002/03)
Progress against Key Indicators.
Partnership, Management and Administration |
Completed Statement of Grant Expenditure to Auditors by September 2002. Ryde Development
Trust established as a company by June 2002. |
Completed Statement of Grant Expenditure to Auditors by first week of October.
A meeting arranged for
16/10/02 to discuss formation of the company has had to be postponed due to
illness of the external facilitator. A
new date will be arranged as soon as possible.
Leverage Private Public Total |
£442,000 £497,600 £939,600 |
Planned Private Sector Leverage £442,000
Actual Private Sector Leverage £556,783
Debit OR Credit £114,783 credit
Planned Public Sector Leverage £497,600
Actual Public Sector Leverage £1,008,930
Debit OR Credit £511,330 credit
SRB expenditure defrayed |
£915,000 |
Actual SRB expenditure defrayed
£665,812
Defrayed expenditure continues to be under the planned figure due to the
freeze on infrastructure projects until the Public Realm Strategy is in
place. Additionally, the capital spend
at the George Street Centre has slipped, but we are confident this time will be
made up by the end of the financial year.
No1 Learning
& Employment 1b Ryde Young People’s Inclusion Project 1d Not
Just Enterprises 1f Baptist Church – George Street |
(b) Volunteers
recruited by Sept 2002. (d) Appointment of office skills trainer by June
2002 (f) Commence construction work by April 2002. (f)
Develop organisational structure for management of the centre by Sept 2002 |
(b)
The
volunteer’s scheme has been re-launched with a replacement coordinator and
additional volunteers being recruited, with mostly ‘at risk’ students
supported.
(d) Appointment delayed due to
funding delay. Gap funding from SRB now
agreed – trainer
should be in place Q3.
(f)
The
project was re-tendered as a result of the original tenders not producing any
competitive bids as advised by the Project Construction Surveyors for the
project. The tendering process is
expected to be completed shortly with construction commencing in November.
The organizational structure for
management of the centre has been timetabled to reflect the new construction
schedule.
No2 Social Inclusion2a Ryde Women’s Day 2d Ryde ArtWorks (RAW) 2f
SunRyders 2i Streets Ahead |
(a) 1 new
team member appointed by Aug 2002. (d) Establishment of 3 year plan for Festival
Development by June 2002 (d) RAW
Partnership constituted & feeding into cultural strategy by Sept 2002. (f) Childcare facility in place & equipped by
May 2002 (i) Implement summer projects working in coastal
areas by August 2002. |
(a) A new team
member was appointed and commenced employment in September 2002 on a three month trial basis.
(d) Interim plan received, full plan due
Q3.
(d) Part of cultural strategy with effect from June.
(f)
As previously advised, a review has been undertaken on
this project. Childcare facility should
be running by end of financial year.
(i) Summer projects were implemented and this was the busiest quarter of the project, supporting young people from overseas as well as from the Island. The biggest external influence to the summer programme was the murder of a Swedish student on the Island, which had a knock on effect.
No3 Physical Regeneration3e
Physical Enhancement Project Officer
3f Ryde Countryside Ranger |
(e) Ryde
Esplanade Phase 2 outline design completed by Sept 2002. (f)
Action Plan for landscape improvements implemented by Sept 2002 |
(e) Outline design held up due to the Public Realm Strategy (PRS) being put in place. A twin track approach with PRS and outline design will allow a second phase to go ahead if required, in December, rather than waiting until April for the PRS to be implemented.
(f) The Ryde Countryside Ranger resigned May and a holding position has been maintained with Countryside Section staff of the Isle of Wight Council providing cover until a replacement Ranger is in post in November.
No 4 Business Development |
(a) Interviews, gap analysis and workshops for all
key stakeholders completed to produce first draft of AIF by June 2002. (a) AIF
in place and used as a management tool by LSP and IW Economic Partnership by
July 2002 |
(a) Draft
report and investment audit report received.
Draft copy has been circulated to LSP and IWEP and comments are being
fed back for final document to be produced – November 2002.
Capacity building activities being planned with
LSP to enable them to take ownership of the document.
Outputs |
11
Buildings improved by September 2002 [6C] 497
Training weeks delivered by September 2002 [1E] |
6(c) 13 buildings improved
1(e) 1205.7 training weeks delivered.
Signature: Name: [BLOCK CAPITALS] |
|
Position: Date: |