PAPER D
AUDIT PANEL - 9 MARCH
2004
REPORT OF THE CHIEF INTERNAL AUDITOR
This report is to provide the Panel with a summary of Internal Audit activity completed since the last report of 25th November 2003; to apprise the Panel of progress in developing a new strategic audit plan and to inform the Panel of legislative changes affecting the panel’s responsibilities. The Panel is invited to note the contents of the report and to seek clarification of any issues arising from audits undertaken.
BACKGROUND
In keeping with good corporate governance practice, a Panel of elected members should have oversight of the activities of the Internal Audit Service for the following purposes:
v The Panel should monitor Internal Audit’s performance, both in terms of the quality and quantity of its work;
v The Panel should satisfy itself that Internal Audit has devoted its attention to the appropriate issues;
v The Panel should consider the results of Internal Audit reviews to ensure that any significant findings are addressed, including control weaknesses and to ascertain whether, in the opinion of the Chief Internal Auditor, adequate and satisfactory responses have been given by the Authority’s management;
v The Panel should recommend, if necessary, that further attention should be given to some of the issues raised;
To facilitate this process, attached as appendix A are synopses and summaries of audit work completed since 25th November this year. The Panel should also refer to the audit plan approved at the February 2003 meeting.
Audit resources have also been bolstered by employing a contractor to provide ICT audit during the period (funded by savings from delayed appointments). This has proved to be a particularly useful initiative with the main purpose of introducing the appropriate skills (ICT audit is a particularly technical area of internal audit). So far the contractor has produced five pieces of work on:
v ICT operations
v Unix security
v ICT audit plan
v ICT maintenance
v ICT E Mail System – synopsis included within this report.
It was hoped to be able to bring the revised plan to this meeting but unavoidable delays in identifying all strategic risks have meant that the revised plan cannot be completed until March when it will be subject to consultation with officers. The revised plan will be brought to the June meeting of the Panel.
The Office of the Deputy Prime Minister has revised the Accounts and Audit Regulations effective from 1st April 2003. The revised regulations require that the Council include within its published accounts for financial years 2003/04 onwards, a Statement of Internal Control (SIC). The implications of this change only became clear in January of this year when CIPFA published guidance on what authorities would need to do to comply with the new Regulations.
The CIPFA guidance advises that the SIC should inform readers of the published accounts as to the level of assurance that can be derived from the Council’s system of internal control. This is being interpreted as meaning that the Council’s overall arrangements for corporate governance and risk management will need to be evaluated annually and an assessment of the level of assurance that can be placed on these arrangements reported publicly in the SIC.
The sources of assurance will include:
v departmental managements’ self assessment of their risk management performance
v internal audit
v external audit
v other inspectorates
v
The Audit Panel
The SIC has to be signed by the Chief Executive and the most senior member of the Council.
The evaluation of the SIC will form an important part of the Audit Commission’s audit of the Council’s accounts. Therefore, it is important that the Council’s arrangements in respect of corporate governance and risk management can be shown to be robust.
FINANCIAL, LEGAL, CRIME AND DISORDER IMPLICATIONS
There are no significant financial or legal implications of this report , given that it is a progress report on the Internal Audit function. The Panel is reminded that the Council is required by statute (the Accounts and Audit Regulations) to have an adequate and effective Internal Audit function.
1. ICT E MAIL SYSTEM
The Isle of Wight Council operates an e-mail system
as a communication tool, provided through Microsoft Exchange Server and a
Microsoft Outlook client. The service enables receipt of electronic mail from
any Council location, its retention, generation of reply and the facility to
transmit to any other Council or third party location.
There is a need to access the Exchange Server to
review system files, mailbox controls and to test the system security features.
The review identified a number of minor control weaknesses,
and also identified 1 significant area of control weakness which is detailed
below: -
It was reported that the Tumbleweed server, which
manages external content filtering, is not backed up. However, a spare machine
is maintained to ensure that the services provided by this server could be
replaced in an emergency.
Risk: - Without a backup being taken it would not be
possible to restore the current configuration if required.
The findings were discussed with relevant staff, and
appropriate recommendations were made to resolve the control issues. These have
all been agreed with the staff, and target dates have been set for the control
weaknesses to be resolved.
2.
WASTE MANAGEMENT
REPORT
The audit was carried out as part of the 2003-04
Audit Plan agreed by the Audit Committee on 24 February 2003. The overall
objectives were to provide assurance to management that the Council’s
Integrated Waste Management Service is operating as prescribed in contract
documentation and that risks identified in operating the service are subject to
an effective risk mitigation programme.
The service is operating successfully and has a
robust risk mitigation strategy that effectively transfers most of the risks
involved to the service provider. Inspection of the contractor is robust and
there is a high level of awareness within the department of new legislation and
proposed changes to service requirements.
3.
CONTRACT AUDIT
Financial Regulations require that the Chief
Financial Officer is afforded the opportunity to examine every contract final
account. During this quarter nine final accounts relating to Education
construction projects, Highways works and other construction projects were
examined and passed for payment as there were no significant issues arising from
our examination. These were as follows:-
Gurnard Primary – Extension to form entrance
St Helens Primary – New reception
Cowes Primary – Music suite
Carisbrooke High – Autistic resource centre
Yarmouth bridge Phase 3
Church Lane Ryde – Retaining wall
Kite Hill Wootton – Pedestrian refuge
Blacklands Bridge
Cothey Bottom Heritage centre
The Audit section is also responsible for carrying
out financial evaluation of prospective contractors and suppliers and during
this period evaluations were undertaken for the IT Department and Revenues
Services.
An auditor is also a member of the Education
Partnering Project Team and during this quarter has been involved in further
evaluation of the short-listed Contractors and Consultants who have submitted
tenders. The tenders are being evaluated on the basis of cost, quality and
their ability to enter into a partnering arrangement.
4.
PROJECT AUDITS
We are currently involved in a large number of
projects. Our work is largely in
providing formal assurance services in the role of “Project Assurer”, a role
defined under the Prince2 project management methodology. We currently undertake this for:
GAGS related projects:
Customer Relationship Management (CRM)
DIP/EDM
Business Process Re-engineering
Front Office Working
eGovernment related projects:
eProcurement
ePIPS
Other:
ACCISS replacement project (SWIFT) – see below for
more details
We have retained a “watching brief” over the GAGS
programme and we have retained our seat on the GAGS Programme Board. The work on GAGS is, at this stage, confined
to advising and assisting on the
management of risk, issues, dependency and change. Following the Programme Board on Thursday 26th
February 2004 we will be re-issuing our audit plan for GAGS.
Since the last report we have issued three, one-page
assurance/audit reports on the ACCISS replacement project. Generally we consider the project to be
“on-track” to deliver the stated benefits.
The Way Forward
The role of assurer defined in the Prince2
methodology is the best way we have found of engaging with a project and
because the role is defined the expectations of the project team are
successfully managed. The aspect of the
work we often need to do on a project that is not explicitly covered within the
role of assurer is the evaluation of the controls being built or changed as a
deliverable of the project. However, as
assurer we are an accepted team member and in a better position to make this
contribution than we would otherwise be.
One of our goals is to integrate our mainstream audit toolkit into the
toolkit of the project manager so that we can promote the concept of self-audit
on projects. This will also assist in
the embedding of risk management in the culture of the organisation. To this end we are working with members of
staff in other departments, notably the Best Value Unit and ICT to develop the
appropriate toolkit and training.
At the request of the Resources Select Committee,
Internal Audit has been examining the way in which the Council procures its
printing requirements. The Committee had previously expressed its concern that
the Council’s policy which requires printing to be sourced through the
Council’s own Print Unit had not been followed. The corollary to that was that
the Council might not always receive value for money when meeting its printing
requirements.
Analysis
undertaken as part of audit’s examination appeared to indicate that, despite
the concerns raised by the Select Committee, there appeared to be even more
work being done outside than in previous years. Further work was then
undertaken to identify a sample of items and this was used to compare the price
paid externally with the cost if produced ‘in-house’. The results indicated
that in around 25% of cases the in-house option would have been more
cost-effective.
The Portfolio holder for Resources has now requested
that the Head of Corporate Policy develops and implements a protocol which
requires all spending departments to consult with the Council’s Print Unit
Manager, who will advise on the most appropriate and cost-effective source for
printed material, whether that is in-house or externally sourced. A further
report will be provided to the Resources Select Committee in August.
6.
MEMBERS
ALLOWANCES
This audit was carried out as part of the 2003-04
Audit Plan agreed by the Audit Committee on 24 February 2003. The overall
objective was to provide assurance to management that the arrangements for
making payments to members are in accordance with guidelines and regulations.
Assurance could not be given that payments are made
in accordance with established procedures and recommendations have been made to
improve the system to include the verification and authorisation of claims by
Committee Services, to give consideration to revising the method of reimbursing
members for travel and subsistence to reflect the varying responsibilities of
members and thirdly to ensure guidance issued to members by way of the Members
Handbook reflects the modern decision making structure adopted by the
Authority. Additionally a recommendation has been made and implemented to
improve the quality of management information”
7.
THE LEARNING
CENTRE
An audit review of the Learning Centre was included
in the 2003/2004 internal audit plan. This audit was conducted using our new
risk based methodology involving a facilitated workshop to identify and
prioritise key risks, and to determine the effectiveness of existing control
arrangements to manage the key risks facing this function. Attached as Appendix
B is a summary report using our SPA or single page assurance report formatted
as agreed at the last Audit Panel meeting in October.
8.
ACCISS
REPLACEMENT PROJECT
Attached as appendices C
and D are two further SPAs showing the status of this project in December 2003
and February 2004.
9. SCHOOL VISITS
During the period full audits have been carried out
in two Middle Schools and four Primary Schools. In addition audit reviews have
taken place at one High School, seven Middle Schools, twenty two Primary
Schools and both Special Schools. This leaves only three Schools still to be
visited by audit this year and appointments for these have been arranged.
Reports have been issued to each school with copies sent to Education Finance
and the relevant Link Inspector.
Overall the administration and general management
within the schools were found to be satisfactory, however the audits visits
raised a number of control weaknesses, which were common to many of the
schools. These included
Failure to review the scheme of delegation on a regular basis
Failure to review Committee Terms of Reference
annually
Failure to maintain the inventory and to carry out an
annual check
Delays in the production and/or audit of school fund
accounts
Copy of the approved budget not filed with the
relevant Governors minutes.
During the course of an audit at one of the Middle Schools, invoices were noted
for electrical works within the school.
On further investigation it was noted that the contractor used was not
on the Council approved list of Contractors as held by Property Services. In
these circumstances a member of the Property Services Team should have
inspected the works. This did not happen which raises a number of issues
regarding contractor competence and public liability insurance cover.
10. RISK ASSESSMENT WORKSHOPS
The section has been assisting the Insurance and Risk
Management Unit to run risk assessment workshops with Departmental Management
Teams. The purpose of the workshops is to identify further strategic risks
facing the authority to re-fresh the corporate risk register. This process will
be completed by early March 2004.
11. WORK IN PROGRESS
The following projects are in progress and should be
completed by the end of the financial year:
v
Industrial Sites
v
County Transport
v
Dinosaur Isle
v
Wight Leisure Cash
Recording
v
Wight Leisure “One
Card” Scheme
v
Payroll
v
Council Tax
v
Pension Benefits
v
Revenues and Benefits
Computer Systems
v
Social Services
Establishments
v
The Children and
Families Community Team
v
Rights of Way
APPENDIX B
SPA REF |
THE LEARNING CENTRE |
|
|||||||||
2003/001 |
|||||||||||
date |
10-Nov-03 |
Claire Shand |
|
||||||||
roll
up based on the orm.atrix for objectives 1 to 7 |
|||||||||||
|
|
|
|
|
|||||||
|
KP Group |
|
|
HEADLINE |
|||||||
1 |
Development of the
Objectives |
|
|
The key area of o/s work
is specifically relating the Service's objectives to the Corporate objectives |
|||||||
2 |
Development of the
Objectives' PI |
|
|
The mechanism to adjust
performance to achieve continuous improvement needs to be trialed |
|||||||
3 |
Current Objectives'
Performance Trend |
|
|
The first set of full
measurements need to be taken |
|||||||
4 |
Status for the Risks |
|
|
The majority of key risks
scored RED |
|||||||
5 |
Current Risk Performance
Trend |
|
|
The regular review of the
RIF's needs to commence |
|||||||
6 |
Development of the Risk
Treatment Action Plans |
|
|
Additional actions
identified need to be implemented |
|||||||
7 |
Current performance of
the RTAP's |
|
|
The setting of targets
and measuring performance is outstanding |
|||||||
8 |
RTAPs' performance trend |
|
|
No measurements have been
taken |
|||||||
9 |
Quality of Management
Information |
|
|
The gap analysis between
the MI available and the MI needed has not yet been undertaken |
|||||||
10 |
Review Processes |
|
|
The review of performance
based on revised PI's is not yet possible |
|||||||
11 |
Response Processes |
|
|
Trigger points need to be
established and the procedure written for escalation |
|||||||
12 |
Overall Rating* |
|
|
Improvement plan tasks
need to be assigned |
|||||||
|
|
|
|
|
|
|
|
|
|||
KEY ISSUES |
|
|
|
|
|||||||
Ref |
Description |
DUE DATE |
Action |
Owner |
Status |
||||||
1 |
Availability of resources |
|
Utilise technology better
in delivery of the service |
CS |
|
||||||
2 |
The need to demonstrate
value creation |
|
Develop benefit
realisation model |
CS |
|
||||||
|
|
|
|
|
|
|
|
|
|||
KEY RISKS |
|
|
|
|
|||||||
Ref |
Description |
DUE DATE |
Action |
Owner |
Status |
||||||
1 |
Staff/managers/senior
managers are not aware of the evaluation outcomes following training creating
a lack of understanding of the value created (risk 31) |
12mth |
Pre-define value and
measure outcomes with better, regular communication |
CS |
|
||||||
2 |
Failure to support other
areas to achieve their objectives and therefore the corporate objectives
(risk 43) |
12mth |
Get involved in service
planning earlier and create better feedback loops |
CS |
|
||||||
|
|
|
|
|
|
|
|
|
|||
IN BOUND KEY DEPENDENCIES |
|
|
|
|
|||||||
Ref |
Description |
DUE DATE |
Action |
Owner |
Status |
||||||
1 |
The PDP process |
12mth |
Develop benefit
realisation model |
CS |
|
||||||
2 |
Service Planning |
12mth |
Get involved in service
planning earlier and create better feedback loops |
CS |
|
||||||
OUT BOUND KEY DEPENDENCIES |
|
|
|
|
|||||||
Ref |
Description |
DUE DATE |
Action |
Owner |
Status |
||||||
1 |
Providing the framework
for learning/training and development |
12mth |
Better information
required to understand priorities |
CS |
|
||||||
2 |
Designing and providing
courses and events to met identified needs |
12mth |
Pre-define value and
measure outcomes with better, regular communication |
CS |
|
||||||
|
|
|
|
|
|
|
|
|
|||
OVERALL COMMENTARY |
|
|
|
|
|||||||
The challenge for the
Learning Centre is to understand needs and provide solutions that create
demonstrable value. There is a need
to embrace technology, not only the demands for training in the face of new
technology but also how to deliver training via applied technology
solutions/different channels. The key
aspect of the operation of the service thats needs to be improved is the
capture, collation and interpretation of feedback from all stakeholders. An innovative approach to creating some
capacity within the team is also required, and the concept of the "first
aiders" (a network of specialist internal course/content providers)
needs to be seriously pursued. The
impact of partnerships needs to be understood, both the opportunities of the
partners/partnerships that the authority is currently engaged with and those
in the future. The early
participation of the Learning Centre in the lifecycle of service planning is
key to understanding the priorities, needs and requirements of all areas and
this is a key driver for the development of the model for benefit realisation
(at all levels of the authority). |
|||||||||||
Prepared by |
|
Ken May |
APPENDIX
C
SPA REF |
ACCISS Replacement Project |
Overall RAG |
a |
|||||
ACCISS002 |
||||||||
date |
23-Dec-03 |
David Shambrook |
Overall Trend* |
stat |
||||
*TREND - IMP=improving, STAT = static, DET =
deteriorating |
||||||||
Key Performance Scores |
|
|
|
|||||
IND |
KP Group |
RAG |
TREND* |
HEADLINE |
||||
1 |
Plan & Resources |
a |
stat |
The development of the
plans is becoming a priority |
||||
2 |
Progress |
a |
stat |
Developed plans will
support monitoring and the management of tolerances |
||||
3 |
Deliverables |
a |
stat |
Developed plans will
ensure all deliverables are identified |
||||
4 |
Testing |
a |
n/a |
Piloting in progress to
test environment |
||||
5 |
Quality |
a |
stat |
Some aspects need
tightening up particularly the reviews |
||||
6 |
Issues |
a |
stat |
|
||||
7 |
Risk |
g |
imp |
|
||||
8 |
Change |
a |
stat |
Developed plans will
assist in the management of change |
||||
9 |
Dependency |
a |
stat |
The interdependency with
GAGS needs to be managed |
||||
10 |
Interfaces |
g |
stat |
|
||||
11 |
Migration |
g |
stat |
|
||||
12 |
Implementation |
r |
stat |
The first assessment of
Go/No Go criteria is now due |
||||
|
|
|
|
|
|
|
|
|
KEY ISSUES |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Communication paths need
to be clarified, particularly in light of the changes in the Board |
Reissue the job
descriptions for the key roles and obtain fomal acknowledgement |
DS |
n/a |
||||
2 |
Business case does not
include the PSA targets, therefore no review of the impact of the programme
on those targets and the consequential risk to the funding |
Update the business case |
DS |
n/a |
||||
|
|
|
|
|
|
|
|
|
KEY RISKS |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Risk that we cannot
implement the cultural change to realise the benefits of the system |
Communication/visioning -
keeping everyone involved and informed |
GG |
a |
||||
2 |
The risk of sacrificing
quality in light of fixed end dates and budgets without contingency |
Examine scope and
identify the opportunity to build in contingency and reinforce the change
control process |
DS |
a |
||||
|
|
|
|
|
|
|
|
|
IN BOUND KEY DEPENDENCIES |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Anite's Swift Product |
Liaison and piloting of
the product |
DS |
g |
||||
2 |
Health sector partner |
Liaison and inclusive
decision making |
GG |
a |
||||
3 |
Thin client rollout |
Testing and
piloting. Clarity required around
requirements. |
KD |
a |
||||
OUT BOUND KEY DEPENDENCIES |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Single assessment process |
to be rated next time |
|
|
||||
2 |
Identification, referral
and tracking |
to be rated next time |
|
|
||||
3 |
Secure shared environment |
to be rated next time |
|
|
||||
|
|
|
|
|
|
|
|
|
OVERALL COMMENTARY |
|
|
|
|||||
The key task of
developing plans is crucial to other activities: (a) Full and complete
plans will ensure that all deliverables have been identified and will ensure
that resourcing is appropriate, (b) Developed plans will allow
tolerances and any resulting exceptions to be managed more effectively,
particularly Cost/Budget tolerances.
The other key aspect of the project that needs to be addressed is the
specification of the Quality Standards and the reviews of Quality
achieved. Once Plan and Quality
issues have been addressed, the viability of the project in terms of meeting
objectives can be critically tested and then thought can be given to the
method of realising benefit and monitoring those benefits. In many respects the project is similar to
the GAGS programme and the key similarity is the visioning and the cultural change
required to realise many benefits. It
is suggested that the project forges stronger links with the GAGS programme
to ensure maximum benefit from the work being done on Vision and Benefit
Realisation. |
||||||||
Prepared by |
Ken May |
APPENDIX
D
SPA REF |
ACCISS Replacement Project |
Overall RAG |
a |
||||
ACCISS003 |
|||||||
date |
09-Feb-04 |
David Shambrook |
Overall Trend* |
imp |
|||
*TREND - IMP=improving, STAT = static, DET =
deteriorating |
|||||||
Key Performance Scores |
|
|
|
||||
IND |
KP Group |
RAG |
TREND* |
HEADLINE |
|||
1 |
Plan & Resources |
a |
stat |
|
|||
2 |
Progress |
a |
stat |
|
|||
3 |
Deliverables |
a |
stat |
|
|||
4 |
Testing |
n/r |
n/a |
Development of the UAT
plans and data to be a priority |
|||
5 |
Quality |
r |
det |
Formal reviews and sign
off are needed to underpin the achievement of objectives |
|||
6 |
Issues |
a |
stat |
|
|||
7 |
Risk |
a |
stat |
|
|||
8 |
Change |
g |
imp |
Process efficiency
savings are realisable |
|||
9 |
Dependency |
a |
stat |
The interdependency with
GAGS needs to be managed |
|||
10 |
Interfaces |
g |
stat |
|
|||
11 |
Migration |
g |
stat |
|
|||
12 |
Implementation |
r |
det |
The assessment of Go/No
Go criteria is now overdue |
|||
|
|
|
|
|
|
|
|
KEY ISSUES |
|
|
|
||||
Ref |
Description |
Action |
Owner |
TREND* |
|||
1 |
Acceptance of the roles
and responsibilities by members of the board |
Prince2 session to be run
for key members |
DS/JC |
det |
|||
2 |
Business case does not
include the PSA targets or any firm benefit data, therefore no review of the
impact of the programme on those targets and the consequential risk to the
funding |
Update the business case |
DS |
det |
|
|
|
|
|
|
|
|
|
KEY RISKS |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Risk that we cannot
implement the cultural change to realise the benefits of the system |
Communication/visioning -
keeping everyone involved and informed |
GG |
a |
||||
2 |
The risk of sacrificing
quality in light of fixed end dates and budgets without contingency |
Examine scope and
identify the opportunity to build in contingency and reinforce the change
control process |
DS |
a |
||||
|
|
|
|
|
|
|
|
|
IN BOUND KEY DEPENDENCIES |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Anite's Swift Product |
Liaison and piloting of
the product |
DS |
g |
||||
2 |
Health sector partner |
Liaison and inclusive
decision making |
GG |
a |
||||
3 |
Thin client rollout |
Testing and piloting. |
KD |
a |
||||
OUT BOUND KEY DEPENDENCIES |
|
|
|
|||||
Ref |
Description |
Action |
Owner |
TREND* |
||||
1 |
Single assessment process |
to be rated next time |
|
|
||||
2 |
Identification, referral
and tracking |
to be rated next time |
|
|
||||
3 |
Secure shared environment |
to be rated next time |
|
|
||||
|
|
|
|
|
|
|
|
|
OVERALL COMMENTARY |
|
|
|
|||||
In overall terms, the
project score has improved and is very near the benchmark for a proejct of
this type (at this stage). There is a
risk, however, that the hard work to date to enforce certain disciplines will
be lost if key members of the Board do not accept the roles and
responsibilities that are part and parcel of the Prince2 methodology. We are expecting the session on Prince2
that is being co-ordinated by John Clack to increase awareness of the
importance of the tasks that need to be done. We are aware of the visioning exercises that are due to start
next week and with this in mind would suggest a more formal degree of liaison
with the GAGS programme particularly the DIP project and the Business Process
Re-engineering project, both of which could provide valuable guidance and
experience in key areas. We say again
that the key elements/criteria that need to be in place for launch are
identified and under-pin the acceptance criteria that are used to judge the
Quality of the key deliverables - this would also guide User Acceptance
Testing. |
||||||||
Prepared by |
Ken May |