PAPER F

 

AUDIT PANEL - 29 JULY  2004

 

INTERNAL AUDIT PROGRESS REPORT

 

REPORT OF THE CHIEF INTERNAL AUDITOR

 

REASON FOR AUDIT PANEL CONSIDERATION :

This report is to provide the Panel with a summary of Internal Audit activity completed since the last report of 9th March 2004.

 

ACTION REQUIRED BY AUDIT PANEL :

The Panel is invited to note the contents of the report and to seek clarification of any issues arising from audits undertaken.

 

BACKGROUND 

In keeping with good corporate governance practice, a Panel of elected members should have oversight of the activities of the Internal Audit Service for the following purposes:

v      The Panel should monitor Internal Audit’s performance, both in terms of the quality and quantity of its work;

v      The Panel should satisfy itself that Internal Audit has devoted its attention to the appropriate issues;

v      The Panel should consider the results of Internal Audit reviews to ensure that any significant findings are addressed, including control weaknesses and to ascertain whether, in the opinion of the Chief Internal Auditor, adequate and satisfactory responses have been given by the Authority’s management;

v      The Panel should recommend, if necessary, that further attention should be given to some of the issues raised;

To facilitate this process, attached as appendix A are synopses and summaries of audit work completed since 9th March this year. The Panel should also refer to the audit plan approved at the February 2003 meeting.  

 

RELEVANT PLANS, POLICIES, STATEGIES AND PERFORMANCE INDICATORS

 None

 

CONSULTATION PROCESSES

None

 

FINANCIAL, LEGAL, CRIME AND DISORDER IMPLICATIONS

There are no significant financial or legal implications of this report , given that it is a progress report on the Internal Audit function. The Panel is reminded that the Council is required by statute (the Accounts and Audit Regulations) to have an adequate and effective Internal Audit function.

 

APPENDICES ATTACHED

Appendix A - synopses and summaries of audit work completed since 9th March this year

 

BACKGROUND PAPERS USED IN THE PREPARATION OF THIS REPORT

Audit project files held by G Richardson – ext 3683

Contact Point : G Richardson, Chief Internal Auditor ( 823683

 

GED RICHARDSON

Chief Internal Auditor


 

 

APPENDIX A

 

 

1.             Treasury Management

 

The overall objective of this audit was to provide assurance to management that effective controls and procedures are in place to ensure that short term lending of Council funds is carried out in accordance with Council policy and to prevent any misuse of those funds.

 

Overall the system in place for short term lending of funds is sound with effective controls and procedures in place. However, one major area of weakness was noted. This related to the verification of the borrowers bank details prior to the actual transfer of the funds. It is possible with the present system for incorrect details to be entered into the system.

 

An additional control has been recommended which will increase the security in this area. Three further recommendations that are of a minor nature and refer to the administration of the section have also been made.

 

2.             Main Accounting System

    

This audit was carried out as part of the 2003-04 Audit Plan agreed by the Audit Panel on 24 February 2003. The overall objective was to provide assurance to management that the Council’s Main Accounting System is operating in accordance with existing controls and that they are adequate to ensure the integrity of the Authority’s Financial Management System. The audit was carried out by interviewing relevant officers and carrying out testing on selected areas to determine the level of compliance with Council policies and procedures.

 

In general assurance can be given to management that systems in place are operating satisfactorily. One recommendation has been made to improve the management information available. This has been accepted by management.

 

3.             Children and Families Community Team – Social Services Department

 

The audit was carried out as part of the 2003-04 Audit Plan agreed by the Audit Panel on 24 February 2003. The overall objectives were to provide assurance to management that the objectives of the service are being met and that appropriate risk mitigation strategies are in place and operating satisfactorily.

              

During the audit a workshop was held in which the Service Team’s objectives were
defined. A risk register based upon those objectives was compiled and risk mitigation
strategies are in place.  Many of the risk identified related to resourcing, performance
management and relationships with other stakeholders and a number of initiatives and strategies have been put in place to address them, such as:

a)            The introduction of the Local Prevention Strategy;

 

b)            Recruitment and Retention Strategy which has seen the vacancy level drop form 24% to        1%;

c)            Increased emphasis on team development and relevant training;

         d)            Successful introduction of multi agency working at the St James Centre, showing staff it can work.

Assurance can therefore be given that the objectives of the service are being met and as
 a result no recommendations were made to Management.

 

4.             Wight Leisure One Card

 

An audit of the basic controls operating in respect of One Card was performed in February-April 2004. One card is a card that allows the freedom to participate in a number of sports and leisure activities with the advantage of unlimited use giving a discount on normal charges. There are approximately 22,000 current card holders.

 

This audit was not included in the annual audit plan for 2003-2004 as it was anticipated that Wight Leisure would be externalised. However once it became questionable whether externalisation would take place, the plan was amended to incorporate some coverage of Wight Leisure activities.

 

We found a number of areas of weakness in the financial control arrangements mainly of a minor nature. One area we regarded as having a fairly significant risk was:

 

· The lack of a documented procedure for disaster recovery in case of a catastrophe at the Quay Street Office with regards to the ability of the flex computer system and operational logistics to be supported until return to normal operation.

 

We made 11 recommendations for improvements in internal control all of which     have been accepted by management.

 

5.             Wight Leisure Cash Receipting Arrangements

 

An audit of the basic financial controls operating over income in a sample of Wight Leisure establishments was performed in February 2004. Total income from the four centres in the financial year 2003/04 amounted            to some £1.38m. This audit was not included in the annual audit plan for 2003-2004 as it was anticipated that Wight Leisure would be externalised. However once it became questionable whether externalisation would take place, the plan was amended to incorporate some coverage of Wight Leisure activities.

 

We found a number of areas of weakness in the financial control arrangements mainly of a minor nature. One area we regarded as having a fairly significant control risk (albeit the potential losses would not be material) was at one Leisure Centre. The issues were:

 

· When Antiques Fairs are promoted there was no system to ensure that all admission income collected was properly brought into account as tickets sold were not reconciled to cash received.

 

· The ad-hoc sales of refreshments outside the café area did not operate a proper till system. We noted that the only figures recorded were cash received and not the z readings (audit roll), which would allow identification of over or under cash receipts.

 

We made 14 recommendations for improvements in internal control all of which have been accepted by management.


 

6.             Payroll

 

The overall objective of this audit was to provide assurance to management that the internal control system governing the payroll operation is performing in an adequate and effective manner.

 

Our main findings were that in general the payroll services department is operating satisfactorily. However there   were a number of issues tangential to payroll that gave cause for concern. These were:

 

1.It has not been possible to ascertain whether a payroll local agreement operating within Wight Leisure had been properly authorized;

 

2.Problems were identified in the administration of pay honoraria where honoraria have been granted in questionable circumstances;

 

3.Problems were identified with respect to the recovery of debts from former employees for car loans and relocation expenses.

 

We made seventeen recommendations for system improvements all of which have been accepted by management.

 

7.            Transport

 

The audit was carried out as part of the 2003-04 Audit Plan agreed by the Audit Panel on 24 February 2003. The overall objectives were to provide assurance to management that the objectives of the service are being met and that appropriate risk mitigation strategies are in place and operating satisfactorily.

 

Assurance can be given that this is the case, and no recommendations have    been made to management as a result of this audit.

 

8.             Industrial sites

 

The audit was carried out as part of the 2003-04 Audit Plan agreed by the Audit Panel on 24 February 2003. The overall objectives were to provide assurance to management that the objectives of the service are being met and that appropriate risk mitigation strategies are in place and operating satisfactorily.

 

In general assurance can be given that this is the case. However the quality of management information is poor and too much reliance is placed on the knowledge and experience of one officer. The main recommendation arising from this report is that some form of administrative support be afforded to the Principal Estates Surveyor, at least in the short term, to improve information held and to properly document decisions made. Other recommendations have been made to improve the quality of management information, to improve checks carried out on prospective tenants and reduce the likelihood of costs not being recovered at Garden Estate Ventnor. All our recommendations have /have not been accepted by management.

 

9.             Rights of way

 

The audit was carried out as part of the 2003-04 Audit Plan agreed by the Audit Panel on 24 February 2003. The overall objectives were to provide assurance to management that the objectives of the service are being met and that appropriate risk mitigation strategies are in place and operating satisfactorily.

 

There are no major areas of concern arising from this audit, and assurance can be given to management that the Rights of Way Section is operating in accordance with the current regulations and that risk mitigation strategies are operating satisfactorily. Risks identified as being within the control of the section are being managed well. Where identified risks are outside of the control of the section action has been taken by the Countryside Access Manager to raise the profile of these risks.

 

A lack of resources has been identified as one of the key risks facing the section in the future and a bid for extra funding is within the service plan. Senior Management need to be aware that should additional funding not be made available or that the workload within the section is not reduced  then there is an increased likelihood that the section cannot  meet its statutory obligations. Where this is the case at present work has been prioritised and obligations fulfilled on a basis of need. Defence against litigation has been historically easy to mount due to diligent monitoring processes but any reduction in the services ability to meet statutory requirements increases the risk of being unable to defend against claims.

 

10.         Dinosaur Isle

 

The audit was carried out as part of the 2003-04 Audit Plan agreed by the Audit Panel on 24 February 2003. The overall objectives were to provide assurance to management that the Dinosaur Isle is operating in accordance with the Council’s policies and procedures and that risks identified relating to the achievement of service objectives are subject to an appropriate risk mitigation strategy.

           

The main concerns arising from this review were how to successfully manage the conflicting objectives of being a centre of scientific excellence whilst at the same time maximising income from casual visitors whilst facing severe financial constraints. Eight recommendations have been made which in addition to addressing the above issue will also improve the budget monitoring process and ensure limited resources are deployed effectively. The need for a revised and updated business plan has been highlighted.

 

All the recommendations were agreed by management.

           

11.         Schools Audits

 

All schools received an audit visit during 2003/04. Full audits were carried out in two High Schools, three Middle Schools and four Primary schools. The remaining primary (42), Middle (11), High (3 ) and Special (2) schools were subject to an audit review. Reports have been issued to each school with copies sent to Education Finance and the relevant Link Inspector.

 

In the majority of schools the administration and general management were found to be  satisfactory or good, however the audit visits raised a number of weaknesses which were common to many of the schools. These included :

 

·         Failure to review the Scheme of Management Delegation on a regular basis.

·         Failure to review Committee Terms of Reference annually

·         Failure to complete and /or review annually the Register of Business Interests               

·         Failure to maintain the inventory and to carry out annual checks.                        

·         Delays in the production and/or audit of school fund accounts.                                        

 

All the recommendations in the audit reports were accepted by the schools. Checks will be carried out during audit visits in 2004/05 to ensure that the recommendations have been implemented.

 

12.          Greater Access to Greater Services (GAGS) – General

 

We continue to support the GAGS programme in a number of ways, primarily providing risk management and assurances services consistent with the Prince2 project management methodology.  We continue to attend the Programme Board meetings and “host” the GAGS Programme Risk Register, facilitating regular updates of the register.  We have been instrumental in improving programme controls, for example, the management of risk and the formulation of the approach to benefit realisation.  We have recently put together the first edition of the Lessons Learned Log for the programme.

 

13.         Customer Relationship Management (CRM)

 

We continue to support the CRM project and provide risk management and assurances services.  We attend the Project Board and our one-page project assurance reports issued in the last review period appear below.  We have also been involved in the testing of Phase 2 of the CRM system and we are planning our testing of Phase 3.  We “host” the CRM Risk Register, facilitating regular updates of the register.  We act as facilitators for the CRM Working Group, the forum that is responsible for the future direction of the system.  Our involvement ensures appropriate consideration is given to controls and risks, including more recently advice on the legislative considerations of proposed functionality to register and authenticate customers contacting the authority and the sharing of customer data.

 

14.         Document Imaging Processing (DIP)

 

We continue to support the DIP project and provide risk management and assurances services.  We attend the Project Board and our one-page project assurance reports issued in the last review period appear below.  Latterly we have worked closely with the project manager to drive out a system for recording, monitoring and tracking project benefits – a set of protocols and templates we have shared with other projects.  We “host” the DIP Risk Register, facilitating regular updates of the register.

 

15.         E-GOVERNMENT

 

Our current activity is to specify the control objectives for the e-Procurement system ahead of the selection of a solution.  We have been involved in an advisory capacity in the selection of new BACS transmission software.

 

16.         ACCISS REPLACEMENT

 

We continue to support the ACCISS replacement project in a number of ways, primarily providing risk management and assurances services consistent with the Prince2 project management methodology.  We continue to attend the Project Board meetings and our one-page project assurance reports issued in the last review period appear below.  Latterly we have orked closely with the project manager to develop a system for assessing the operational preparedness of SWIFT (Launch Criteria assessments) for launch in September as an additional risk management strategy.  We are currently reviewing the business case for the selection of the alternative system for Supporting People

 

17.    DS5 – Ensuring Systems Security

 

In March 2004 we conducted a pilot audit as part of our rollout of a new ICT audit framework (COBIT).  This also allowed us to pilot our risk-based approach on an ICT entity.  The entity selected was “Ensuring Systems Security”, an audit in the 2004/5 plan and we used this entity because it had been subject to external review – our review results were therefore seen in part as validating that external review result.  Our approach is fundamentally driven by the identification of risks that would prevent the achievement of objectives and the driving out of improvement plans to manage the risks identified.  The bulk of the work is conducted in a workshop with key stakeholders. The pilot, whilst confirming the results of previous reviews also identified a number of key actions to improve the administrations of users access rights.  Our one-page audit report appears below.  The overall rating for this entity was AMBER – additional actions recommended, one implemented, will improve control and ensure that identified risks are managed to an acceptable level.

 

17.         FORENSIC INVESTIGATIONS

 

At the request of management we have facilitated the redrafting of our acceptable use policies (Communication Policy) and this now includes the protocols for undertaking computer forensic investigations where that is deemed necessary.  That policy is currently awaiting approval by the Portfolio Holder under delegated powers.

 

18.         PENETRATION TESTING

 

As a consequence of our work on the systems security audit we also collaborated further with ICT management to draft a “Risk Bid” for the funds to conduct specialised security testing.  We are currently preparing the Directors’ Group paper and the Testing Proposal for the purposes of tendering for the service.  Penetration testing is specialised testing of our web-based infrastructure and applications.  It is designed to identify security weaknesses.

 

19.         INFORMATION MANAGEMENT GROUP

 

We were recently invited to join the Information Management Group.  This participation will enable us to pursue a body of audit work to test the Council’s compliance with the Data Protection Act and its preparedness for the implementation of the Freedom of Information Act in January 2005.

 

20.         PO3 – Determine Technology Direction

 

On the 25th June we conducted the second risk based ICT audit defined under our new ICT Audit framework.  The documentation is currently being drafted in readiness for review by key stakeholders.  At this time it can be reported that the current overall result will be RED – this is defined as – “a significant threat exists to the achievement of objectives”.  We are currently working on the risk treatment action plans to manage the risks identified.  These will be dependent on better alignment between the respective business and ICT strategies, going forward.

 

 

21.         DS4 – Ensure Continuous Service

 

In June we started a body of work to review the Council’s business continuity recovery plans, building on the work conducted by Marsh.  This work aligns with the Directors’ Group report currently being drafted by the Chief Fire Officer.  Our concern, one shared by the Chief Fire Officer, is that we have no adequate processes in place to maintain the service recovery plans we have put in place.  Additionally, without further work, the plans will remain incomplete and inconsistent in a number of areas.

 

22.         PARTNERSHIPS

 

MTI FUNDED PROJECTS

 

We are currently working with the Libraries, Museums and Archives Manager in an advisory capacity to produce the appropriate project documentation for a number of projects and we are providing risk registers and will help with developing risk mitigation strategies.

 

23.         SAFER COMMUNITIES

 

We are currently working with the Head of Democratic & Legal Services to draft a governance structure for the recently merged Drug Action Team and Crime & Disorder Partnership (“Safer Communities Partnership”).  We are due to present on that to the Safer Communities Board on 28th July 2004.

 

24.         PROJECT MANAGEMENT

 

We are currently working with colleagues from Policy, ICT and the Learning Centre to construct a training programme and a best practice guide for project management as part of the CPA Improvement Plan.

 

25.         COMMUNITY DEVELOPMENT/WIGHT LEISURE

 

We are currently working with colleagues to prepare a “risk profile” report to facilitate the strategic decisions to be taken in respect of the re-integration of Wight Leisure.