PAPER B1
ISLE
OF WIGHT COUNCIL DEVELOPMENT CONTROL COMMITTEE -
TUESDAY, 6 SEPTEMBER 2005
REPORT
OF THE HEAD OF PLANNING SERVICES
WARNING
1.
THE RECOMMENDATIONS CONTAINED IN THIS REPORT OTHER THAN PART 1 SCHEDULE
AND DECISIONS ARE DISCLOSED FOR INFORMATION PURPOSES ONLY.
2.
THE RECOMMENDATIONS WILL BE CONSIDERED ON THE DATE INDICATED ABOVE IN
THE FIRST INSTANCE. (In some
circumstances, consideration of an item may be deferred to a later meeting).
3.
THE RECOMMENDATIONS MAY OR MAY NOT BE ACCEPTED BY THE DEVELOPMENT
CONTROL COMMITTEE AND MAY BE SUBJECT TO ALTERATION IN THE LIGHT OF FURTHER
INFORMATION RECEIVED BY THE OFFICERS AND PRESENTED TO MEMBERS AT MEETINGS.
4.
YOU ARE ADVISED TO CHECK WITH THE DIRECTORATE OF ENVIRONMENT SERVICES
(TEL: 821000) AS TO WHETHER OR NOT A DECISION HAS BEEN TAKEN ON ANY ITEM BEFORE
YOU TAKE ANY ACTION ON ANY OF THE RECOMMENDATIONS CONTAINED IN THIS REPORT.
5.
THE COUNCIL CANNOT ACCEPT ANY RESPONSIBILITY FOR THE CONSEQUENCES OF ANY
ACTION TAKEN BY ANY PERSON ON ANY OF THE RECOMMENDATIONS.
The various documents, letters and other correspondence referred to in the Report in respect of each planning application or other item of business.
Members are advised that every application on this report has been considered against a background of the implications of the Crime and Disorder Act 1998 and, where necessary, consultations have taken place with the Crime and Disorder Facilitator and Architectural Liaison Officer. Any responses received prior to publication are featured in the report under the heading Representations.
Members are advised that every application on this report has been considered against a background of the implications of the Human Rights Act 1998 and, following advice from the Head of Legal and Democratic Services, in recognition of a duty to give reasons for a decision, each report will include a section explaining and giving a justification for the recommendation.
LIST OF PLANNING APPLICATIONS ON REPORT TO COMMITTEE – 6 SEPTEMBER 2005
01 |
P/02074/04
CAC/10858/L |
Ryde |
Conditional Permission |
|
26 Bellevue Road, Ryde, Isle Of Wight, PO33 2AR Conservation Area Consent for demolition of
building; construction of a three storey building to form 14 flats with accommodation
within roof space; alterations to vehicular access, parking area and
landscaping (revised scheme) |
|
|
02 |
P/02104/04
TCP/10858/K |
Ryde |
Condition Permission |
|
26 Bellevue Road, Ryde, Isle Of Wight, PO33 2AR Three storey building to form 14 flats with
accommodation within roof space; alterations to vehicular access, parking
area and landscaping (revised scheme) |
|
|
03 |
P/00973/05
TCP/21625/A |
Brighstone |
Conditional Permission |
|
land at Cheverton Chalk and Gravel, Cheverton
Shute, Shorwell, Newport Continued extraction of chalk in previously
worked area and extension of chalk quarry westward into new area (revised
site boundary) |
|
|
04 |
P/00974/05
TCP/21625/B |
Brighstone |
Conditional Permission |
|
Cheverton Chalk and Gravel, Cheverton Shute,
Shorwell, Newport, PO30 3JE Extension of gravel pit |
|
|
05 |
P/00975/05
TCP/21625/B |
Brighstone |
Conditional Permission |
|
Cheverton Chalk and Gravel, Cheverton Shute,
Shorwell, Newport, PO30 3JE Continued extraction of flint gravel hogging and
extension of extraction area, proposed tipping of inert materials and
reclamation of land, part OS parcel 0001, Limerstone Down |
|
|
06 |
P/01111/05
TCP/23793/D |
Ventnor |
Conditional Permission |
|
Westfield Holiday Park, Shore Road, Ventnor 3 storey building to form 17 flats (revised
position); retention of 3 flats |
|
|
07 |
P/00160/04
TCP/06159/T |
Freshwater |
Conditional Permission |
|
106 School Green Road, Freshwater, Isle Of Wight,
PO40 9AY Demolition of building; outline for six
dwellings; formation of pedestrian access |
|
|
08 |
P/00750/05
TCP/26996 |
East
Cowes |
Conditional Permission |
|
area seaward side of Venture Quays, Castle
Street, East Cowes Demolition of slipway and suspended deck
structure and its replacement with a solid waterfront apron extension,
including a hoist dock, concrete crane pad and docking pontoons (revised
plans) |
|
|
09 |
P/00854/05
TCP/11878/E |
Shanklin |
Refusal |
|
Alverstone House, 32, Luccombe Road, Shanklin,
PO37 6RR Continued use of dwelling as private school;
vehicular access and parking |
|
|
10 |
P/01028/05
TCP/03605/U |
Seaview |
Conditional Permission |
|
Seaview Hotel and Restaurant, High Street,
Seaview, Isle Of Wight, PO34 5EX Demolition of public toilets; detached building
to form additional hotel accommodation to include seven additional bedrooms and
associated facilities; alterations to vehicular access |
|
|
11 |
P/01122/05
TCP/03605/V |
Seaview |
Conditional Permission |
|
Seaview Hotel and Restaurant, High Street,
Seaview, Isle Of Wight, PO34 5EX Continued use of buildings for guest and staff
accommodation and associated office space (The Studio, Methuen Suite and
Jasmine Cottage) |
|
|
12 |
P/01036/05
TCP/10228/V |
Ryde |
Conditional Permission |
|
Jalna, Appley Rise, Ryde, Isle Of Wight, PO33 1LE Demolition of dwelling; erection of eight flats
in two blocks and one semi-detached house with parking and alterations to
access (revised scheme) |
|
|
13 |
P/01037/05
CAC/10228/U |
Ryde |
Conditional Consent |
|
Jalna, Appley Rise, Ryde, Isle Of Wight, PO331LE Conservation Area Consent for demolition of
dwelling in connection with erection of eight flats in two blocks and one
semi-detached house with parking and alterations to access (revised scheme) |
|
|
14 |
P/01060/05
TCP/26954/A |
Calbourne |
Refusal |
|
Downsview, Lynch Lane, Calbourne, Newport, PO30 Demolition of single storey extension; proposed single/2 storey extension to provide
additional living accommodation (revised scheme) |
|
|
1
& 2. |
Reference
Number: P/02104/04 - TCP/10858/K & P/02074/04 – CAC/10858/L Parish/Name: Ryde - Ward/Name: Ryde North East Registration
Date: 05/10/2004 -
Full Planning Permission Officer: Mr J Mackenzie Tel: (01983) 823567 Applicant: Mr J Tilden-Smith Three
and four storey building to form 14 flats; alterations to vehicular access, parking
area and landscaping (revised scheme) Conservation Area Consent for demolition of
building; construction of a three and four storey building to form 14 flats;
alterations to vehicular access, parking area and landscaping (revised
scheme) 26
Bellevue Road, Ryde, Isle Of Wight, PO332AR |
The applications are recommended for conditional
permission subject to an S106 agreement and Conservation Area Consent.
REASON FOR COMMITTEE CONSIDERATION This is a major application which proved to be contentious
by reason of conflicting policy considerations, the site's location with the
Conservation Area. It can be
considered concurrently with the Conservation Area Consent application. |
1. Details
of application
1.1 These two applications seek full
permission and Conservation Area Consent for the demolition of the existing
building and for its replacement with 14 flats. Plans show a 3/4 storey building of three distinct elements. Constructed in masonry with hipped, slated
roofs, stone margins to windows or stone faced quoins and plinths but with a
majority of the elevation finished in painted render.
1.2 The three elements comprise three
storeys of 6 flats on the western side, a four storey block on the eastern side
comprising 8 flats and a four and half storey "tower" feature linking
the two containing stairs, landing and lift shaft.
1.3 The flats are a repeated and handed
layout comprising two bedrooms, kitchen/living room and two bathrooms with a
gross floor area of approximately 85 sq.m.
The building is proposed to be sited as a direct replacement of the
existing, the two major blocks being set back from the highway by 5m and 2m
respectively. Pedestrian access is
shown to be directly off Bellevue Road via a footbridge since the site levels
are beneath those of the road.
Vehicular access to serve the premises are shown by that existing
further to the east but joined with the existing development known as Holm Oak,
situated fronting East Street just to the north-east of the site. The remainder of the site is shown to be
landscaped but with a communal garden area situated in the north-west corner of
the site. Car parking includes only 5
spaces but sufficient space for 14 cycles and bin store.
1.4 Details
of Justification for Demolition of Existing Building
Situated in a Conservation Area and
comprising the demolition of a substantial building, Conservation Area Consent
is required for the demolition of the existing structure. Accompanying the application are three
alternative Feasibility Studies, each with the intent of retaining the existing
building and comprising the conversion of the existing building into
apartments; the converting/upgrading including the partial reroofing of the
flat roofed areas to convert the building into apartments; and the partial
demolition of the existing building and conversion of the remaining structure
and proposed extension forming additional self-contained flats.
1.5 Each of these alternatives have
financial implications and conclude that the three alternatives are all
uneconomic and therefore unviable. The
building is in a poor state of maintenance and is deteriorating but appears to
be structurally sound.
2. Location
and site characteristics
2.1 Site has an approximate area of 0.15
hectares and is presently occupied by a substantial two/three storey building
which is not Listed but the majority of it is of Victorian origins. It has been extended by the addition of a
two storey flat roofed wing at the rear and the existing building has been
painted white with the quoins picked out in black. Formerly used as a nursing home, the building is now empty, the
grounds are beginning to grow over.
2.2 To the north-east of the site is a
terrace of three, modern two-storey dwellings or maisonettes which front onto
East Street; to the west is a pair of modern semi-detached properties but the
area is one of mixed development, some two and some three storeys, of fairly
substantial properties in large sites.
2.3 In close proximity, directly to the
north of the site and in part impacting upon it, is the route of the tunnel
serving the railway linking Ryde St Johns to The Esplanade railway
station. The front boundary with Bellevue
Road is a mix of stone walls and iron railings and there is no footway on that
side of the highway. The site contains
some trees, the majority of which are located along the northern boundary, and
a single, substantial tree immediately adjoining the existing building on its
eastern side.
3. Relevant
history
3.1 In July 2004 an application seeking
consent for the demolition of the existing building and redevelopment of the
site with 12 three storey town houses was refused for reasons of inappropriate
design, external appearance and inappropriate scale and character and, in
addition, on the basis that insufficient detail had been submitted to justify
the demolition of the building which is located within a Conservation
Area. Also, a further reason for
refusal was on the basis of an inadequate access due to limited visibility.
4. Development
Plan policy
4.1 National
Policy Guidance
PPS1
(Delivering Sustainable Development) requires schemes to be good enough to
approve, not bad enough to refuse.
PPG3
(Housing) supports use of brownfield sites within urban areas especially,
increased densities for best use of urban land.
PPG15 (Planning and the Historic
Environment) refers to development within Conservation Areas, especially
regarding demolition of non-Listed buildings.
4.2 UDP
Policy
Policies D1 - Standards of Design;
D2 - Standards for Development within the Site; B6 - Protection and Enhancement
of Conservation Areas; B7 - Demolition of Non-Listed Buildings and TR7 -
Highway Considerations for New Development are applicable.
4.3 The
site is not within an Area of Outstanding Natural Beauty but it is within the
designated Conservation Area.
5. Consultee
and third party comments
5.1 Internal
Consultees
Highways Engineers
recommend conditions if approved but wish to limit the use of the access in
connection with this development to a level commensurate with the approved
use. Accordingly recommends a maximum
of 5 car parking spaces.
The Property
Services Department have reviewed the supporting documentation regarding the
three alternative Feasibility Studies and have concluded that the building
costs explained therein are reasonable and that the sales values are also
realistic.
Conservation and
Design Team comments. Extensive negotiations
have taken place between the agents and Conservation Team which have culminated
in the present revised application. The
resultant scheme is thought to be the best that can be achieved via the current
application.
5.2 External
Consultees
·
Network Rail expresses areas of concern but raise
no objection while wishing to ensure safeguarding of the tunnel to the rear of
the site.
·
English Heritage, commenting on original proposal
observe that the building was felt to be sound but with poorly designed, more
modern extensions; considered that the replacement building was of excessive
mass and would have an adverse effect on the Conservation Area.
·
Environmental Health Officer raises concern
regarding passage of sound between flat units.
5.3 Town
Council Comments - not applicable.
5.4 Neighbouring
Properties
8 letters of objection to the
demolition of the existing building and its replacement with either the
originally submitted or the revised scheme on grounds of inadequate car
parking; increased traffic on a narrow highway thus causing traffic danger and
congestion. Access rights to East
Street, alternative uses should be explored; new building of excessive height;
installation of further windows which could create exacerbated loss of privacy;
unnecessary demolition and that the building should be converted into
flats. Excessive and adverse visual
impact on the Conservation Area; destruction of a building of architectural
merit; noise pollution; loss of habitats and loss of stone walls; change of character
for the Conservation Area; inaccurate plans; development out of keeping with
the Conservation Area and creation of a precedent for further similar
proposals, and adverse effect on the railway tunnel.
6. Evaluation
6.1 The
main issues relating to this application are:
·
Policy and principle.
·
The justification for demolition of properties in a
Conservation Area.
·
The design of the replacement building in this
Conservation Area setting.
·
Traffic and access implications.
·
Effect on adjoining properties, and
·
Proximity to the tunnel.
6.2 Site is located within the development
envelope and in an area of predominantly residential use. Purely in land use terms the residential use
of the land is acceptable in principle and in policy terms, the utilisation of
brownfield sites and the best use of urban land are consistent with
governmental and local policies. Given
the area of the site the overall density is acceptable.
6.3 The first step in any redevelopment in a
conservation area is justifying the demolition of an existing building. PPG15 makes it quite clear that the general
presumption should be in favour of retaining buildings which make a positive
contribution to the character or appearance of the conservation area. It is expected that proposals to demolish
such buildings should be assessed against the same broad criteria as proposals
to demolish Listed buildings. However,
in less clear cut cases, where a building makes little or no such contribution,
the Local Planning Authority will need to have full information about what is
proposed for the site after demolition.
It is usual for the demolition to be prohibited until there are acceptable
detailed plans for redevelopment. It is
also usual that, in the event that both planning permission and Conservation
Area consent for the demolition and redevelopment of the site within a
Conservation Area, that demolition is prevented until a binding contract for
the commencement and implementation of the replacement development has been
provided.
6.4 In order to justify the demolition of a
non-Listed building in a Conservation Area, all matters should be considered in
reaching a decision as to whether Conservation Area consent should be granted. These criteria can be wide ranging but
essentially fall into the following categories. Firstly the visual contribution the existing building makes to
the Conservation Area. Assuming the
building is of insufficient merit alone, or in a group, to warrant it being
included in the listing, some buildings still can contribute significantly if
only by continuity of the style of buildings in a particular area. Structurally, if the building is in poor
condition, the economics of repair and refurbishment are factors which are
inextricably linked with alternative developments or uses for such a structure,
and lastly but no means least the visual impact of the loss of the building and
its potential replacement.
6.5 In this instance schemes have been put forward
by the agent to see if conversion to flats for example would make the retention
of the building economically and practically viable. These have proved to be unviable.
6.6 Turning to the design of the
replacement, your officers are of the opinion that after extensive negotiations
the scheme which has emerged is the best that can be achieved via the current
application. Members will be aware that
Ryde has a fairly distinctive design style and is well known for its roofscapes
and design articulation, in particular the Italianate tower with lanterns and
the overall majesty of many of its buildings.
To complement this a design on this site should be capable of
integrating well with the understated simple, elegant late Regency/early
Victorian style. In its determination
the Committee will be mindful of the exhortations of PPS1 (see para 4.1
above). Notwithstanding the
recommendation, if Members consider the design to be, on balance, inappropriate
they may refuse but equally will need to refuse the Conservation Area Consent
application.
6.7 No details appear to have been submitted
in respect of the bin store. OK it's
only a minor point but what is quite clear is that it is of insufficient size
to accommodate 14 separate bins unless the users of the far bins climb across
the other ones. Maybe communal bins are
the answer, but it is at this level of detail that one should be designing in a
Conservation Area.
6.8 In terms of traffic and access, the
conflict seen here is that the existing establishment had sufficient parking
for 5 vehicles to be used in connection with the operational requirements of
the former use, the former nursing home.
The provision of a greater capacity of car parking would inevitably lead
to an increased use of the vehicular access onto Bellevue Road which, in turn,
would warrant the improvement of the access by the formation of visibility
splays and the removal of the brick and stone boundary wall running along the
Bellevue Road frontage. This would have
significant impacts in the Conservation Area and therefore it is felt that the
development should be provided with only the same level of car parking that the
former nursing home use would have generated.
This limited provision meets with the approval of the Highways Engineers
who recognise that in this location, a lesser parking provision may be made due
to the UDP policies and advice in PPG13 (Transport).
6.9 However, the proposed cycle parking bays
are totally unacceptable. They are not
covered, enclosed or secured. They are not
conveniently located for persons entering or leaving the building and neither
are they in what might be termed "defensible space". Their location and layout is an open
invitation to theft contrary to 'Designing Out Crime'. If Members are minded to view the
application favourable this aspect and the bin store will need to be delegated
back to officers for further consideration prior to the issue of any approval.
6.10 Turning to the effect on adjoining
properties, in effect the pair of semi-detached houses located to the west of
the site, Nos. 24 and 24A Bellevue Road, are those which are most likely to be
affected; despite the fact that the adjoining property has a blank gable facing
the site, the possible effects of overlooking of the rear garden could be
significant if windows were included but the design scheme shows false windows,
windows that appear to have been subsequently blocked up, a feature which
occurs in some older buildings. It is
important to include this feature since, otherwise, the elevation would be
blank and plain. Otherwise the
development is unlikely to affect the surrounding properties more than the
existing building.
6.11 The tunnel, through which the Island Line
runs between Ryde Esplanade and Ryde St Johns Stations, is situated only a few
metres to the north. Bearing in mind
this particular feature, liaison has taken place between the agent and Network
Rail who have set out criteria and conditions which need to be observed. No objections are raised providing those
safeguards are undertaken.
6.12 A
S106 obligation is required to cover education and open space contributions.
7. Conclusion
and justification for recommendation
7.1 Situated in the Conservation Area and
comprising a comparatively large building mass, the site is underlain by the
railway tunnel which places a constraint on the site, forcing development into
the south-west corner due to the route of the tunnel beneath. The loss of the building in the Conservation
Area has been investigated and treated as though the building were Listed, as
required by PPG15. The existing
building is not Listed but its style does make a positive contribution to the
character of the area, however, in practical terms, the retention of the building
appears economically unviable as the most valuable use of the structure, for
residential purposes, has proved to be economically unviable. Without redevelopment the site is most
likely to fall into further disrepair and dereliction, detracting further from
the Conservation Area.
7.2 The use of the site and the building as
a nursing home has already ceased, as upgrading of the accommodation to meet
necessary standards is also uneconomic and impractical. Since there is no policy to prevent the loss
of nursing homes, there is no policy objection to the use of the site for an
alternative and suitable purpose which, in this location, is residential use.
7.3 Whilst a fairly substantial development,
it is apparent that only 5 car parking spaces would be provided. This restriction on parking is important
since although it provides only one space for approximately 3 flats, the
restriction is a result of discussion with the Highways Engineer who does not
wish to see any increase in the use of the vehicular access which is very poor
in terms of visibility, exacerbated by the fact that there is no footway
adjoining the site's boundary. In order
to increase the capacity of the site for car parking, it would be necessary to
remove the stone boundary wall which presently forms an important feature in
the Conservation Area if visibility is to be improved. The loss of the stone wall is felt to be
inappropriate therefore a restriction on the capacity of the car park is
proposed.
7.4 Your officers, after much deliberation
and negotiation are of the opinion that under the present circumstances this is
the best scheme likely to emerge. It is
only just on the margins of acceptability.
If Members are of a like view the proposed development would therefore
be consistent with policies G1, D1, D2, B6, B7, H1, H5 and TR7 of the Unitary
Development Plan and also consistent with PPG15 regarding planning and the
historic environment.
8. Recommendation
Conditional
permission (subject to S106 agreement) for P/02104/04 and Conservation Area
Consent for P/02074/04/.
Conditions/Reasons:
The
development hereby permitted shall be begun before the expiration of 5 years
from date of this permission. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990 (as amended). |
|
2 |
No development
shall take place until [samples of materials/details of the materials and
finishes, including mortar colour] to be used in the construction of the
external surfaces of the development hereby permitted have been submitted to
and approved in writing by the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with policy D1 (Standards of Design) of the IW Unitary
Development Plan. |
3 |
No
development shall take place until full details of both hard and soft
landscape works have been submitted to and approved in writing by the Local
Planning Authority and these works shall be carried out as approved. These details shall include proposed
finished levels or contours; means of enclosure; car parking layouts; other
vehicle and pedestrian access and circulation areas; hard surfacing
materials; minor artefacts and structures (eg. furniture, play equipment, refuse
or other storage units, signs, lighting, etc); proposed and existing
functional services above and below ground (eg. drainage power,
communications cables, pipelines, etc, indicating lines, manholes, supports,
etc); retained historic landscape features and proposals for restoration,
where relevant. Reason: To ensure the appearance of the
development is satisfactory and to comply with policy D3 (Landscaping) of the
IW Unitary Development Plan. |
4 |
Front boundary
wall of the site abutting Bellevue Road shall be retained, repaired and
enhanced in accordance with a specification to be submitted to and approved
by the Local Planning Authority prior to the commencement of works on site. Reason: In the interests of maintaining the
amenity value of the area and to comply with policy D1 (Standards of Design)
and B6 of the IW Unitary Development Plan. |
5 |
Notwithstanding condition 4 above, no development shall take
place until details have been submitted to and approved in writing by the
Local Planning Authority of the positions, design, materials and type of
boundary treatment to be erected. The
boundary treatment shall be completed before the buildings hereby permitted
are occupied. Development shall be carried
out in accordance with the approved details. Reason: In the interests of maintaining the
amenity value of the area and to comply with policy D1 (Standards of Design)
and B6 of the IW Unitary Development Plan. |
6 |
No
building hereby permitted shall be occupied until space has been laid out
within the site in accordance with the details submitted for a maximum of 5
cars and 16 bicycles to be parked and for vehicles to turn so that they may
enter and leave the site in forward gear.
The space shall not thereafter be used for any purpose other than that
approved in accordance with this condition. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
7 |
Notwithstanding
condition 4 above, no development shall take place until full details of both
hard and soft landscape works have been submitted to and approved in writing
by the Local Planning Authority. No
dwelling hereby permitted shall be occupied until these works have been
carried out in accordance with the approved details and the works shall
thereafter be maintained in accordance with the approved details. These
details shall include the provision to restrict parking on the site to 5 car
parking spaces, hard and soft surfacing materials, extent of hard and soft
landscaping, proposed and existing functional services above and below
ground, Reason: To ensure that parking provision within
the site is limited to 5 spaces and to comply with policies TR16 and TR7
(Highway Considerations) of the IW Unitary Development Plan. |
8 |
The works hereby authorised shall be begun not
later than 3 years from the date of this consent. Reason: As required by s18 Planning (Listed
Buildings and Conservation Areas) Act 1990 as amended. |
9 |
The works of demolition hereby authorised shall
not be commenced until a binding contract for the carrying out of the works
of redevelopment of the site has been entered into and planning permission
has been granted for the redevelopment for which the contract provides. Reason: In order to protect the special character
of the area and to prevent the site remaining vacant for a significant period
of time and to comply with policies B1 to B8 (Listed Buildings and
Conservation Areas) and D1 (Standards of Design) of the IW Unitary
Development Plan. |
Conditions/Reasons for Conservation Area Consent:
1 |
P06 |
The works hereby authorised shall be begun not
later than 3 years from the date of this consent. Reason: As required by s18 Planning (Listed
Buildings and Conservation Areas) Act 1990 (as amended). |
2 |
P05 |
The works of demolition hereby authorised shall
not be commenced until a binding contract for the carrying out of the works
of redevelopment of the site has been entered into and planning permission
has been granted for the redevelopment for which the contract provides. Reason: In order to protect the special character
of the area and to prevent the site remaining vacant for a significant period
of time and to comply with policies B1 to B8 (Listed Buildings and
Conservation Areas) and D1 (Standards of Design) of the IW Unitary
Development Plan. |
3. |
Reference
Number: P/00973/05
- TCP/21625/A Parish/Name: Brighstone - Ward/Name: Brighstone and
Calbourne Registration
Date: 18/05/2005 - Full Planning Permission Officer: Mr S Cornwell Tel: (01983) 823575 Applicant:
Mr D Newnham Continued
extraction of chalk in previously worked area and extension of chalk quarry
westward into new area (revised site boundary) land
at Cheverton Chalk and Gravel, Cheverton Shute, Shorwell, Newport, PO30 |
This application is recommended for conditional
permission.
REASON FOR COMMITTEE CONSIDERATION This application involves major development
relating to minerals extraction within a designated landscape area. |
1. Details
of application
1.1 This is a full application seeking
permission to work a section of a previously worked area as well as extending
the extraction operation into a totally new but adjoining area.
1.2 Cheverton Chalk Quarry has been worked
for a significant number of years and currently stretches approximately 500
metres along the northern side of the valley. Whilst the eastern and western
ends have been worked out the central section which bites deeper into the
hillside has not yet been fully worked and it is an area in this vicinity with
a face approximately 80 metres by 60 metres in depth which is the subject of
the current application.
1.3 The proposed extension area lies
immediately up the valley to the west, occupying an area approximately 200
metres long by 60 metres. The northern
edge of the site follows an irregular line reflecting the need to avoid a
badger sett and an area of open grassland where the Early Gentian flower has
been located. The presence of the sett
was known and taken into account when submitting the original plan. However, the emergence of the presence of
the Early Gentian has resulted in a revision to the submitted plan to leave
this area undisturbed.
1.4 Information with the application
indicates that the floor of the quarry is of approximately 97 metres aod, with
the top being approximately 140 metres aod.
The submitted plans show the proposal for the extension to run a level
quarry floor in for approximately half of the depth of the site, with the back
section tiered to ensure the stability of the ground beyond. A 15 metre
freeboard is shown as being left at the top of the quarry face to the applicant's
property boundary.
1.5 Applicant estimates that the reserve is
approximately 190,000 tonnes, which at an extraction rate of approximately
9,000 tonnes per year gives a 20 year life.
1.6 The mineral is won by machine, no
blasting takes place. The intention is
to follow the same working hours as previous, which are 0700 hrs to 1800 hrs on
Monday to Friday, 0700 to 1300 hrs on Saturdays, with no working on Sundays or
Bank Holidays.
1.7 Applicant indicates that the quarry
provides a unique chalk prized for its hardness and low moisture content. It is also suggested that it offers material
with different characteristics, with the central section in the previously
worked area providing larger pieces of chalk which are suitable for
construction purposes whilst the extension area is anticipated to provide
material of a lower diameter suitable for use as sub base or to be crushed for
liming agricultural fields. Applicant
has provided a list of the top ten customers as well as indicating that they
supply 42 farms with lime and chalk and
have a further 100 customers who are builders, ground workers and private
individuals.
1.8 At the end of the working life the
intention is to allow the quarry face and floor to regenerate naturally. This is a process which has already
commenced in those areas which have been previously worked out. To mitigate the loss of the grassland, the
applicant is proposing to undertake long term management of the remaining
grassland areas to stop any further degradation from scrub encroachment.
1.9 Given the nature of the proposal and its
location within an Area of Outstanding Natural Beauty, application was
accompanied by an Environmental Impact Statement which addresses the following
issues.
- Agriculture and soils
- Archaeology
- Dust
- Ecology
- Hydrology
- Noise
- Impact on people
- Traffic
- Visual impact.
Within
the Statement each area has been taken in turn and the proposal tested and
assessed against it.
2. Location
and site characteristics
2.1 The application site relates to the
northern slope of a dry valley which runs up in a westerly direction from the
Newport to Shorwell Road. Access is
obtained by a roadway running to the north of the group of buildings which
forms Cheverton Farm. The site is
approximately 1.5 km west of the main road.
The linking roadway is a combination of tarmac, concrete and compacted
stone. In addition to the chalk quarry
applicant also operates a waste transfer station from a substantial building in
the bottom of the valley and from parts of the quarry which have now been
worked out. A roadway runs through the
quarry following the bottom of the valley in a westerly direction providing
access to the gravel pit which lies at the head of the valley.
2.2 To
the north and south is agricultural land but not within his control.
2.3 The proposed extension area, which
occupies part of the south facing slope of the valley, consists of both some
open grass areas and areas overgrown with gorse and scrub. It is part of an unmanaged degrading
semi-natural calcareous grassland. This
belt continues in a westerly direction along this side of the valley slope.
3. Relevant
history
3.1 Planning permission granted for chalk
extraction in part of the worked area in April 1982 for a temporary period
expiring 31 March 1989. Consent granted
for extraction of stone from a 1.1 hectare site to the south-west of the
current application site granted in April 1984 which expired 31 December 1989.
Continued extraction of chalk and
extension to approved extraction area was granted temporary consent in July
1992 and expired 30 September 2002.
3.2 In October 2003 planning permission was
granted for change of use of building from agricultural/plant use to waste
transfer station for the sorting and recycling of inert builder's waste and
storage of processed material within two identified areas of the chalkpit and
in a series of bunkers. One of the
identified areas lies immediately to the north of the main building which was
the subject of the application and the second area occupies the western arm of
the original extraction area. That
consent expires on 30 September 2008.
4. Development
Plan policy
4.1 National
Policy Guidance
·
PPS1 - Delivering Sustainable Development. Sets out general framework of Government's
national policies on different aspects of land use planning. States sustainable development is core
principle underpinning planning.
Emphasises requirement for and implementation of plan led system. States where Development Plan contains
relevant policies applications should be determined in line with Plan. Promotes the protection and enhancement of
the environment.
·
PPS7 - Sustainable Development in Rural Areas. Government's objectives include raising
quality of life and environment in rural areas as well as promoting more
sustainable patterns of development.
Decisions on development proposals should be based on sustainable
development principles ensuring integrated approach to consideration of factors
including effective protection and enhancement of the environment as well as
prudent use of natural resources.
Document advises that AONB has been confirmed by Government as highest
status of protection in relation to landscape and scenic beauty. When determining applications for development
in countryside should consider need for development, if opportunity exists for
it to be relocated outside designated area or met in some other way and any
detrimental effects on the environment.
·
PPS9 - Biodiversity and Geological Conservation. Requires Local Authorities to protect and
positively enhance biodiversity.
Promotes features that support biodiversity and geological conservation
in and around development. Local
Authorities should refuse schemes where significant harm to wildlife and
geological features cannot be prevented, mitigated or compensated.
·
PG16 - Archaeology and Planning sets out policy on
archaeological remains on land giving advice on the handling of archaeological
remains and discoveries including weight to be given to them in planning
decision and the use of planning conditions.
·
PPG23 - Planning and Pollution Control - sets
guidance on the relevance of pollution controls in the exercise of planning
functions. Stresses need to avoid duplication of controls which are the statutory
responsibility of other bodies. Regarding Development Control considerations
gives guidance and weight to be given to these factors in determination.
·
PPG24 Planning and Noise - Gives guidance for local
authorities on the use of planning powers to minimise adverse impact of noise
and considerations to be taken into account in determining planning
applications both for noise sensitive development and for those activities
which will generate noise. Recommends appropriate levels for exposure for
different sources of noise and advice on use of conditions to minimise impact.
·
MPG1 - General Considerations and the Development
Plan System. Sets out the Government's
basic policy on minerals and planning issues and offering guidance on factors
to be taken into account in determining individual planning applications.
·
MPG2 - Minerals Planning Guidance - Applications,
Permissions and Conditions. This note
provides guidance on aspects of the development control system of particular
relevance on the preparation and determination of individual planning
applications. It promotes the concept
of pre-application consultation and the identification as to whether an
Environmental Assessment is required.
Guidance considers the procedural aspects for determining an application
and if considered acceptable the type and scope of conditions that should be
imposed.
·
MPS2 - Controlling and Mitigating the Environmental
Effects of Minerals Extraction in England.
Sets out policies and considerations Minerals Planning Authorities
expected to follow in both preparation of both local development frameworks and
in considering applications for minerals development. Contains technical annexes on particular environmental effects,
specifically dust and noise.
4.2 Unitary
Development Plan Policies
A wide spectrum of policies apply
to this proposal which are identified below.
Of specific note is the reference to this site in Appendix E (Minerals
Sites) with the following reference: "Downland site. Site visible from Worsley Trail to
south. Cannot be readily screened. Arable farmland to north, scrub to east and
west, grazing land to south. No reason
why consent should not be renewed within current approved area if extraction
not completed. Scope for limited
expansion of site."
4.3 Strategic
Policies
S4
- The countryside will be protected
from inappropriate development.
S10 - In areas of designated or defined
scientific, nature conservation, archaeological, historic or landscape value, development
will be permitted only if it will conserve or enhance the features of special
character of these areas.
S12 - Sufficient land will be made available for
mineral extraction to provide for the needs of the Island over the planned
period and longer term.
4.4 Detailed
Policies
G4 - General Locational Criteria of Development
G5 - Development Outside Defined Settlements
C1 - Protection of Landscape Character
C2 - Areas of Outstanding Natural Beauty
C8 - Nature Conservation as a Material Consideration
B9 - Protection of Archaeological Heritage
M1 - Availability of Mineral Resources
M2 - Criteria for Defined Mineral Workings
P1 - Pollution and Development
P5 - Reducing the Impact of Noise
W1 - General Waste Disposal
W2 - Landfill
TR7 - Highway Considerations for New Development
U19 - Safeguarding of Aquifers and Water Resources
5. Consultee
and third party comments
5.1 Internal
consultees
·
Highway Engineer - no highway conditions requested.
·
Ecology Officer -
Although no designated sites are
involved, proposed chalk extraction area has high biodiversity value. Consequently, proposals been subject of pre-
and post-application discussions.
Quarry adjoins narrow south facing
slope of unmanaged calcareous grassland of which about two-thirds is scrubbed
over. Open third is of high
conservation value. Largest block at
western end home to a population of Early Gentian, a plant legally protected by
national and EC legislation. Revised
proposal would allow for retention of this block.
Chalk grassland extends beyond
application site. If approved advise
management of chalk grassland area through Section 106 Agreement. Management Plan should be implemented once agreed
to stop scrub encroaching into area of Early Gentian.
Badger Report submitted as part of
application. Revision to extraction
area can only help protect them and the sett.
Applicants should be reminded by a letter that extraction within 30
metres of entrance of an active sett requires a licence issued by English
Nature and that works must be overseen by a licensed badger worker.
One of the quarry faces proposed
for extraction is home to an established breeding pair of ravens (one of only
four Island sites). They appear
tolerant of activity. Ravens protected
at nest site by Wildlife and Countryside Act 1981. Have protracted nesting period commencing early February. Advise condition imposed no chalk extraction
in immediate vicinity of the occupied nest site.
A pair of Peregrine Falcons nest on
part of the old quarry face not in any extraction area. Applicants should be advised by letter it is
an offence to disturb nest site under Wildlife and Countryside Act.
·
County Archaeological and Historic Environment
Service - I have considered this application and find that it concerns a site
of archaeological interest. The
applicant has a prior arrangement with the County Archaeological Service
whereby the Archaeologist monitors the topsoil stripping as each parcel of land
is prepared to gravel extraction. This
agreement has worked well in the past and, given the time scale and methodology
of the proposed works, the County Archaeologist is willing to continue this
agreement. Consequently, in order that
archaeological features can be adequately recorded recommend that any approval
which may be granted is made subject to conditions.
·
Isle of Wight AONB Lead Officer -
(Summary) Given that this quarry has been in existence since the 1950s
(before the designation of the Isle of Wight AONB in 1963) we accept the
principle of mineral extraction on this site is established. This quarry also provides an important
supply of local materials, provides economic benefits to the local economy, and
is generally in accordance with national planning policy guidance and
statements, and indeed a policy objective of the AONB Management Plan. We accept that the extraction and loading
are short lived sporadic events, which provided they are controlled by
appropriate conditions would not significantly impact on the quiet enjoyment of
the AONB. Provided that the nature
conservation interest can be conserved, we are generally satisfied that this
proposal will have minimal impact on the landscape character of the area.
With regard to the restoration of
the sites, we support the proposed restoration of the chalk extraction site as
set out in the Environmental Statement.
For the restoration of the gravel extraction site, our preferred option
would be partial restoration as described in paragraph 6.2 of the Environmental
Statement leaving a 6 metre bare quarry face for the benefit of biodiversity
and to provide a record of geological information. We are also content that this would be a visual reminder of man's
relationship with the landscape and that AONB landscapes are living and
dynamic.
·
Environmental Health Officer - request conditions.
5.2 External
consultees
·
Environment Agency - to be reported.
·
The Countryside Agency - has no formal
representations to make in this instance.
5.3 Parish
Council comments
Brighstone Parish Councillors
considered the above application at their meeting on 8 June. They are of the opinion that continued
extraction, particularly of the unique chalk to the Island, and the gravel, is
necessary and are pleased that reinstatement of disused sites is taking
place. Councillors support the
application.
5.4 One
letter has been received from the owners of farm surrounding site making the
following comments.
·
Wish to express concern. Understand previous planning permission ceased 2002 but
extraction has continued.
·
In 2001 due mainly to not following planner's
recommendations landslip occurred and crack appeared in our land above
landslip. Despite approaches to
landowner nothing done to resolve problem.
Negotiations at present through solicitors. Part of agreement so far is creation of buffer zone. Such an area should be included above new
extraction area.
·
If chalk face stepped to prevent similar problem
and area around badger's sett avoided, seems large scar on landscape for
relatively small amount of chalk.
·
After heavy rain excessive water floods our land.
·
Traffic already very considerable with chalk and
gravel lorries, recycling builders' waste, service traffic and customers'
vehicles together with equestrian and motor cycle trials events. All add to seven days a week often outside
permitted hours.
5.5 Islandwatch - object to application,
while recognising site designated for mineral extraction believe there are
legally protected species on or adjacent site for chosen extension.
5.6 Hampshire and Isle of Wight Wildlife
Trust: concerned that application would have detrimental input on protected
bird and plant species present on site.
Trust been informed that Early Gentian protected under schedule 8 of
Wildlife and Countryside Act 1981 is present on site. Trust request that extension of quarry and extraction of chalk
takes place in an area of site away from areas where protected species are
present.
6. Evaluation
6.1 The determining considerations with
regard to this application are firstly whether the proposal conforms with
national guidance as expressed through the Planning Policy Guidance Notes,
Planning Policy Statements, Mineral Planning Guidance Notes and Mineral Policy
Statements. Secondly, on the basis that
the proposal was the subject of detailed pre-application discussions at which
time the requirement for an Environmental Statement was identified it is
considered that it would be appropriate to test the proposal using those
primary topic areas that were identified at that stage against the detailed
policies contained in the Unitary Development Plan. Following on from the above the third consideration would be to
examine whether in the processing of the application other factors have come to
light which warrant further consideration including any points made during the
consultation process.
6.2 Firstly, with regards to the national
guidance, the protection status given to the Area of Outstanding Natural Beauty
is now considered to be as great as that which applies to a National Park. On that basis, a clear justification is
required before allowing any development within such an area. It is generally recognised that by their
very nature mineral deposits can only be worked where they occur. Given the characteristics of the Isle of
Wight this has placed the majority of our mineral sites within designated
landscape areas.
6.3 Whilst there are other chalk quarries on
the Island it must also be recognised that the nature of the deposit at
Cheverton generates a unique type of material which makes it particularly
suited to certain specialised projects.
On that basis, the site passes the test of importance that justifies the
location within a designated landscape area generating a material that could
not otherwise be sourced locally but would have to be imported with all the
requirements associated with such an activity.
6.4 Secondly, with regards to the topic
areas identified in the Environmental Statement, these are outlined below and
assessed against the relevant planning policies.
·
Agriculture and soils. The soils have already been stripped from
the previously approved extension area.
The proposed extension site comes under class 3b-4 agricultural land and
accordingly would not result in the loss of good agricultural land and
therefore does not conflict with Policy C14 (Safeguard Best Agricultural
Land). The floor of the quarry will
return to agricultural use at the end of the extraction process.
·
Archaeology. With regards to this specific site there are
not considered to be any archaeological features within the proposed extension
area. The Council's Archaeologist does
however intend to monitor the topsoil stripping exercise (where any finds would
be evident) and accordingly, the proposal would be in accordance with Policy B9
(Protection of Archaeological Heritage).
·
Ecology. That section of the previously approved
extraction area which is to be finally worked out as part of this proposal does
contain one element of conservation value which is the nesting of two
ravens. The Environmental Impact Report
survey indicates that these have frequented the quarry for the past five years,
occupying two nests, one with the proposed central extraction area with the
other nest outside. The Report
acknowledges that the ravens are protected species and recommends that
extraction in the vicinity of the active nest should be avoided during the
breeding season which runs for approximately 6½ weeks from February or
March. This proposal is supported in
the assessment by the Ecology Officer.
The Peregrine Falcon nest was
observed in a section of the chalk face which has already been worked out, and
other than an informative there is no need to limit operations in that area.
Regarding the
proposed extension site, the assessment recognises the presence of an active
badger sett in the north west part of the site and a potentially inactive sett
in the north east part of the site.
Although included within the red lined site a protection zone is
identified to exclude work close to the setts.
If over time the setts are abandoned he could seek the necessary licence
consent to close them up and work out the whole area. At the time of the survey it did not pick up the presence of the
Early Gentian Violet in the largest of the remaining open grassland areas
within the application site. As
consequence of this the application plan has been revised to exclude this area
from being excavated.
As a mitigating
factor, applicant has offered to undertake active management of two remaining
areas of calcareous grassland and submitted a Draft Management Plan with the
stated aim of arresting the decline of calcareous grassland and setting out a
series of actions to control scrub encroachment. This proposal is considered to be an active benefit for the
conservation value of the area and on the basis that the management also
applies to the Early Gentian area carries the support of the Council's Ecology
Officer. Under those circumstances it
is considered that the proposal does not conflict with Policy C8 (Nature
Conservation as a Material Consideration).
With regards to the proposed management agreement, on balance this can
be achieved by condition rather than a legal agreement and given the
recognition of the presence of the Early Gentian the management should commence
as soon as the agreement is signed.
·
Dust and noise. Given the low key nature of the extraction
(no blasting is involved) and its location any problems associated with dust
generation are considered to be negligible.
The nearest residential properties are at Cheverton Farm approximately
600 metres to the north east and at Cheverton Cottages 700 metres to the south
east. There are not considered to be
any ecological features in sufficient proximity to be harmed by any dust. In periods of dry weather dust control
methods could be implemented.
With regards to noise
generation, this will result from the machinery associated with the extraction
process from crushing which is limited to April to October and from general
traffic associated with the site.
Again, given the distances involved to nearby residential properties and
the proposed operating hours which have been set out by the applicant it is not
considered that any disturbance will arise.
I am conscious of the closer proximity of a number of well used
footpaths but on balance consider that the noise generated by any machinery in
the quarry base or any vehicles driving to or away from the pit would not be
significantly different that hearing any agricultural machinery operating on
surrounding land.
Given the
circumstances outlined above it is not consider that the proposal would be
contrary to Policies P1 (Pollution and Development) or P5 (Reducing the Impact
of Noise).
Hydrology. The site operates at a significant level
above the water table (approximately 65m+).
On the basis that general operational controls are in place relating to
the storage of any fuels there should be no threat to the quality of the water
aquifers from the extraction process.
Accordingly,
the quarry proposal does not conflict with Policy U19 (Safeguarding of Aquifers
and Water Resources).
·
Traffic. All vehicle movements associated with this
site share the same access as the gravel pit and Waste Transfer Facility off
the main Newport to Shorwell Road and utilises a private roadway. This is the arrangement that has existed for
a substantial number of years. Given
this arrangement the proposal does not conflict with policy TR7 (Highway
Considerations for New Development).
·
Visual Impact. As part of the pre-application discussions
the applicant was encouraged to undertake a Visual Impact Assessment of the
existing and proposed operation, both from the Worsley Trail to the south and
from the east including the roadway running up to the Chillerton Mast from
Cheverton Shute and from Newburn Down, which is the high ground lying to the
north of the Chillerton TV mast. This
exercise has consisted of assessment from 8 viewpoints.
The majority of the existing
quarry is in view from the Worsley Trail at a distance of approximately 600
metres. This is the closest that the
public footpath comes to the site (assessment viewpoint No. 2). From this position the lower section of the
extension area is screened by an intervening hillside. To the west of this point the views begin to
be more oblique, with the lower section of the new extraction site continuing
to be screened by the intervening land.
Viewpoints 5 to 8 are
positions on the concrete roadway running up towards Cheverton Down and on the
bridleway above West Ridge Down and Newborn Down. Whilst on a number of occasions an unobstructed view of the
existing quarry and the proposed extension area are provided, these are at an
oblique angle and involve distances in the region of 2 to 3 kilometres.
From none of the
viewpoints assessed does any of the operations break the skyline. When viewing the site it is noticeable that
the eastern and western arms, which have been worked out, are less bright than
the active working face in the centre and are also beginning to show signs of
vegetation establishing on the faces.
Taking all factors
into consideration, excavations on site are not considered to be significantly
detrimental to the general character of the landscape or the designated Area of
Outstanding Natural Beauty.
Accordingly, the proposal is not considered to be contrary to Policies
C1 (Protection of Landscape Character) or Policy C2 (Areas of Outstanding
Natural Beauty).
6.5 The third factor to consider is whether
or not any of the representations have raised issues that have not been
addressed above. Members will note that
of the representations received only the one from the local landowner has raised
some points of concern relating to the expiry of the original permission, the
stability of the worked faces, drainage and traffic issues.
The adjoining landowner is correct
in the statement that the original permission to work this site expired in
September 2002. When this was noted in
June 2003 the operator was advised that any continued works were
unauthorised. At that time a decision
was taken that on the basis he was continuing to extract within the previously
approved area and that the UDP identified the continued working of the quarry,
as a proposal that would be likely to gain support, it was not felt appropriate
to take any immediate enforcement action.
Since that time the discussions with the landowner have focused on the
nature of the application that is now before Members.
With regards to the concern over
the stability of the quarry face and the impact that this has had on the
adjoining land to the north, the site operator has provided a copy of a Report
that had been commissioned on this subject.
The Report notes that the site is being worked leaving the walls with a
batter angle of repose between 65º to 78º.
It concludes that the walls have been worked in a manner that would
leave them in a stable condition. The
area of failure resulted because of too steep an angle, that the ground was
riddled with rabbit holes, that the land behind provided run off into the area
and because of the geological characteristics of this particular corner of the
site. The Report recommends a proposal
to regrade the top of the area to a shallower angle, and once regraded the land
should be topsoiled and pinned with a geotech style membrane and sown with a
deep rooted grass mix. The site
operator has also positioned some material at the foot of this corner of the
site to further stabilise the ground behind.
Under these circumstances it is considered appropriate to leave any
further discussions on this matter with regards to compensation between the two
parties concerned as a civil matter.
With regards to the concerns over
drainage and traffic, on the basis that the quarry lies in a low section of the
valley it is unclear how drainage problems would occur. Concerning traffic levels, the Highway
Engineer has considered the proposal and raises no objection.
Both Islandwatch and the Wildlife Trust
have raised concerns over the impact of the operation on protected
species. These points have been
addressed in the revised details and will also be covered in the conditions.
7. Conclusion
and justification for recommendation
7.1 This report relates to a proposal to
continue working an area where planning permission has already been approved in
the past for the winning of chalk but has not been worked out during the life
of the consent, and for an extension to the operational area, extending the
quarry in a westerly direction. Based
on the level of extraction the applicant calculates that the existing and
extended area would give the operation a life of approximately 20 years.
7.2 The proposal would open up the new
extraction area whilst the central section of the old site is still being
worked, as they provide different types of material. To mitigate for the loss of any calcareous grassland in the
extended area the landowner has offered to enter into a management agreement on
other land which he owns to control scrub invasion. This management would also apply to the area of the original
application site on which the Early Gentian flower was located and has now been
excluded from the proposal. The
intention is to allow the quarry face to naturally regenerate and Members will
note that the walls are already providing a site for nesting birds.
7.3 The proposal has been the subject of
detailed pre-application discussions which has resulted in the submission of an
Environmental Statement. This was
requested given the location within a designated landscape area. However, it has been recognised that with
the expense in generating this statement that the applicant will be looking for
a planning concept with a 20 year life rather than the previous consent which
had a limited 10 year life.
7.4 Clearly, one of the benefits of engaging
in the detailed pre-application discussions which identified the main
considerations to be included within any Environmental Statement is that this
process has anticipated all the concerns that were likely to be raised by any
of the consultees, and this is reflected in the representations outlined in
this report. A number of concerns have
been raised by an adjoining landowner, but they are not considered that they
raise any fundamental issues that would warrant withholding consent. Those concerns raised by Islandwatch and the
Wildlife Trust have also been addressed and resolved.
7.5 This scheme has been tested against both
the Government's policy statements and guidance notes and against the Council's
own Unitary Development Plan policies.
The site is recognised in the UDP as one with planning permission for
continued extraction of the 1996 approved site is likely to be given with
reference to an appropriate extension.
On balance the proposal currently in front of the members reflects this
statement.
8. Recommendation
That
subject to appropriate conditions the application is approved.
In addition that
an informative letter is sent with the decision notice advising the applicant
about the protected status of the badger sett, the Peregrine Falcon nest site
and the Raven nest site.
Conditions/Reasons:
Extraction of minerals shall cease by 30
September 2025 and restoration shall be completed by 31 December 2027 unless
otherwise approved by the Mineral Planning Authority. Reasons: To comply with Section 91 of the Town
& Country Planning Act 1990. |
|
2 |
The site shall be progressively reclaimed in
accordance with the conditions of this permission and shall be restored in
its entirety by 31 December 2027 or within 12 months from the cessation of
minerals operations as defined in this permission whichever is the earlier. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
3 |
Prior to
any works commencing in the extension area as identified in the application,
a plan showing the proposed phased working of this area shall be submitted
for agreement. Working of the site
shall then be undertaken in accordance with the approved scheme and the
programme. Reason: To minimise the visual impact of the
extraction on the surrounding area and to comply with policies C1 (Protection
of Open Countryside) and C2 (Areas of Outstanding Natural Beauty) of the IW
Unitary Development Plan. |
4 |
Before
any excavations are undertaken in the extension area as defined within the
application a scheme and programme shall be submitted to the Mineral Planning
Authority for agreement in writing of arrangements providing for the
installation of robust ground markers around the site boundary and shall
include details of: (a) a
plan showing the location of the ground markers (b) the
type and number of ground markers to be used which may include posts, fencing
or other means, and (c) the
method of protection of the ground markers. The agreed arrangements shall be implemented in
the their entirety within one week of the Mineral Planning Authority's
written agreement, and retained throughout the period of this
permission. No change to the marker
positions shall take place without the written agreement of the Mineral
Planning Authority. All plant
movement and any extraction shall be confined to the designated area. Reason: To ensure that the extraction operation is
confined to the approved area and to protect the surrounding nature
conservation interests in accordance with policy C8 of the IW Unitary
Development Plan. |
5 |
A copy of
this permission and the approved plans showing the method and direction of
working and restoration shall be displayed in the operator's site office at
all times during the life of the site.
Any subsequent approved amendments shall also be displayed. Reason: To ensure that operators and contractors
working at the site are familiar with the requirements of the scheme and the
permission. |
6 |
Notwithstanding the provisions of Part 19 and 21 of Schedule 2
of the Town & Country Planning (General Permitted Development) Order 1995
(or any Order amending, replacing or re-enacting that Order): (a) no
fixed plant or machinery, buildings, structures or erections or private ways
shall be erected, extended, installed, rearranged, replaced, repaired or
altered at the quarry complex without the prior planning permission from the
Mineral Planning Authority. Reason: To protect the amenities of the area and
to comply with policies D1 (Standards of Design) and M2 (Defined Mineral
Working) of the IW Unitary Development Plan. |
7 |
Except in
emergencies to maintain safe quarry working (which shall be notified to the
Mineral Planning Authority at the earliest opportunity, together with details
of the emergency and the operations carried out) or unless the Mineral
Planning Authority has agreed otherwise in writing: No operations, other than servicing,
environmental monitoring, maintenance and testing of plant shall be carried
out at the site except between the following times: 0700 and 1800 hours Mondays to Fridays 0800 and 1300 hours Saturdays No servicing, maintenance and testing of plant
shall be carried out at the site between 0800 and 1700 hours on any date (and
at no time on Sundays, Bank or Public Holidays); No operations for the formation and subsequent
removal of material from (…) (eg. any environmental banks and soil storage
areas) shall be carried out at the site except between the following times: 0700 and 1800 hours Mondays to Fridays 0800 and 1300 hours Saturdays No operations other than environmental monitoring
and water pumping at the site shall take place on Sundays, Bank or Public
Holidays. Reason: To protect the amenities of local
residents and to comply with policy D1 (Standards of Design) of the IW
Unitary Development Plan. |
8 |
The developer shall afford access at all
reasonable times to any archaeologists nominated by the Local Planning
Authority and shall allow them to observe all groundwork and to record
[items/features] of archaeological significance and finds. Notification of the opening up and information as
to whom the archaeologist should contact on site shall be given in writing to
the address below (or to any alternative address notified to the developer by
the Local Planning Authority) not less than 14 days before the commencement
of any work: County Archaeologist County Archaeological Centre 61 Clatterford Road Carisbrooke Newport Isle of Wight PO30 1NZ Reason: In order to ensure access by specified
archaeologists during the permitted operations and to comply with policies B9
(Protection of Archaeological Heritage) and B10 (Parks and Gardens and
Landscapes of Historic Interest) of the IW Unitary Development Plan. |
9 |
Vehicle
access to the site for any purposes shall be confined to utilising the existing
roadway which serves the site and which joins the B3323 immediately north of
Cheverton Farm, and no vehicle access shall be obtained via the Worsley
Trail. Reason: In the interests of protecting the
amenities of the locality and to comply with policies C1 (Protection of
Landscape Character), C2 (Areas of Outstanding Natural Beauty) and TR7
(Highway Considerations for New Development) of the IW Unitary Development
Plan. |
10 |
The
excavations shall be undertaken utilising an excavator and no blasting shall
take place. Reason: In the interests of protecting the
amenities of the locality and to comply with Policies C1 (Protection of
Landscape Character) and C2 (Areas of Outstanding Natural Beauty) of the IW
Unitary Development Plan. |
11 |
No chemicals,
oil or fuel shall be stored on the quarry floor. Reason: To minimise any threat and to protect the
quality of groundwater and to comply with policy U19 (Safeguarding of
Aquifers and Water Resources) of the IW Unitary Development Plan. |
12 |
Within
one month of this decision notice a Management Plan for the calcareous
grassland at Cheverton Farm setting out the aims and objectives for the
management of the open grassland lying to the west of the extension site and
including the area excluded from the planning application, identified on
Drawing No. 470/15 titled Extent of the Calcareous Grassland adjacent the
Cheverton Chalk Quarry shall be submitted and approved in writing with the
Mineral Planning Authority. The
submitted plans shall also include the time of year when the management
measures shall be undertaken. The
agreed scheme shall then come into effect immediately and remain in force
hereafter. Reason: To compensate for any loss of nature
conservation interest from the excavation site and to enhance the nature
conservation value of other land within the operator's control and to improve
on biodiversity in accordance with policy C8 (Nature Conservation as a
Material Consideration) of the IW Unitary Development Plan. |
13 |
Topsoil
shall be stripped, handled and stored to be retained and available for use
during the restoration proposals. No
plant or vehicle shall cross any area of unstripped topsoil except where such
trafficking is essential and unavoidable for purposes of essential/emergency
access. Reason: To prevent loss or damage of soil and to
ensure that it is reused at the restoration of the site. |
14 |
All
topsoil and subsoil shall be stored in mounds not to exceed 3 metres in
height unless otherwise agreed in writing with the Mineral Planning
Authority. The mounds shall be
constructed with the minimum amount of soil compaction to ensure stability
and shape so as to avoid collection of water in surface undulations. The material shall not be moved or added
to until required for restoration purposes. Reason: To prevent loss or damage of soil and to
ensure that it is reused at the restoration of the site. |
15 |
Prior to
soil stripping and formation of storage mounds, a scheme for grass seeding and
management of all the storage mounds that will remain in situ for more than
three months shall be submitted for the written approval of the Mineral
Planning Authority. Seeding and
management of the storage mounds shall be carried out in accordance with the
approved details. Reason: To prevent loss or damage of soil and to
ensure that it is reused at the restoration of the site. |
16 |
The
site/quarry complex shall be reclaimed and managed in accordance with the
scheme to be submitted and approved by the Mineral Planning Authority at
........... The scheme shall include
details of: (a) the nature of
the intended after use of the site. (b) the
ripping of the quarry floor and the respreading over the floor of the
excavated area of overburden/subsoil and topsoil previously stripped on the
site. (d) a
proposal to level out the whole of the western arm of the quarry between the
two extraction areas and the access roadway that runs through this area. the ripping of
any compacted layers of final cover to ensure adequate drainage and aeration,
such ripping should normally take place before placing of the topsoil. (e) the machinery to
be used in soil respreading operations. (f) grass seeding of
reclaimed areas with a suitable herbage mixture. Reason: To ensure that the site is restored to a
visually acceptable condition and to comply with policies C1 (Protection of
Landscape Character) and C2 (Areas of Outstanding Natural Beauty) of the IW
Unitary Development Plan. |
17 |
An agricultural aftercare scheme outlining the
strategies shall be submitted for the written approval of the Mineral
Planning Authority at least 3 months before spreading of subsoil
commences. The strategy shall provide
for: (a) a 5
year period of aftercare in accordance with Annexe A of NPG7, specifying the
steps to be taken and the period during which they are to be taken, and who
will be responsible for taking those steps.
The scheme shall include provision of a field drainage system and
provide for an annual meeting with the Mineral Planning Authority. (b) a detailed
annual programme, in accordance with annexe A of NPG7 to be submitted to the
Mineral Planning Authority. Reason: To ensure that the site is restored to a
visually acceptable condition and to comply with policies C1 (Protection of
Landscape Character) and C2 (Areas of Outstanding Natural Beauty) of the IW
Unitary Development Plan. |
18 |
As part of the restoration scheme the chalk faces
of the quarry shall be left undisturbed and allowed to develop a vegetation cover
naturally and to be exposed to natural processes. Reason: To ensure that the site is restored to a
visually acceptable condition and to comply with policies C1 (Protection of Landscape
Character) and C2 (Areas of Outstanding Natural Beauty) of the IW Unitary
Development Plan. |
19 |
Not to undertake any extraction operations or
vehicle movements from ....... for a period of 6 and a half weeks within X
metres of the Raven nest. Reason: To avoid any disturbance to the nesting
areas during the breeding season and to comply with condition 8 (Nature
Conservation as a Material Consideration) of the IW Unitary Development Plan. |
20 |
Not to undertake any extraction of chalk below X
metres above Ordnance Datum. Reason: To minimise any threat and to protect the
quality of groundwater and to comply with policy U19 (Safeguarding of
Aquifers and Water Resources) of the IW Unitary Development Plan. |
4
& 5. |
Reference
Number: P/00974/05 -
TCP/21625/B & P/00975/05 -
TCP/21625/C Parish/Name: Brighstone - Ward/Name: Brighstone and
Calbourne Registration
Date: 18/05/2005 -
Full Planning Permission Officer: Mr S Cornwell Tel: (01983) 823575 Applicant:
Mr D Newnham Extension
of gravel pit Cheverton
Chalk and Gravel, Cheverton Shute, Shorwell, Newport, PO303JE |
These applications are recommended for conditional
permission.
REASON FOR COMMITTEE CONSIDERATION Both applications involve major schemes relating
to minerals extraction within a designated landscape area. |
1. Details
of Application
1.1 Application
ref: TCP/21625/B is a full planning application seeking permission to extend the
size of an existing gravel pit.
1.2 Planning Application ref: TCP/21625/C is
a full application seeking permission to renew the temporary permission granted
in 1994 which expires 30 September 2005 for the excavation of a gravel pit.
1.3 On the basis that the extension site
would be a continuation of the renewal site it is proposed to refer to both in
the general description below and elsewhere in this report.
1.4 The previously approved site measures
approximately 85 metres by 200 metres, with the depth of workings shown as up
to approximately 9 metres. All the top
soil has been stripped but the depth has not been fully worked out. The
previous permission allowed for the tipping of inert material to restore the
site back to its original levels. However, no imported material has been
brought onto the site.
1.5 The material to be excavated is flint
hogging which lies in a plateau deposit. The material, once excavated, is
graded on site using mobile plant but is not washed. The material is used in
building and engineering developments including roadways and gabion baskets.
Its angular characteristics make it good material in stabilisation works. The
estimated annual extraction rate of 3,750 tonnes of gravel per year gives an
estimated life of 20 years. Actual figures are obviously dependant on the
demand. Any sorted material is stock piled in the pit bottom.
1.6 On the basis that the existing site has
not been worked out within the life of the consent the first application seeks
to continue working this area whilst the second proposal is to extend the
working area into a new section of ground approximately 80 metres wide and
between 40 to 45 metres long in a northerly direction. Cross sectional plans show an anticipated
depth of 8.25 metres. Applicant advised
that the area is likely to be worked in two or three strips each approximately
15 metres wide.
1.7 Plans indicate option of restoring the
site with material approximately 2 metres deep utilising the waste from the
extraction process (approximately 25%) which would result in a 6 metre face
being left around the edge of the quarry, or alternatively if the operator
obtains a Waste Management licence, proposal would then be to restore the site
back to its original levels. This option would require some 92,000 tonnes of
inert fill material and would be undertaken in association with the Waste
Transfer Facility operated by the same individual within the building close to
the chalk quarry. Which ever option is adopted the land returns to agricultural
use.
1.8 Vehicle access to the site would be via
the existing roadway which runs down to the chalk quarry and continues through
to the Newport to Shorwell Road meeting the highway adjacent Cheverton Farm.
1.9 Operating hours would be 0700 - 1800
hours Monday to Friday and 0700 - 1300 hours on Saturday with no working on
Sundays or Bank Holidays.
1.10 The
whole operation would take place in three phases:
Phase 1 The 'existing' pit is worked out and
the screen bund is formed alongside the building on the south side of the pit
and landscaped.
Phase 2 Excavators move into the new area
with soil stored along boundaries.
Phase 3 Importation waste (subject to
licence)
1.11 Given the nature of the proposal and its
location within an Area of Outstanding Natural beauty, application was
accompanied by an Environmental Impact Statement which addresses the following
issues:
- Agriculture and soils
- Archaeology
- Dust
- Ecology
- Hydrology
- Noise
- Impact on people
- Traffic
- Visual impact
Within
the statement each area has been taken in turn and the proposal 'tested' and
assessed against it.
2. Location
and Site Characteristics
2.1 The sites lie at the head of a dry
valley which runs westward for a distance of approximately 1.2 kilometres off
the Newport to Shorwell Road (B3323).
2.2 The site consists of the existing active
gravel pit whilst the proposed extension area to the north is currently
agricultural grazing land (Class 3) bounded by post and wire fencing.
2.3 Immediately to the south is a large
agricultural cattle building. Some 200
metres further away in this direction is the Worsley Trail. The north west corner of the existing quarry
represents the crest of the ground levels in the area with the land falling
gently away to the north before rising again into Brighstone Forest which lies
some 300 metres away from the application site. The general character of the area is one of open rolling
downland.
3. Relevant
History
3.1 Records
indicate that gravel extraction was approved in the southern part of the
extraction site (but now worked out) in December 1950.
3.2 Continued extraction of flint gravel
hogging and extension to extraction area together with proposed tipping of
inert material and reclamation of land was granted conditional planning
permission in August 1996. That
permission expires 30 September 2005.
4. Development
Plan Policy
4.1 National
Policy Guidance
·
PPS1 - Delivering Sustainable Development. Sets out general framework of Government's
national policies on different aspects of land use planning. States sustainable development is core principle
underpinning planning. Emphasises
requirement for and implementation of plan led system. States where Development Plan contains
relevant policies applications should be determined in line with Plan. Promotes the protection and enhancement of
the environment.
·
PPS7 - Sustainable Development in Rural Areas. Government's objectives include raising
quality of life and environment in rural areas as well as promoting more
sustainable patterns of development.
Decisions on development proposals should be based on sustainable
development principles ensuring integrated approach to consideration of factors
including effective protection and enhancement of the environment as well as
prudent use of natural resources.
Document advises that AONB has been confirmed by Government as highest
status of protection in relation to landscape and scenic beauty. When determining applications for
development in countryside should consider need for development, if opportunity
exists for it to be relocated outside designated area or met in some other way
and any detrimental effects on the environment.
·
PPS9 - Biodiversity and Geological
Conservation. Requires Local
Authorities to protect and positively enhance biodiversity. Promotes features that support biodiversity
and geological conservation in and around developments. Local Authorities should refuse schemes
where significant harm to wildlife and geological features cannot be prevented,
mitigated or compensated.
·
PPG16 - Archaeology and Planning sets out policy on
archaeological remains on land giving advice on the handling of archaeological
remains and discoveries including weight to be given to them in planning
decision and the use of planning conditions.
·
PPG23 - Planning and Pollution Control - sets
guidance on the relevance of pollution controls in the exercise of planning
functions. Stresses need to avoid duplication of controls which are the
statutory responsibility of other bodies. Regarding Development Control
considerations gives guidance and weight to be given to these factors in
determination.
·
PPG24 Planning and Noise - Gives guidance for local
authorities on the use of planning powers to minimise adverse impact of noise
and considerations to be taken into
account in determining planning applications both for noise sensitive
development and for those activities which will generate noise. Recommends
appropriate levels for exposure for different sources of noise and advice on
use of conditions to minimise impact.
·
MPG1 - General Considerations and the Development
Plan System. Sets out the Government's
basic policy on minerals and planning issues and offering guidance on factors
to be taken into account in determining individual planning applications.
·
MPG2 - Minerals Planning Guidance - Applications,
Permissions and Conditions. This note
provides guidance on aspects of the development control system of particular
relevance on the preparation and determination of individual planning
applications. It promotes the concept
of pre-application consultation and the identification as to whether an
Environmental Assessment is required.
Guidance considers the procedural aspects for determining an application
and if considered acceptable the type and scope of conditions that should be
imposed.
·
MPS2 - Controlling and Mitigating the Environmental
Effects of Minerals Extraction in England.
Sets out policies and considerations Minerals Planning Authorities
expected to follow in both preparation of both local development frameworks and
in considering applications for minerals development. Contains technical annexes on particular environmental effects,
specifically dust and noise.
4.2 Unitary
Development Plan Policies
A wide spectrum of policies apply
to this proposal which are identified below.
Of specific note is the reference to this site in Appendix E (Minerals
Sites) with the following reference: "Downland site adjacent arable
farmland to south, west and north and grazing/downland to east. Site visible in part from Worsley Trail to
south. Site to be restored to arable
use by tipping and grading of inert waste.
No reason why consent should not be renewed within current approved area
if extraction not completed. Scope for
limited expansion of site."
4.3 Strategic
Policies
S4
- The countryside will be protected
from inappropriate development.
S10 - In areas of designated or defined scientific,
nature conservation, archaeological, historic or landscape value, development
will be permitted only if it will conserve or enhance the features of special
character of these areas.
S12 - Sufficient land will be made available for
mineral extraction to provide for the needs of the Island over the planned
period and longer term.
4.4 Detailed
Policies
G4 - General Locational Criteria of Development
G5 - Development Outside Defined Settlements
C1 - Protection of Landscape Character
C2 - Areas of Outstanding Natural Beauty
B9 - Protection of Archaeological Heritage
M1 - Availability of Mineral Resources
M2 - Criteria for Defined Mineral Workings
P1 - Pollution and Development
P5 - Reducing the Impact of Noise
W1 - General Waste Disposal
W2 - Landfill
TR7 - Highway Considerations for New Development
U19 - Safeguarding of Aquifers and Water Resources
5. Consultee
and Third Party Comments
5.1 Internal
consultees
·
Highway Engineer -
No highway conditions requested.
·
County Archaeological and Historic Environment
Service - I have considered this application and find that it concerns a site
of archaeological interest. The
applicant has a prior arrangement with the County Archaeological Service
whereby the Archaeologist monitors the topsoil stripping as each parcel of land
is prepared to gravel extraction. This
agreement has worked well in the past and, given the time scale and methodology
of the proposed works, the County Archaeologist is willing to continue this
agreement. Consequently, in order that
archaeological features can be adequately recorded recommend that any approval
which may be granted is made subject to conditions.
·
Isle of Wight AONB Lead Officer - (Summary). Given that this quarry has been in existence
since the 1950s (before the designation of the Isle of Wight AONB in 1963) we
accept the principle of mineral extraction on this site is established. This quarry also provides an important
supply of local materials, provides economic benefits to the local economy, and
is generally in accordance with national planning policy guidance and
statements, and indeed a policy objective of the AONB Management Plan. We accept that the extraction and loading
are short lived sporadic events, which provided they are controlled by
appropriate conditions would not significantly impact on the quiet enjoyment of
the AONB. Provided that the nature
conservation interest can be conserved, we are generally satisfied that this
proposal will have minimal impact on the landscape character of the area.
With regard to the
restoration of the sites, we support the proposed restoration of the chalk
extraction site as set out in the Environmental Statement. For the restoration of the gravel extraction
site, our preferred option would be partial restoration as described in
paragraph 6.2 of the Environmental Statement leaving a 6 metre bare quarry face
for the benefit of biodiversity and to provide a record of geological
information. We are also content that
this would be a visual reminder of man's relationship with the landscape and
that AONB landscapes are living and dynamic.
·
Ecology Officer - Agree comments in environmental
statement that current ecological interest of gravel quarry site is low. However, old quarry workings have
considerable potential to provide bio-diversity gains as acknowledged in
statement. A partial restoration of site would allow biodiversity gains to be
expressed as well as providing some diversity in local landscape. If approved
advice that any restoration scheme does not provide full restoration but allows
for retention of some quarry faces and naturally vegetated quarry edges.
·
Environmental Health Officer - request conditions.
5.2 External
consultees
·
Environment Agency - No objection in principle to
the proposal. Infilling of void space
will require formal permit from Agency.
·
The Countryside Agency - has no formal
representations to make in this instance.
5.3 Parish
Council comments
Brighstone Parish Council
considered the above application at their meeting on 8 June. They are of the opinion that continued
extraction, particularly of the unique chalk to the Island, and the gravel, is
necessary and are pleased that reinstatement of disused sites is taking
place. Councillors support the
application.
5.4 One
letter has been received from local landowner making the following points:
·
Concerns relate to drainage, as after heavy rain
excess water floods up onto our land
·
Traffic to chalk pit already very considerable with
chalk and gravel lorries, skips, recycling of builders' waste, service traffic
and customers for retail business of hard landscaping materials, stone,
sleepers, paving stones etc., and associated with equestrian and motor cycle
trials events. All these are adding to
constant traffic seven days a week and are often permitted hours.
·
Before considering this application we feel these
problems need resolving and if permission is given the conditions imposed
should be strictly adhered to. Also at
present there is little protection above the quarry to prevent a potential
accident occurring.
·
We are seriously concerned that our land is
jeopardised by this planning application.
6. Evaluation
6.1 The determining considerations with
regard to both applications are firstly whether the proposal conforms with
national guidance as expressed through the Planning Policy Guidance Notes,
Planning Policy Statements, Mineral Planning Guidance Notes and Mineral Policy
Statements. Secondly, on the basis that
the proposal was the subject of detailed pre-application discussions at which
time the requirement for an Environmental Statement was identified I consider
that it would be appropriate to test the proposal using those primary topic
areas that were identified at that stage against the detailed policies
contained in the Unitary Development Plan.
Following on from the above the third consideration would be to examine
whether in the processing of the application other factors have come to light
which warrant further consideration including any points made during the
consultation process.
6.2 Firstly, with regards to the national
guidance, the protection status given to the Area of Outstanding Natural Beauty
is now considered to be as great as that which applies to a National Park. On that basis, a clear justification is
required before allowing any development within such an area. It is generally recognised that by their
very nature mineral deposits can only be worked where they occur. Given the characteristics of the Isle of
Wight this has placed the majority of our mineral sites within designated
landscape areas.
Whilst gravel and flint are
available elsewhere on the Island it must also be recognised that the nature of
the deposit at Cheverton generates a unique type of material (angular) which
makes the material particularly suited to certain specialised projects,
particularly those involving stabilisation work. On that basis, this site passes the test of importance that
justifies the location within a designated landscape area generating a material
that could not otherwise be sourced locally but would have to be imported with
all the requirements associated with such an activity.
6.3 Secondly, with regards to the topic
areas identified in the Environmental Statement, these are outlined below and
assessed against the relevant planning policies.
·
Agriculture and soils. The site comes under class 3 agricultural
land and accordingly would not result in the loss of good agricultural land and
therefore does not conflict with Policy C14 (Safeguard Best Agricultural Land). Members should also note that at the
cessation of the use (whichever restoration scheme is implemented) the site
will be reinstated to agriculture.
·
Archaeology. With regards to this specific site there are
not considered to be any archaeological features within the proposed extension
area. The Council's Archaeologist does
however intend to monitor the topsoil stripping exercise (where any finds would
be evident) and accordingly, the proposal would be in accordance with Policy B9
(Protection of Archaeological Heritage).
·
Ecology. Given the existing use of the site as
agricultural pasture, the land has no ecological importance and therefore there
is no breach of Policy C9 (Nature Conservation as a Material Consideration). Potentially
the lower level restoration proposal could raise the ecological value of the
site and this is favoured by both the Ecology Officer and the AONB Lead
Officer. It would also be encouraged by
the recently issued PPS9 on Biodiversity and Geological Conservation.
·
Dust and noise. Given the low key nature of the extraction
and its location any problems associated with dust generation are considered to
be negligible. The nearest residential properties
are at Cheverton Farm approximately 1.9 kilometres to the east and away at
Limerstone to the south. There are not
considered to be any ecological features in sufficient proximity to be harmed
by any dust.
With regards to
noise generation, this will result from the machinery associated with the
extraction process. Again, given the
distances involved to nearby residential properties and the proposed operating
hours which have been set out by the applicant I do not consider that any
disturbance will arise. I am conscious
of the closer proximity of a number of well used footpaths but on balance
consider that the noise generated by any machinery in the quarry base or any
vehicles driving to or away from the pit would not be significantly different
that hearing any agricultural machinery operating on surrounding land.
Given the circumstances outlined above it is not considered that the proposal would be contrary to Policies P1 (Pollution and Development) or P5 (Reducing the Impact of Noise).
· Hydrology. The site operates at a significant level above the water table. On the basis that general operational controls are in place relating to the storage of any fuels there should be no threat to the quality of the water aquifers from the extraction process. Equally, on the basis that the materials are screened but not washed there is no need to consider disposal of any waste water.
With regards to the restoration proposal, providing this is confined to inert material this should cause no threat to groundwater contamination. Accordingly, neither quarry proposal nor the infilling proposal conflicts with Policy U19 (Safeguarding of Aquifers and Water Resources).
· Traffic. All vehicle movements associated with this site share the same access as the chalk quarry off the main Newport to Shorwell Road and access the gravel site utilising a private roadway. This is the arrangement that has existed for a substantial number of years. Given this proposal I do not consider that the proposal conflicts with policy TR7 (Highway Considerations for New Development).
· Visual Impact. As part of the pre-application discussions the applicant was encouraged to undertake a Visual Impact Assessment of the existing and proposed operation, both from the Worsley Trail to the south and from the roadway running up to the Chillerton Mast from Cheverton Shute and from Newburn Down, which is the high ground lying to the north of the Chillerton TV mast.
From the south the
site operation currently benefits from a combination of a favourable
topography, the fact that the excavation has gone down below the line of site
and also by the presence of the substantial cattle building on its southern
edge. The combination of these factors together with the developing bund,
provides an effective screen to the existing site and will do so to the
extension.
From the east, the barn and bund are less effective at screening the site. However, given the distance involved and the colour of the deposit concerned, the visual impact of that section of the quarry which can be seen is not considered to be significant.
Taking all factors into consideration, excavations on site are not considered to be significantly detrimental to the general character of the landscape or the designated Area of Outstanding Natural Beauty. Accordingly, the proposal is not considered to be contrary to Policies C1 (Protection of Landscape Character) or Policy C2 (Areas of Outstanding Natural Beauty).
6.4 The third factor to consider is whether
or not any of the representations have raised issues that have not been
addressed above. Member will note that all the representations received only
the one from local landowner has raised some points of concern relating to
drainage and traffic issues. I do not believe that the gravel quarry lying as
it does below the surrounding ground levels could generate any drainage
concerns. With regards to the traffic issues, the Highway Engineer has
considered the proposal and raised no objection.
7. Conclusion
and Justification for Recommendation
7.1 This report relates to two
proposals. Firstly, to continue working
an area where planning permission has already been approved in the past for the
winning of gravel and flint hogging but has not been worked out during the life
of the consent, and secondly for an extension to the operational area,
extending the quarry in a northerly direction.
Based on the level of extraction the applicant calculates that the
extended area would give the operation a life of approximately 20 years.
7.2 The proposal would also involve the
restoration of the site back to agriculture.
Two scenarios are put forward, the first involving limited infilling
operations drawing on the waste material generated from the extraction process
and grading which would leave an exposed gravel face around the base of the
quarry, or a second proposal with the applicant obtaining a waste disposal
licence through which he would seek to reinstate the site back to its original
levels.
7.3 The proposal has been the subject of
detailed pre-application discussions which has resulted in the submission of an
Environmental Statement. This was
requested given the location within a designated landscape area. However, it has been recognised that with
the expense in generating this statement that the applicant will be looking for
a planning concept with a 20 year life rather than the previous consent which
had a limited 10 year life.
7.4 Clearly, one of the benefits of engaging
in the detailed pre-application discussions which identified the main
considerations to be included within any Environmental Statement is that this
process has anticipated all the concerns that were likely to be raised by any
of the consultees, and this is reflected in the representations outlined in this
report. A number of concerns have been
raised by an adjoining landowner, but they do not raise any fundamental issues
that would warrant withholding consent.
7.5 With regards to the restoration of the
site and the two options that have been presented by the applicants, members
should note that with the onset of recycling and given the costs of obtaining
the licence this site has not seen the importation of any material. As a
consequence, the void space effectively represents the whole of the site. When this situation arose at Knighton
Sandpit where a previous consent had also intended importation of inert
material to restore the site to its former levels, the plans associated with
the most recent consent were negotiated to acknowledge that the site would not
be reinstated to its full capacity.
7.6 Whilst there may be some justification
in the importation of material by vehicles which are collecting materials it is
not considered that it would be appropriate simply to create a disposal
site. Accordingly, whilst conditioning
the final restoration details it would not be inappropriate to express the
Council's support for the lesser scheme that would involve partial infilling of
the site leaving an exposed face around the pit.
7.7 This scheme has been tested against both
the Government's policy statements and guidance notes and against the Council's
own Unitary Development Plan policies.
The site is recognised in the UDP as one with planning permission for
continued extraction of the 1996 approved site is likely to be given with
reference to an appropriate extension.
On balance the proposals currently in front of the members reflects this
statement.
8. Recommendation
That
subject to appropriate conditions both application are approved.
Conditions/Reasons:
The development hereby approved shall cease on 30
September 2025 and no further extraction or importation of waste materials
shall take place after that day.
Restoration shall be completed by 31 December 2027 unless otherwise approved
by the Mineral Planning Authority. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
|
2 |
The permission hereby granted applies to the area
of land shown within the red line on plan number 470/2 and relates to the excavation
of gravel and flint hoggin and the restoration of the site and its
aftercare. The development shall be
commenced before the expiration of 3 years from the date of this permission
and shall thereafter have a life expiring on 30 September 2025, excluding the
duration of the requirements set out in any conditions below. A minimum of 7 days' notice in writing
shall be given to the Local Planning Authority prior to the development being
commenced. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
3 |
A copy of
the approved scheme of working and a copy of this permission shall be
displayed at the site offices at all times for operators and contractors
working at the site to refer to. Reason: To ensure that operators and contractors
working at the site are familiar with the requirements of the scheme and the
permission. |
4 |
Notwithstanding the provisions of the Town and Country Planning
(General Permitted Development) Order 1995 (or any Order revoking and
re-enacting that Order with or without modification): No fixed plant or machinery, buildings,
structures and erections, or private ways shall be erected, extended,
installed or replaced at the site, without the prior agreement in writing of
the Local Planning Authority; Reason: To protect the amenities of the area and
to comply with policies D1 (Standards of Design) and M2 (Defined Mineral
Working) of the IW Unitary Development Plan. |
5 |
Vehicle
access to the site shall be from the applicant's access track which serves
the existing chalk extraction operation and which joins the B3323 immediately
north of Cheverton Farm. No vehicle
access shall be obtained by the Worsley Trail. Reason: In the interests of protecting the amenities
of the locality and to comply with policies C1 (Protection of Landscape
Character), C2 (Areas of Outstanding Natural Beauty) and TR7 (Highway
Conditions for New Development) of the IW Unitary Development Plan. |
6 |
Any
imported waste material to be tipped within the site shall be confined to
inert, non-toxic, non-putrescible material. Reason: To protect the groundwater from pollution
and to comply with policy U19 (Safeguarding of Aquifers and Water Resources)
of the IW Unitary Development Plan. |
7 |
The developer shall afford access at all
reasonable times to any archaeologists nominated by the Local Planning
Authority and shall allow them to observe all groundwork and to record
[items/features] of archaeological significance and finds. Notification of the opening up and information as
to whom the archaeologist should contact on site shall be given in writing to
the address below (or to any alternative address notified to the developer by
the Local Planning Authority) not less than 14 days before the commencement
of any work: County Archaeologist County Archaeological Centre 61 Clatterford Road Carisbrooke Newport Isle of Wight PO30 1NZ Reason: In order to ensure access by specified archaeologists
during the permitted operations and to comply with policies B9 (Protection of
Archaeological Heritage) and B10 (Parks and Gardens and Landscapes of
Historic Interest) of the IW Unitary Development Plan. |
8 |
The site shall be restored and managed for
agricultural purposes in accordance with a scheme to be submitted to and
approved in writing by the Local Planning Authority before 2010. The scheme shall include details of: The nature of the intended afteruse of the site; The sequence of phasing of (backfilling and)
restoration showing clearly their relationship to the working scheme; The restoration proposal shall make an allowance
for an exposed 5 metre face on the western, eastern and northern sides of the
quarry. In addition, a 4 metre wide
zone shall be created at the foot of the eastern, western and northern faces
through the installation of a post and wire fence line, with the area between
the fence and the foot of the exposed face left to regenerate naturally. The respreading over the floor of the excavated
area of overburden, subsoil and topsoil previously stripped from the site, in
that order [specify details, depths and placement of respreading materials as
necessary]; The ripping of any compacted layers of final
cover to ensure adequate drainage and aeration; such ripping should normally
take place before placing of the topsoil; The machinery to be used in soil respreading
operations; Drainage of the restored land including the
formation of suitably graded contours to promote natural drainage and the
installation of artificial drainage; The reinstatement of the plant site and access
roads by clearing plant, buildings, machinery and concrete or brickwork, deep
cultivation in both directions to remove rocks and other obstructions, replacing
of subsoil and then topsoil previously stripped from the sites; Grass seeding of restored areas with a suitable
herbage mixture; A timetable for implementation and aftercare; and upon approval such scheme shall be
implemented as approved unless a variation has been agreed in writing by the
Minerals Planning Authority. Reason: To ensure that the site is restored in an
orderly manner to a condition capable of beneficial afteruse and in the
interests of the amenities of local residents and to comply with policies M8
(Restoration and Aftercare) and M2 (Defined Mineral Workings) of the IW
Unitary Development Plan. |
9 |
Within the first 2 years after the date of the
consent a landscaping scheme to cover the planting of the southern bund shall
be submitted to and approved in writing by the Local Planning Authority. The
scheme shall detail the numbers, species and positions on planting. Reason: To ensure the appearance of the
development is satisfactory and to comply with policy D3 (Landscaping) of the
IW Unitary Development Plan. |
10 |
All planting, seeding or turfing comprised in the
approved details of landscaping shall be carried out in the first planting
and seeding seasons after the submission of the scheme. Any trees or plants
which within a period of 5 years from the completion of the development die,
are removed or become seriously damaged or diseased shall be replaced in the
next planting season with others of similar size and species, unless the
Local Planning Authority gives written consent to any variation. Reason: To ensure the appearance of the
development is satisfactory and to comply with policy D3 (Landscaping) of the
IW Unitary Development Plan. |
11 |
No extraction shall take place below the levels
shown on drawing number 470/7. Reason: To protect the groundwater from pollution
and to comply with policy U19 (Safeguarding of Aquifers and Water Resources)
of the IW Unitary Development Plan. |
12 |
The storage of any materials or mobile plant
shall be confined to the base of the gravel pit. Reason: To protect the visual character and
appearance of the locality and to comply with policy C1 (Protection of
Landscape Character) and C2 (Areas of Outstanding Natural Beauty) of the IW
Unitary Development Plan. |
13 |
Except in emergencies to maintain safe quarry
working (which shall be notified to the Local Planning Authority at the
earliest opportunity, together with details of the emergency and the operations
carried out) or unless the Local Planning Authority has agreed otherwise in
writing: No operations, other than water pumping,
servicing, environmental monitoring, maintenance and testing of plant shall
be carried out at the site except between the following times: 0700 and 1800 hours Mondays to Fridays 0800 and 1300 hours Saturdays No servicing, maintenance and testing of plant
shall be carried out at the site between 0800 and 1700 hours on any date (and
at no time on Sundays, Bank or Public Holidays); No operations for the formation and subsequent
removal of material from (#) (eg. any environmental banks and soil storage
areas) shall be carried out at the site except between the following times: 0700 and 1800 hours Mondays to Fridays 0800 and 1300 hours Saturdays No operations other than environmental monitoring
and water pumping at the site shall take place on Sundays, Bank or Public
Holidays. Reason: To protect the amenities of local
residents and to comply with policy D1 (Standards of Design) of the IW
Unitary Development Plan. |
14 |
All
topsoil shall be stripped, handled, stored in accordance with a scheme which
shall have been approved in writing by the Mineral Planning Authority before
the commencement of and soil stripping takes place on site. Reason: To prevent loss or damage of soil and
ensure that it is re-used in the restoration of the site. |
6 |
Reference
Number: P/01111/05 - TCP/23793/D Parish/Name: Ventnor - Ward/Name: Ventnor East Registration
Date: 08/06/2005 -
Full Planning Permission Officer: Mr J Mackenzie Tel: (01983) 823567 Applicant: Westfield Lodges Holiday Centre 3
storey building to form 17 flats (revised position); retention of 3 flats Westfield
Holiday Park, Shore Road, Ventnor, PO38 |
The application is recommended for conditional
permission.
REASON FOR COMMITTEE CONSIDERATION This is a major submission which has proved to be
contentious. |
1. Details
of application
1.1 This is a full application for retention
of some works already undertaken and for the erection of a further block of 17
holiday flats in a revised position and of a different appearance from the
previous scheme.
1.2 Permission was granted for the erection
of an extension to the existing building and for the reconstruction of part of
the holiday centre a few months ago, and the work was commenced. This proposal seeks to retain the works
already implemented, but which has not been implemented strictly in accordance
with the existing permission, and for the erection of a free-standing building
instead of an extension, again, to comprise 17 flats for holiday purposes.
1.3 The plans show the building works which
have already been implemented having a lower pitched roof, but higher eaves,
the change being made due to the need to increase the thickness of the floor
above the swimming pool which was retained on ground floor. The first floor accommodation comprises 3
holiday flats.
1.4 Revised plans of the free-standing
building show the new structure to be only 0.7 of a metre from the existing
building and to comprise three storeys of accommodation, again for holiday
purposes, arranged in single and two bedroomed units of varying sizes.
1.5 The new building is shown to be 32
metres long and a maximum of 16 metres deep, constructed in brickwork with some
rendered panels of the elevation under gabled roofs clad in concrete tiles.
1.6 New building is shown to be located on
the east side of the existing structure with car parking, sufficient for one
vehicle per unit situated immediately adjoining to the north.
2. Location
and site characteristics
2.1 Westfield Holiday Centre is located off
Shore Road and occupies a site of approximately 1.1 hectares. It comprises several holiday chalets and
bungalows which sit in a significant depression in this coastal location
located off Shore Road.
2.2 The land rises to the south where it
meets the cliff edge and then falls steeply to the shore. To the west are holiday bungalows known as
Westfield Bungalows which are masonry holiday bungalows, not within the
ownership of the application site.
2.3 Further to the north are two terraces of
holiday units and immediately to the north of the building is Westfield Mansion,
a two storey, Grade II Listed building of majestic appearance, but one that
dominates the application building due to significantly higher land levels.
3. Relevant
history
3.1 In June 2004, the partial demolition of the
holiday centre (retaining the swimming pool), for an extension over the pool
building and for a further three storey extension to form 17 holiday flats, was
withdrawn.
3.2 In November 2004 a planning application
for a revised scheme of partial demolition of the holiday centre (retaining the
swimming pool) for an extension over the pool building and a three storey
extension to form 17 holiday flats was approved. This permission included conditions, amongst others, restricting
the occupation of the holiday flats to holiday accommodation; restricting the
height of the building to a height commensurate with the then existing
building; and requiring a further survey of ground conditions to be undertaken
prior to commencement of works on site.
3.4 At
one time it was understood that the holiday centre, the mansion and all of the
holiday bungalows were within one ownership.
4. Development
Plan policy
4.1 National
Policy Guidance
PPG20
(Coastal Planning) recognises tourism as a rapidly expanding activity but
steers developments towards existing urban areas.
PPG21 (Tourism)
supports developments which expand and improve the tourism industry,
accommodation etc.
4.2 UDP
Policy
Shown in the Isle of Wight Unitary
Development Plan to be outside the designated development envelope but as an
existing tourist accommodation centre to which policy T6 applies.
T6 states:
"Planning
applications for the expansion of existing permanent accommodation sites, as
defined on the proposals map, will be approved where the following criteria can
be met:
(a) they adjoin or
are directly related to the existing built facilities;
(b) they do not
detract from their surroundings;
(c) they enhance
the environment, or improve the visual appearance of the site;
(d) new or replacement
units are appropriate in design and appearance, and the resulting density of
the site does not adversely affect the rural character of the area."
4.3 Policy
TR7 relates to highway issues, access and parking.
4.4 The
site is not within an Area of Outstanding Natural Beauty but the cliff is a
Site of Importance to Nature Conservation.
5. Consultee
and third party comments
5.1 As with the previous application,
Engineers consider that as traffic speeds are very low and the fact that the
access has been subject to higher levels of usage in the past, conditions are
recommended if approval is granted.
5.2 Ventnor
Town Council see no reason why planning permission should not be granted.
5.3 External
Consultees
NATS
- no objection.
5.4 Neighbours
Letters from Westfield Mansion and
Westfield Residents' Association objecting to the development on grounds that
the development that has occurred already has not been built in accordance with
the approval, that it is too high, objecting to the building in phases,
objecting to the excavation into the southerly bank; development is more
visible with greater visual impact, access is inadequate in terms of width,
visibility and construction, and inadequate access is maintained to existing
cesspit for servicing.
19 letters of objection (some
duplicated) objecting to the development on grounds of visual impact;
development resulting in a higher building and one of greater mass, increased
traffic, overdevelopment, inadequate access and ground instability.
6. Evaluation
6.1 The
main issues relating to this application are:
Policy and
principle
Design, height and
mass
Traffic generation
Effect on
Westfield Mansion
Geotechnical
considerations.
6.2 In terms of policy and principle, Policy
T6, supported by PPG21 (Tourism) encouraged the improvement and enlargement of
existing tourist sites, especially for accommodation. This is a site which is outside the designated development
envelope but is an established and annotated tourist accommodation site. The principle of additional accommodation
has already been granted last year and therefore there are considered to be no
policy and principle objections to the scheme.
6.3 This scheme has been submitted as an
alternative to the previously approved scheme last year which authorised the
erection of an extension for 17 holiday flats and, in addition, the rebuilding
of part of the holiday complex over the existing swimming pool which, in
itself, was shown in the plans to accommodate a further three holiday
units. This alternative scheme has been
submitted due to difficulties found with the ground conditions on the footprint
of the then extension. A geotechnical
engineer has recommended to the developer that the original scheme would
straddle a plane of differing geological strata which would be likely to result
in differential settlement and possibly failure. He has also recommended that the additional accommodation be
free-standing and not attached to the original part of the complex for similar
reasons.
6.4 The design of the building is fairly
traditional, with pitched roofs and gables, and comprises 17 holiday flats of
differing accommodation but, essentially, either one or two bedroomed.
6.5 The proposed new building is of
comparatively large proportions and will inevitably have some visual impact on
the landscape. However, it is situated
in a trough where the contours form a valley running east to west. Consequently the building will not be
visible from the beach and is significantly lower than the adjoining properties
to the north.
6.6 The height of the existing building and
the proposed new building has proved to be a matter of controversy. At the time the application was approved
last year, the plans showed that the proposed ridge height would not exceed the
height of the ridge of the original building.
However, objections have been received which claim that the building is
higher, but it should be remembered that as the new building as constructed is
considerably narrower than the old part of the superstructure, the ridge of the
new part of the building is moved further south. When viewed from an elevated position, the movement of the ridge
away from the viewer gives the appearance that the ridge is higher. Accordingly there appears to be very little
difference, if any, in heights of the structure as constructed and the original
building.
6.7 The new building proposed in this
application is moved significantly in a southerly direction, further away from
the adjoining property, known as Westfield Mansion. Due to the resiting, forward of its originally approved position,
it will inevitably be more visible from Westfield Mansion despite the greater
distance and, to a certain extent, the natural growth will not be so effective
in screening. However, I consider the
marginal difference between the siting of this proposal and that previously
approved will not be significant visually and will not have a significantly
greater impact on the setting of the Listed Building.
6.8 In terms of traffic generation, as with
the previous application, the Highway Engineers accepted that the use of the
holiday centre, as it was, if resumed at the intensity previously would be
likely to generate higher levels of vehicular flow and accordingly recommended
conditions if consent was forthcoming.
In effect this development is an alternative to that previously approved
and therefore it is not anticipated that the volumes of traffic will be any
greater.
6.9 In terms of the effect on Westfield
Mansion, it should be remembered that Westfield Mansion is a Grade II Listed
Building and developments which affect its setting must be considered carefully
to ensure that the character of the Listed Building is not adversely affected
to such a degree that would warrant refusal.
Prior to the demolition of a substantial part of the holiday centre, the
view from the mansion to the former holiday centre was of a poorly
proportioned, probably 1960s building with a low pitched roof, a building
having a multitude of colours and in much closer proximity to the common
boundary between the properties. At one
time the Westifleld Mansion and the Westfield Holiday Centre were one property
but the mansion has been subsequently converted into residential flats and
disposed of in separate ownerships. The
replacement two storey structure is of considerably lesser mass since it is
significantly shallower and constructed in more traditional materials. The subsequent effect is less than before.
6.10 The new building clearly increases the
built mass on site but is further from Westfield Mansion and at a significantly
lower level. Outlook from the Mansion
towards the sea will be unchanged although it is accepted that the new building
would be visible. However, it is not
felt that an adverse effect on the setting of the Listed Building is sufficient
to warrant refusal.
6.11 In terms of the geology, a geotechnical
engineer has been engaged by the prospective developer as a result of the
condition attached to the former permission, carried out an investigation into
ground conditions which concluded that the former siting straddled a plane
between differing strata and consequently recommended the developer alter the
scheme to account for this feature.
Irrespective of the work done as described above, I consider it
appropriate again to impose the condition requiring survey work and the result
of such survey work to be submitted to the Local Planning Authority for
consideration regarding ground conditions.
7. Conclusion
and justification for recommendation
7.1 The application seeks an alternative
scheme to that which was approved last year resulting in 20 holiday flats as an
extension or enlargement to this established holiday centre, a development
which is supported by UDP policy. Whilst
close to Westfield Mansion, a Grade II Listed Building, the ground level is
significantly lower and the setting of the Listed Building is felt not to be
sufficiently adversely affected such as to warrant a refusal of permission. In traffic terms the potential and lawful
use of the holiday centre could have resumed and the traffic flow involved in a
fully functioning holiday centre unlikely to be in excess of that which is
currently proposed, and on that basis the Highway Engineers have not expressed
resistance to the proposal.
8. Recommendation
Conditional
permission
Conditions/Reasons:
The development hereby permitted shall be begun
before the expiration of 5 years from date of this permission. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
|
2 |
No development shall take place until [samples of
materials/details of the materials and finishes, including mortar colour] to
be used in the construction of the external surfaces of the development hereby
permitted have been submitted to and approved in writing by the Local
Planning Authority. Development shall
be carried out in accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with policy D1 (Standards of Design) of the IW Unitary
Development Plan. |
3 |
None of the accommodation hereby permitted shall
be used other than as holiday accommodation. Reason: To ensure that the development remains for
holiday purposes and to comply with policies T1 (Tourism) and T3 (Holiday
Accommodation) of the IW Unitary Development Plan. |
4 |
The height of the building hereby permitted shall
not exceed that described in the plans.
Reason: In the interests of the amenities and
character of the area and to comply with policy D1 (Standards of Design) of
the IW Unitary Development Plan. |
5 |
Within 1 month of the date of this permission
details shall be prepared by a competent person of the retaining wall or works
where it adjoins the boundary of the site with Westfield Mansion and such
details shall be submitted to the Local Planning Authority for its approval
in writing. Reason: To ensure as a result of the development
that the land is not destabilised in accordance with Policy G7 (Unstable
Land) of the IW Unitary Development Plan. |
6 |
Notwithstanding condition 5 above, details of
boundary works including the means of the closing off of the former means of
access from Westfield Mansion shall be submitted to and approved by the Local
Planning Authority and the approved details shall be implemented and
completed prior to the occupation of the building hereby permitted Reason: To ensure as a result of the development
that the land is not destablilised in accordance with policy G7 (Unstable
Land) of the IW Unitary Development Plan. |
7 |
The use hereby permitted shall not commence until
parking and turning provision, in accordance with the parking layout as shown
on the approved plan attached to and forming part of this decision notice,
has been provided, surfaced and drained in accordance with details to be
submitted to and approved by the Local Planning Authority in writing. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
8 |
The holiday accommodation hereby permitted shall
not be occupied until a new sewage treatment plant has been installed in accordance
with details to be submitted to and agreed in writing with the Local Planning
Authority. Reason: To minimise the risk of pollution and to
comply with policy P1 (Pollution and Development) of the IW Unitary
Development Plan. |
9 |
Within one month of the date of this permission,
a survey of ground conditions shall be undertaken and the results provided to
the Local Planning Authority. The
survey shall be taken at such points and to such depth as the Local Planning
Authority may stipulate. A scheme of
remedial, preventive and precautionary measures to deal with the stability of
the site and adjoining land shall be submitted to and approved by the Local
Planning Authority in writing before the development hereby permitted
commences and the scheme as approved shall be fully implemented and completed
before any [residential] unit hereby permitted is first occupied. Reason: To ensure that any adverse ground
conditions encountered may be satisfactorily overcome and the site developed
for [residential] purposes and to comply with policy G7 (Development on
Unstable Land) of the IW Unitary Development Plan. |
7. |
Reference
Number: P/00160/04
- TCP/06159/T Parish/Name: Freshwater - Ward/Name: Freshwater Afton Registration
Date: 23/01/2004 -
Outline Planning Permission Officer: Mr A White Tel: (01983) 823550 Applicant:
Mr M McNulty Demolition
of building; outline for six dwellings; formation of pedestrian access 106
School Green Road, Freshwater, Isle Of Wight, PO409AY |
The application is recommended for conditional
permission.
REASON FOR COMMITTEE CONSIDERATION This Report was first considered by the
Development Control Committee in June 2004 at the request of the former local
Member. Although he did not object to
the principle of redeveloping this site, he was concerned that the proposal
made no provision for on site parking, meaning that residents would park outside
the proposed dwellings, resulting in standing vehicles which may add unduly
to the hazards of other road users.
Members attached some weight to the concerns expressed by the local
Member and therefore decided to defer consideration to enable negotiations to
take place on this particular issue.
Numerous meetings and discussions have taken place during the
intervening period, and the purpose of this report is to update Members on
the current situation and to seek a resolution. |
1. Details
of application
1.1 Outline permission is sought for
demolition of buildings and for residential development of 6 dwellings with
siting and means of access to be considered.
Application is accompanied by illustrative plans which indicate two
pairs of semi-detached houses and a semi-detached pair comprising a house and a
bungalow. The dwellings are shown to be sited in a stepped fashion having a
minimum distance off the back edge of footpath of 1 metre. The split pair of
house/bungalow is situated at the western end of the site and is partly angled
in order to take account of the prominent location of that part of the site.
The house which forms part of this pair is shown to have a wider frontage onto
School Green Road in order to create a reasonable degree of separation between
proposed dwelling and existing chalet bungalow to the rear.
1.2 The proposed scheme does not make
provision for on site parking. Agent
has confirmed that each of the proposed dwellings would provide a maximum of
two bedrooms.
2. Location
and site characteristics
2.1 Application relates to site on southern
side of School Green Road presently occupied by single storey building
previously used as a bakery. Area is
characterised by a mix of uses although premises immediately adjacent to the site
are residential. School Green Road is one of the main thoroughfares into
Freshwater and is lined on either side by a mixture of established or modern
developments, either two or three storeys in height. There is an existing
detached chalet style dwelling (Green End) located to the rear of the site with
that property directly abutting recreation ground known as Stroud playing
fields.
3. Relevant
history
3.1 P/01078/02–TCP/06159S – Full application
for three pairs of semi-detached houses refused in August 2002 on grounds of a)
cramped arrangement of dwellings, b) intrusive development out of scale and
character having adverse effect on immediate adjoining dwellings and c)
proposal would give poor arrangement of dwellings in relation to the property
to the rear adversely affecting the outlook from that property. This decision was not subject of an appeal.
4. Development
Plan policy
4.1 PPG3 (Housing) can be summarised
as follows:
·
Provide wider housing opportunity and choice by
including better mix and size, type and location of housing.
·
Give priority to reusing previously developed land
within urban areas to take pressures off development of greenfield site.
·
Create more sustainable patterns of development
ensuring accessibility by public transport to jobs, education and health visit
facilities.
·
Make more efficient use of land by adopting
appropriate densities, with 30-50 units per hectare quoted as being appropriate
levels of density.
·
Document advises that new housing development
should not be viewed in isolation but should have regard to immediate buildings
and wider locality.
·
More than 1.5 parking spaces per dwelling are
unlikely to reflect the Government's emphasis on sustainable residential
development.
4.2 PPG13 (Transport) stresses the need to
reduce car dependence by facilitating more walking and cycling, by improving
linkages with public transport, local services and local amenities. Local Planning Authorities should examine
critically the standards they apply to new development, particularly with
regard to roads, layout and car parking, to avoid the profligate use of land.
4.3 Site is within the development envelope
boundary for Freshwater as shown on the Isle of Wight Unitary Development Plan
(UDP). The following policies of the
said Plan are considered to be relevant:
S1
- New development will be
concentrated within existing urban areas.
S2
- Developments will be encouraged on
land which has been previously developed (brownfield sites).
S6
- All developments will be expected
to be of a high standard of design.
S7
- There is a need to provide for the
development of at least 8,000 housing units over the planned period.
G1
- Development envelopes for towns and
villages.
G4
- General locational criteria for
development.
D1
- Standards of design.
D2
- Standards for developments within
the site.
H4
- Unallocated residential
development.
H5
- Infill development.
TR7
- Highway considerations for new
development.
TR16
- Parking policies and guidelines.
4.4 Site is located within Parking Zone 3 of
the UDP which restricts parking to 0-75% of the maximum non-operational parking
provision. In the case of residential
development, maximum provision is one space per bedroom and it is confirmed
that the proposal before Members would comprise of 5 two bedroom dwellings and
a single one bedroom bungalow.
4.5 Reference is also made to the Housing
Needs Survey, the conclusions of which acknowledge the need for single person
accommodation, although there continues to be an ongoing demand for two or
three bedroom units to meet statutory homeless requirements.
5. Consultees
and third party comments
5.1 Internal
consultees
5.1.1 Highway Engineer confirms that visibility
from the site would be some 40 metres to the east and 50 metres to the
west. Within the 30 mph speed limit, 90
metres is the minimum visibility required, unless it can be proven that actual
vehicle speeds are slower than 30 mph.
For the above levels of visibility to be acceptable, the 85%ile vehicle
speeds would have to be no higher than 23 mph.
The most recent speed survey from outside the nearby school shows
westbound 85%ile speeds of 32 mph and eastbound of 31 mph. It is quite possible that vehicle speeds may
be slightly higher there than outside the application site as the road is
slightly straighter, although the Highway Engineer does not believe that the
difference is that much. On this basis,
the Highway Engineer would recommend refusal to a vehicular access on grounds
of inadequate visibility. Although the
previous use of the site as a bakery would have generated some vehicular
movements, 6 dwellings would generate significantly more. It is therefore unlikely that the applicant
could justify sub-standard visibility for the proposed development on the
previous levels of usage.
5.1.2 Whilst the Highway Engineer would generally
favour one space per dwelling in a Zone 3 location such as this, he does
recognise that a satisfactory access cannot be achieved to serve this number of
units. Therefore, considering that
proposal is for six modest homes offering a total of eleven bedrooms, the
proximity to a nearby public car park and reasonable access to public
transport, he confirms that a no parking scheme is, on balance, acceptable in
this instance.
5.2 Parish
Council comments
5.2.1 Freshwater Parish Council object on grounds
of gross overdevelopment of the site, increase of traffic on an already
dangerous and busy road, entrance/exit would be on the corner of a dangerous
road and development would be within 100 yards of a school entrance creating an
additional hazard.
5.3 Neighbours
and local residents
5.3.1 Application
is subject of 3 letters of objection from residents of School Green Road the points
raised summarised as follows:
·
Proposal represents excessive development which
will generate a level of car ownership increasing on street parking in the area
adding to hazards for highway users.
·
A reduced density with on site parking would appear
to be a better solution.
·
Initial proposals did not indicate the changing
levels in respect of the application site in relation to the property to the
rear. (Revised Plans now indicate section).
·
One objector points out that the site has been
known to be subject to flooding.
·
Any houses on this property would result in
overlooking of the property to the rear from first floor accommodation.
·
One objector makes reference to inadequacy of
drainage system in the area to accept additional discharge from development to
this site.
·
Reference made to a specific plant species (White
Butterbur) being a rare marsh plant unique to this area. (Consultation been
carried out with Council’s Senior Countryside Officer who confirms the species
are not protected).
6. Evaluation
6.1 Determining
factors in considering this application are as follows:
·
Principle
·
Density
·
Layout
·
Parking
6.2 This is a brownfield site within the
defined development envelope boundary and therefore, in terms of principle, is
considered to be a suitable candidate for residential development. Accordingly, proposal accords with policies
S1, S2, G1 and H4 of the UDP.
6.3 In terms of density and layout, proposal
constitutes intensive use of site but nevertheless would be reflective of
prevailing pattern of development which in some instances is tight knit. Each of the proposed dwellings would have
its own amenity space and the proposed layout would not compromise spatial
characteristics of street scene, which generally comprises terraces and
semi-detached buildings. Accordingly,
officers are satisfied that site is of a sufficient size to accommodate six
dwellings without appearing cramped. It
is also worthy of note that design and layout was not regarded as an issue of
concern when this application was originally considered by Committee in June
2004.
6.4 In terms of parking, the applicant has
investigated ways of making on site provision since Members raised this as a
concern. However, as said above, the provision
of an access onto this section of School Green Road would fall well short of
visibility requirements. Accordingly,
the Highway Engineer would have no alternative but to recommend refusal on
grounds of inadequate access if parking were to be provided for this
development. Members are therefore
presented with something of a dilemma, whereby the only likelihood of this
prominent and unattractive brownfield site being developed with housing is if a
zero parking scheme is accepted.
6.5 With regard to the issue of zero
parking, it is acknowledged that the failure to provide parking is causing
concern to local residents. However,
the location of this site adjacent the main thoroughfare into and out of
Freshwater, its position within Zone 3 of the parking policy (0 – 75% of
guidelines) and the fact that lack of parking was not cited as a reason in
respect of the 2002 refusal suggests that it would be unreasonable to refuse
the application on the basis that it fails to provide any on site parking. Any such
refusal would be likely to render this site as undevelopable as parking is
simply not an option.
6.6 In addition to the above, Members are
also requested to consider the following points in favour of a zero parking
scheme. Firstly, the site is within a
short and level walking distance of a public car park, the village centre and a
local supermarket. Secondly, the site
fronts onto a main road which is used by the local bus service. Thirdly, following negotiations, the
applicant has confirmed that the proposed dwellings would offer modest one and
two bedroom accommodation, although a condition in this respect may be
difficult to enforce given the fact that internal subdivision is beyond
Planning control. Revised plans have
therefore been submitted showing a reduced footprint which in turn restricts
floor space to a point where it can only practically provide two bedrooms. One of the reasons that officers are
suggesting that any properties on this site should not provide any more than
two bedroom accommodation is precisely because zero parking schemes are likely
to function more readily with the smaller type of unit as opposed to the family
sized unit. Obviously there can be no
guarantees, but any purchaser or occupier of these properties would do so with
the knowledge that there is no on site parking provision. It is recommended that siting be deleted
from the application and become an issue to be considered at reserved matters
stage.
6.7 With regard to any on street parking
availability, the side of the road onto which this site fronts is subject to
parking restrictions by virtue of a single yellow line which effectively
restricts any parking on this side to over night only but does allow short term
loading and unloading from the road during the day which obviously is of some
importance when the site was used as a bakery. Given the pressures that
residential use is likely to place within this limited parking zone, it may be
considered appropriate to seek a traffic order to ban parking entirely.
6.8 This would involve the submission of a
formal request through the Highways Department which would go through a public
consultation procedure with the order being advertised in the local press.
Comments would not only be invited from the public but also from the Parish
Council and local Councillor. Comments of the Traffic Section of the Highways
Department along with the police would also be taken into account. The whole
process could take up to 3 months to conclude. The outcome of such an order
would not necessarily be certain to ban even limited parking on this side of
the road as this could be deemed to be simply transferring that parking to
roads in the vicinity where no parking controls are exercised. It is assumed
that this would be a number of material considerations that would be taken into
account in assessing the merits of any such traffic order to ban parking in its
entirety on this side of the road.
Because the need for such controls is driven by this application, it
would be only correct for the applicant to pay for any costs involved in this
exercise. This can be achieved through
a legal agreement.
6.9 Bearing the above points in mind, lack
of parking should not necessarily be seen as a negative in this instance, but
should be seen as an ingredient towards achieving a sustainable housing scheme
within a built up location where essential and desirable services/facilities
are easily accessible to the future occupants of this development.
7. Conclusion
and justification for recommendation
7.1 Having given due regard and appropriate
weight to all material considerations referred to in this report, it is
considered that this outline proposal does effectively address the reasons for
refusal in respect of the 2002 application.
Whilst acknowledging the concerns relating to no on-site parking, it
must be considered that parking is not possible in this instance owing to the
fact that an acceptable access cannot be provided onto this section of School
Green Road. Therefore, considering the
objective of reducing the reliance on the motor car and the relatively short
distance between the application site and local facilities such as the car
park, shops, leisure centre, etc., a no parking scheme is considered to be
acceptable in this location and fully in accordance with local and
national policies.
8. Recommendation
To
grant conditional permission.
Conditions/Reasons:
The development hereby permitted shall be begun
either before the expiration of 5 years from the date of this permission, or before
the expiration of 2 years from the date of approval of the last of the
reserved matters to be approved, whichever is the later. Reason: To comply with
Section 92 of the Town and Country Planning Act 1990. |
|
2 |
Application for approval of the reserved matters
shall be made to the Local Planning Authority before the expiration of 3
years from the date of this permission. Reason: To comply with
Section 92 of the Town and Country Planning Act 1990. |
3 |
Approval of the details of the design and external
appearance and the landscaping of the site shall be obtained from the Local
Planning Authority in writing before any development is commenced. Reason: In order to secure a satisfactory
development and be in accordance with policies S6 (Standards of Design), D1
(Standards of Design), D2 (Standards of Development within the Site) and D3
(Landscaping) of the IW Unitary Development Plan. |
4 |
The development hereby permitted shall not be
initiated by the undertaking of a material operation as defined in Section
56(4)(a)-(d) of the Town & Country Planning Act 1990 in relation to the
development until a planning obligation pursuant to the Section 106 of the
said Act relating to the land has been made and lodged with the Planning
Authority that the Local Planning Authority has notified the person
submitting the same that it is to the Local Planning Authority's
approval. The said obligation will
require the applicant/developer to apply for and obtain a Traffic Regulation
Order to ban parking immediately outside of the application site and to pay
the Council's administration costs in the respect. Reason: In the interests of highway safety and to
comply with Policy TR7 (Highway Considerations for New Development) of the IW
Unitary Development Plan. |
5 |
The existing access to the site shall be stopped
up and abandoned and the footway crossings/kerb shall be reinstated on
completion of the new access. Reason: In the
interests of highway safety and to comply with Policy TR7 (Highway
Considerations) of the Isle of Wight Unitary Development Plan. |
6 |
No development shall take place until a detailed
scheme including calculations and capacity studies have been submitted to and
agreed with the Local Planning Authority indicating the means of foul and surface
water disposal. Any such agreed foul and surface water disposal system shall
indicate connections at points on the existing system where adequate capacity
exists or shall provide for attenuation measures to ensure any additional
flows do not case flooding or overload the existing system. No dwelling shall
be occupied until such agreed systems have been completed. Reason: To ensure an
adequate system of foul and storm water drainage is provided for the
development in compliance with Policy U11 (Infrastructure and Services
Provision) of the Isle of Wight Unitary Development Plan. |
7 |
No development shall take place until there has
been submitted to and approved in writing by the Local Planning Authority a
plan indicating a 2 metre high screen close boarded fence along the south
eastern boundary. Such fencing shall be completed before occupation of any of
the dwellings on the site. Reason: In the
interests of the amenities of the adjoining property in compliance with
Policy D1 (Standards of Design) of the Isle of Wight Unitary Development
Plan. |
8 |
The dwellings hereby approved shall not be
occupied until a wall has been erected along the highway boundary in
accordance with a scheme to be agreed in writing by the Local Planning
Authority. The wall shall be retained
thereafter. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations for New Development) of the IW
Unitary Development Plan. |
Second recommendation
That letter be sent to applicant advising that the
illustrative plans were afforded little weight and in no way commit the Council
to that form of development in a future reserved matter application.
8 |
Reference
Number: P/00750/05 – TCP/26996 & P/02074/04 – CAC/10858/L Parish/Name: East Cowes - Ward/Name: East Cowes North Registration
Date: 18/04/2005 - Full Planning Permission Officer: Roger Prescott, Halcrow (Consultants) South of England Development Agency
(SEEDA) Demolition
of slipway and suspended deck structure and its replacement with a solid
waterfront apron extension, including a hoist dock, concrete crane pad and
docking pontoons (revised plans) Area
seaward side of Venture Quays, Castle Street, East Cowes, PO32 |
The application is recommended for full planning consent, subject to conditions.
REASON
FOR COMMITTEE CONSIDERATION Although
this is a minor application, it has given rise to a number of objections from
local individuals and groups, who have alerted the attention of the local
Member. In addition, the application
raises some complex technical issues that may provide precedent and input
into the forthcoming outline planning application for the comprehensive
redevelopment area for East Cowes. |
1. Details of application
This is a full application, submitted by
SEEDA. It seeks to extend the existing apron
in front of the complex of industrial buildings on the site. In addition, it seeks to install a hoist,
and to establish pontoons.
In detail, the proposal comprises the
demolition of the existing deck slipway and apron. It seeks to replace these with a new apron (using the demolished
material) and to extend its size by about 4,500 square metres by reclamation of
land from the inter-tidal and sub-tidal areas to create a larger apron.
The new structure will be used to store and
handle wind turbine blades of up to 70m in length, which would be transferred
by the hoist onto a special shallow draft transporter barge, the
"Bladerunner 2", that would take the blades to Southampton and thence
to windfarms in the UK and overseas.
The site is proposed to be occupied by the Vestas turbine manufacturer,
which has a lease with SEEDA for use of the site for a further 5 years. It is understood that the shallow draft of
the special craft avoids the need for dredging of the site or of any access
channel within the Medina Estuary.
The pontoon system allows for the safe and
stable docking of the Bladerunner barges, but will also provide three spurs,
capable of providing docking/berthing for boats using the Venture Quays
waterfront, including the Offshore Challenges, and will provide additional
secure berthing during special events.
The pontoon system is an integral element of the emerging masterplan for
the redevelopment of SEEDA's land within East Cowes.
2. Location and site characteristics
2.1 The site lies immediately north of the Red Funnel vehicular
ferry terminal. The landward part of
the site is one which was, itself, reclaimed in the early twentieth century,
and which has been used for maritime industrial purposes for many years. The main building to the east of the site,
the Columbine Building, was formerly used by GKN for hovercraft manufacture,
and is easily recognisable by its Union Flag motif, easily visible to visitors
to the Island and from West Cowes. The
building will remain under this proposal.
2.2 The proposed pontoon system extends
north-west into the estuary by 80 metres and then turns in a northerly
direction for 30 metres.
2.3 Under the current Masterplan, the activities of Vestas would no
longer take place, and the site would be occupied by a mixture of marine
industry and the proposed Maritime Heritage Experience museum. The masterplan proposals would allow for
enhanced public access along this stretch of the estuary, in contrast to the
continued lack of access, necessitated on health and safety grounds, under the
present application. The Masterplan
proposals would require further reclamation of land.
2.4 The application site includes the steps which allow access
down to the foreshore from the Esplanade.
The steps would not be demolished through this application, but public
access across this private land would not be possible because of the proximity
of the industrial operations by Vestas.
Railings are proposed to be erected along this boundary, which would be
demarked by a revetment.
3. Relevant History
None which is
directly relevant to the current proposal.
4. Development Plan policy
National policy
guidance, RPG or RSS
PPS 9 Nature Conservation Biodiversity and geological
conservation
This Government
policy is brand new, having been issued in August 2005, replacing the former
PPG9 on Nature Conservation. It seeks to ensure that planning decisions are based
on up-to-date information about the environmental characteristics of their
areas, and an assessment of the potential to sustain and enhance biodiversity
and geological resources.
PPG16 stresses the importance of archaeological
remains, as they are ‘irreplaceable,’ ‘finite’ and ‘non-renewable.’ It states that, “…the key to informed and
reasonable planning decisions…is for consideration to be given early, before
formal planning applications are made, to the question whether archaeological
remains exist on a site where development is planned and the implications for
the development proposal” (paragraph 12).
It calls for ‘positive planning and management’ and notes that, “…appropriate
planning policies in development plans and their implementation through
development control will be especially important” (paragraph 14).
This government
guidance describes the importance of this finite and dynamic resource. It considers that the key policy issues for
coastal planning are:
- conservation of
the natural environment;
- development,
particularly that which requires a coastal location;
- risks, including
flooding, erosion and land instability; and
- improving the
environment, particularly of urbanised or despoiled coastlines.
PPG25 Development and Flood Risk
Relevant sections
of this guidance concern the reducing of risks caused by flooding. Reducing the vulnerability of the country to
the dangers and damage caused by unmanaged floods contributes to the
achievement of a better quality of life and the objectives of sustainable
development. Local planning authorities
should, therefore, address the problems which flooding can cause by:
·
recognising that the susceptibility of land to
flooding is a material planning consideration;
·
giving appropriate weight to information on
flood-risk and how it might be affected by climate change in preparing
development plans and considering individual proposals for development;
·
consulting the Environment Agency, which has the
lead role in providing advice on flood issues at a strategic level and in
relation to planning applications, and other relevant organisations;
·
applying the precautionary principle to
decision-making so that risk is avoided where possible and managed elsewhere;
·
improving the information available to the public
about the risks of locating human activities in areas susceptible to flooding;
·
taking into account the responsibility of owners
for safeguarding their own property as far as is reasonably practicable;
·
recognising that flood plains5
and washlands6
have a natural role as a form of flood defence as well as providing important
wildlife habitats and adding to landscape value; and
·
recognising that engineered flood reduction
measures may not always be the appropriate solution, since they can have
economic and environmental costs and impacts on the natural and built
environment, need maintenance and replacement and cannot eliminate all risk of
flooding.
Sections of the RPG (which remains the appropriate regional guidance
until the South East Plan, which is emerging at present, is approved in Spring
2006), which are relevant to this application include:
i) Wider Countryside
including Coastal and River Environment Policy E4
ii) The identification of
the Isle of Wight as a Priority Area for Economic Regeneration (PAER)
UDP policy – Site
falls within the development envelope for the area and is within/adjoins the
Solent Maritime SAC. As such, the
following policies are relevant:
S10 - Designated and Defined Areas
G4 - General
Locational Criteria for Development, especially the following criteria: a; b; d; e; h; and Ij
G6- Development
in Areas Liable to Flooding
G11 - Coastal
Development
B9 - Protection
of Archaeological Heritage
E7 - Employment
Sites With Deep Water Frontages
C8 - Nature
Conservation as a Material Consideration
C9 – Sites
of International Importance for Nature Conservation
SPG – Cowes Waterfront – A Vision for the Medina Valley,
sets out a regeneration framework for East Cowes, together with the whole of
the Medina Valley.
5. Consultee
and third party comments
Internal
consultees
·
Highways
Engineer does not consider there to be any highways implications.
·
Conservation
and Design (see comments on Character
and Appearance below)
·
The
Council’s Planning Archaeologist recommends that the developer be required to
mitigate the effects of the proposed alterations by ensuring that specialist
archaeological contractors undertake an agreed programme of structural
recording of the sea wall as it becomes exposed during development.
External
consultees
·
Environment
Agency
Flood risk - the Agency has no objection on flood risk grounds.
The
Agency wish to draw attention to the fact that the proposal is not in
accordance with the current Shoreline Management Plan, "hold the
line" policy produced by the IWC for this area. The Agency advise that the Venture Quays reclamation should be
considered in combination with SEEDA's wider proposals which potentially
includes major shoreline land reclamation to provide new marshalling yards for
a relocated ferry terminal. The Agency
strongly recommend the Council is satisfied that the proposals set out in this
application do not jeopardise the provision of sea defences which are needed to
facilitate their aspirations for the regeneration of East Cowes.
The
Agency maintains an objection on grounds of the loss of inter-tidal and
sub-tidal habitat which, it argues, runs contrary to the Biodiversity Action Plan.
·
English
Nature (EN), in
its letter of 6 June 2005, expressed concern because part of the application
site lies within the Solent Maritime SAC.
While EN did no wish to object to the proposal due to the loss of inter-tidal
habitat, they reminded the Council that such habitat is finite, and therefore
recommended that the Council should consider possible mitigation and
enhancement to mitigate the loss. EN
is, however, more concerned as to the effects of the proposal in combination
with the other development projects proposed in the Medina system, not simply
those proposed by SEEDA. EN also
expressed some concern as to the potential effect of piling operations on fish
populations.
·
Cowes
Harbour Commissioners - initial concern over potential impact on the future construction of an
eastern fairway approach channel to the harbour, but this matter has since been
resolved (see Section 6 below).
5.3 Town or
Parish Council comments
·
The
East Cowes Town Council have objected on the grounds of potential hazards to
shipping, and that the site is identified as part of the wider East Cowes
Development Scheme.
Neighbours and
third party comments
·
Application
has attracted a total of 11 letters of objection, 8 from local residents, and
letters from Isle of Wight Society, Cowes Corinthian Yacht Club and East Cowes
Sailing Club. Issues raised can be
summarised as follows:
·
Consideration
of application should not be made in isolation of masterplan. Includes need to take account of cumulative
effect on ecology of harbour.
·
Force
the relocation of Red Funnel operations.
·
Proposal
would preclude relocation of Red Funnel slightly to the north of the present
site;
·
Overdevelopment/domination. Not of "a height, mass and density
which is compatible with surrounding buildings and uses."
·
Safety
- prevention of access onto site. Inadequate detail of boundary treatment.
·
Visual
impact on view from Columbine Road.
Prefer to use stone and brick rather than rocks. Concrete visually obtrusive from road. Waterfront would be
"industrialised". Loss of
green lawn area by infill and storage of "commercial products".
·
Development
would cause the loss of stone and brick retaining wall - as used in listed
coastguard complex.
·
Fails
to enhance the seafront, as required of Cowes Waterfront SPG 2003.
·
Loss
of public access (public steps to be lost).
·
Insufficient
benefits to be derived from development because of short term lets.
·
Extension
encroaches into an "area of safety for yachting". Noted that previous proposals for moorings
rejected on safety. Concern over
potential obstruction of narrow "highway" for entering or leaving
Cowes Harbour. If cannot use, then only
alternative for sailing craft is main fairway - not feasible because of tidal
flow at some states of the tide.
·
Lack
of parking for Red-Jet passengers.
·
No
reference made to raising to comply with flood data.
·
Concern
over obtrusive nature of pontoon.
·
Queries
impact on hydrographic status of the harbour.
·
Queries
archaeological surveys carried out in and around site.
·
Concern
that this development would only have short term benefits that could be lost
upon ultimate redevelopment of the Columbine building in the future.
The issues raised by neighbours and third
parties have been explored through discussion with the applicant and its
agents, with statutory consultees and with Council staff.
6. Evaluation
6.1 The main issues relating to this
application are:-
·
The
justification for the development and its relationship with aspirations of the
masterplan;
·
The
effect of the development upon navigation within the harbour, on water
recreation activities, and upon the operation of the Red Funnel ferries;
·
The
effect of the development upon the character and appearance of the area, taking
into account the proposed designation of an East Cowes Conservation Area;
·
Access
to and along the foreshore;
·
The
impact upon the nature conservation value of the estuary;
·
Archaeological
impacts;
·
Flood
defence and sea level rise and sediment movements; and
·
Noise
levels during construction
6.2 Vestas requires the facility with some urgency, because it is now facing increased demand for turbine blades, especially larger (70M) blades associated with offshore windfarms. Vestas manufactures the blades at its St Cross factory, but it is unable to store either the large blades or the required volume of blades there. Further expansion of that facility would impact upon the proposed Special Protection Area of the Upper Medina and a planning application there would be contrary to policy. In any event, access to that site by water is limited to a small part of each tidal cycle, and limits efficiency of working.
6.3 Vestas currently employs some 500 people, either directly or indirectly, on the Island. The facility has a reputation for high quality products and the company has a strong desire to retain its links with the Island. The Venture Quays site provides the best readily available access to deep enough water for transportation. While some of the shorter blades can be stored within the Columbine building, it cannot accommodate the longer blades, which thus would need to be stored in the open. Further expansion of the apron is also necessary to store the blades. The desire of Vestas to provide the facilities is both sincere and justified, and a delay in constructing the facilities as proposed would jeopardise their operations. Therefore, while it would normally be the practice to draw up and adopt a masterplan first, and then seek planning permission for component parts, this application is a justifiable exception to that practice.
6.4 Vestas have stated that they would prefer to remain at the
Venture Quays site. However, their
lease with SEEDA is only for 5 years, and the Masterplan proposals do not allow
for the retention either of the Columbine Building or of the activities that
Vestas undertake. Although no full
search for alternative facilities for Vestas has been undertaken, it is not
likely that many, if any, sites would be readily available at an affordable
price for an industrial use that requires access to the water. Clearly, this application is in accordance
with the UDP Policy E7, which states that “planning
applications to develop existing employment/industrial sites which have deep
water frontages will only be approved where this type of location is essential
to the proposed marine related employment use.”
6.5 Members thus have to consider the effects of the proposals in
the light of the relatively short-term nature of the proposals. They should also consider if the Masterplan
proposals would be jeopardised by the present application. The applicants confirm that the apron
proposed under this application is not a temporary structure and will
ultimately form part of the proposed events space and heritage centre. They also indicate that "in the unlikely event that the masterplan does not come forward
as envisaged, the proposed apron extension will continue to function as a commercial
waterfront." There is
therefore a degree of uncertainty over the long-term future, but the
application should principally be judged on the assessment of its own effects.
The effect on navigation
6.6 As indicated in Section 5 above, the Cowes Harbour
Commissioners were initially concerned that the original pontoon proposal, at
right angles to the shore, would interfere with their aspiration for an eastern
channel to provide an additional or alternative access to the harbour. The applicants thus modified the pontoon
design to turn the seaward end of the main pontoon through about 45
degrees. In that way, the pontoon does
not extend as far, and allows the concept of an eastern channel to remain
viable. It now has minimal effect on
mooring trots and makes access to the Red Funnel terminal easier than under the
original proposals. Accordingly, the
commissioners do not raise any objections to the revised proposals.
6.7 The Harbour Master, was also consulted about the loss of
navigational water, although this is not a material planning
consideration. He has advised that the
ability to sail safety in the harbour would not be significantly affected by
the proposals.
6.8 Red Funnel were consulted but no
response has yet been received.
Character
and appearance
6.9 The comments raised by the
public, set out above, illustrate the concern over the size of the
proposals. However, given the
short-term nature of the works, and the fact that they are largely screened
from views from the land, many of the comments about the impact on the
character of the area are not justified.
Nevertheless, there are some detailed comments that have been examined
in full by the Council’s Conservation and Design staff. These led to a constructive meeting with the
applicant’s landscape and urban design advisors, following which modifications
have been sought. Moreover, the views from
both sides of the Medina are likely to be more significant than those from
land.
There
was concern that the application did not provide any information as
to how the structures will appear in context, including detail on materials,
finishes, guarding, lights, and signs.
Therefore, it is recommended that condition should be applied to ensure
these details are approved before construction begins.
There was initially no information
or illustration of how the proposed extension of the apron will address the
existing sea wall, landing and Esplanade at the northern end of the red lined
area, and how it will be viewed when approaching the seafront from Old
Road. The grass area around the public
toilets on the Esplanade is much used locally, but the applicants were able to
confirm that this area would not be included within the red line showing the
extent of the application. Indeed,
revised drawings have been submitted to confirm the boundary and also a sketch
has been to suggest that the northern end of the site would be marked by new
railings. A condition is also
recommended to ensure that the information is provided to show the accurate
location and detail of those railings.
A design with sharp tops would not be acceptable, given the danger to
people, especially children, using the area.
There has been public and officer
concern as to the future of the wall that runs parallel to the northern side of
the Columbine Building. The stonework
there is both substantial and detailed, and may indicate the location of a
previous slipway, judging from an angle line of stonework within the wall. The stones within it may themselves be the
relicts of previous structures nearby.
It has now been confirmed by the applicant that this wall, which is of significant local interest will not be lost as a result of this
application. However, it should be
noted that it would almost certainly be lost through the implementation of the
masterplan, as now suggested.
The northern eastern part of the
application site is concurrent with the proposed East Cowes Conservation Area,
which is not considered to be jeopardised by the proposals.
It is important to recognise that
the proposed apron would be integrated into a new, accessible areas to be
created through the implementation of the masterplan. These will need to be of a very high standard of design because
they will be visited by many people – residents and visitors alike – and will
be clearly visible not only from the water but also from land, upon the
demolition of the present industrial buildings. SEEDA and their partners English Partnerships have stressed that
they wish to use the new development of East Cowes as an exemplar of high
quality design, to accord with a design code to be jointly drawn up with the
Council.
Access
to and along the foreshore
There is documentary evidence that the public
uses the steps at the north-eastern end of the site to gain access to the
foreshore. However, both the land above
and below high water mark and there is no legal public right of way to use the
steps. Therefore, SEEDA has every right
to include the steps in its application site.
Moreover, given that the site would be used to move heavy turbine blades
by the use of powerful machines and a hoist, it is entirely appropriate that,
for health and safety reasons, the public does not gain access to the site.
The steps would be demolished in order to
reclaim additional land on which the maritime heritage museum would be
located. Although the emerging
masterplan proposals indicate that public access would run from south of the
Red Funnel terminal across this site and then alongside the Esplanade, past the
mouth of the estuary, there is no indication of any public access from such a
route down onto the foreshore. Given
that access is presently achieved by custom and practice, if not via a public
right of way, it is recommended that negotiations with SEEDA on the masterplan
and outline application for the full site seek a safe means of pedestrian
access to the foreshore. The design of
that access would allow for its use by pushchairs and by disabled persons, but
not by vehicles. It would also need to
be consistent with the emerging requirements for flood defence for the
area.
Nature
conservation issues#
English Nature did not wish to object to the
development due to the loss of habitat, but this is not an opinion shared by
the ecologist at the Environment Agency, who considers that the loss of habitat
at the site itself is contrary to the provisions of the Biodiversity Action
Plan, so that the Agency has raised a formal objection to the application.
The information provided by the applicant
concerning the site itself suggests that the site is, indeed, not valuable of
itself, and thus, notwithstanding the comments of the Environment Agency, it is
recommended that there is not adequate evidence to refuse the application on
that basis. This decision is taken in
the light of the current advice contained in PPS 9, on the understanding that
the impact of the application is not likely to be significant and mitigation
and compensation measures can be provided through a strategy associated with
the comprehensive redevelopment proposals.
However, there is certainly some
justification in the argument that the incremental loss of inter-tidal and
sub-tidal habitat within the Medina system would be both irreversible and
damaging, especially as, to date, there are limited compensation (off-site) or
mitigation (on-site) measures. English
Nature had, in pre-application discussions, advised SEEDA that there would
certainly be the need to undertake an Appropriate Assessment of the effects of
the development in the light of the 1998 Habitats Regulations that apply to
designations (or proposed designations) of sites of international importance
for their birds or habitats. In this
case, the principal designation is the candidate Special Area of conservation
(cSAC). Accordingly, an Appropriate
Assessment was undertaken by ABPmer, on behalf of SEEDA.
Under the Regulations, the Assessment has to
be reviewed by the “appropriate” or determining authority, in this case the
Council.
The ABPmer report
details the interest features known or likely to be present in the Medina
Estuary. This includes subtidal areas
that will be lost as a result of the proposed development. These areas are described as being of low
ecological value and, considering the fact that a relatively small designated
area will be lost, it is agreed that this development will not, in itself, have
a significant effect on the integrity of the European Site. However, in accordance with the Regulations,
which came into effect in 1998, the total subtidal habitat lost since
designation should be calculated and added to that which will be lost to
current and proposed future developments, so that a true picture of subtidal
habitat loss can be developed. This
process would allow in-combination subtidal losses to be more thoroughly
assessed and it can be established whether this will be considered a
significant effect on integrity of the European Site.
Impacts upon other
features of the cSAC are unlikely due to the lack of proximity to the area of
the works. Changes in the hydrological
and sediment regimes are predicted to be local and minimal and as such,
features present further upstream of the development are unlikely to be
impacted by the development.
The extent of the
Solent and Southampton Water SPA and Ramsar within the Medina is restricted to
the mid and upper reaches of the estuary.
As such, the development is unlikely to directly affect any of the
features of these designations.
Indirect impacts through changes in the hydrological and sediment
regimes have the potential to impact upon features of the SPA, however,
modelling of these regimes suggests that changes will be local and minimal and
therefore are unlikely to impact that far up the estuary.
The ABPmer report
considers the Venture Quays development in-combination with other plans and
projects in the area. Included are
examples of completed, current and proposed developments. However, it is considered that the report
needs to include developments as far back as 1998, when the area was first
designated, and they have not been included.
It is also important that the regeneration proposals for East Cowes, of
which Venture Quays is part, are also included in the appropriate
assessment. SEEDA has already advised
the Council that the East Cowes regeneration masterplan will include extensive
redevelopment of the waterfront requiring reclamation of inter-tidal and
sub-tidal land. It is important that
the effect of these proposals forms part of the in-combination assessment. It has already been shown that the estuary
is being moved away from its ideal state of equilibrium and further
developments, not considered in the ABPmer report, have the potential to
increase this problem. The
in-combination effects on tidal prism, hydrological and sediment regimes may
differ significantly from that described in the present report if all proposals
were included, and – indeed - could have a significant bearing on the
assessment of any adverse effect on the integrity of the European Site.
The cumulative
loss of subtidal habitat since designation should be calculated and summed with
predicted losses as a result of future developments including the East Cowes
regeneration proposals. That process
would establish whether the in-combination loss of subtidal habitat should be
treated as a significant effect.
The ABPmer report
concludes that the Venture Quays Apron Extension would not represent an adverse
effect on the integrity of the European Sites in isolation. The report also concludes that
in-combination with other plans and projects the Venture Quays Apron Extension
proposal is unlikely to contribute to any adverse effects caused by other
schemes.
As stated above, it
is agreed that the proposal is unlikely to cause a significant adverse effect
on the European Sites in isolation.
However, to reach a similar conclusion with regard to the in-combination
effects it is important that other significant developments proposed for the
area are considered as part of the appropriate assessment. This should especially include the proposals
for the regeneration of East Cowes, of which the Venture Quays proposal is a
part, but also development on both sides of the estuary. These have the potential to move the estuary
further away from its ideal state, which may have an adverse impact upon the
European Sites.
English Nature has
been consulted on the Halcrow review of the Appropriate Assessment and accepts
its conclusions. It considers that
there are no grounds for objection to this application on the basis of the
in-combination effects because it is entirely reasonable to ensure that a
comprehensive Assessment, as outlined above, should be sought prior to the
submission of the outline planning application for the regeneration area. That exercise would not only help to advise
the Council on the acceptability of that application, but Identify a critical
value that establishes how far the estuary can be moved away from its ideal
state before significant impacts are likely to occur to the system and
habitats, by suggesting if an area of inter-tidal habitat can be
developed. The assessment would, as
indicated earlier, be based upon calculated total intertidal and subtidal
habitat loss since 1998 and the predicted future losses as a result of proposed
developments.
It is considered that it would be
inappropriate to impose a requirement for SEEDA to search for and establish a
site to compensate for the loss of land associated with this application. However, EN is strongly of the opinion,
supported by the Environment Agency, that the masterplan proposals to be
submitted by SEEDA should require, as an essential element, a habitat
compensation strategy, drawn up in co-operation with the two government
advisors and the Council. That strategy
would take account of potential effects of the development proposals on the
Medina system as a whole. EN is concerned
that SEEDA would be bound to draw up such a strategy and then to implement it.
No specific proposals for mitigation or
compensation are recommended, therefore, in association with a consent for this
proposal.
The concern by English Nature over the
impact of vibration on fish stocks is considered under the section related to
noise, below.
As has been stated earlier in this report,
the land on which the present apron stands has been reclaimed in the recent
past, and is thus unlikely to contain material of archaeological
significance. However, the proposal
does include reclamation from the river, and there is a possibility that the
reclaimed area and adjacent riverbed may contain interesting features either
because of boats and other material lost under water, or because sea level rise
has covered parts previously dry land.
Accordingly, much of the research associated
with this site has been related to the area below high water mark, and has
included a detailed geophysical survey.
Technical difficulties meant that the results of the survey were
initially complex to interpret, but evidence now suggests that there is nothing
significant within that area to prevent development or worthy of further
investigation or recording prior to development.
The jurisdiction for archaeological issues
below low water mark lies not with the Council, as is the case for the land
above that mark, but with English Heritage (EH). Accordingly, the Council's planning archaeologist has maintained
close liaison with EH since the application was submitted.
This liaison has been particularly important
as a precursor to the outline application for the full redevelopment site, in
order that a protocol for dealing with continuing desk-top and site-based
research can emerge. Attention is
particularly focussed upon the area as a whole because of the knowledge, proven
through documentary records, that Henry VIII established a castle in East
Cowes. The castle was demolished, and
there is now no certainty as to where it once stood. Nevertheless, its site is almost certainly within the redevelopment
area. If found, the site would become a
Scheduled Ancient Monument, a designation that would preclude development in
the immediate area. However, if it were
found, the effect would be more likely to be positive than negative, as it
could become the focal point of the redevelopment area.
Discussions are continuing between the
council, English Heritage and the applicant's archaeologists on the method on
on-site research to be adopted across the site to ensure that a representative
examination is permitted while not proving too onerous, in terms of cost or
time, to the applicants.
The Council's planning archaeologist
considers that the stone wall that lies beneath the present apron, while not
part of the Henrician castle, might be composed of stone from that
structure. He therefore considers that
examination and recording of the wall to learn from its construction may
provide useful clues about the castle.
The applicant has indicated that the wall will not be demolished as part
of this development, but it is recommended that prior to construction works for
the new development taking place, visual examination and recording should be
permitted, and a condition is accordingly related to the permission granted to
the applicants.
Flood defence and sediment movements
It is noted that the Environment Agency
raises no objections in terms of flood risk.
It does point out the proposal runs contrary to the “hold the line”
policy of the Shoreline Management Plan, but the incursion into the estuary is
minor, and it is recommended that it would be more appropriate to consider the
impacts of the final proposals for the whole regeneration area against the
emerging revised Shoreline Management Plan and the Council’s coastal defence
strategy, in order that a co-ordinated response to flood defence emerges and
can be programmed into the final development proposals. The Agency is concerned that the proposals
should not have an adverse effect on the provision of sea defences for the full
redevelopment area, but the statement on behalf of SEEDA that there would be no
prejudicial effects is accepted by your officers, in the absence of any
evidence to the contrary.
The Agency is concerned that there has been
no assessment of the effects of SEEDA’s subsequent phases of development, and
suggests that the baseline for assessing those effects on morphology should be
the present situation, before Venture Quays is constructed. This suggestion is entirely reasonable, and
SEEDA will be advised accordingly. It
is not considered appropriate to impose a condition to that effect upon any
planning consent.
The Agency raises an argument on the
cumulative effects of development on the morphology of the river and on flood risk
similar to arguments made by themselves and English Nature in respect of losses
of habitat. Officers support the
Agency’s concern over such matters, and its recommendation that a strategy
should be prepared to manage the impact of such development. However, we do not consider that the
preparation of such a strategy is a necessity for the permission of this
application.
Noise levels during construction
The site is
situated in an industrial area and therefore it is considered unreasonable to
stipulate conditions limiting noise generation during operations, particularly
as no new exceptionally noisy processes would be utilised. Should future complaints about the noise
from the operations arise, existing statutory legislation (Control of Pollution
Act 1974 and the Environmental Protection Act 1990) would allow a noise
abatement notice to be served.
It is the
generation of noise during construction which could potentially prove
problematic, particular as the many of the works need to be undertaken at low
tide. Therefore, it is considered to be
onerous and unreasonable for construction works to be subject to a condition
restricting times of work: this is likely to cause a significant slip in the
construction programme. The principal
receptors of noise generated would be houses at Old Road, Albany Road,
Haresfield Road and Dover Road.
The subject of
noise generation has thus been discussed by the council’s Environmental Health
staff and advisors from Halcrow. They
consider that, while there is evidence to suggest night time levels from
construction should not exceed 45dB(A) Lmax at the façade of residential
properties, such a tight limit would be difficult to achieve in practice.
British Standard
8233 recommends that peak night-time noise levels within bedrooms should not
exceed 45dB(A) Lmax to avoid sleep disturbance. Similarly, the standard
recommends that a continuous noise level of 35dB(A) Leq is considered
‘reasonable’ for bedrooms at night.
Therefore, it is
suggested by Halcrow that maximum night-time noise levels, measured 3.5m from
the at the point of reception, of 55dB(A) Lmax and 45dB(A) Leq would be
reasonable, on the assumption that it would represent an internal noise level
of 45dB(A) Lmax and 35dB(A) Leq when bedroom windows are open.
Accordingly, a
“capping” condition to that effect is proposed at this site, and noise levels
will be monitored during construction works, especially at night, to ensure it
is not exceeded.
Although it is
recognised that piling works would cause vibration, our advisors consider that
effects on properties more than some 40-50m away from the source are unlikely
to cause complaint.
English Nature
also expressed some concern that piling works would have an impact on fish
populations, because of vibration. The
Medina does not, however, have a very important fish population. Also, the works are proposed to take place
during autumn and early winter, when spawning does not occur, so the effect
would not be significant if the piling works were to progress during that
period. The applicant is requested to
advise the Council if the piling programme were to extend into early spring,
when fish spawning could be affected by vibration from piling.
The means of
piling can alter the degree of vibration produced. A method known as vibropiling is known to be less disruptive than
typical percussive piling. Details of
the method of piling have been sought from the applicant, but not yet
provided. Therefore, it is recommended
that a condition is attached to any consent to require a method statement for
piling to be submitted to and approved by the Council prior to development
commencing.
7. Conclusion
and justification for recommendation
7.1 The principal process to follow in drawing up a
recommendation for determining this application was to balance the need for the
development against the environmental consequences, both of construction and
operation of the facilities. The
argument for need has been highlighted by Vestas, as tenants of SEEDA. It has presented a strong case to utilise
this important waterside location, especially as alternative sites are not
readily available. Retention of Vestas’
activities on the Island is particularly important because of the implications
on maintaining a vibrant economy. It is
a cause for concern that the future of Vestas, not only at this site, but on
the Island, after its lease expires in five years’ time, remains uncertain.
7.2 Issues in relation to appearance, archaeology, impact on navigation,
access to the waterfront, and noise and vibration during construction have been
clarified to the officers’ satisfaction during the negotiation process and
through the submission of additional information, and through the proposed
imposition of conditions.
7.3 Potentially more significant have been the inter-connected
factors of potential effect on nature conservation, on flooding and on coastal
processes. While the Environment Agency
considers that the direct effects of this proposed development on the
inter-tidal and sub-tidal habitat would be significant, it would be difficult
to substantiate such an allegation.
7.4 However, the long-term effects on the coastal and estuarine
system of the Medina and north coast of the Island arising from the many
developments at the river-mouth remain unknown and give rise for concern. In addition to those developments proposed
by SEEDA, there are many waterside proposals on both banks of the estuary which
could potentially cause further loss of habitat of international importance,
both directly and indirectly, and it is particularly the combination of
developments which led to the Appropriate Assessment legislation and which has
guided English Nature’s reasoned concern for this area. Thus, a full study of potential impacts will
be required prior to the submission of the outline application for the
regeneration area as a whole, so that a strategy governing development in and
adjacent to the estuary can be developed in a more comprehensive manner.
8. Recommendation
It is recommended that full planning consent
is granted, subject to the following conditions:
Conditions/Reasons:
1 |
A10 |
The development hereby permitted shall be begun
before the expiration of 5 years from date of this permission. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
2 |
B12 |
No development shall take place until details
have been submitted to and approved in writing by the Local Planning
Authority of the positions, design and intensity of lighting at the
application site, both during construction and operation. The intensity of illumination shall not
exceed 1600 candela per m² and lanterns should be shrouded to prevent undue
light pollution. Reason: In the interests of the amenities of the
area and to comply with policies D6 (Advertisements in Defined Settlements)
and D14 (Light Spillage) of the IW Unitary Development Plan. |
3 |
S03 |
No development shall take place until details of the
materials and finishes to be used in the construction of the external
surfaces of the development hereby permitted have been submitted to and
approved in writing by the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with policy D1 (Standards of Design) of the IW Unitary
Development Plan. |
4 |
M33 |
No development shall take place until details
have been submitted to and approved in writing by the Local Planning
Authority of the positions, design, materials and type of boundary treatment
to be erected. The boundary treatment
shall be completed before the use hereby permitted is commenced in accordance
with a timetable agreed in writing with the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In the interests of maintaining the
amenity value of the area and to comply with policy D1 (Standards of Design)
of the IW Unitary Development Plan. |
5 |
Q40 |
The level of noise emitted from the site during
the construction phase as measured 3.5m from the worst affected facade of the
nearest noise sensitive receiver to the site shall not exceed: 70dB LAeq 1-hour between 0700 and 1800 hours
Mondays to Fridays; 45dB LAeq 5-min and 55dB LAmax at any other
time]. Reason: In the interests of the amenities of the
area in general and adjoining residential property in particular and to
comply with policy P5 (Reducing the Impact of Noise) of the IW Unitary
Development Plan. |
6 |
UN1 |
No development shall take place until the
applicant or their agents has secured the implementation of a programme of
archaeological watching brief recording in accordance with a written scheme
of investigatiion which has been submitted to and approved by the Planning
Authority in writing. Reason: To
ensure that good practice is applied in the event of a feature of potential
archaeological interest is discovered during construction operations. |
7 |
UN2 |
No
development shall take place until the applicant or their agents has secured
the implementation of a programme of historic structure recording in accordance
with a written scheme of investigation which has been submitted to and
approved by the Local Planning Authority in writing. Reason: To
ensure appropriate examination and recording of the form, status and
condition of the wall lying under the present apron, during the period after
that has been demolished and before construction of the new apron commences,
so advantage can be taken of temporary high light levels. |
8 |
UN3 |
To facilitate monitoring of the on-site
archaeological works, notification of the start date and appointed
archaeological contractor should be given in writing to the address below not
less than 14 days before the commencement of works: The County Archaeologist County Archaeological Centre 61 Clatterford Road Carisbrooke Newport Isle of Wight PO30 1NZ Reason: To
facilitate sound and constructive continuing dialogue between the applicant
and the Council Archaeological Service. |
9 |
UN3 |
No development shall take place until there has
been submitted to and approved in writing by the Local Planning Authority
details of methods of piling to be used, including hours of operation. Thereafter, development shall be carried
out in accordance with the agreed method and hours of operation. Reason: In
the interests of the amenities and character of the area and to comply with
Strategic Policy S10 (Designated and Defined Areas) and Policies C1
(Standards of Design), C8 (Nature Conservation as a Material Consideration)
and C9 (Sites of International Importance for Nature Conservation) of the IW
Unitary Development Plan. |
9. |
Reference
Number: P/00854/05 - TCP/11878/E Parish/Name: Shanklin - Ward/Name: Shanklin South Registration
Date: 03/05/2005 -
Full Planning Permission Officer: Mr D Long Tel: (01983) 823854 Applicant: Priory School Continued
use of dwelling as private school; vehicular access and parking Alverstone
House, 32, Luccombe Road, Shanklin, PO376RR |
This application is recommended for refusal and
enforcement action.
REASON FOR COMMITTEE CONSIDERATION This is a contentious application on a site with
a background of public concern, consideration of which was deferred from the
15 June 2005 meeting. |
1. Details
of application
1.1 This
is a full application.
1.2 The
proposal is for the continued use of a former dwelling as a private school,
including a new vehicular access and parking facility.
1.3 Although the majority of the details
noted within the Committee Report of 15 June 2005 has not changed, the access
arrangements from the highway have been altered. The existing access is proposed to be widened to accommodate
two-way traffic by removing a number of trees with a turning circle created in
the curtilage of the site. A school
travel plan has been submitted and a land levels survey undertaken.
2. Location
and site characteristics
2.1 Please refer to the Committee Report of
15 June 2005. The location and site characteristics
are detailed within that Report, with no change whatsoever.
3. Relevant
history
3.1 TCP/11878/D, continued use from dwelling
to private school; vehicular access and parking. Application refused, 18 April 2005 for the reason detailed
within the previous Committee Report.
3.2 P/00854/05. Continued use from dwelling to private school; vehicular access
and parking. Application went before
the Development Control Committee on 15 June 2005. Application deferred for the following reasons:
·
Clarification on impact on protected trees.
·
Further information on the School Travel Plan.
·
A land levels survey.
4. Development
Plan policy
4.1 The policies contained within sections
4.1 to 4.3 of the Committee Report of 15 June 2005 remain as existing, still
being relevant to the determination of this application.
5. Consultee
and third party comments
5.1 Internal
consultees
·
Highways recommend refusal upon the revised
application for the following reasons:
i. The
development would generate a significant increase in vehicular traffic entering
and leaving the public highway.
ii. The
access is unsatisfactory to serve the proposed development by reason of
unacceptable visibility.
·
The School Travel Plan Adviser (Highways) advises that
the revised School Travel Plan meets the criteria set by the Department for
Transport/Department of Education and Skills (DfT/DfES) and the “travelling to
school” action plan. The set of
criteria assesses all schools undertaking a School Travel Plan, being a
requirement by the DfT/DfES.
·
The Countryside Manager recommends approval. The use of the singular access to the school
is more appropriate than the original plans.
5.2 Third
party
The application has attracted 7
letters of objection, that have not raised any additional points to
those summarised in the Committee Report of 15 June 2005.
The application has attracted an
additional petition of 329 signatures of support, not addressing any
additional points to those outlined within the Committee Report of 15 June
2005.
5.3 No
other consultees mentioned within the previous Committee Report raised any
additional points.
6. Evaluation
6.1 The
main issues relating to this application are:
·
the principle of the change of use from a dwelling
to a private school.
·
highway considerations concerning access,
visibility and generation of traffic onto public highway, and School Travel
Plan.
·
the removal of protected trees in the widening of
the existing access to Alverstone House.
6.2 As noted within the Committee Report of
15 June, the Local Planning Authority accept the principle of the change of use
from a dwelling to a private school.
6.3 Following completion of the levels
survey it was clearly demonstrated that the proposed new access would not have been
feasible, as your officers indicated at the time. The fall was around 3m and a suitable ramp and parking area could
not realistically be created. The
applicants have therefore dropped this proposal in favour of a modification to
the existing access. This will consist
of a turning head combined with an enlarged parking area plus a partially
separated dedicated exit route but using the existing access point. However, the existing gates appear to be
proposed to be retained and given their width and proximity to the back edge of
the footway it is unlikely that a two way vehicular (not to mention a safe
pedestrian) flow could be achieved. The
revised access arrangements, albeit still not perfect or even acceptable, do at
least allow retention of virtually all the trees on the Luccombe Road frontage,
as previously sought by your officers, to the overall benefit of the general
environmental character of the area.
6.4 However this revised access arrangement does
not overcome the inadequate visibility this site possesses and the increased
traffic movements to and from the site.
The Highways Consultant for the applicant has suggested that the
guidance used by the Council’s Highways Officer should not use strict
parameters, allowing a certain amount of leeway to judge the correct visibility
splay for this use. “Places, Streets
and Movements” published by Central Government is nationally recognised
standard guidance for residential development, although the standards are
required for other uses. The Council's
Highways Officer suggests that it is not fair to expect that a visibility splay
is designed for each separate development and the guidance takes into account
many variables including adverse weather conditions, road alignment, driving
skill, surface grip and types of highway user.
All these account to gain the correct visibility splay for a specific
type of use. The agent’s consultants
suggest that “the guidance given here needs to be assessed in the circumstances
of each case. Sight lines should never
be reduced to a level where danger is likely to be caused”. Your officers remain of the opinion that by
lowering the visibility splay at this access to a level below that recommended
by the Highways Engineer is to a reduced standard where likely danger will
occur.
6.5 Members must note that this land use is
extremely sensitive, and lowering the splay requirement would not be
appropriate in this circumstance. The
applicant wishes to reduce the visibility beyond the recognised standards which
would be inappropriate for any use, especially a school.
6.6 The Highways Engineer suggests that
pedestrians, cyclists, private cars, deliveries, school buses and residential
traffic will have to co-exist within the highway at this location, and as such
good visibility and inter-visibility is essential to allow the safe free flow
of all traffic types. The agent’s
highway consultants suggest that “delay to passing traffic is not really an
issue”, but surely by acknowledging that delay to passing traffic is likely to
occur if the splay is lowered, are they not inferring that “danger is likely to
be caused”? It is also recognised that
the speed survey was undertaken in February 2005, when the school was not in
operation and would not have a bearing on the flows of traffic along Luccombe
Road, where it was noted back in February that there are only 350 movements per
day. Once the school had opened the
trip rate along that road would have increased, due to the level of staff,
pupils and associated trips. The
agent’s highways consultant’s assertion that “the overall level of traffic here
is very low” is therefore somewhat misleading.
6.7 The Council's School Travel Plan adviser
has indicated that the School Travel Plan is in accordance with the guidance
laid out by the DfT and DfES and has been signed off accordingly. It is noted that this is a laudable
initiative that can help reduce traffic numbers in and around schools. But it does justify an inadequate access in
terms of visibility in and out of the school.
The Plan is a well-intentioned scheme that clearly is a sound investment
in the health of pupils and a useful attempt to bring down the trip rates
associated with the school run, but it still remains an essentially theoretical
exercise reliant on wish fulfilment.
Neither is it a justification to allow a development of this nature to
be served off an access that is inadequate in any way. Members must note that a School Travel Plan
will be extremely difficult, if not impossible, to enforce as it relies on the
school itself to regulate and encourage parents to adhere to the outline of the
Plan. Members are invited to consider
the following data from the Travel Plan.
Currently around 60% of the 110 pupils come to school by car or taxi (a
few car share) but when asked 62% said they would like to travel by
bicycle. Given the location of the site
on a narrow road up a steep hill and significant clusters of pupils living in
the Sandown, Lake and Ryde areas, Members might ask whether this declared
preference for cycling is actually achievable.
Added to this is that the number who walk or come by bus is currently
40% (only 1% currently cycle) but their choice would be to reduce this number
to about 20%. This may be a reflection
of the inadequacy and perceived lack of safety on the current footway network.
6.8 Although annual inspections are carried
out by the school, if it is failing in any area the Local Planning Authority
cannot force the school to change their vehicular trip rate or mode of travel
which, because of its Islandwide catchment area, naturally has a far greater
proportion of carborne pupils than might be expected at a local neighbourhood
school. It also relies on education of
parents and children to act responsibly, and constant reinforcement of that
message to maintain the ethos of the Plan.
As such, if Members were minded to approve this application the Local
Planning Authority would have no effective enforcement role or sanction within
the implementation and regulation of this Travel Plan. This could potentially increase the
vehicular movements within the area, increasing the danger of highway users on
Luccombe Road.
6.9 The Countryside Service has no objection
to the application, as the reasons outlined within the Committee Report of 15
June 2005 have been addressed to their satisfaction. By omitting the secondary access on the proposal, the protected
trees along that frontage have been retained, keeping the integrity of the
public visual amenity along Luccombe Road.
It is noted that although a number of trees will be lost within the
widening of the existing access to the school, the majority of these trees are
set back within the site, not being highly visible from the public domain, or
of a standard that is of little significance and can be replaced via a planning
condition.
7. Conclusion
and justification for recommendation
7.1 Although the principle of change of use
is accepted, this is subject to consultee responses and their professional judgement
on how the operation will affect the amenities of the area.
7.2 Since the deferral of the application by
Committee on 15 June 2005 the agent has supplied a School Travel Plan
sufficient to meet the requirements of the Department of Education and Skills
and the Department for Transport. The
School Travel Plan adviser therefore has no objection. Nevertheless it still remains an untried and
untested proposal and hence is currently of a theoretical nature only.
7.3 The Countryside Service no longer objects
to the application as the majority of protected trees within the area will be
retained in the best possible way, and can be reinforced by a planning
condition. Although the trees to be
lost within the widening of the new access are protected, i.e. are set to the
rear of the site forming little public visual amenity or are of a standard not
suitable for protection.
7.4 Although a number of reasons for refusal
within the last Committee Report have been addressed to the satisfaction of the
Local Planning Authority, this does not outweigh the extreme importance of
highway considerations within this application. Although the single access does alleviate some of the previous
reasons for refusal in its current form it will not function any more
efficiently or effectively than the current access and furthermore it still has
inadequate visibility, creating adverse impacts to highway users. This is a sensitive use in a sensitive
location and Members should be minded to refuse this application on this sole
reason. Although the School Travel Plan
is an encouraging asset to a school, this should not be a justification for
allowing a development to be served off an inadequate access of any sort. Members must also note that the School
Travel Plan is not enforceable and relies on the school itself to regulate and
maintain the details outlined within that Plan. The Local Planning Authority will have no control, possibly
increasing traffic movements in the area to the detriment of highway
safety.
8. Recommendation
This
application is recommended for refusal.
Should Members be minded to refuse
the application the Local Planning Authority suggests that an enforcement
notice is issued requiring the property revert back to an independent dwelling
and that the date of compliance should be no later than 31 December 2005.
Conditions/Reasons:
The
proposed development would generate a significant increase in vehicular
traffic entering and leaving the public highway to the detriment of highway safety
and would add unduly to the hazards of highway users and would therefore be
contrary to policies TR7 (Highway Considerations for New Development) of the
IW Unitary Development Plan. |
|
2 |
The
access is unsatisfactory to serve the proposed development by reason of
unacceptable design and visibility and would therefore be contrary to Policy
TR7 (Highway Considerations for New Development) of the IW Unitary
Development Plan. |
10. |
Reference
Number: P/01028/05 - TCP/03605/U Parish/Name: Seaview - Ward/Name: Seaview &
Nettlestone Registration
Date: 26/05/2005 -
Full Planning Permission Officer: Mr P Stack Tel: (01983) 823575 Applicant: Seaview Hotel & Restaurant Demolition
of public toilets; detached building to form additional hotel accommodation
to include seven additional bedrooms and associated facilities; alterations
to vehicular access Seaview
Hotel & Restaurant, High Street, Seaview, Isle Of Wight, PO345EX |
This application is recommended for conditional
planning permission.
REASON FOR COMMITTEE CONSIDERATION Application TCP/3605/U involves Council owned
land and therefore falls to be determined by the Development Control
Subcommittee. |
1. Details
of application
1.1 This is a full application involving
removal of the two detached single storey flat roofed public toilet blocks
which are located on the eastern side of Rope Walk approximately some 50 metres
north of junction with West Street and their replacement with a hotel
annexe. Existing rendered buildings
straddle rear service road to hotel which provides access to parking area and
also allows for pedestrian access to rear of premises.
1.2 Property is owned by Council on which
appropriate notice has been served and application seeks to demolish existing
buildings and replace with new build comprising two/three storey building which
whilst maintaining roadway provides cantilevered accommodation over and
alongside service road. New building
would have footprint of approximately 10.25 metres depth by 14 metres width
with average height to eaves of 5.9 metres above ground level and ridge height
some 8.5 metres above ground level.
These levels reflect revised plans subsequently received showing drop of
approximately half a metre from original submission.
1.3 New build would provide for seven
bedrooms to be used as additional hotel accommodation with building having
benefit of internal stairway and lift. Ground
floor also includes store building, and centrally located refuse store and
small staff changing room. Access to
first and second floor accommodation will be gained via doorway located in Rope
Walk elevation.
1.4 In terms of design the proposal seeks to
provide simple double gabled featured elevation onto front walk with slight set
back to central cantilevered section and provision of Dormer and Velux windows
within roof slop. Apart from two small
high level windows at ground floor level there are no side facing window
openings proposed.
1.5 Concerning external finish, details show
building to comprise brick ground floor finish with rendered walls over
underneath slate roof. In terms of
parking, space for 11 vehicles is shown within central courtyard which retains
existing provision.
1.6 In connection with development,
applicant advises the Council have entered into contract with owners of hotel
for long lease of site of public toilets which subject to planning approval
being granted such toilet facilities being reprovided within main hotel
building. Contract requires facilities
to be maintained by hotel and be open to public between hours of 0700 and 1900
hours daily except for the period from 22nd to 28th December inclusive. Agent indicates that in practice opening
hours will be longer than this and toilets will be clearly marked and will
provide modern, clean and attractive facilities to much higher standard than
currently exists.
2. Location
and site characteristics
2.1 Hotel premises has main frontage
elevation onto High Street but does have return frontage onto Rope Walk which
provides service/visitor access to rear parking area between existing toilet
blocks.
2.2 Hotel premises encompasses adjoining
property known as Bank Place, which is itself Grade II Listed building, and
entire application site is located within Seaview Conservation Area and
development envelope.
2.3 In terms of general character of
development, fronting Rope Walk buildings are a mix of styles and size, and
whilst generally speaking is of two storey height there is example of three
storey development within locality.
Several buildings are located close to highway edge and do not benefit
from any off-street parking provision.
3. Relevant
history
See
TCP/3605V.
4. Development
Plan policy
4.1 National Policy is covered in PPG4 –
Industrial and Commercial Development
in Small Firms, PPG15 - Planning and the Historic Environment, and PPG21 –
Tourism.
4.2 The
following UDP policies are considered relevant in this case.
S1
- New development will be
concentrated within the existing urban areas.
S2
- Development will be encouraged on
land which has been previously developed (brownfield sites).
S5 - Proposals for development which on balance
will be for the overall benefit of the Island by enhancing the economic, social
or environmental position will be approved provided any adverse impacts can be
ameliorated.
G1
- Development envelopes for towns and
villages.
G4
- General locational criteria.
G10
- Potential conflict between proposed
developments and existing surrounding uses.
D1
- Standards of design.
D2
- Standards for development within
the site.
B6
- Protection and enhancement of
Conservation Areas.
B7
- Demolition of non-Listed buildings
in Conservation Areas.
T1
- Promotion of tourism and extension
of season.
T3
- Criteria for developments for
holiday accommodation.
TR7
- Highway considerations for new
developments.
TR16
- Parking policies and guidelines.
5. Consultee
and third party comments
5.1 Internal
consultees
·
Conservation and Design Team Leader comments that
in context the properties on either side are two storey, with properties
opposite single or two storey in mass.
Hotel buildings within the yard are one, one and a half and two storey
high and lane fronting site is narrow with no footway. The only three storey buildings are some
distance away and address a wider part of the lane, they do not read with this
site. Roofs in the row are distinctive
in that they are hipped with ridges running from front to back and valleys
between the properties. Opposite are
rear gardens, parking, a garage and a sub-station, and there is a distinct
building line on either side of the site, and in the lane as a whole buildings
are set close to the back of kerb line.
In respect of proposal, which has
been revised following pre-application negotiations, she advises that
applicant’s agents have taken on board pre-application advice and have reduced
scheme to two storeys plus attics. The
eaves are the same height as the property adjoining on one side and a little
higher than those on the other, in line with a slight fall in level. Given the variety of heights and styles in
this area the scheme is not out of scale and is quite simple in its
design. Care will be needed in
detailing and the choice of materials, and it may be helpful to be specific
about relative slab and eaves heights in numerical terms to ensure that the
relativity is measurable. In her
opinion the proposal is certainly no worse than the existing situation here,
and may well be held to be an enhancement in terms of the South Lakeland case.
·
Environmental Health Officer has no adverse
comments to make in respect of this application.
·
Highway Engineer comments that revised plan has
been received showing existing and proposed levels of visibility
available. The plan confirms that the
proposed building does not impinge on existing visibility splays and can
therefore be supported.
In terms of
parking provision and UDP policy, Highway Engineer points out that document
states that hotel use requires a minimum of one parking space per residential
staff. Application does not detail how
many residential staff there are on site and as such it is difficult to
calculate whether the level of parking shown is appropriate to serve
proposal. It should also be borne in
mind that existing 11 parking spaces also serve hotel rooms, restaurant and
staff. UDP states that an A3
(restaurant) use should have a minimum parking provision of one lorry
space. Even whilst bearing in mind that
Seaview falls within Zone 3 of parking guidelines which are flexible in
requiring between 0 and 75% of normal requirements he does not feel that he
could raise a sustainable objection to application on grounds of inadequate
parking. This is due in part to very
low minimum parking requirements contained within UDP and it is likely that
hotel and restaurant attracts a large proportion of its trade and staff from
the local area. As such he does not require
any further information relating to staffing levels in order to calculate
parking provisions.
5.2 External
consultees
None.
5.3 Parish
Council comments
Parish
Council objects to application on the following grounds:
·
Development constitutes urban development in a
rural location representing material over intensification of site.
·
Area has been Conservation Area since 1974 and
although there is a three storey building in the street this was constructed
prior to that date.
·
Size of the proposed development will have
detrimental effect on character and appearance of area when compared with
existing building.
·
Amenities of adjoining properties will be adversely
affected, i.e. overlooking causing a loss of privacy as Rope Walk is a narrow
thoroughfare.
·
It is believed that there will be a considerable
increase in noise and unpleasant smells because of the growth and number of
deliveries and collections.
·
Whilst the proposal allows for increase of seven
bedrooms, there are no plans for additional car parking in an already congested
village.
5.4 Neighbours
39
letters of objection have been received from local residents and
businesses. Points of objection are
summarized as follows.
·
Development is out of keeping with character and
scale of Conservation Area, dwarfing surrounding properties.
·
Inappropriate building form in Conservation Area.
·
Increase in access width will allow larger vehicles
to service to rear of hotel.
·
Existing problems concerning deliveries to rear
resulting in blockage of Rope Walk.
·
Existing parking problem which will be exacerbated
by increased accommodation and no resultant increase in parking provision on
site.
·
Increased problems with deliveries to front of site
and impact on highway circulation.
·
Choice of materials is significantly different from
that used in locality.
·
Loss of amenity by reason of overlooking.
·
Proposal will result in loss of privacy and light
to surrounding residential occupiers.
·
Health risk and increase in level of noise and smell,
and general concern concerning increase in pollution levels.
·
Potential conflict in highway safety terms with
pedestrians using Rope Walk.
·
Loss of toilet facilities and lack of similar
replacement facility and availability within hotel.
One writer expresses no objection
in principle to removal of toilets, however expresses concern concerning the
detail of proposed replacement building.
Reference is also made to views
expressed in Parish Plan, however the contents of such a document should be
given limited weight given that such views appear to be contrary to tourism
policies contained within the adopted UDP which is of primary importance in
consideration of this proposal.
6. Evaluation
6.1 The
main planning considerations relating to this application are:
·
Specific Development Plan policies contained within
the UDP.
·
Appropriateness of development in terms of scale,
mass, design and detailing and its impact on the locality.
·
Impact on surrounding residential occupiers.
·
Implications in terms of highway and parking
issues.
6.2 Development planning system obliges
Planning Authorities to determine application in accordance with the plan
unless material considerations indicate otherwise. Of principal importance therefore are the relevant policies of
the Unitary Development Plan which have been referred to in section 4.2.
6.3 Proposal in seeking to increase
accommodation on established site is supported by tourist related policies,
provided the impacts of such a proposal both on the locality in terms of Conservation
Area status and immediately adjoining residential occupiers are not unduly
impacted upon, these issues being covered by the relevant Plan policies for
design standards and protection of conservation areas.
6.4 In seeking to increase accommodation
proposal complies with Strategic and Local policies which seek to concentrate
development within existing urban areas on brownfield sites whilst enhancing
tourist economy. Therefore in terms of
land use the proposal is supported in the main by Unitary Development Plan
policies.
6.5 Turning to more site specific issues,
consideration should be given to potential impact of development on character
of Conservation Area and Members will be aware of the requirements of section
72 of the Planning (Listed Buildings and Conservation Areas) act 1990 which
requires Authorities to pay special attention to the desirability of preserving
or enhancing the character or appearance of that area.
6.6 As Conservation and Design Team Leader points
out, revised scheme has reduced eaves level of proposal, resulting in same or
similar levels with immediately adjoining residential properties. Given the variety of heights and styles in
the area the scheme is not considered out of scale and quite simple in design
terms. Lack of similar two/three storey
developments immediately adjoining site is not a reason per se to refuse scheme. Members will have to consider whether scale, design and detailing
of scheme proposed is inappropriate for its location and relationship with
adjoining properties. Clearly proposal,
in removing existing toilet blocks, represents opportunity to improve street
scene. Simplistic design of proposal is
not considered to present any serious constraint to development of this site
and external treatment finish is not inappropriate and has been used on other
development in locality.
6.7 In terms of direct impact on immediately
adjoining residential occupiers, it is relevant to note the changes to the
built form and compare existing with proposed.
6.8 The new building would be set away from
side boundaries by a minimum of 0.15 metres whereas existing toilet block is
built hard to existing boundaries. In
terms of footprints, the front section of building projects an additional 2
metres towards Rope Walk frontage with an additional projection of
approximately 1 metre from the line of the existing rear wall to the toilet
blocks. The driveway between the blocks
is shown to be increased from an existing 2.7 metres to 3.2 metres.
6.9 In terms of increase in height, top of
parapet to existing toilet block is approximately 4.5 metres above ground
level, with eaves to proposed building increasing this height by an additional
1.5 metres. This would result in new
eaves level approximately 1 metre above adjoining property to north and just
below eaves level of property to immediate south. Given distances to existing property and relatively limited
number of window openings in side elevation and orientation it is considered
that proposal will not cause undue loss of light to either property, which
themselves have benefit of rear additions which project beyond line of the rear
main wall of the proposed building.
Furthermore, given that proposed building is separated from existing
development by passageways and footways, this would help further minimise the
impact and ensure no undue overdominance of those properties is experienced.
6.10 With regards potential overlooking from
rearward facing first and second floor windows, proposed building would have
total of six windows at first floor level of which two are to en suite bathroom
facilities. Remaining four windows
serve two bedrooms whilst second floor windows comprise two single bedroom
windows in gable end features. Given
use to which rooms will be put and fact that rooms will principally look over
communal parking area and rear of hotel, it is not considered that level of
overlooking would be sufficiently serious to warrant refusal in this
instance. This opinion is reinforced by
the fact that immediately adjoining land to north is used as storage yard and
therefore impacts on residential amenity are reduced further.
6.11 Clearly the proposal involves an
intensification of use resulting in an increase in seven bedrooms from the
current operation which comprises a total of sixteen bedrooms (plus 44%). Whilst this represents significant
intensification Members have to balance the need for this type of facility on
Island against potential impacts of increased usage and likely disturbance associated
with such level of usage. Commercial
considerations are not a planning issue which can be taken into account when
determination of this application, which must be assessed purely in land use
terms. Having considered the matter
carefully your officers feel it difficult to substantiate a case that such a
type and level of usage would adversely impact on residential amenity,
particularly given fact that in considering fallback position it is considered
unlikely that infill development for residential purposes would be considered
unreasonable, and as such could have greater impact on locality than current
proposal.
6.12 Given thrust of adopted parking policy and
advice contained within PPG13 (Transport) which seeks to reduce car usage,
proposal complies with zonal parking requirements. With on street parking restrictions and limited parking available
within hotel premises, car usage to a certain extent is self-limiting and it
should be noted hotel premises is located approximately 200 metres from nearest
public car park. With regards to
deliveries, agent states that it is unlikely that there would be increased
numbers of delivery visits, with most deliveries occurring Monday to Friday
between 0730 and 1430, with occasional deliveries on Saturday. Most deliveries are to front of hotel with
only beverages being delivered via Rope Walk.
Most deliveries it is stated are completed within 10 minutes. Given these comments it will be difficult to
conclude categorically that proposal will increase delivery movements and
difficulties above level currently experienced.
6.13 Concerning replacement toilet facilities,
agent advises that whilst contract with Council requires toilets to be open for
a minimum period of 0730 to 1900 hours, toilets will be available at times when
the hotel is open, usually from 0700 to 2330 or later. Members will appreciate that any contract
entered into between the hotel operator and the Council in respect of the
location of replacement toilet facilities is not directly relevant to the
consideration of this application and the implementation and commitment to any
such agreement, whilst clearly dependent on the outcome of the planning
application, is a matter for the Property Services section of this Authority.
7. Conclusion
and justification for recommendation
7.1 Having given due regard and appropriate
weight to all material considerations referred to in this Report I am satisfied
that on balance the development of this site to provide additional hotel
accommodation, impact on Conservation Area in general and adjoining residential
occupiers in particular is not considered sufficient to sustain a
recommendation to refuse permission and application is recommended accordingly.
8. Recommendation
To
grant conditional permission.
Conditions/Reasons:
The development hereby permitted shall be begun
before the expiration of 5 years from date of this permission. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
|
2 |
No development shall take place until details of
the materials and finishes to be used in the construction of the external
surfaces of the development hereby permitted have been submitted to and
approved in writing by the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with policy D1 (Standards of Design) of the IW Unitary
Development Plan. |
3 |
Notwithstanding the provisions of the Town and
Country Planning (General Permitted Development) Order 1995 (or any Order
revoking and re-enacting that Order, with or without modification), no
windows/dormer windows (other than those expressly authorised by this
permission) shall be constructed. Reason: In the interests of the character and
amenities of the area and to comply with policy D1 (Standards of Design) of
the IW Unitary Development Plan. |
4 |
The accommodation hereby permitted shall only be
used as guest accommodation annexe in connection with the operation of
Seaview Hotel and for no other use without the express written prior consent
of the Local Planning Authority. Reason: To protect the amenities of nearby
residential property and to comply with Policy D1 (Standards of Design) of
the IW Unitary Development Plan. |
5 |
The northern eaves level of the building hereby
approved shall not exceed the existing eaves level of the adjacent
residential property 'Spencer' by more than 0.9m without the written consent
of the Local Planning Authority. Reason: In the interests of the amenities of the
area and amenities of adjacent residential occupiers and to comply with
policy D1 (Standards of Design) of the IW Unitary Development Plan. |
6 |
The storeroom at ground floor level shall only be
used for storage purposes and no other use without the express written
consent of the Local Planning Authority. Reason: In the interests of the amenities of the
area and amenities of adjacent residential occupiers and to comply with
policy D1 (Standards of Design) of the IW Unitary Development Plan. |
7 |
The building hereby approved as hotel
accommodation shall not be sold off separately or sub-let from the main hotel
complex without the written prior consent of the Local Planning Authority. Reason: In the interests of the amenities of the
area and amenities of adjacent residential occupiers and to comply with
policy D1 (Standards of Design) of the IW Unitary Development Plan. |
8 |
Each unit of accommodation shall provide no more
than two bed spaces unless the express written consent of the Local Planning
Authority has been obtained for any such variation. Reason: In the interests of the amenities of the
area and amenities of adjacent residential occupiers and to comply with
policy D1 (Standards of Design) of the IW Unitary Development Plan. |
9 |
The proposed hotel annexe building shall not
interrupt the existing visibility splays as shown on the approved plan (ref.
no. 36-2003.B). Nothing that may
cause an obstruction to visibility shall at any time be placed or be
permitted to remain within that visibility splay. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway
Considerations) of the IW Unitary Development Plan. |
10 |
No building hereby permitted shall be occupied
until space has been laid out within the site in accordance with drawing no.
36-2003.2 for four bicycles to be parked.
The space shall not thereafter be used for any purpose other than that
approved in accordance with this condition. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
11. |
Reference
Number: P/01122/05 - TCP/03605/V Parish/Name: Seaview - Ward/Name: Seaview &
Nettlestone Registration
Date: 09/06/2005 -
Full Planning Permission Officer: Mr P Stack Tel: (01983) 823575 Applicant: Seaview Hotel & Restaurant Continued
use of buildings for guest & staff accommodation & associated office
space (The Studio, Methuen Suite & Jasmine Cottage) Seaview
Hotel & Restaurant, High Street, Seaview, Isle Of Wight, PO345EX |
This application is recommended for conditional
planning permission.
REASON FOR COMMITTEE CONSIDERATION Given that application TCP/3605/U (previous item)
is also being determined in respect of this site it is considered appropriate
for Members to consider both submissions at the same Committee meeting, but
on the understanding that each will be determined on its merits in accordance
with adopted policies. |
1. Details
of Application
1.1 This is a full application seeking
retrospective consent for the continued use of specific parts of the existing
premises as office space and accommodation for hotel staff within Jasmine
Cottage to use the Methuen Suite for guest accommodation and a studio flat
previously built as manager’s flat as hotel accommodation.
1.2 With regards the Methuen Suite and
Jasmine Cottage, these premises form the rear part to Bank House. The two storey element which comprises
Jasmine Cottage is used as office accommodation at ground floor level with
conservatory used specifically as manager's office, stairway leading to first
floor accommodation provides bathroom and two further rooms which are used
either as additional office floor space or provide sleeping accommodation for
staff. Jasmine Cottage comprises single
storey element which adjoins southern boundary of site and provides bed-sit
unit used as guest accommodation.
Whilst there are linking doorways to main property, Bank House, it is
understood that these units operate independently with main access gained through
west facing French windows.
1.3 To the rear of hotel is a studio flat
which was originally built as manager's accommodation. It is understood this has been used for some
considerable period of time as ancillary hotel accommodation. This building adjoins northern boundary of
application site.
2. Location
and Site Characteristics
2.1 Premises are located on western side of
High Street with return frontage and service yard accessed via accessed via Rope
Walk. The application site includes Bank House a Grade II Listed building which
building which adjoins main hotel premises and also fronts High Street.
2.2 Methuen Suite and Jasmine Cottage form
rear section of Bank House located close to southern boundary of application
site. Whilst Methuen Suite utilises ground floor accommodation Jasmine Cottage
occupies two floors of accommodation.
2.3 The
suite is located to the rear of the main hotel premises and adjoins the
northern boundary of the application site.
3. Relevant
History
3.1 Various
minor alterations and additions approved.
3.2 More recently consent granted in 1993
for two storey extension to provide manager’s accommodation, replacement beer
store and new external staircase. This consent restricted the manager’s
accommodation to be retained with the hotel as staff accommodation and not be
sold off separately or sub let from main building.
3.3 In 1999 consent granted for change of
use of dwelling to hotel accommodation. This involved Myrtle Cottage which
adjoins northern boundary of site.
3.4 More recently planning consent granted
for demolition of side wall of kitchen extension to enlarge kitchen and
provision of glazed link. Development approved in October 2004. Listed Building
Consent obtained at this time.
3.5 Three applications submitted in November
2004 seeking Lawful Development Certificates for accommodation within hotel
premises. These applications were
withdrawn at the request of the agent.
4. Development
Plan Policy
4.1 National Policies covered in PPG4 –
Industrial and Commercial Development and small firms, PPG15 – Planning and the
Historic Environment and PPG21 – Tourism.
4.2 Site lies within Development Envelope
Boundary and Seaview Conservation Area with Bank House comprising Grade II
Listed Building. The following policies are considered relevant to
consideration of this application:
G1
– Development Envelopes for Towns & Villages
G4
– General Locational Criteria for Development
D1
– Standards of Design
B3
– Change of Use of Listed Buildings
B6
– Protection and Enhancement of Conservation Areas
T1
– Promotion of Tourism and Extension of the Season
T2
– Tourist Related Development
T3
– Criteria for Development of Holiday Accommodation
TR7
– Highway Considerations for New Development
TR16
– Parking Policies and Guidelines
5. Consultee
and Third Party Comments
5.1 Internal
Consultees
·
Highway Engineer does not wish to comment on
application.
·
Environmental Health Officer has been consulted and
confirmed that no complaints concerning noise have been received.
·
None
5.3 Parish
Council comments
19
letters have been received from local residents objecting the proposal on the
following grounds:
·
Undesirable impacts on and use of listed building
·
Potential problems from use of rear garden by
occupiers/staff of accommodation concerned
·
Contrary to Unitary Development Plan Policy
·
Increased problems relating to noise, pollution and
traffic
·
Lack of increase in off street parking
·
Inappropriate development for conservation area.
·
Resultant lack of privacy
6. Evaluation
6.1 The
main issues relating to this application are:
·
Planning policy
·
Potential impact on Conservation Area and Listed
Building.
·
Any potential impacts on residential occupiers.
·
Highways.
6.2 In terms of policy UDP generally
supports and promotes tourist development provided such proposals minimise any
detrimental or adverse impacts (Policy T1).
Policy T3 also supports development of holiday accommodation where they
are associated with an existing permanent accommodation site and that
development will be retained for holiday use only. Additionally Policy T2 supports other tourist related
developments other than accommodation which would include provision of infrastructure,
i.e. staff and office accommodation.
Similarly Policy T8 supports in principle ancillary development
associated with tourism uses.
6.3 In terms of policy implications in
respect of Conservation Area and Listed Building, Policy B6 and Planning (Listed
Buildings and Conservation Areas) Act 1990 requires applications to preserve or
enhance the character or appearance of Conservation Areas whilst Policy B3
supports applications for change of use of Listed Buildings provided that
alternative will not detrimentally affect long term of structure of building
and will preserve any historic or special architectural features it
possesses. Advice in PPG15 states that
generally best way of securing upkeep of historic buildings and areas is to
keep them in active use. For the great
majority this means economically viable uses, and new and even continuing uses
will often necessitate some degree of adaption. Guidance goes on to state that whilst best use will very often be
use for which building was originally designed, not all original uses are
viable or even necessarily appropriate, nature of uses can change over time so
that in some cases the original use may now be less compatible with building
than an alternative. PPG15 guidance
therefore suggests that provided the fabric interior and setting of the
historic building is maintained then appropriate alternative uses are
acceptable. Conservation Officer
confirms that uses themselves are not harmful to character or setting of Listed
Building.
6.4 With regards impacts on residential
amenity, whilst retrospective nature of application is disappointing this is
not a material consideration as Section 73A of Planning Act does provide formal
procedure for Local Planning Authorities to grant planning permission with retrospective
effect. I understand that these uses
have existed for some time, and in particular the Studio apartment has, it is
alleged, been used as guest accommodation for the majority of time since it was
approved in 1993. Furthermore the hotel
use on this site has existed for a long period of time without any significant
complaint or objection.
6.5 Whilst merits of application should be
judged as if fresh submission it is relevant to note that no formal complaints
have been received by the Environmental Health Division of this Authority in
respect of noise levels emanating from the hotel premises. Methuen Suite provides small bedsit unit
immediately adjoining southern boundary of site with staff accommodation more
centrally sited with doorways and window openings facing into main site. Studio apartment has been used as a single
bedroom guest accommodation and is accessed from central courtyard area. It should be noted that proposal only
involves additional two units of guest accommodation, with the remainder of
accommodation comprising office floor space and occasional overnight staff
accommodation. Given the long
established nature of hotel premises it is considered that these uses in
themselves, given their location and use to which the buildings are put, are
unlikely to have detrimental impacts on residential amenity for adjoining
occupiers. Consideration should also be
given to fallback position as it is likely that any alternative use of this
accommodation would be for some form of ancillary accommodation in connection
with established hotel premises and would inevitably involve commercial use of
some sort. Such alternative use may
well involve more intensive use of site, for example by utilising existing
office accommodation and occasional staff accommodation as additional guest
accommodation, thereby further intensifying use of site.
6.6 In terms of highway implications,
Highway Engineer's reluctance to comment is understandable given comments
contained in previous paragraph, as any alternative use of buildings would have
similar implications in terms of parking provision and application of parking
policy within adopted UDP.
7. Conclusion
and Justification for Recommendation
7.1 Given established commercial nature of site
it is considered that proposal, in seeking to retain two guest units and
existing office and staff accommodation facilities, would have no material
impacts on general locality in terms of Conservation Area status, is neutral in
terms of its impact on the Listed Building and would not unduly harm amenities
of surrounding residential occupiers.
8. Recommendation
To
grant conditional permission.
Conditions/Reasons:
The accommodation hereby approved within Jasmine Cottage shall only be used for hotel administrative purposes and as staff accommodation and for no other use without the express written consent of the Local Planning Authority. Reason: To enable the Local Planning Authority to control
the future commercial activity of the existing hotel premises and to comply
with Policy D1 (Standards of Design) of the adopted Unitary Development Plan. |
|
2 |
The garden area to the immediate rear (west) of
the Methuen Suite and Jasmine Cottage shall not be used as a sitting out area
or for any ancillary use in connection with the operation of the hotel
without the express written consent of the Local Planning Authority. Reason: To enable the Local Planning Authority to
control the future commercial activity of the existing hotel premises and to
comply with Policy D1 (Standards of Design) of the adopted Unitary
Development Plan. |
12 |
Reference
Number: P/01036/05
- TCP/10228/V Parish/Name: Ryde - Ward/Name: Ryde St Johns West Registration
Date: 27/05/2005 -
Full Planning Permission Officer: Mr A White Tel: (01983) 823550 Applicant:
Mr J W Hetherington Demolition
of dwelling; erection of eight flats in two blocks and one semi-detached
house with parking and alterations to access (revised scheme) Jalna,
Appley Rise, Ryde, Isle Of Wight, PO331LE |
This is a Joint Report with P/01037/05 – the
application is recommended for conditional permission.
REASON FOR COMMITTEE CONSIDERATION The local Member, Councillor J Bowker, has
requested that this application is considered by the Development Control
Committee for the following reason: "The development of this site for increased
residential purpose would result in undesirable arrangement of dwellings,
which would prejudice the privacy of neighbouring properties, as well as
being contrary to the prevailing pattern of construction in the locality, and
would create an undesirable precedent for this form of development.” |
1. Details
of application
1.1 This Report considers two
applications. One is a Conservation
Area Consent to demolish the existing bungalow and the other seeks full
planning permission to redevelop the site with 8 flats and a house.
1.2 Conservation Area Consent is sought to
demolish a 1960s style bungalow of buff brick construction under a concrete
tile roof. This bungalow is considered
to have little in the way of architectural merit.
1.3 The proposed development is divided into
two blocks offering a total of 9 dwellings within two/three storey
buildings. The western block would
contain 5 flats and is shown as being two storey adjacent the common boundary
with Marine Lodge, stepping up to three storey towards the centre of the site. The eastern block would compromise 3 flats
within a three storey building stepping down to an octagonal shaped single
dwelling which is mainly arranged over two floors but with a study within a
turret type feature at second floor level.
1.4 The front elevation overlooking the
boating lake is well articulated both in terms of its broken ridge line and
staggered layout. The development is
shown to have north facing gable features and balconies with overall proportions
being vertically emphasised, reminiscent of nearby Victorian style properties
in terms of overall scale, mass and detailing.
Balconies that were originally shown to wrap around three sides of the
octagonal building have been deleted from the scheme as they appeared
contrived. Balcony also deleted from
the western end of the building, closest to the neighbour at Marine Lodge. Buildings would be constructed of buff brick
with stone features under a natural slate roof. Windows are shown to be white painted timber vertical sliding
sashes and the metalwork to the balconies would be similar in pattern and
colour to those on adjoining buildings.
1.5 Proposed layout makes provision for 7
parking spaces with access off Appley Rise.
Bicycle parking and a bin storage area is also indicated.
2. Location
and site characteristics
2.1 This is an irregular shaped site which
is situated on the north-eastern side of Appley Rise, bounding Bird Cage Walk
to the north and overlooking Ryde Boating Lake and the Esplanade. Site falls away steeply in a northerly
direction. As said, the existing
property comprises of a 1960s style bungalow which is arguably out of context
within an area which is mainly characterised by substantial Victorian
buildings. Of particular note is
Wilmington, which is a large Victorian building occupied as flats immediately
south-east of the application site.
North-west of the site is a small group of Victorian style villas which
have recently undergone renovation, conversion and some new build, and these go
under the name of Marine Lodge and Melmouth Lodge.
3. Relevant
history
3.1 P/2169/04-TCP/10228/S – Full permission
refused in April of this year for 8 flats and a single dwelling. Reasons for refusal refer to excessive scale
relative to adjoining buildings which in turn would have resulted in an
intrusive and overbearing development detrimental to adjoining residents and
the surrounding area in general.
Proposed parking layout was also considered to be inadequate.
3.2 P/2313/04-CAC/10228/T – Conservation
Area Consent refused in April of this year on the grounds that proposal did not
provide for a suitable replacement building, leaving an unsuitable gap in the
Conservation Area.
3.3 Both
of the above are subject of an appeal to the Planning Inspectorate.
4. Development
plan policy
4.1 PPS1 (Delivering Sustainable
Development) stresses the need for good design to ensure that spaces and places
are attractive, usable and durable for people.
Designs which are inappropriate in their context and/or failing to improve
the character and quality of an area should not be accepted. Good design should:
·
be integrated into the existing urban form and
natural built environment.
·
optimize the potential for site to accommodate
development.
·
respond to local context and create and enforce
local distinctiveness.
·
be visually attractive as a result of good
architecture and appropriate landscaping.
4.2 PPG3 (Housing) stresses the need to make
efficient use of land, but states that this should not be at the expense of
cramped development prejudicial to the surrounding environment. Whilst advocating higher densities, it is
stressed that good design is key in order to create attractive, high quality
living environments in which people will choose to live. It is suggested that housing developments
achieve between 30 and 50 dwellings per hectare, and higher where good links
with public transport exist.
4.3 PPG15 (Planning and the Historic
Environment) states that special attention must be paid to ensuring
preservation and enhancement of the character and appearance of Conservation
Areas and states that applicants should be expected to provide written
information and/or drawings indicating their understanding of the context of an
area.
4.4 In terms of Local Plan Policies, site is
within the development envelope boundary for Ryde and is within the St John’s
Conservation Area. Relevant policies
are as follows:
S1
- New developments will be
concentrated within existing urban areas.
S6
- All developments will be expected
to be of a high standard of design.
S10
- Areas of historic value.
G1
- Development envelopes for towns and
villages.
G4
- General locational criteria for
development.
G5
- Development outside defined
settlements.
D1
- Standards of design.
D2
- Standards for development within
the site.
B6
- Protection and enhancement of
Conservation Areas.
H4 - Unallocated residential development to be restricted to defined
settlements.
H5
- Infill development.
H6
- High density residential
developments.
TR7
- Highway considerations for new
developments.
TR16
- Parking policies and guidelines.
U11
- Infrastructure and services
provision.
4.5 Site is within Zone 2 in respect of the
Council’s parking policies which require the developer to provide a maximum of
0 to 50% of parking guidelines. Parking
guidelines require a parking space per bedroom.
5. Consultee
and third party comment
5.1 Internal
consultees
·
Highway Engineer recommends conditions should
application be approved.
·
The Council’s Conservation Officer confirms that
the reduction in height and separation
into blocks has reduced the overall impact and improved the relationship to
existing buildings compared to the scheme that was recently refused. He confirms that the area is characterised
by large Victorian buildings of varying heights which are influenced by the
local topography and that this proposal would respect the existing pattern of
development. It is considered that the
revised proposal has addressed previous concerns, but does suggest conditions
in respect of external materials and other details such as windows, balconies
and decorative gable features.
5.2 Neighbours
3
letters received from neighbouring property occupiers who object on grounds
which can be summarised as follows:
·
Inappropriate scale and mass.
·
Too high.
·
Out of character.
·
Overlooking.
·
Loss of light.
·
Inadequate parking.
·
High flood risk area.
·
Inadequate drainage.
·
May undermine stability of boundary stone wall
between site and Marine Lodge.
6. Evaluation
6.1 Bearing in mind the site is within the
development envelope boundary and is currently in residential use, it is
considered that the principle of developing this site more intensively is
acceptable. The determining factor is
whether the site can be developed as proposed without being detrimental to the
amenities currently enjoyed by neighbouring property occupiers or the character
of the surrounding area in general, which Members will note is a designated
Conservation Area. In order to make
this assessment, it is necessary to compare the proposed scheme with the recent
refusal and to address the following issues:
·
Density
·
Scale, mass and height
·
Design
·
Access and parking
·
Drainage.
6.2 Members will be aware that local and
national policies in respect of housing encourage the efficient use of land,
with PPG3 advocating densities of between 30 to 50 dwellings to the hectare,
and higher where good links to public transport can be achieved. Such advice is echoed in Policy H6 of the
UDP. It is inevitable that flats result
in higher densities, hence the proposed scheme would amount to some 81
dwellings to the hectare. Policy does
not rule out densities in excess of 50 dwellings to the hectare, and it is
relevant to note that the site does lie within a level walking distance of bus
and railway stations as well as cross-Solent ferry terminals. Accordingly, the application site is
considered to be a suitable candidate for high density development given
accessibility to public transport and its location within a built-up area. However, the main test in respect of any
residential development is whether or not the site can accommodate a given
number of units without being at the expense of cramped development to the
detriment of neighbouring property occupiers or the surrounding area in
general. But to refuse this application
on the grounds of excessive density alone would be unsustainable.
6.3 One of the principal concerns in respect
of the refused scheme was the overall height of the development and, in
particular, the poor relationship that would have resulted with adjoining
buildings. The revised scheme before
Members indicates that better use would be made of the steep slope and a
reduction in height. The combined
effect of these changes is that the proposed development is between 1 and 2
metres lower than the refused scheme.
These changes, coupled with the articulated nature of the proposed
design, show a development that appears sympathetic to the prevailing scale and
height of surrounding buildings. The
western block, although having a higher ridge level, does not appear
excessively large in relation to the neighbouring building at Marine
Lodge. Although having a higher floor
level compared to the said property, this relationship is generally reflective
of the local topography and would respect the existing pattern of
development. The most significant
reduction in height compared to the refused scheme is the point where the
proposed development sits forward of Wilmington. The benefits of this reduction are twofold. Firstly, the revised scheme would not be as
overbearing as the refused development and secondly, important views of
Wilmington from a northerly direction would remain much intact. Accordingly, the revised proposals have
satisfactorily addressed the previous concern in respect of scale, mass and
particularly height, meaning that proposal complies with requirements of
Policies G4 and D1.
6.4 The proposed design is consistent with
the appearance of Victorian buildings in this part of Ryde and elements of the
proposed detailing are reflective of the recent development on adjoining land
to the west. Agent has agreed to revise
north elevation in order to resolve concerns regarding overproliferation and
appearance of balconies. The remaining
balconies appear integral to the overall design. The choice of the proposed materials, including timber sliding
sash windows and stone detailing, is sympathetic to surrounding building
styles. Accordingly, proposed design
respects the distinctiveness of the surrounding area and therefore complies
with policies G4 and D1 in this respect.
In considering that proposal would be more reflective of prevailing
building styles than the existing 1960s bungalow, it is felt that proposal
would enhance the character and appearance of the Conservation Area and
therefore accords with Policy B6 in this respect.
6.5 The existing bungalow, although of
little architectural merit, is low key and has little physical impact on the
occupants of adjoining buildings. It is
inevitable that the proposal, being that much larger than the existing
property, would have a greater impact but this is not considered to be of such
significance as to justify withholding consent. The rear yard area to Marine Lodge enjoys very little in the way
of privacy although it would be beneficial to obscure glaze certain windows
that face in this direction. The
occupant of Marine Lodge is concerned that there could be a conflict between
one of his balconies and a balcony serving a proposed flat. However, any conflict would be no worse than
existing views into the objector’s balcony from the application site and the
adjoining public footpath at Bird Cage Walk.
The fragmented nature of the proposed development would help reduce its
overall bulkiness relative to adjoining properties.
6.6 In terms of access, the revised scheme
has overcome the concerns expressed by the Highway Engineer in respect of
visibility. The proposed parking layout
is now considered to be workable.
Whilst seven spaces as shown would fall short of one space per unit,
this level of parking is considered to be acceptable given that site is within
Zone 2 of the parking guidelines and that a range of public transport is easily
accessible. Fundamentally, proposal is
consistent with the objective of reducing reliance on the motor car.
6.7 In terms of drainage, it is proposed to
dispose of foul sewage and surface water into the existing combined system in
Esplanade South. There is no evidence to
suggest that there is a capacity problem with this system, but it is advisable
to impose a condition to ensure that adequate provision has been made before
work commences. Concern in respect of
surface water runoff will be controlled under the Building Regulations.
6.8 In terms of other concerns, site is not
shown as being at risk on Environment Agency flooding maps. There are no specific ground stability
concerns in respect of this site, and the developer will have a duty of care
insofar as neighbour property is concerned.
This will also be monitored under the Building Regulations. Therefore neither concern presents a
justifiable reasons to withhold consent.
7. Conclusion
and justification for recommendation
7.1 Having given due regard and appropriate
weight to all material considerations referred to in this report, it is
considered that proposal would strike the balance of making efficient use of
this brownfield site but not at the expense of adjoining property occupiers or
the surrounding area in general. In
respect of the latter, your Officers are of the view that the proposal,
although much larger than the existing bungalow, would preserve and arguably
enhance the character and appearance of the Conservation Area as it is more
reflective of surrounding buildings than the existing 1960s bungalow. It is also considered that a more intensive
use of this site can be adequately served in terms of access, parking and
drainage. In summary, proposal would
result in a pleasing and sustainable addition to the surrounding townscape and
therefore accords with the policies and objectives of the Unitary Development
Plan.
8. Recommendation
Conditional
permission be granted in respect of both applications.
Conditions/Reasons:
The development hereby permitted shall be begun before the expiration of 5 years from date of this permission. Reason: To comply with Section 91 of the Town and
Country Planning Act 1990. |
|
2 |
No development shall take place until samples of
the materials and finishes to be used in the construction of the external
surfaces of the development hereby permitted have been submitted to and
approved in writing by the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with policy D1 (Standards of Design) of the IW Unitary
Development Plan. |
3 |
No development shall take place until details of
balconies and decorative gable features, including materials, design and
colour, have been submitted to and approved in writing by the Local Planning
Authority. Development shall be
carried out in accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with Policy D1 (Standards of Design) and B6 (Protection
and Enhancement of Conservation Area) of the IW Unitary Development Plan. |
4 |
No development shall take place until details,
including material, dimensions and colour, of all windows and doors have been
submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in
accordance with the approved details. Reason: In the interests of the amenities of the
area and to comply with Policy D1 (Standards of Design) and B6 (Protection
and Enhancement of Conservation Area) of the IW Unitary Development Plan. |
5 |
No development shall take place until a detailed scheme,
including calculations and capacity studies, have been submitted to and
agreed in writing with the Local Planning Authority indicating the means of
foul and surface water disposal. Any
such agreed foul and surface water disposal system shall include connection
points on the system where adequate capacity exists. Including any reasonable repairs which may
be required, or shall provide for attenuation measures to ensure any
additional flows do not cause flooding or overload the existing system. No dwelling shall be occupied until such
systems have been completed in accordance with the approved details. Reason: To ensure an adequate system of drainage
is provided for the development in accordance with Policy U11 (Infrastructure
and Services Provision) of the IW Unitary Development Plan. |
6 |
No development shall take place until full
details of both hard and soft landscape works have been submitted to and
approved in writing by the Local Planning Authority and these works shall be
carried out as approved. These
details shall include proposed finished levels or contours; means of
enclosure; car parking layouts; other vehicle and pedestrian access and
circulation areas; hard surfacing materials; minor artefacts and structures
(eg. furniture, play equipment, refuse or other storage units, signs,
lighting, etc); retained historic landscape features and proposals for
restoration, where relevant. Reason: To ensure the appearance of the development
is satisfactory and to comply with policy D3 (Landscaping) of the IW Unitary
Development Plan. |
7 |
No development shall take place until there has
been submitted to and approved in writing by the Local Planning Authority a
scheme of landscaping, which shall include indications of all existing trees
and hedgerows on the land, and details of any to be retained, together with
measures for their protection in the course of development. Reason: To ensure the appearance of the
development is satisfactory and to comply with policy D3 (Landscaping) of the
IW Unitary Development Plan. |
8 |
All planting, seeding or turfing comprised in the
approved details of landscaping shall be carried out in the first planting
and seeding seasons following the occupation of the buildings or the
completion of the development, whichever is the sooner, and any trees or
plants which within a period of 5 years from the completion of the
development die, are removed or become seriously damaged or diseased shall be
replaced in the next planting season with others of similar size and species,
unless the Local Planning Authority gives written consent to any variation. Reason: To ensure the appearance of the
development is satisfactory and to comply with policy D3 (Landscaping) of the
IW Unitary Development Plan. |
9 |
No dwelling hereby permitted shall be occupied
until space has been laid out within the site in accordance with drawing
number 2614-04-A (Rev 2) for 7 cars to be parked and for vehicles to turn so that
they may enter and leave the site in forward gear. The space shall not thereafter be used for any purpose other
than that approved in accordance with this condition. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
10 |
Prior to commencement of the development hereby
approved, the roadside boundary of the site shall be lowered to a maximum of
1 metre in height above existing road level over the whole frontage and shall
be maintained thereafter at a height no greater than one metre. Reason: In the interests of highway safety and to
comply with policy TR7 (Highway Considerations) of the IW Unitary Development
Plan. |
11 |
The lower half of all sash windows serving
bedrooms and lounges in the west elevation identified yellow on the approved
floor plans shall be fitted with obscure glass with a glass panel which has
been rendered obscure as part of its manufacturing process to Pilkington
Glass classification 5 (or equivalent of glass supplied by an alternative
manufacturer) and shall be retained to this specification as obscure glazed
hereafter and shall be fixed shut at all times. Reason: In the interests of the amenities and
privacy of the adjoining property occupier and to comply with Policy D1
(Standards of Design) of the IW Unitary Development Plan. |
12 |
The two bathroom windows in the western elevation
identified by brown on the approved floor plan shall be fitted with obscure glass
with a glass panel which has been rendered obscure as part of its
manufacturing process to Pilkington Glass classification 5 (or equivalent of
glass supplied by alternative manufacturer) and shall be retained to this
specification as obscure glazed hereafter. Reason: In the interests of the amenities and
privacy of the adjoining property occupier and to comply with Policy D1
(Standards of Design) of the IW Unitary Development Plan. |
13 |
No development shall take place until details of
any openings to those windows specified under conditions 11 and 12 have been
submitted to and approved in writing by the Local Planning Authority. Such details shall include the height of
opening sections above respective floor level. Development shall only proceed in accordance with the agreed
details and shall be retained and maintained thereafter. Reason: In the interests of the amenities and
privacy of the adjoining property occupier and to comply with Policy D1
(Standards of Design) of the IW Unitary Development Plan. |
14 |
No development shall take place until details
have been submitted to and approved in writing by the Local Planning
Authority of the positions, design, materials and type of boundary treatment
to be erected. The boundary treatment
shall be completed before the dwellings hereby permitted are occupied. Development shall be carried out in
accordance with the approved details. Reason: In the interests of maintaining the
amenity value of the area and to comply with policy D1 (Standards of Design)
of the IW Unitary Development Plan. |
13. |
Reference
Number: P/01037/05
- CAC/10228/U Parish/Name: Ryde -
Ward/Name: Ryde St Johns West Registration
Date: 27/05/2005 -
Conservation Area Consent Officer: Mr A White Tel: (01983) 823550 Applicant:
Mr J W Hetherington Conservation
Area Consent for demolition of dwelling in connection with erection of eight
flats in two blocks and one semi-detached house with parking and alterations
to access (revised scheme) Jalna,
Appley Rise, Ryde, Isle Of Wight, PO331LE |
This is a Joint Report with P/01036/05 - the
application is recommended for conditional permission.
Conditions/Reasons:
1 |
The works hereby authorised shall be begun not later than 5 years from the date of this consent. Reason: As required by s18 Planning (Listed
Buildings and Conservation Areas) Act 1990. |
2 |
The works of demolition hereby authorised shall not
be commenced until a binding contract for the carrying out of the works of
redevelopment of the site has been entered into and planning permission has
been granted for the redevelopment for which the contract provides. Reason: In order to protect the special character
of the area and to prevent the site remaining vacant for a significant period
of time and to comply with policies B1 to B8 (Listed Buildings and
Conservation Areas) and D1 (Standards of Design) of the IW Unitary
Development Plan. |
3 |
The existing dwelling shall be demolished, all
resultant debris and material shall be carted away and the site left in a
tidy and workmanlike condition within a period of three months from when
demolition work first commences. Reason: To protect the character and appearance of
the Conservation Area and to comply with policy B6 (Protection and
Enhancement of Conservation Areas) of the IW Unitary Development Plan. |
14. |
Reference
Number: P/01060/05 - TCP/26954/A Parish/Name: Calbourne - Ward/Name: Brighstone and
Calbourne Registration
Date: 14/06/2005 -
Full Planning Permission Officer: Mrs J Penney Tel: (01983) 823593 Applicant:
Mr & Mrs S F Biles Demolition
of single storey extension; proposed
single/2 storey extension to provide additional living accommodation (revised
scheme) Downsview,
Lynch Lane, Calbourne, Newport, PO30 |
The application is recommended for Refusal.
REASON FOR COMMITTEE CONSIDERATION The local Member, Councillor C West, has
requested that this application is considered by the Development Control
Committee for the following reasons: 1. Application
is fully supported by the Parish Council and the applicant's neighbours. 2. The
applicant has compiled a large document supporting his claim. 3.
The openness and transparency that the full Committee can give to this
application will be of benefit to the local residents. Chairman Councillor A Taylor subsequently
submitted information: 1. Architect
designed building using local materials not detrimental to character of area. 2. Larger
than policy guidelines but part built into ground. 3. Building
situated in large area with no neighbouring properties and no objections. 4. Extension
required as applicant has large family. |
1. Details
of application
1.1 This
is a full application.
1.2 Proposal is a revised scheme and
comprises demolition of single storey non-habitable outbuildings which appears to
have been long-standing and for calculation purposes in terms of assessing
acceptable volume increases has been treated as part of the original
dwelling. Large two storey projection
to the rear of the dwelling with additional single storey elements. The proposed scheme clearly shows a level
plot throughout. Applicant has
submitted supporting information as to why he considers scheme should be
supported. The existing cottage
comprises four bedrooms, four rooms on the ground floor (including a kitchen)
but lacks a bathroom or any internal WC facilities. The scheme proposes the creation of an upstairs bathroom/WC by
partial subdivision of a bedroom.
2. Location
and site characteristics
2.1 The site is located in a rural area to
the south of the main Calbourne village, on the eastern side of Lynch Lane
immediately to the south of a small group of farm buildings. The area is open countryside with
traditional character buildings with no large modern extensions noted in the
locality.
2.2 The site is within the AONB, is highly visible from the lane and is set
against rising land to the rear and open land to the south, with limited
boundary screening. The dwelling is of
traditional materials of some character, in a poor state of repair and appears
to have been unoccupied for some time.
3. Relevant
history
3.1 TCP/26954-P/627/05 - application for
demolition of single storey extension; proposed single storey and single/two
storey extension to provide additional living accommodation. Approved May 2005.
3.2 The previous application followed
lengthy negotiations to produce a scheme that was marginally acceptable both in terms of design, size, siting and
in accordance with policy.
4. Development
Plan policy
4.1 Development national policies are
contained in PPS1 (Delivering Sustainable Development); PPS7 (Sustainable
Development in Rural Areas).
4.2 Relevant
Unitary Development Plan policy:
S4 - The
countryside will be protected from inappropriate development.
S6 - All
development will be expected to be of a high standard of design.
S10 - If it will
conserve or enhance the features and special character of these areas.
G4 - General
Locational Criteria for Development
G5 - Development
Outside Defined Settlements
C1 - Countryside
will be protected from inappropriate development
C2 - Areas of
Outstanding Natural Beauty
D1 - Standards of
Design
H7 - Extension and
alteration of existing properties.
5. Consultee
and third party comments
5.1 Internal
Consultees
Area of Outstanding Natural Beauty
Officer is of the view that previous scheme followed a number of
pre-application discussions resulting in consent for the site. Of view it is unfortunate that the revised
scheme has been submitted seeking to amend this approval. AONB Partnership does not consider revised
scheme represents a significant departure from approved scheme. Accept proposal seeks to increase volume of
dwelling; this is not significant in terms of its impact upon the designated
area. Re-iterate support for sympathetic restoration and re-use of Downsview
which will be an enhancement to the area over its current derelict
appearance. Therefore raises no
objection to revised proposal.
5.2 Town
or Parish Council Comments
A letter on behalf of Calbourne
Parish Council supporting the scheme as proposal is subservient, not
obtrusive. Consider it of appropriate
scale to dwelling and character of area.
Practical improvement to family's living space and dwelling better cared
for when lived in and their needs better met if extra accommodation is
approved. (Written on behalf of the
Parish Council by a supporter of the scheme and possibly an informal comment).
Subsequently a
further formal comment from the Clerk to the Parish Council which states “would like it to be noted that there
are no objections”.
5.3 Neighbours
10 comments in support of
application have been received. It
should be noted that the content of much of the communication appears to have
been duplicated (several being close to being pro forma letters) and not all
from immediate neighbours. (E.g. Cowes,
Yarmouth, Newport and Southampton).
Support relates to development
being in keeping with the existing dwelling and character of area, being
marginally different from existing approval.
At last the property will be cared for and will be of benefit to local
school, shops and post office and rural area bringing disused dwelling back
into village. Scheme reflects intentions
of PPS7 and PPG3 and will enhance the area and improve appearance.
6. Evaluation
6.1 The
main issues relating to this application are:
·
Policy
·
The scale, mass and design of the proposal
·
Impact on the character of the original property
and surrounding area.
6.2 With regard to policy, there is no
objection in principle to an extension on the site subject to appropriate size
and design as evidenced by the permission already granted. Volume calculations in respect of the recently
approved scheme represents a 34% increase.
Calculations on this current scheme represent a 54% increase. The Council’s adopted Supplementary Planning
Guidance states “As a guideline extensions are more likely to be acceptable if
they do not exceed 35% of the volume of the original dwelling”. It advises against very large extensions, which dominate the existing house or
introduce a fundamental and often damaging change to the landscape
character. Extensions in excess of a
35% volume increase will be assessed primarily on the impact of the resulting
dwelling, in terms of its size, design and siting. The extension of existing buildings must be of a scale and
character appropriate to the locality.
6.3 In floorspace terms the original dwelling not including the
non-habitable outhouses has a gross externally measured floorspace of
170m2. The extensions proposed will
double the area of the ground floor and with the part first floor proposed add
a further 102m2 – a 73% increase. The
original outbuildings extended to approximately 35m2. The permitted scheme was more modest comprising an extension of
around 50m2 at ground floor and 30m2 above; a total 57% increase.
6.4 Due to the increased width of the
proposal, the roof pitch is now pushed
up higher, resulting in development that does not read as a subservient
addition; also the two storey element is now deeper and the single storey
element larger. The proposal will be
very visible when travelling north-east as there is limited screening on this
boundary, and it is considered that a landscaping scheme would not mitigate
this factor.
6.5 For
information the submitted plans are inaccurate insomuch as the elevational
details show different roof designs.
6.6 The previously approved scheme represented
significant alteration to this countryside property which could be accommodated
subject to appropriate materials and in accordance with policy. The differences in the current scheme in
terms of volume and design and the resultant visual impact particularly from
the road is significant and justifies a refusal. Given the facts set out above your officers have concluded that
the previous scheme was the maximum that could reasonably be accommodated to
enable the original property to remain as the dominant feature. The increase in this scheme will result in a
scheme that does not complement the host dwelling and is not of appropriate
size and design.
6.7 With regard the property being brought
back into use and supporting the village, the originally approved scheme
enables this. Personal circumstances of
the applicant do not override the planning policies. Members are advised that
the Parish Council’s supposed support is not a valid planning consideration and
no weight can be given to the large document in support compiled by the
applicant except in so far as it refers to material planning
considerations. That it is architect
designed is not in itself a reason to grant permission and it is only
reasonable to expect the use of local materials which the permitted scheme
already does (designed incidentally by the same architect). None of the building or the proposed
extension is shown on the submitted plans as being below ground level and hence
there is no “trade off” against policy guidelines. The lack of objections, is not a material planning consideration
and the policy/SPG are intended to cover houses in the open countryside. The personal needs of the applicant are
totally irrelevant as are the applicants qualifications and experience, matters
relating to capital gains tax, the size of the family or number of children or
a threat to leave the premises vacant or to seek in the alternative a
permission to replace Downsview.
6.8 The Local Planning Authority have
successfully defended relevant appeals to the Planning Inspectorate. In particular TCP/1152/E Meadcott, Heathfield Road, Bembridge, April
2003 – urban area. In this case, the
Inspector was concerned about the bulk and mass of a proposal. TCP/15212/C, South View Grange, Bagwich
Lane, Rookley – June 2004 – rural area where main issue effect on the character
and appearance of surrounding countryside.
Inspector referred to unspoilt and deeply rural character and existing
dwelling unobtrusive within attractive rural landscape because of its modest
scale and proportions. In this scheme,
he noted the proposal was architecturally designed to be compatible with the
existing dwelling and not visible from front of house; the Inspector was
concerned about the substantially greater depth and overall bulk that seriously
harmed the distinctive character and appearance of the surrounding
countryside.
7. Conclusion
and justification for recommendation
7.1 It is important that Members are aware
that often what may be read on plan form as small changes to schemes can make
the difference of it being acceptable or not.
Based on experience on appeals and professional judgment, It is
considered the changes in the current proposal compared to the approved scheme
are significant not only in terms of the volume increases but as importantly
how the resultant building and design fits in with the original property and
the impact on the visual amenity of the area.
If Members are minded to approve the application, the current policies
and guidance will be undermined. It is
your officers view therefore that the appropriate test of these policies
is through the appeal process.
7.2 Having
given due regard and appropriate weight to all material considerations, your
officers consider that the proposal is unacceptable by reason of size, siting
and design and is contrary to adopted
Policy. There is an approved
scheme which can be implemented; personal circumstances and letters of support
do not outweigh the policy considerations.
8. Recommendation
Refusal
Conditions/Reasons:
The proposed extension because of the scale, mass, siting and design, would be an intrusive addition, out of scale and character with the existing dwelling and have a serious and adverse effect on the visual amenity of the locality and landscape character. The proposal would therefore be contrary to Policies S6 (To Be Of A High Standard of Design) G4 (General Locational Criteria for Development), D1 (Standards of Design), H7 (Extension and Alteration of Existing Properties) and C1 (Protection of Landscape Character) of the Isle of Wight Unitary Development Plan and Isle of Wight Supplementary Planning Guidance – Extending Your Home. |