PAPER B

 

Committee:                AUDIT AND PERFORMANCE COMMITTEE

 

Date:                          21 SEPTEMBER 2006

 

Title:                            INTERNAL AUDIT OUTCOMES REPORT

 

REPORT OF THE CHIEF INTERNAL AUDITOR

___________________________________________________________________

 

PURPOSE

 

1.                  This report is to provide the Committee with a summary of Internal Audit activity completed since the last outcomes report to the Committee in May 2006.

 

2.                  The Committee is invited to note the contents of the report and to seek clarification of any issues arising from audits undertaken.

 

BACKGROUND 

 

3.                  In keeping with good corporate governance practice, a Committee of elected members should have oversight of the activities of the Internal Audit Service for the following purposes:

 

·        The Committee should monitor Internal Audit’s performance, both in terms of the quality and quantity of its work;

 

·        The Committee should satisfy itself that Internal Audit has devoted its attention to the appropriate issues;

 

·        The Committee should consider the results of Internal Audit reviews to ensure that any significant findings are addressed, including control weaknesses and to ascertain whether, in the opinion of the Chief Internal Auditor, adequate and satisfactory responses have been given by the Authority’s management;

 

·        The Committee should recommend, if necessary, that further attention should be given to some of the issues raised;

 

4.                  To facilitate this process, attached as Appendix 1, are reports of significant audit work completed since the May 2006 report to the Audit Committee.

 

FINANCIAL, LEGAL, CRIME AND DISORDER IMPLICATIONS

 

There are no significant financial or legal implications of this report, given that it is a progress report on the Internal Audit function. The Committee is reminded that the Council is required by statute (the Accounts and Audit Regulations) to have an adequate and effective Internal Audit function.

 


RELEVANT PLANS, POLICIES, STRATEGIES AND PERFORMANCE  INDICATORS

 

None.

 

CONSULTATION PROCESSES

 

None.

 

BACKGROUND PAPERS USED IN THE PREPARATION OF THIS REPORT

 

Audit project files held by G Richardson

 

APPENDICES ATTACHED

 

None

 

Contact Point:  Ged Richardson, ( 3683, Email:  [email protected]

 

 

 

 

GED RICHARDSON

Chief Internal Auditor

 

 

 


APPENDIX 1

A: AUDIT SERVICES REPORT – CAR PARKS

 

 

EXECUTIVE SUMMARY

 

1.         INTRODUCTION

 

1.1       The audit was carried out as part of the Audit Plan. The plan was developed using a risk based approach with the Car Park Service being scored as a B on a scale of A - D with A being considered the highest risk.

 

1.2              A risk workshop was held with two Auditors, the Traffic and Transportation Manager, the Car Parks Manager and members of the Car Parks Service. At this workshop the main objectives of the service were established, and the key risks identified and scored for impact and likelihood. A Risk Register was produced that listed all 44 risks identified; 14 key risks were then identified and these were scored for impact and likelihood.

 

1.3       Following the workshop an audit programme was developed that considered the risks facing the service identified at the workshop and included testing of financial management, supervision and control issues. This approach was used to ensure the audit covered the management of identified risks and financial and operational procedures.

  

2                    OBJECTIVES

 

2.1       To provide assurance to the Authority that the management of the Car Park Service is operating in accordance with the current regulations and that risk mitigation strategies identified by the service are operating satisfactorily.

 

 

3           OVERALL CONCLUSION

 

3.1       The risks identified in the workshop are clearly understood by the service. However, tests carried out on financial management, supervision and control within the section raised issues that need to be addressed. The following points should be noted:

 

1)      It is recommended that the statistics regarding the locations of tickets issued are examined to confirm that there have been no major changes in usage patterns.

 

2)      It is recommended that a member of staff is designated as Deputy Finance Officer to ensure continuity during any absence of the Finance Officer.

 

3)      It is recommended that performance measures are introduced for all staff.

 

4)      A named officer should be given responsibility for overseeing the computer systems, SIDEM and PARKFOLIO.

 

5)      It is recommended that the possibility of the acceptance of car park coinage be considered as part of the requirements for the main banking contract when it is renewed in 2007.

 

6)      It is recommended that:

 

·         The discrepancies on car park machines are recorded to identify any problems with specific machines.

 

·         Cash reconciliation needs to be carried out on a regular and timely basis to  identify errors, and

 

·         Where errors are identified on the cash reconciliation account, corrections need to be made immediately to ensure that they are not overlooked.

 

            7)  With the departure of the temporary Finance Officer on the 17 March 2006, there were no contingency arrangements in place to ensure that their work was covered. Not only were reconciliations not carried out, but income was not being processed. This is unacceptable because:

 

·         There has been a past history of failure to reconcile income due and identification of income that has not been received ( 2003/04 and 2004/05)

 

·      The failure of the Car Parks Section to recognise their responsibilities in this area.

 

·      Failure to process income has an adverse impact on the Council's bank reconciliation, which is a fundamental part of the end of year closedown processes. The requirement to carry out a regular bank reconciliation is also one of the criteria for judgment at Level 2 in CPA Use of Resources - failure to do so would mean we score 1 on Internal Control.

 

·      Lack of processing of income indicates an internal control weakness - on that basis, the assurance statement for Engineering Services may now have to be updated to include income processing as a weakness for inclusion in the Council's published Statement on Internal Control.

 

            8)  The £2,850 outstanding from the Post Office for 2003/04 should be recovered.

 

            9)    The Car Parks Section appears to have taken no action to limit the effect of the introduction of the car parking permit on their day to day work.

 

                   It had been known for six months that the Car Parks Manager was due to leave on 31 March 2006, and that the secondment of the Finance Officer was only temporary. In addition, although the final details had not been confirmed, the introduction of the parking permits was anticipated. As such it is unacceptable that detailed contingency arrangements were not in place.

 

It is recognised by Internal Audit that actions have been taken by management to address many of the issues raised in this report. The variation to the job description for Office Manager and the subsequent appointment of a Manager who has considerable experience of financial issues is to be welcomed, and it is felt that these actions will go a long way to mitigating the financial risks identified in this report.

 

       ACKNOWLEDGEMENTS

 

I would like to take this opportunity to thank the Traffic and Transportation Manager and the staff of the Car Parks Service for their assistance during the currency of this audit.


AUDIT SERVICES REPORT ACTION PLAN:         CAR PARKS

DATE REPORT ISSUED:                                         18 AUGUST 2006

 

Main Findings

Possible Consequences

Recommendations

(Action Required)

Priority

Officer Responsible

Target date

 

The routes used by the Inspectors are based on statistics that were produced several years ago.

 

The deployment of staff may not match current car park usage.

Potential loss of income.

 

The statistics should be reproduced to confirm if the current routes are still valid

 

Low

 

Office Manager

 

30/12/06

 

There was no member of staff to cover for the absence of the Finance Officer.

 

Income records not up to date: loss of income to Council. Loss of internal control.

 

A member of staff should be designated as Deputy Finance Officer.

 

High

 

Office Manager

 

30/12/06

 

There are no performance measures for staff.

 

Staff deployed ineffectively; Targets not set. Training needs not identified.

 

Develop and implement appropriate PI’s.

 

Medium

 

Office Manager

 

30/12/06

 

No member of staff has responsibility for overseeing the computer systems, SIDEM and Park folio.

 

Risk of failure of systems.

 

A named officer should be given responsibility for overseeing the computer systems.

 

Medium

 

Office Manager

 

31/12/06

 

With the introduction of the Island Parking Permit the amount of coinage collected may reduce.

 

If the reduction is significant, the possibility of including the banking of the coins in the Councils main banking contract should be explored.

 

Liaise with Officer responsible for negotiating main bank contract.

 

Low

 

Office Manager

 

30/10/06

 

Discrepancies on car parking machines occur frequently – cash figures are assumed to be the correct amounts.

 

Loss of income due to lack of accurate figures.

Risk of Fraud.

Loss of internal control.

 

Discrepancies should be recorded to identify which machines are causing problems.

 

Medium

 

Office Manager

 

31/10/06

Cash reconciliation was not carried out on a regular and timely  manner.  A past history of failure to reconcile income due and identify income not received.

 

Loss of income to the Council.

Risk of Fraud.

Loss of internal control.

Inadequate audit trail.

 

Income to be reconciled regularly on a timely basis.

 

High

 

Office Manager

 

Immediate

 

Where errors  were found on the cash reconciliation, corrections were not carried out in a timely manner.

 

Corrections not completed.

Incorrect / incomplete financial information.

 

Corrections to be actioned immediately.

 

High

 

Office Manager

 

30/10/06

 

Lack of contingency arrangements to cover loss of Temporary Finance Officer.

 

Failure to process income:  Possible impact on both CPA and SIC.

Lack of forward planning.

 

Actioned by Financial Services.

Forward planning to be improved.

 

High

 

Office Manager

 

30/10/06

 

No action has been taken by the car parks service to recover an amount of £2,850 owed to the Council by the Post Office from 2003/04.

 

Loss of income.

 

 

Recovery to be implemented by car parks Section.

 

High

 

Office Manager

 

30/10/06

 

The Car Parks service failed to take responsibility for recording and monitoring income.

 

Failure to process income:  Possible impact on both CPA and SIC.

 

Car Parks Service to recognise their responsibility for financial procedures.

 

High

 

Office Manager

 

30/10/06

 

Lack of forward planning for the introduction of the new Island parking permit  at the same time as the Car Park Manager was to leave and no permanent finance officer.

 

The day to day work of the section disrupted at the end of the financial year.

 

Forward planning & management of service to be improved

 

High

 

Traffic & Transportation Manager

 

 

30/10/06

           


AUDIT SERVICES REPORT

 

 

B: BEST VALUE PERFORMANCE INDICATORS

 

EXECUTIVE SUMMARY

 

 

1.1       Introduction

 

The audit was carried out as part of the 2006/07 Audit Plan. The plan was developed using a risk based approach with Performance Indicators ranking as a top priority. Best Value Performance Indicators provide a measure of actual achievement against targets for the local authority as directed by central government prescribed definitions.

 

1.2       Objectives

 

To provide assurance to management that the Isle of Wight Council’s Best Value Performance Indicators are calculated in accordance with ODPM and Audit Commission definitions and have been correctly applied.

 

1.3       Summary of Findings

 

A sample of Performance Indicators was reviewed. From the information available three BVPIs may be amended because the definition had not been correctly applied in terms of data collection, and each BVPI relied upon the same collected data. Five BVPIs were identified where corrections have been required or data requiring further clarification.          

 

1.4       Overall Conclusion

 

There were two generic recommendations made both of which have been agreed by management. These are detailed in the attached action plan.

 

1.5       Acknowledgements

 

I would like to thank the Performance Improvement team and those departments involved for their help during this audit.

 


 

 


Internal Audit Action Plan

 

Title of Report:                                Best Value Performance Indicators     

Date Final Report issued:            19 June 2006

 

 

Scope of PI

Main Findings

Possible Consequences

Recommendation

Reference

Action Required

Priority

Responsibility

Target Date

Pedestrian crossings with disabled facilities

Administrative error

Incorrect supporting working paper

14.0

That corrected BVPI information is received in time for this years inspection.

4

PI Co-ordinator responsible

30/06/06

Cleanliness of highways

Definition incorrectly applied

BVPI amendment

14.1

That account is taken of the finding to ensure the correct definition is applied to future years.

4

PI Co-ordinator responsible

Unable to correct

Homelessness

Incorrect numbers used

BVPI amendment

14.0

That corrected BVPI information is received in time for this years inspection.

4

PI Co-ordinator responsible

Implemented

Abandoned vehicles

Incorrect numbers used

BVPI amendment

14.0

That corrected BVPI information is received in time for this years inspection.

4

PI Co-ordinator responsible

Implemented

Conservation areas

Incorrect numbers used

BVPI amendment

 

14.0

That corrected BVPI information is received in time for this years inspection.

4

PI Co-ordinator responsible

Implemented

           

 

Priority Rating :-           1 – Serious control weakness requiring immediate action. 

2 – Control weakness requiring action within follow up period.

3 – Low priority control weakness requiring action within timescale determined by  establishment.

                                     4 – Other -Systems related matters, value for money, administrative.

 

 


AUDIT SERVICES REPORT

 

 

C: BANK RECONCILIATION

 

EXECUTIVE SUMMARY

 

 

1.1       Introduction

 

The audit was carried out as part of the 2006-07 audit plan and the plan was developed using a risk based approach with the bank reconciliation system being scored as risk factor 46, classing the audit as important to tackle.

 

The bank reconciliation is a control to ensure that entries that pass through all the Council’s bank accounts are correctly recorded in the Isle of Wight Councils books of account. This process should be done in a timely manner to ensure that any variances are corrected at the earliest opportunity.

 

1.2       Objectives

 

To provide assurance to management that the Isle of Wight Council’s bank reconciliation processes are completed in an appropriate and timely manner.

 

1.3       Summary of Findings

 

There were findings with six recommendations as detailed in the attached action plan.

 

1.4       Overall Conclusion

 

There is room for improvement in some administrative processes.

 

1.5       Acknowledgements

 

I would like to thank staff at the Sandown cash office and all those involved in bank reconciliation at County Hall.

 



Internal Audit Action Plan

 

Title of Report: Bank Reconciliation

Date Final Report issued:  01/09/06

 

 

Finding Reference

Main Findings

Possible Consequences

Recommendation

Reference

Action Required

Priority

Responsibility

Target Date

2.2

No up to date procedure manual

Failure to take the required steps for satisfactory completion of the bank reconciliation

3.1

That the systems Team Leader in conjunction with other staff document a procedure manual preferably electronically and version controlled and securely held

3

Systems Support Team Leader

30th September

2006

2.3

Staff guidance as to process target dates not issued

Slippage of overall target date for bank reconciliation completion

3.2

That the target dates are issued to staff

3

System Support Team Leader

30th September 2006

2.7

Late receipt of bank statements

Failure to complete the Income and Bank Reconciliation within expected target dates

3.4

That steps are taken to ensure statement details are received earlier

3

System Support Team Leader

30th September 2006

2.9

Possible unnecessary report production

Increased storage required

3.6

A review of the method of production of this report and others

4

System Support Team Leader

30th September 2006

2.12

Cheque payment details were not being received by Newport Cashiers within a reasonable time

Unprocessed cheque data hindering the satisfactory completion of the bank reconciliation.

Lack of audit trail

3.3

That cheque request slips are completed in all instances

2

Revenue Team Leader

Now implemented

 

 

 

 

 

 

 

2.16

Inadequate staff cover for completion of the Income reconciliation

Slippage of bank reconciliation completion

3.5

That adequate training is given to another member of staff to cover sickness or annual leave at the Sandown Cash Office.

 

 

2

Revenue Team Leader

30th September 2006

 

 

 

           

 

Priority Rating :-    1 – Serious control weakness requiring immediate action.                   

                             2 -  Control weakness requiring action within follow up period.

                             3 – Low priority control weakness requiring action within timescale determined by establishment.

                             4 – Other -Systems related matters, value for money, administrative.

 


AUDIT SERVICES REPORT

 

D: CREDITOR PAYMENTS

 

EXECUTIVE SUMMARY

 

 

1.1       Introduction

 

The audit was carried out as part of the 2005/06 Audit Plan. The plan was developed using a risk based approach with Creditors ranking as B on a scale of A-D, A being the highest risk category. The administration of the system is carried by the Creditor Payment Section.

 

1.2       Objectives

 

To provide assurance to management that the Isle of Wight Council’s creditor payment system is operating in accordance with management control arrangements and that they are adequate to ensure the integrity of the Authority’s Financial Accounting System.

 

1.3       Summary of Significant Findings

 

There was not a robust enough procedure in place to adequately chase suppliers for certified copies of VAT invoices to ensure recovery of the VAT element in all cases. New procedures have now been documented and responsibility for the process rests with the Creditor Payments section.

 

Recommendations of a less significant nature have also been made which are included in the attached action plan.     

 

1.4       Overall Conclusion

 

Overall we can give assurance that the system of internal control within creditor payments is operating in a satisfactory manner.

 

1.5       Acknowledgements

 

I would like to thank the Creditor Payments section and Property Management Department for their help during this audit.

 

 


 


Internal Audit Action Plan

 

Title of Report: Creditors                                                                                                                                                 Date Final Report issued:  10/07/2006

 

Finding Reference

Main Findings

Possible Consequences

 

Recommendation

Reference

Action Required

Priority

Responsibility

Target Date

2.1

A specified limit

Regarding invoice authorisation was not on file

Breach of financial regulations.

1

2.5

That the Payments and Exchequer officer ensures that the appropriate authorisation is received.

2

Payment and Customer Accounts Manager

30/04/2006

4.1

There is not a robust procedure in place to ensure that VAT due to the Council is reclaimed in all cases.

Loss of income

Loss of internal control

2

 

 

 

 

3

4.3

 

 

 

 

4.4

That there is a documented procedure regarding the system of VAT recovery and responsibility should rest with a named officer.

 

Those invoices currently on file should be reviewed immediately to recover the outstanding VAT.

 

 

1

 

 

 

 

1

Payments and Customer Accounts Manager

 

Payments and Customer Accounts Manager

 

 

 

30/04/2006

 

 

 

 

30/04/2006

5.7

Invoices were passed without evidence of a purchase order being raised

Breach of financial regulations

Loss of internal control

4

5.11

That no payment is made without the appropriate evidence of a purchase order having been raised in line with financial procedure rule 3.4.2 and the order reference is written on the invoice.(subject to recommendation 5.12 below)

2

Payments and Customer Accounts Manager

 

Immediate

 

 

 

 

 

 

 

 

 

 

 

 

5.9 & 5.10

 

No reference has been made to the principles regarding periodical and utility payments in the financial procedures 

Failure to ensure appropriate procedures are documented

5

5.12

That the Financial Procedure 3 (Buying Goods and Services) is amended to include reference to the procedures regarding periodical types of expenditure

4

Programme Lead Performance Improvement

30/06/2006

10.3

 

 

 

 

 

10.6

 

 

A payment was made twice in respect of a periodical payment

 

It is questionable whether the creditor payments section should carry the responsibility of raising payment requests on behalf of the Property Services Department

Lack of internal control

Inappropriate payments

 

 

Failure to make efficient use of resources

6

 

 

 

 

 

7

10.7

 

 

 

 

 

10.8

 

Review the current procedures to ensure that the systems are appropriately managed and robust in respect of periodical payments.

 

 

That a review incorporates the feasibility of using Technology Forge to replace the current system surrounding periodical payments

2

 

 

 

 

 

4

Payments and Customer Accounts Manager

 

 

Payments and Customer Accounts Manager

 

Office Manager Property Services

 

31/08/2006

 

 

 

 

 

31/08/2006

 

 

 

 

31/08/2006

 

      10.5

No plans to have insurance owners on the Technology Forge system

Failure to make efficient use of resources

8

10.9

That the Technology Forge system includes details of the appropriate insurer

4

Senior Insurance and Risk Officer

Corporate Property Manager

 

    31/08/2006

 

Priority Rating :-  1 – Serious control weakness requiring immediate action. 2 - Control weakness requiring action within follow up period.

                                3 – Low priority control weakness requiring action within timescale determined by establishment.4 – Other -Systems related matters, value for money, administrative.


AUDIT SERVICES REPORT

 

E: DISABLED FACILITIES GRANTS

 

EXECUTIVE SUMMARY

1.1       Introduction


This audit was carried out as part of the 2006-07 Audit Plan. The purpose of the audit is to provide assurance to Management that there are adequate controls and procedures in place and that they are implemented effectively by Housing Staff.

 

Local councils are required by law to give Disabled Facilities Grants to eligible applicants to make houses suitable for disabled people.

 

Disabled Facilities Grants are available to owners and tenants in both private and social housing subject (in England) to a limit of £25,000.

 

For year 2005-06 the number of completed grants was 112. The 2006-07 budget is £800,000 and this is expected to cover 133 applications.

 

2005-06 saw the introduction of the Home Improvement Agency, Anchor, who were awarded the contract following a tender process.  During the financial year 2005-06, Anchor’s involvement in grants was minimal.

 

However, they now have a more prominent involvement in the process.  Anchor act as the clients agent and are paid 10% of the final grant value.  If the maximum grant is awarded it must include all fees.

 

The legislation covering these grants is the Housing Grants Construction and Regeneration Act 1996.

 

The audit was carried out by interviewing relevant officers and carrying out testing on selected areas to determine the level of compliance with Council policy and procedures.

 

1.2        Summary of Significant Findings

Anchor was rarely used during 2005-06 but now play a more prominent role in those applications dealt with so far in 2006-07. Because of the limited instances of dealing with Anchor the relationship between them and the council is in its early stages.  Due to this, a number of administrative errors have arisen.  These are being dealt with and as the relationship progresses, procedures will become embedded to provide the expected levels of control.

 

The Councils own systems for referrals, the checking of applications, obtaining estimates and invoice payments are sound with a comprehensive control framework in place.

 

1.3       Overall Conclusion

 

There were no major areas of concern from this audit, six minor recommendations of a mainly administrative nature have been made which are detailed in the attached action plan.


1.4       Acknowledgements

I would like to take this opportunity to thank all staff involved in Housing for their co-operation and assistance in carrying out this review.

 

 


INTERNAL AUDIT ACTION PLAN

 

Title of Report:                     Disabled Facilities Grants  

Date draft Report issued: 

 

Report Reference

Main Findings

Possible Consequences

Action Required

Priority

Responsibility

Target Date

4.3

An inaccurate invoice payment was made due to unclear documentation.

Decreases availability for future grant funding.

1. Obtain credit note for payment on DFG/90/05.

2. Persistent diligence in checking future payments

1

Housing Renewal Manager

Immediate

7.1

Discretionary recovery of funds where an applicant has not remained in the altered home does not occur.

Recovered monies would assist in providing funding for future applications.

1.  Adjust in house documents to highlight the requirements of remaining in the altered home.

2.  Ensure that visiting officers explain the circumstances in which recovery may occur and that this is documented on the summary form, as a tick box for example.

3

Housing Renewal Manager

February 2007

7.2

There were financial errors involving cost of works and invoicing whilst working in partnership with the Home Improvement Agency.

Unobserved overspends.

1.  Embed new working practices to allow smoother transactions between the Home Improvement Agency and Housing staff.

2.  Assiduous checking of all incoming financial documentation.

3

Housing Renewal Manager

February 2007

 

Priority Rating: -          1          Serious control weakness requiring immediate action.

2           Control weakness requiring action within follow up period.

3           Low priority control weakness requiring action within timescale determined by establishment. 

 

 

 

 

AUDIT SERVICES REPORT

 

F: ELECTRICAL SERVICES/ STREET LIGHTING

 

EXECUTIVE SUMMARY


1.1       Introduction


This audit was carried out as part of the 2006-07 Audit Plan. The purpose of the audit is to provide assurance to Management that there are adequate controls and procedures in place and that they are implemented effectively by the Street Lighting Service .


The audit was carried out by interviewing relevant officers and carrying out testing on selected areas to determine the level of compliance with Council policy and procedures.

 

 

1.2      Summary of Significant Findings

There were no significant findings from this audit, minor recommendations of    a mainly administrative nature have been made which are detailed in the attached action plan.

 

1.3       Overall Conclusion


There are no significant areas of concern relating to the provision of this service. The risk of a substantial increase in electricity costs has been identified appropriately by the service. The recent tender awards in respect of the maintenance of street lighting have complied with all relevant regulations and policies.

 

1.4       Acknowledgements

I would like to take this opportunity to thank all staff involved in Street Lighting for their co-operation and assistance in carrying out this review.



 


Internal Audit Action Plan

 

Title of Report:                                Street Lighting / Electrical Services

Date draft Report issued:            28 June 2006

 

Main Findings

Possible Consequences

Action Required

Priority

Responsibility

Target Date

Further information will be required by the Audit Commission to verify the Best Value Performance Indicators

Amendment / Qualification of BVPI

Ensure tickets issued by the contractor are available for the Audit Commission

2

Principal Engineer – Street Lighting

BVPI Inspection

.

There is occasionally a significant delay between the award of contract and notification to Legal Services.

Delay in preparation of formal contract

Develop procedures to reduce the period of time taken to pass information to Legal Services.

This may be considered during forthcoming review of contract management.

3

Operational Manager - Maintenance

Ongoing

.

Stores systems used either have out of date minimum and maximum stock levels or no levels at all.

Too much or too little stock held delays in ordering stock.

Review FIDO stores system and stores system used by Street Lighting. Include lead in period / re order levels. Information to be passed to the Systems Support Team Leader who will ensure the FIDO stores system is updated.

2

Principal Engineer – Street Lighting &

Systems Support Team Leader

 

September 2006

There has been no resolution to the ongoing situation regarding Street Lighting on the ex prison estates

Significant maintenance costs may be incurred

Obtain consensus with Central Government on responsibility for Street Lighting

3

Operational Manager - Maintenance

Ongoing

 

Priority Rating: -          1          Serious control weakness requiring immediate action.

2          Control weakness requiring action within follow up period.

3          Low priority control weakness requiring action within timescale determined by establishment.


AUDIT SERVICES REPORT

 

G: STREET CLEANSING & LITTER MANAGEMENT

 

EXECUTIVE SUMMARY


1.1       Introduction

 

This audit was carried out as part of the 2006-07 Audit Plan. The purpose of the audit is to provide assurance to Management that there are adequate controls and procedures in place and that they are implemented effectively by the Street Cleansing Section.

 

Litter collection and street cleaning on the IW is carried out under contract by Island Waste Services. The current contract commenced on 2 April 2001 at which time the existing contracts within the old South Wight and Medina Borough areas were combined and common standards adopted. The new contract included the addition of 270 kilometres of rural highways that were not previously cleaned. The contract includes the emptying of litter and dog bins. The contract was awarded for an 8 year period with the option to extend for a further 4 years, therefore the contract will again be subject to competitive tendering in either 2009 or 2013.


The audit was carried out by interviewing relevant officers and carrying out testing on selected areas to determine the level of compliance with Council policy and procedures.

 

1.2       Summary of Significant Findings

Significant findings have already been reported in the Best Value Performance Indicator audit, these findings are reiterated here and recommendations made to ensure the process for 2006-07 is amended to ensure indicators are not qualified by the Audit Commission.

 

The inspections carried out for BVPI 199a, b and c for 2006-07 must be amended to ensure the requirements of the BVPI are met.

 

Recommendations of a less significant nature have also been made which are included in the attached action plan.

 

1.3       Overall Conclusion

 

There is only one significant area of concern relating to the provision of this service.  In general the service is performing well, and the standard of contract performance is good. Positive relationships with the contractor ensure that resources are deployed effectively. There is generally a high level of satisfaction expressed by the public regarding the cleanliness of Island Streets.

1.4       Acknowledgements

I would like to take this opportunity to thank all staff involved in Street Cleaning for their co-operation and assistance in carrying out this review.


Internal Audit Action Plan

 

Title of Report:                                Street Cleansing & Litter Management

Date Final Report issued:            21 July 2006

 

Main Findings

Possible Consequences

Action Required

Priority

Responsibility

Target Date

Inspections carried out in respect of BVPI 199 for 2005-06 were not, in a small number of instances, in accordance with guidelines issued by DEFRA.

Amendment / Qualification of BVPI

Ensure 2006-07 follow guidance issued by DEFRA.

1

Operational Manager - Maintenance

Immediate

.

Effects of the requirements of the BVPI on the inspection regime may have an adverse effect on the quality of contract monitoring.

 

Reduction in quality of service received.

 

Monitor any effects on ability to inspect the contract.

 

3

 

Principal Contracts Management Officer

 

Ongoing

.

The last full inspection of weigh bridge tickets relating to the Street Cleaning Contract  was carried out in 2002

 

The authority is incorrectly charged for refuse disposal.

 

Should sufficient resources exist then a further review should be carried out in 2006-07

 

3

 

Senior Waste Management & Contracts Officer

 

March 2007

 

There is a potential overspend within the budget of £30,000. Other sources of income are being identified but should this not be possible then a reduction in the level of service should be negotiated.

 

Budgets are overspent for 2006-07

 

Identify other income streams or reduce level of service

 

2

 

 

Operational Manager – Maintenance &Business Development Manager - Finance

 

September 2006

 

Priority Rating:            1          Serious control weakness requiring immediate action.

2          Control weakness requiring action within follow up period.

3          Low priority control weakness requiring action within timescale determined by establishment.