PAPER B
Committee : AUDIT
AND PERFORMANCE COMMITTEE
Date
: 10 OCTOBER 2006
Title
: INTERNAL AUDIT PROGRESS REPORT
REPORT OF THE CHIEF INTERNAL AUDITOR
1.
This
report is to provide the Committee with information regarding internal audit’s progress
in delivering the annual audit plan for 2006/07.
2.
The
Committee is invited to note the contents of the report and to seek
clarification of any issues arising from the progress achieved to date.
BACKGROUND
3.
In
keeping with good corporate governance practice, a Committee of elected members
should have oversight of the activities of the Internal Audit Service for the
purpose of monitoring Internal Audit’s performance, both in terms of the
quality and quantity of its work. This report largely addresses the issue of
quantity but with some qualitative data also provided to give a flavour of
overall performance to date in this financial year.
4.
To
facilitate this process, attached as Appendix A is the annual audit plan for
2006/07 with the status of each planned audit indicated in the “status” column
in Appendix A. The numbers in the
status column should be interpreted as follows:
1 indicates that the audit
has been completed;
2 indicates that the audit
is in progress;
3 indicates that the audit
has not yet commenced.
5.
The
status indications reflect the progress achieved by the end of September 2006,
which is the mid-way point in the financial year.
PROGRESS AGAINST THE PLAN TO DATE
6.
The
table below summarises the progress to date against the annual audit plan:
Corporate Objective (Derived from Aim High) |
Planned Days |
Completed Audits – Planned Days |
In Progress Audits – Planned Days |
Not Started Audits – Planned Days |
2.3.1
Regeneration |
155 |
22 |
93 |
40 |
2.3.2
Health and well being |
80 |
13 |
35 |
32 |
2.3.3
Safer communities |
40 |
- |
20 |
20 |
2.3.4
Outcomes for children |
153 |
3 |
35 |
115 |
2.4.1
High performance |
877 |
195 |
355 |
197 |
TOTAL |
1175* |
233 |
538 |
405 |
*N.B.
This total excludes 130 days contingency.
7.
From
the table above it can be seen that:
20% of planned work has been completed;
46% of planned work is in progress;
34% of planned work has yet to commence.
Overall, we estimate that 38% of the plan has been
achieved by the end of September. The rate of delivery of the plan will
accelerate during the rest of the year as new members of staff advance through
their learning curves and hence become more productive. By way of comparison,
the outturn for the financial year 2005/06 was 56% of planned work achieved.
8.
The
audit plan has been slightly modified to reflect changing priorities during the
year and amended projects are shown in bold in appendix A.
9.
The
lack of progress in outcomes for children is due to the long term sickness
absence of the lead auditor for this area due to injury in a road traffic
accident. This officer is now fit and
inroads will now be made into the backlog of work in this area.
10.
The
ICT audit plan has also been modified to take account of the rapidly changing
environment and developing corporate priorities such as the new performance
management system.
11.
Overall,
we expect to achieve at least 85% of the planned programme of work by the end
of the financial year.
QUALITY
PERFORMANCE MEASURES
12.
Other performance measures include the number
of recommendations accepted by management as a proportion of all
recommendations made. To date this year we have made 70 recommendations all of
which have been accepted by management.
13.
We
routinely obtain feedback from clients as to the quality of the audit product
from their perspective. We measure client satisfaction on a scale of 0 to 4, 0
being poor and 4 being excellent. The objective is to achieve an overall
average score of at least 3 which represents “good”. The current average score is
3.18 which is in line with expectations. The final figure for 2005/06 financial
year was 3.25.
FINANCIAL, LEGAL, CRIME AND DISORDER IMPLICATIONS
There are no significant financial or legal
implications of this report, given that it is a progress report on the Internal
Audit function. The Committee is reminded that the Council is required by
statute (the Accounts and Audit Regulations) to have an adequate and effective
Internal Audit function.
RELEVANT PLANS, POLICIES, STRATEGIES AND PERFORMANCE
INDICATORS
None.
CONSULTATION PROCESSES
None.
BACKGROUND PAPERS USED IN THE PREPARATION OF THIS
REPORT
Audit files
Contact Point : Ged
Richardson – ext 3683
INTERNAL AUDIT PLAN 2006/07